National Highways Authority Of India vs Nazir Ahmed on 3 March, 2025

0
188

Jammu & Kashmir High Court

National Highways Authority Of India vs Nazir Ahmed on 3 March, 2025

Bench: Sanjeev Kumar, Moksha Khajuria Kazmi

                                                                            Sr. No. 09

        HIGH COURT OF JAMMU & KASHMIR AND LADAKH
                        AT JAMMU

LPA No. 12/2025 in
WP (C) No. 826/2024

1. National Highways Authority of India,                    .....Appellant(s)/Petitioner(s)
   through Project Director, PIU-Ramban,
   Sh. Parshotam Kumar Phonsa.
2. Union of India,
   through Ministry of Road Transport & Highways,
   New Delhi.

                                  Through :- Mr. Sunny Mahajan, Advocate

                          v/s
1. Nazir Ahmed,                                                         .....Respondent(s)
   S/o Habibullah Gattoo,
   R/o Krawah, Banihal, District Ramban.
2. Sajad Ahmed Ganai,
   S/o Ali Mohd. Ganai,
   R/o Farwagan, Banihal, District Ramban.

                                  Through :- Mr. Arshad Ahmed Malik, Advocate


CORAM:      HON'BLE MR. JUSTICE SANJEEV KUMAR, JUDGE
            HON'BLE MS. JUSTICE MOKSHA KHAJURIA KAZMI, JUDGE

                                     ORDER

03.03.2025
(Sanjeev Kumar-J)

1. This intra-court appeal by the National Highways Authority of India is

directed against an order and judgment dated 24.12.2024 passed by the

learned Single Judge of this Court [“the Writ Court”] in WP (C) No.

826/2024 titled Nazir Ahmed Vs. Union of India & Anr. whereby, the

Writ Court has allowed the writ petition of the respondents and issued

the following directions:

“7….. Viewed thus, for what has been observed, considered and
analysed hereinabove, the instant petition is disposed of as under:

(i) The Deputy Commissioner shall offer a hearing to the
respondent no. 2 herein in respect of the quantum of damage
assessed by the committee in its report dated 09.08.2023
2 LPA No. 12/2025 in
WP (C) No. 826/2024

within a period of two weeks from the date a copy of this
order is produced by either of the parties and therefore within
two weeks have the damage assessed by the committee in its
report re-assessed while taking into consideration the stand of
the petitioner herein.

(ii) Upon such re-assessment, the respondent no. 2 herein shall
pay the said re-assessed amount of compensation to the
petitioner herein within four weeks’ time thereafter alongwith
interest at the rate of 6% P.A from the date of damage till its
payment.”

2. Briefly stated, the facts leading to the filing of the instant appeal are that

the appellant authority executed the construction work of NH44 at

Krawah Banihal District Ramban by use of heavy machinery. With a

view to constructing the road, the appellant authority resorted to earth

cutting in the area. As per the case setup by the writ petitioner, the earth

cutting which was resorted to by the appellant authority remained

unattended during winter season for a considerable period of time and as

a result whereof, the school building and the house of the respondents

suffered extensive damage, in that, it developed cracks because of the

rain water percolating from the catchment area due to melting of snow

etc.

3. The respondents approached the office of Deputy Commissioner,

Ramban and Police Station, Ramban with their grievance, whereupon the

Additional Deputy Commissioner, Ramban vide letter dated 20.03.2020

directed the Executive Engineer, PWD (R&B) Division to furnish a

detailed report after making spot inspection. The Executive Engineer

concerned submitted his report on 06.08.2020, reporting therein that the

construction work of NH44 on the uphill side of area by way of Deep

Gulla Earth cutting and also by deploying heavy machinery and
3 LPA No. 12/2025 in
WP (C) No. 826/2024

thereafter keeping the site unattended during winter season has led to

drainage of rain/surface water downhill and has affected the structure of

the respondents.

4. In a nutshell, as per the opinion of the Executive Engineer concerned, the

damage to the structures of the respondents has occasioned due to the

surface cutting resorted to by the appellant authority in the process of

construction of NH44. It seems that with a view to verify the claim made

by the respondents, the Tehsildar also constituted a committee which

inter alia included representative of appellant authority as well.

Simultaneously, the appellant authority also sought a report from its

consultancy agency i.e. SMEC Private Ltd. The report of the committee

constituted by Tehsildar Banihal and the inspection report submitted by

the consultancy agency of the appellant authority have both confirmed

that the damage to the structures of the respondents are because of

construction of road by the appellant authority.

5. Relying upon the aforesaid two reports and the opinion of the Executive

Engineer concerned, the respondents approached the appellant authority

for compensation but the same was denied by the appellant authority on

the ground that the damage to the structures of the respondents, if any,

was not attributable to any act or omission of the appellant authority.

6. Feeling aggrieved, the respondents filed WP (C) No. 826/2024 which

was contested by Respondent No. 2. The Writ Court, after having

considered the rival contentions and material on record, has allowed the

writ petition with the directions reproduced hereinabove vide its

judgment dated 24.12.2024. It is this judgment passed by the Writ Court

which is called in question before us in this appeal. The impugned

judgment is assailed by the appellants inter alia on the ground that the
4 LPA No. 12/2025 in
WP (C) No. 826/2024

appellant authority was never associated either by the committee

constituted by the Tehsildar or by the Executive Engineer, PWD (R&B)

Division who initially conducted the inspection of the structures of

Respondent No. 1.

7. Mr. Sunny Mahajan, learned counsel appearing for the appellant

authority submits that the Writ Court has erroneously recorded that the

appellant authority has accepted the report and the only question that

remains to be decided is the amount of compensation payable to the

respondents.

8. Having heard learned counsel for the parties at length and perused

the material available on record, we are of the considered opinion that

the judgment passed by the Writ Court is legally perfect and

unquestionable. Apart from other things what persuades us to agree

completely with the Writ Court is that there is a report by the

consultancy agency of the appellant authority on record which clearly

demonstrates that the damage has been caused to the structures of the

respondents due to construction of road and failure of the appellant

authority to prevent drainage of rain water downhill towards the

structures of the respondents.

9. It may be pertinent to note that the report has been submitted by the

consultancy agency of the appellant authority on the request of the later.

Neither the aforesaid report has been disputed by the appellant authority

nor the appellant authority has referred the matter to some other experts

to have a fresh opinion in the matter. The appellant authority, having

accepted the report of its own consultancy, cannot be allowed to turn

around and say that the damage caused to the structures of the

respondents because of the construction of the road has not been proved
5 LPA No. 12/2025 in
WP (C) No. 826/2024

and that the appellant authority is not liable to compensate the

respondents. There is ample evidence on record which unequivocally

suggests that the damage to the structures of the respondents is only due

to the construction of the road. The structures of the respondents are

situate downhill and because of cutting of earth and the gap that was

created between the structures and the earth cutting, resulted into seepage

of rain/surface water, damaging the structures of the respondents.

10. In view of the aforesaid evidence available on record, the Writ Court

could not have taken any opinion other than the one taken in the

judgment impugned.

11. For all these reasons, we are not inclined to interfere with the well

reasoned judgment passed by the Writ Court. The appeal is found to be

without any merit and the same is, accordingly, dismissed along with

connected application(s), if any.

12. Interim direction, if any, shall stand vacated.

                                                 (Moksha Khajuria Kazmi)             (Sanjeev Kumar)
                                                          Judge                            Judge
          JAMMU
          03.03.2025
          Manan

                                        Whether the order is speaking :     Yes/No
                                        Whether the order is reportable :   Yes/No




Manan Mahajan
2025.03.05 18:15
I attest to the accuracy and
integrity of this document

[ad_1]

Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here