The Special Deputy Collector vs J. Rama Rao on 7 March, 2025

Date:

Telangana High Court

The Special Deputy Collector vs J. Rama Rao on 7 March, 2025

Author: Abhinand Kumar Shavili

Bench: Abhinand Kumar Shavili

      HON'BLE SRI JUSTICE ABHINAND KUMAR SHAVILI
                          AND
       HON'BLE SMT. JUSTICE TIRUMALA DEVI EADA

                       L.A.A.S.No.275 of 2014

JUDGMENT:

(per Hon’ble Smt. Justice Tirumala Devi Eada)

This appeal, under Section 54 of the Land Acquisition Act,

1894, (for short ‘the Act’) is preferred by the Special Deputy

Collector, SRSP, Pochampad, Nizamabad District, aggrieved by the

order and decree dated 22.12.2011 passed in O.P.No.12 of 2006 by

the learned Senior Civil Judge at Nirmal (hereinafter referred to as

‘the Reference Court’).

2. For convenience and clarity, the parties herein are referred to

as they were arrayed before the Reference Court.

3. The facts of the case in brief are that based on the

requisition made by the Deputy Executive Engineer, Division Land

Acquisition Rehabilitation SRSP Pochampad, the agricultural lands

at Temborni Village have been acquired, for the purpose of

submergence under Sriramsagar Project. Draft notification and

draft declaration proposals have been published in the Gazette on

19.11.1999 and 20.11.1999 respectively. After conducting due

enquiry, the Land Acquisition Officer has granted Rs.9,000/- per

acre besides statutory benefits. Aggrieved by the said award, the
AKS,J & ETD,J
LAAS No.275_2014
2

claimants have filed a petition for reference and the same was

referred under Section 18 of the Act to the Court of Senior Civil

Judge at Nirmal.

4. The Reference Court has framed the following point for

consideration:

“1. Whether the compensation awarded by the Land Acquisition
Officer to the claimants needs any enhancement, if so, what
would be just and reasonable compensation?

2. To what relief?”

5. Before the Reference Court, the claimants got examined PW1

and got marked Ex.A1. On the other hand, the respondents got

examined RWs 1 and 2 and got marked Ex.B1.

6. Based on the evidence on record, the Reference Court has

enhanced the compensation from Rs.9,000/- per acre to

Rs.20,000/- per acre and also granted additional market value

@12% per annum under Section 23(1-A) of the Act on the market

value from the date of notification or date of possession whichever

is earlier till the date of award. Aggrieved by the said

enhancement, the Special Deputy Collector has preferred the

present appeal.

AKS,J & ETD,J
LAAS No.275_2014
3

7. Heard the submissions of learned Government Pleader for

the appellant and Sri V.Manohar Rao, learned counsel for the

respondents.

8. Learned counsel for the appellant has submitted that the

reference Court ought not to have enhanced the compensation and

it has simply taken into consideration, another award passed by

the Court for the lands acquired in an adjacent village and went

ahead in enhancing the compensation to Rs.20,000/- per acre,

which is contrary to law. Learned counsel further argued that the

additional market value cannot be granted from the date of

possession but it can only be considered from the date of

notification and also that the interest cannot be awarded from the

date of possession. He, therefore, prayed to set aside the award

passed by the reference Court by allowing this appeal.

9. Learned counsel for the respondents has submitted that the

Reference Court has rightly considered Ex.A1 and has enhanced

the market value and that the facts of the said OP are similar to

the present case and hence, the order and decree passed by the

reference Court do not need any interference, and therefore, prayed

to uphold the same.

AKS,J & ETD,J
LAAS No.275_2014
4

10. Considering the above rival contentions, this Court frames

the following points for consideration:

1. Whether the claimants are not entitled for
enhancement of compensation?

2. Whether the claimants are not entitled to
additional market value @12% from the date of
dispossession till date of realization?

3. Whether the claimants are not entitled to the
interest from the date of dispossession till date of
realization?

4. Whether the order and decree of the reference
Court need any interference?

5. To what relief?

11. POINT NOs.1 AND 2:

a) The record discloses that on 18.02.1976, the possession of

agricultural lands in Temborni village was acquired by the

irrigation authorities in pursuance to a requisition made by the

Executive Engineer, Land Acquisition, DNSRP, Pochampad. The

Land Acquisition Officer has passed the award on 30.03.2005 but

the award with regard to the lands under reference was deferred on

the ground that they are the Poramboke lands. Thereafter, the

pattadars filed petition along with Faisal patti, Pahani patrak and

letter addressed to the Mandal Revenue Officer requesting to make

payment of compensation. Thereupon, draft notification and draft
AKS,J & ETD,J
LAAS No.275_2014
5

declaration were published on 19.11.1999 and 20.11.1999

respectively.

b) The claimants before the Reference Court have not filed any

sale deeds for reference. So also no sales statistics are reflected in

the award passed by the Land Acquisition Officer as revealed from

Ex.A1. It is elicited that no sales transactions took place in the

preceding three years as on the date of draft notification, because

the entire village was under sub-mergence. Ex.A1 further reveals

that Land Acquisition Officer has relied on the market value fixed

by the reference Court in O.P.No.729 of 1984 wherein the rate of

wet double crop lands were fixed @Rs.9,000/- per acre.

c) The claimants, on the other hand, have relied upon the

orders passed by the reference Court in O.P.No.07/2000 relating to

the land in the same village.

d) RW1/claimant has stated in his evidence that he used to

produce paddy crop and get an income of Rs.10,000/- per acre

after deducting all expenses.

e) RW2 is one of the claimants in O.P.No.07 of 2000 and he

deposed that his land and the land of the claimants are in the

same village and adjacent to each other, both lands are similar in

nature and fertility.

AKS,J & ETD,J
LAAS No.275_2014
6

f) PW1 is the referring officer in the case on hand, he admitted

that the entire village was submerged. He further stated that the

land owners who lost their lands for the same purpose are entitled

to receive same amount of compensation without any

discrimination. Ex.B1 i.e. certified copy of judgment in O.P.No.07

of 2000 dated 17.04.2006 is considered by the reference Court and

thus, the compensation was enhanced to Rs.20,000/- per acre.

g) The first contention raised by the appellant counsel is that

the Reference Court ought not to have enhanced the compensation

based on the judgment pertaining to earlier O.P. whereunder, the

lands of another village were acquired. A perusal of the record

reveals that both the villages are adjacent to one another and the

purpose for acquisition is one and the same i.e. submergence

under Sriramsagar project. Therefore, the contention of the

appellant counsel cannot be considered in this regard.

h) Then the second contention raised by the appellants counsel

is with regard to the additional market value i.e. granted by the

reference Court from the date of dispossession to the date of

realization.

i) It is pertinent to refer Section 23(1-A) of the Act and the

same is extracted hereunder for the sake of reference:

AKS,J & ETD,J
LAAS No.275_2014
7

“23.(1-A) In addition to the market value of the
land, as above, the Court shall in every case award
an amount calculated at the rate of twelve per
centum per annum on such market value for the
period commencing on and from the date of the
publication of the notification under Section 4 Sub-

Section (1), in respect of such land to the date of
the award of the Collector or the date of taking
possession of the land, whichever is earlier”.

j) Thus, a plain reading of Section 23(1-A) would infer that 12%

of additional market value has to be awarded from the date of

publication of notification under 4(1) to the date of the award of

Collector or the date of taking possession of the land, whichever is

earlier.

k) In Special Tahsildar (LA), P.W.D. Schemes v.

M.A.Jabbar 1, it was held that the possession having already been

taken on 15.02.1965, i.e. before publication of the notification

under Section 4(1) which was on 06.03.1980, the award of

additional amount for the period from 06.03.1980 to the date of

making award i.e. 30.09.1983 is perfectly correct.

l) It was observed by the Apex Court in Asstt.Commr., Gadag

Sub-Division v. Mathapathi Basavannaewwa 2 that if possession

is taken prior to the notification, then the strict construction of

23(1-A) would lead to unjust result, hardship to the owner and

1
(1995) 2 SCC 142
2
(1995) 6 SCC 355
AKS,J & ETD,J
LAAS No.275_2014
8

defeats legislative object. Therefore, in its view, the expression

“whichever is earlier” in Section 23(1-A) had to be construed in that

backdrop and the claimant is entitled to the additional amount

from the date of taking possession. Since advance possession was

taken prior to the publication of notification under 4(1), ‘the

claimants, by necessary implication are entitled to the payment of

the additional amount by way of compensation from the date of

taking over possession for the loss of enjoyment of the land.

m) Analyzing these two decisions, the Constitutional Bench in

Siddappa Vasappa Kuri v. Special Land Acquisition Officer3

has held that from Section 23(1-A), the starting point for the

purposes of calculating the amount to be awarded @12% p.a. on

the market value is the date of publication of Section 4(1)

notification. The terminal point for the purpose is either the date

of the award or the date of taking possession, whichever is earlier.

In the present case, the possession of the land having been taken

prior to the publication, that terminal is not available. The only

available terminal is the date of the award. Therefore, it was held

that the appellants are entitled to the additional compensation

under Section 23(1-A) from the date of notification till date of

award. By holding so, the Apex Court has held that the decision

3
(2002) 1 Supreme Court Cases 142
AKS,J & ETD,J
LAAS No.275_2014
9

laid down in M.A.Jabbar (supra 1) is the correct law, while the

decision rendered in Mathapathi Basavannewwa‘s case (supra 2)

has not been correctly laid down. Thus, the Apex Court has

finally held that the additional market value has to be awarded

from the date of notification till the date of award. Therefore, the

contention of the appellant’s counsel is valid and in conformity

with the law laid down by the Apex Court.

n) In view of foregoing discussion, in the present case, it is held

that the additional market value of 12% needs to be granted from

the date of notification but not from the date of possession.

12. POINT NO.3:

a) With regard to the interest that is to be awarded. It was held

in R.L.Jain v. DDA 4 that publication of notification is sine qua non

for any proceedings and if possession is taken prior to the issuance

of notification, it would not be in accordance with the Section 16 or

17 and it will be without any authority of law and consequently

cannot be recognized for the purposes of the Act. Therefore, if at

all any interest has to be awarded, it is from the date of

notification, but not from the date of dispossession. It was further

held that where possession is taken prior to the issuance of the

preliminary notification, it will be just and equitable that the

4
(2004) 4 SCC 79
AKS,J & ETD,J
LAAS No.275_2014
10

Collector may also determine the rent or damages for use of the

property to which the landowner is entitled while determining the

compensation amount payable to the landowner for the acquisition

of the property.

b) Further, in Tahera Khotoon v. Revenue Divisional

Officer 5, the decision of R.L.Jain (supra 4) was discussed and it

was further held that the rents/damages at the rate of 15% on the

compensation is to be awarded from the date the landowners were

dispossessed till the date of issuance of the preliminary

Notification.

c) In view of the law laid down by the Apex Court in R.L.Jain

(supra 4) and in Tahera Khotoon (supra 5), it is held that the

claimants would be entitled for the interest from the date of

dispossession. Point No.3 is answered accordingly.

13. POINT NO.4:

In view of the reasoned finding arrived at point No.1 to 3, the

order and decree dated 22.12.2011 passed in O.P.No.12 of 2006 by

the learned Senior Civil Judge at Nirmal need to be modified with

regard to the additional market value and the interest. The

Reference Court has awarded 12% of additional market value from

the date of possession till the date of award, which is not tenable in
5
(2014) 13 Supreme Court Cases 613
AKS,J & ETD,J
LAAS No.275_2014
11

the eye of law. Therefore, it is held that the claimants are entitled

for additional market value @ 12% per annum under Section

23(1-A) of the Act on the enhanced amount from the date of

notification till the date of award. The claimants are also entitled

to the interest @ 9% per annum from the date of dispossession for

the first one year and thereafter @ 15% per annum till the date of

realization.

14. POINT NO.5:

In the result, the appeal is partly allowed by modifying the

order and decree dated 22.12.2011 passed in O.P.No.12 of 2006 by

the learned Senior Civil Judge at Nirmal, to the extent of additional

market value and the rate of interest i.e. the claimants are entitled

to additional market value @ 12% per annum under Section

23 (1-A) of the act on the enhanced compensation from the date of

notification till the date of award and with regard to the interest

the claimants are entitled to the interest on the enhanced

compensation including solatium from the date of dispossession

@ 9% per annum for the first one year and thereafter @ 15% till the

date of realization. The remaining award so far as the

compensation awarded by the reference Court shall stand

confirmed. No costs.

AKS,J & ETD,J
LAAS No.275_2014
12

Miscellaneous Petitions pending, if any, shall stand closed.

________________________________
ABHINAND KUMAR SHAVILI, J

___________________________
TIRUMALA DEVI EADA, J
Date: 07.03.2025
ns



Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Share post:

Subscribe

spot_imgspot_img

Popular

More like this
Related