__________________________________________________________ vs Charan Dass on 1 March, 2025

0
30

Himachal Pradesh High Court

__________________________________________________________ vs Charan Dass on 1 March, 2025

( 2025:HHC:5826 )

IN THE HIGH COURT OF HIMACHAL PRADESH AT SHIMLA

LPA No: 68 of 2025
Decided on : 01.03.2025
__________________________________________________________
State of Himachal Pradesh and others
…. Appellants
Versus
Charan Dass
….Respondent
Coram
Hon’ble Mr. Justice G. S. Sandhawalia, Chief Justice.
Hon’ble Mr. Justice Ranjan Sharma, Judge.
1 Whether approved for reporting? Yes.
For the appellants: Mr. Pranay Pratap Singh,
Additional Advocate General.

For the respondents: Nemo.

Per Ranjan Sharma, Judge
CMP(M) No. 107 of 2025

State of Himachal Pradesh, being appellant,

has filed this application seeking condonation of

93 days delay in filing accompanying Letters

Patent Appeal, in assailing the judgement dated

13.08.2024, {referred as Impugned Judgement},

passed by Learned Single Judge in CWP No. 4226

of 2022.

Perusal of the application reveals that

appellant received intimation of passing of judgement

1 Whether reporters of Local Papers may be allowed to see the judgment?

-2- ( 2025:HHC:5826 )

dated 13.08.2024 from office of Advocate General

on 26.09.2024 and thereafter steps were taken by

Land Acquisition Collector and Executive Engineer,

Karsog on 28.09.2024 and then by Engineer-in-

Chief (PW), and the Govt, when, advice from Law

Department was received on 21.10.2024. Thereafter

the Appellant No 1-Secretary (PW) vide letter dated

30.11.2024 directed the official concerned to assail

the impugned judgement in LPA. Pursuant thereto,

steps were taken for drafting LPA by Executive

Engineer, Karsog and upon approval of the higher

authorities, LPA was vetted on 16.12.2024 and

was submitted to the office of learned Advocate

General on 18.12.2024. The draft LPA was vetted

and was finally filed before this Court on 02.01.

2025.

Upon listing of this application, this Court

accepts the reasons indicating sufficient cause, for

condoning delay of 93 days in filing accompanying

LPA, appears to be bonafide and even averments

are supported by an affidavit coupled with the fact

-3- ( 2025:HHC:5826 )

that the delay sought to be condoned is nominal

is accordingly condoned and the instant application

stands disposed of.

LPA No. 68 of 2025

Appellant-State has come up against the

judgement dated 13.08.2024 in CWP No. 4226 of

2022 in Re. Charan Dass versus State of Himachal

Pradesh and others, whereby Learned Single Judge

had allowed the writ petition and directed the

respondent-State Authorities to initiate the process

for acquiring subject land of the petitioner which

was utilized for construction of road inaccordance

with law within eight weeks from the date of passing

of judgement, with directions to appellants herein

to complete entire process within one year thereafter.

FACTUAL MATRIX LEADING TO PASSING OF
IMPUGNED JUDGEMENT

2. Writ petitioner, Charan Dass, invoked the

extraordinary jurisdiction of this Court seeking a

direction to the respondents to acquire his land

comprising in Khata Khatauni No. 61, Khasra Nos.

428 & 429, situated at Mohal Kot, Tehsil Karsog,

-4- ( 2025:HHC:5826 )

District Mandi and to pay him the compensation

in accordance with law. The above prayer was made

on the factual platform that the respondents had

constructed a link road i.e. Mahota-Bagshar Road

over and above the subject land of the petitioner

and neither land has been acquired nor any

compensation has been paid to petitioner whereas

State Authorities have acquired land and disbursed

compensation to other co-owners of adjoining land

parcel, namely, Bhoop Ram and Neem Chand in

pursuant to the judgements dated 24.06.2016

and 5.7.2016, passed in their respective petitions

i.e. CWP No. 2386 of 2009 (Bhoop Ram versus

State of Himachal Pradesh and others) and CWP

No 3090 of 2009 (Neem Chand versus State of

Himachal Pradesh). Incompliance thereto, acquisition

proceedings were initiated by State Authorities and

utilized lands were acquired and compensation was

released in terms of the Award dated 22.02.2022

[Annexure P-2 Colly]. After passing of award in

case of Bhoop Ram and Neem Chand supra,

-5- ( 2025:HHC:5826 )

the writ petitioner submitted representation on

21.4.2022 for similar benefits, on which the Land

Acquisition Collector vide communication dated

27.04.2022 directed the Executing Engineer, HPPWD

Division Karsog, District Mandi to take appropriate

action and even Special Secretary [Public Works]

vide office letter dated 04.05.2022 directed Executive

Engineer concerned to take necessary action in the

matter but in vain.

STAND OF THE STATE AUTHORITIES IN WRIT
PROCEEDINGS:

3. State Authorities filed a reply-affidavit

admitting that Mahota-Bagshar Road was constructed

under Pradhan Mantri Gram Sadak Yojna [in short

PMGSY] and the construction of the road was

completed before February, 2009, which includes

land of petitioner also. However, State Authorities

took a stand that road was constructed on the

verbal consent of petitioner and the writ petitioner

never objected to the construction of road and

therefore, no compensation was to be paid. It is

-6- ( 2025:HHC:5826 )

averred in reply that under Pradhan Mantri Gram

Sadak Yojna [in short PMGSY] there is no provision

for acquisition of land or payment of compensation.

The plea of delay and laches was also raised by

State Authorities.

IMPUGNED JUDGEMENT:

4. Learned Single Judge dealt with the

contentions in Reply Affidavit of State Authorities

in the judgement dated 13.08.2024. In Para 5(i) &

(iii), Learned Single Judge recorded a finding that

benefit of acquisition and compensation has been

accorded by the State Authorities to co-owners of

adjoining lands, namely, Bhoop Ram and Neem

Chand in terms of the Award No 5/2022 dated

22.02.2022 passed by Competent Authority. Based

on these facts, Learned Single Judge had recorded

a categorical finding that once the co-owners of

adjoining land, namely, Bhoop Ram and Neem

Chand, have been released compensation for lands

utilized for construction of road then, the petitioner

deserves same treatment whose land was also

-7- ( 2025:HHC:5826 )

utilized for construction of the same very road.

Learned Single Judge relied upon the judgement

in Para 5(iii) in the case of Labdhu Ram versus

State of Himachal Pradesh and others, CWP

No. 6581 of 2021 that once benefit of acquisition

and resultant compensation for utilizing the land

for construction of road had been accorded to

some land owners then similar benefit is to

be extended to others also. So far as the objection

of State Authorities-Appellant herein that Pradhan

Mantri Gram Sadak Yojna [in short PMGSY] did

not provide for acquisition and compensation in

case of roads are to be constructed under Pradhan

Mantri Gram Sadak Yojna [in short PMGSY] was

dealt with by Learned Single Judge in Para 5

(iv) negating the stand of State in view of the

Full Bench judgement of this Court in State of

Himachal Pradesh and others versus Sita Ram

Sharma, {LPA No. 33 of 2021 decided on 30.3.2022}.

Learned Single Judge categorically held that in

case, the land has been utilized for construction

-8- ( 2025:HHC:5826 )

of road under Pradhan Mantri Gram Sadak

Yojna [in short PMGSY] then also, the landowners

are entitled for compensation unless it is proved

to the satisfaction of the Court that the land

was voluntarily donated or given by private land

owners willingly, which consent/willingness has

to be in writing and same has to be substantiated

by material on record. In this background, since

State Authorities have failed to establish that the

land was voluntarily donated/given by petitioner

for construction of road, the plea of the petitioner

was negated. While dealing with the contention

of State Authorities that claim of writ petitioner

suffers from delay and laches, was repelled by

Learned Single Judge by relying upon various

judgements in Para 5(iii) including the judgement

of Hon’ble Supreme Court in Sukh Dutt Ratra

and another versus State of Himachal Pradesh

and others, (2022) 7 SCC 508, with the findings

that the State cannot evade its legal responsibility

towards those from whom private property has

-9- ( 2025:HHC:5826 )

been expropriated. Even the State cannot shirk

its responsibility of acquiring land for public use

without paying compensation by taking the plea

of limitation for doing justice. Based on aforesaid

reasoning, the Learned Single Judge allowed the

writ petition, in terms of the Impugned judgement

dated 13.08.2024.

5. Upon listing of the matter, Learned State

Counsel has vehemently argued on merits but

by reiterating almost the same contentions, which

stood repelled by Learned Single Judge in the

Impugned judgement. In these circumstances, this

Court, upon hearing the Learned State Counsel

for the appellants herein, proceeds to hear the

appeal, at this stage.

6. Before dealing with the contentions of

Learned State Counsel for the appellants, it is

necessary to have a recap of the mandate of law

on the right to property of a person and its

regime.


6(i).         Based on the principle of eminent domain
                               - 10 -              ( 2025:HHC:5826 )


at relevant time, Article 30(1-A) and provisos to

Article 31-A (1) of the Constitution of India

recognised the right to property and the right of

a person to acquire, hold and dispose of property

was conferred the status of a fundamental right.

However, keeping in view the directive principles

of state policy, the right of property which was

a fundamental right, after the enactment of the

44th amendment in 1978, introducing Article 300-A

in the Constitution of India mandating that “no

person shall be deprived of his property save by

authority of law” was recognised as a “constitutional

right”.

6(ii). Consequent upon being recognised as a

constitutional right, a question arose as to whether

a person can be deprived of his property, save

by authority of law under Article 300-A, merely

by an executive fiat but without any specific

legal authority or without sanctity of law made

by a competent legislature was answered by the

Constitutional Bench of the Hon’ble Supreme Court

– 11 – ( 2025:HHC:5826 )

in K. T. Plantation Private Limited and another

versus State of Karnataka, (2011) 9 SCC 01

mandating that the deprivation of property under

Article 300-A must be for a public purpose and

the same cannot be by an executive fiat but

such deprivation can take place only by operation

of law, which has to be lawful, fair and which

does not undermine the rule of law, failing which

any such law shall be subject to judicial review,

in the following terms:

168. Article 300-A proclaims that no person
can be deprived of his property save by
authority of law, meaning thereby that a
person cannot be deprived of his property
merely by an executive fiat, without any
specific legal authority or without the support
of law made by a competent legislature.

The expression ‘Property’ in Art. 300-A confined
not to land alone, it includes intangibles
like copyrights and other intellectual property
and embraces every possible interest recognised
by law.

169. This Court in State of W. B. & Others
v. Vishnunarayan & Associates (P) Ltd &
Another
(2002) 4 SCC 134, while examining
the provisions of the West Bengal Great
Eastern Hotel (Acquisition of Undertaking)
Act, 1980
, held in the context of Article 300-A
that the State or executive offices cannot
interfere with the right of others unless
they can point out the specific provisions
of law which authorises their rights.

– 12 – ( 2025:HHC:5826 )

170. Article 300-A, therefore, protects private
property against executive action. But
the question that looms large is as to
what extent their rights will be protected
when they are sought to be illegally deprived
of their properties on the strength of a
legislation. Further, it was also argued that
the twin requirements of ‘public purpose’
and ‘compensation’ in case of deprivation of
property are inherent and essential elements
or ingredients, or “inseparable concomitants”

of the power of eminent domain and,
therefore, of entry 42, List III, as well and,
hence, would apply when the validity of a
statute is in question.

171. On the other hand, it was the contention
of the State that since the Constitution
consciously omitted Article 19 (1) (f), Articles
31(1)
and 31(2), the intention of the Parliament
was to do away the doctrine of eminent
domain which highlights the principles of
public purpose and compensation.

172. Seervai in his celebrated book
‘Constitutional Law of India’ (Edn. IV), spent
a whole Chapter XIV on the 44th Amendment,
while dealing with Article 300A. In paragraph
15.2 (pages 1157-1158) the author opined
that confiscation of property of innocent people
for the benefit of private persons is a
kind of confiscation unknown to our law
and whatever meaning the word “acquisition”
may have does not cover “confiscation” for,
to confiscate means “to appropriate to the
public treasury (by way of penalty)”.
Consequently, the law taking private property
for a public purpose without compensation
would fall outside Entry 42 List III and cannot
be supported by another Entry in List III.

173. Requirements of a public purpose and
the payment of compensation according to
the learned author be read into Entry 42
List III. Further the learned author has also
opined that the repeal of Article 19(1)(f) and
31(2) could have repercussions on other

– 13 – ( 2025:HHC:5826 )

fundamental rights or other provisions which
are to be regarded as part of the basic
structure and also stated that notwithstanding
the repeal of Article 31(2), the word
“compensation” or the concept thereof is still
retained in Article 30 (1A) and in the second
proviso to Article 31A (1) meaning thereby,
that payment of compensation is a condition
of legislative power in Entry 42 List III.

174. Learned senior counsel Shri T.R.
Andhyarujina, also referred to the opinion
expressed by another learned author Prof.
P.K. Tripathi, in his article “Right to Property
after 44th Amendment – Better Protected
than Ever Before” (reported in AIR 1980 J pg. 49-

52). Learned author expressed the opinion
and the right of the individual to receive
compensation when his property is acquired
or requisitioned by the State, continues
to be available in the form of an implied
condition of the power of the State to
legislate on “acquisition or requisition of
property” while all the exceptions and limitations
set up against and around it in Article
31
, 31A and 31B have disappeared.

Learned author opined that Article 300-A
will require obviously, that the law must be
a valid law and no law of acquisition or
requisitioning can be valid unless the acquisition
or requisition is for a public purpose, unless
there is provision in law for paying compensation,
will continue to have a meaning given to
it, by Bela Banerjee’s case (supra).

175. Learned author, Shri S.B. Sathe, in
his article “Right to Property after the 44th
Amendment” (AIR 1980 Journal 97), to some
extent, endorsed the view of Prof. Tripathi
and opined that the 44th amendment has
increased the scope of judicial review in
respect of right to property. Learned author
has stated although Article 300A says that
no one shall be deprived of his property
save by authority of law, there is no
reason to expect that this provision would

– 14 – ( 2025:HHC:5826 )

protect private property only against executive
action. Learned author also expresses the
wish that Article 21 may provide viable
check upon Article 300A.

176. Durga Das Basu in his book “Shorter
Constitution of India”, 13th Edition, dealt
with Article 300A in Chapter IV wherein
the learned author expressed some reservation
about the views expressed by Seervai, as
well as Prof. Tripathi Learned author expressed
the view, that after the 44th amendment Act
there is no express provision in the Constitution
outside the two cases specified under Article
30(1A)
and the second proviso to 31(1A)
requiring the State to pay compensation to
an expropriated owner. Learned author also
expressed the opinion that no reliance could
be placed on the legislative Entry 42
of List III so as to claim compensation on
the touchstone of fundamental rights since
the entry in a legislative list does not confer
any legislative power but only enumerates
fields of legislation.

177. Learned counsel on the either side,
apart from other contentions, highlighted the
above views expressed by the learned authors
to urge their respective contentions.

178. Principles of eminent domain, as
such, is not seen incorporated in Article
300A
, as we see, in Article 30(1A), as well
as in the 2nd proviso to Article 31A(1)
though we can infer those principles in
Article 300A. Provision for payment of
compensation has been specifically incorporated
in Article 30(1A) as well as in the 2nd
proviso to Article 31A(1) for achieving specific
objectives. Constitution’s 44th Amendment
Act, 1978
while omitting Article 31 brought
in a substantive provision Clause (1A) to
Article 30. Resultantly, though no individual
or even educational institution belonging
to majority community shall have any
fundamental right to compensation in case
of compulsory acquisition of his property

– 15 – ( 2025:HHC:5826 )

by the State, an educational institution
belonging to a minority community shall have
such fundamental right to claim compensation
in case State enacts a law providing for
compulsory acquisition of any property of
an educational institution established and
administered by a minority community. Further,
the second proviso to Article 31 A (1)
prohibits the Legislature from making a
law which does not contain a provision for
payment of compensation at a rate not
less than the market value which follows
that a law which does not contain such
provision shall be invalid and the acquisition
proceedings would be rendered void.

179. Looking at the history of the various
constitutional amendments, judicial
pronouncements and the statement of objects
and reasons contained in the 44th Amendment
Bill which led to the 44th Amendment
Act we have no doubt that the intention
of the Parliament was to do away with the
fundamental right to acquire, hold and
dispose of the property. But the question
is whether the principles of eminent domain
are completely obliterated when a person
is deprived of his property by the authority
of law under Article 300 A of the Constitution.

Public purpose

180. Deprivation of property within the
meaning of Art. 300-A, generally speaking,
must take place for public purpose or public
interest. The concept of eminent domain
which applies when a person is deprived
of his property postulates that the purpose
must be primarily public and not primarily
of private interest and merely incidentally
beneficial to the public. Any law, which
deprives a person of his private property
for private interest, will be unlawful and
unfair and undermines the rule of law
and can be subjected to judicial review.
But the question as to whether the purpose
is primarily public or private, has to be

– 16 – ( 2025:HHC:5826 )

decided by the legislature, which of course
should be made known.

6(iii). Another question arose before the Hon’ble

Supreme Court in the case of K.T. Plantation

(supra) as to whether a person who is deprived

of property for public purpose is entitled to

get compensation has to be justified by the

State on judicially justifiable standards depending

upon the law formulated by a State, which has

to be just, fair and reasonable. In case, State

enactment provides for acquiring a private property

for public purpose for no compensation or nil

compensation then, the Court in exercise of

judicial review will test such a law, as mandated

in the following terms:

183. Payment of compensation amount
is a constitutional requirement under Article
30(1A)
and under the 2nd proviso to Article
31A(1)
, unlike Article 300A. After the 44th
Amendment Act, 1978, the constitutional
obligation to pay compensation to a person
who is deprived of his property primarily
depends upon the terms of the statute
and the legislative policy. Article 300-A,
however, does not prohibit the payment of
just compensation when a person is deprived
of his property, but the question is whether
a person is entitled to get compensation,
as a matter of right, in the absence of

– 17 – ( 2025:HHC:5826 )

any stipulation in the statute, depriving
him of his property.

189. Requirement of public purpose, for
deprivation of a person of his property under
Article 300A, is a pre-condition, but no
compensation or nil compensation or its
illusiveness has to be justified by the state
on judicially justiciable standards. Measures
designed to achieve greater social justice,
may call for lesser compensation and such
a limitation by itself will not make legislation
invalid or unconstitutional or confiscatory.

In other words, the right to claim compensation
or the obligation to pay, though not expressly
included in Article 300A, it can be inferred
in that Article and it is for the State
to justify its stand on justifiable grounds
which may depend upon the legislative policy,
object and purpose of the statute and host
of other factors.

190. Article 300A would be equally violated if
the provisions of law authorizing deprivation of
property have not been complied with. While
enacting Article 300A Parliament has only
borrowed Article 31(1) [the “Rule of law” doctrine]
and not Article 31(2) [which had embodied the
doctrine of Eminent Domain]. Article 300A
enables the State to put restrictions on
the right to property by law. That law
has to be reasonable. It must comply
with other provisions of the Constitution.
The limitation or restriction should not
be arbitrary or excessive or what is beyond
what is required in public interest.
The limitation or restriction must not
be disproportionate to the situation or
excessive.

191. The legislation providing for deprivation
of property under Article 300A must be “just,
fair and reasonable” as understood in
terms of Articles 14, 19(1)(g), 26(b), 301, etc.
Thus in each case, courts will have to
examine the scheme of the impugned Act,
its object, purpose as also the question

– 18 – ( 2025:HHC:5826 )

whether payment of nil compensation or
nominal compensation would make the
impugned law unjust, unfair or unreasonable
in terms of other provisions of the
Constitution as indicated above.

192. At this stage, we may clarify that
there is a difference between “no” compensation
and “nil” compensation. A law seeking to
acquire private property for public purpose
cannot say that “no compensation shall
be paid”. However, there could be a law
awarding “nil” compensation in cases where
the State undertakes to discharge the liabilities
charged on the property under acquisition
and onus is on the government to establish
validity of such law. In the latter case,
the court in exercise of judicial review will
test such a law keeping in mind the
above parameters.

198. Article 300 A, unlike Articles 31A(1)
and 31C, has not made the legislation
depriving a person of his property immune
from challenge on the ground of violation
of Article 14 or Article 21 of the Constitution
of India, but let us first examine whether
Article 21 as such is available to challenge
a statute providing for no or illusory
compensation and, hence, expropriatory.

6(iv). Reference in the case of K. T. Plantation

(supra) was answered by the Supreme Court

mandating that public purpose is a pre-condition

for depriving a person from his property under

Article 300-A and right to claim compensation

is also inbuilt under that Article and when a

person is deprived of his property the State has

– 19 – ( 2025:HHC:5826 )

to justify such deprivation on the basis of the

statute or legislative policy and its object and

purpose and other related factors.

6(v). The judgement in K. T. Plantation‘s case

was followed by the Hon’ble Supreme Court in

Association of Vasanth Apartments’ Owners versus

V. Gopinath and others, 2023 SCC OnLine

SC 137, Civil Appeal No. 1890-91 of 2010, decided

on 13.02.2023 that illegal deprivation is attracted

where a person is deprived of his property, in case

of “no compensation” in the following terms:

118. The Court also reiterated the distinction
between ‘no compensation’ and ‘Nil
compensation’, as laid down in K.T. Plantations
(supra). The Court proceeded to find that
it was a case of ‘no compensation’ at all,
and therefore, it attracted the vice of
illegal deprivation of property and gave
relief on the said basis. This is after finding
that the property in question was a productive
asset.

144. An acquisition is a compulsory vesting
of the property of a person with the state.
It is traceable undoubtedly to the power of
eminent domain assured to every sovereign.
It can undoubtedly be exercised only for
securing public interest as contrasted with
promotion of private interest (See K.T. Plantation
(supra).

145. K.T. Plantations (supra) was a case
which involved the validity of a law which

– 20 – ( 2025:HHC:5826 )

provided for compulsory acquisition under
the State enactment. The understanding of
this Court in K.T. Plantations (supra) was
that a person cannot be deprived of his
property merely by executive fiat without
any specific legal authority or without
support of law made by a competent
Legislature (See paragraph-168). We must
notice here that law for the scope of Article
300A
has been explained by this Court
in Bishambhar Dayal Chandra Mohan and
others v. State of Uttar Pradesh and others

as follows:

“41. There still remains the question
whether the seizure of wheat amounts to
deprivation of property without the
authority of law. Article 300-A provides
that no person shall be deprived
of his property save by authority of
law. The State Government cannot while
taking recourse to the executive power
of the State under Article 162, deprive
a person of his property. Such power
can be exercised only by authority
of law and not by a mere executive
fiat or order. Article 162, as is clear
from the opening words, is subject to
other provisions of the Constitution.
It is, therefore, necessarily subject to
Article 300-A. The word “law” in the
context of Article 300-A must mean
an Act of Parliament or of a State
legislature, a rule, or a statutory
order, having the force of law, that
is positive or State made law. The
decisions in Wazir Chand v. State of
H.P.
[AIR 1954 SC 415: (1955) 1 SCR
408 : 1954 SCJ 600 : 1954 Cri LJ 1029]
and Bishan Das v. State of Punjab
[AIR 1961 SC 1570 : (1962) 2 SCR
69 : (1963) 1 SCJ 405] are an authority
for the proposition that an illegal seizure
amounts to deprivation of property
without the authority of law…..”.

– 21 – ( 2025:HHC:5826 )

146. What this Court in K. T. Plantations
(supra) meant was to distinguish ‘law’ as
a legislative measure as distinct from mere
Executive fiat.

6(vi). Right for compensation in case property

of a private owner is utilized by the State has

been answered by the Hon’ble Supreme Court in

Ultra-tech Cement Limited versus Mast Ram

and others, (2025) 1 SCC 798, Civil Appeal No.

10662 of 2024 decided on 20.09.2024 in the

following terms:

52. Acquisition of land for public purpose
is undertaken under the power of eminent
domain of the government much against
the wishes of the owners of the land which
gets acquired. When such a power is
exercised, it is coupled with a bounden duty
and obligation on the part of the government
body to ensure that the owners whose
lands get acquired are paid compensation
/awarded amount as declared by the statutory
award at the earliest.

6(vii). The intent and object of Article 300-A

having been outlined by the Hon’ble Supreme Court in

K.T. Plantation, V. Gopinath and in Ultra-tech

Cement Limited (supra), this Court on the basis

of existing material on record is of the considered

view, that the appellant-State Authorities have not

– 22 – ( 2025:HHC:5826 )

pointed out any law enacted by State Legislature

empowers the State to divest a person of his land

without paying compensation. In absence of any

statute having been enacted by State [which has

not placed before this Court], the action of State

Authorities in divesting the Writ petitioner-Charan

Dass of his private property and by utilizing

his land(s) for construction of Mahota-Bagshar Road

under Pradhan Mantri Gram Sadak Yojna package

2003-2004, for which the work commenced in

the year 2005 and was completed in the year

2009 and moreover, when, pursuant to judicial

intervention, once the lands of landowners having

adjoining lands, namely, Bhoop Ram and Neem

Chand stood acquired and compensation stands

released by way of an Award dated 22.2.2022

then, this Court sees no reason as to why the

writ petitioner be not held entitled for similar

compensation. Even the action of the State that

land of writ petitioner and others were utilized

for construction of Road under a Scheme (in short

– 23 – ( 2025:HHC:5826 )

PMGSY} cannot come to the rescue of the State

when, in Para 27 of the Full Bench judgement

of this Court in case of State of Himachal Pradesh

versus Sita Ram {LPA No 33 of 2021 dated 30.3.2022}

the reference stands answered that there is no

provision in PMGSY Guidelines for depriving private

land owners of property without consent and without

giving them compensation. In these circumstances,

the State Authorities cannot by way of an executive

fiat divest the writ petitioner-Charan Dass of his

private land(s), without his consent and without

paying compensation and by utilizing such land

for construction of road in question, and such

expropriation of property, by the State, without

any sanction of law visits a landowner with civil

consequences, depriving him of the right to use

his own property and action confers a continuing

cause to a landowner to claim compensation.

Even the whimsical and anarchical manner of

depriving the landowner-writ petitioner of property

and right of compensation shocks the conscience

– 24 – ( 2025:HHC:5826 )

of this Court. Accordingly, the judgment passed

by Learned Single Judge after noticing the material

on record and the factual and the legal aspects

herein, does not require any interference in instant

appeal.

7. CONTENTION OF STATE AUTHORITIES IN
INSTANT APPEAL:

First contention of Learned State Counsel

for the appellant is that the land of writ petitioner-

Charan Dass herein, was utilized for construction

of road i.e. Mahota-Bagshar Road upon giving a

verbal consent and even the writ petitioner did not

object to cutting of road in the year 2005 till

its completion in February, 2009.

7(i). Above contention of the appellant is

ex facie not tenable, for the reason, that the State

Authorities have not produced any material on

record either before the writ court or even in

these proceedings that the writ petitioner had given

consent for construction of the said road.


7(ii).      Plea    as    set-up         in    instant     appeal    by
                              - 25 -             ( 2025:HHC:5826 )


State Authorities denying claim for compensation

by asserting that the land was utilized on the

oral consent of land owner-petitioner stands negated

by the Full Bench of this Court, in Shankar

Dass alias Shankru versus State of Himachal

Pradesh and others in CWP No. 1966 of 2010-C

decided on 2.3.2013 [2013 SCC OnLine HP 681],

mandating that that the oral consent cannot be

presumed until some evidence of consent either

in form of letter, writing or signatures on a

representation for construction of road is placed

on record and in these circumstances, the plea

of oral consent is not tenable, in the following

terms:

51. On the question of consent, I am of
the considered view that after the judgement
in Nokhia’s case, quoted hereinabove, the
State should not have constructed roads
without taking consent in writing from the
land owners. If the State did so, it did at
its own peril. his Court had issued clear
cut directions which have held the field since
1984 that the State should ensure that
roads are constructed only after the land
owners give informed consent.

52. Oral consent cannot be presumed
in the case of poor persons or those living
in rural or remote areas. In cases where parties

– 26 – ( 2025:HHC:5826 )

are rich and educated and they do not
approach this Court within a reasonable period,
then the Writ Court may direct them to
approach the Civil Court. But in cases where
people are poor and uneducated, it would
invariably be better to take a more liberal
view.

53. The State also cannot plead consent
or implied consent only on the basis that
the road had been constructed. There must
be some better evidence in this regard. If
some evidence of consent, either in the
form of letter, writing or signatures on
a representation for construction of road,
is placed before this Court, then this
Court may not exercise its writ jurisdiction
and direct the party to approach the Civil
Court. But if the only sort of consent
pleaded is the implied consent due to
construction of road, then this Court
may entertain the writ petition.

7(iii). Similar plea of divesting a land private

owner of his lands and in utilizing it for the

construction of road without paying compensation,

by taking the “plea of consent of land owner(s)”

was repelled by the Hon’ble Supreme Court in

Raj Kumar versus State of Himachal Pradesh

and others, SLP (C) No. 2373 of 2014 [arising

from LPA No 285 of 2012], decided on 29.10.2015,

in the following terms:

Appearing for the appellant, Mr. Anil
Nag, learned counsel for the appellant argued
that the High Court was in error in declining

– 27 – ( 2025:HHC:5826 )

to intervene and grant relief prayed for by
the appellant. It was submitted that the case
of the appellant was no different from that of
Kanwar Singh in whose case the High Court
had not only issued a Mandamus for
acquisition of the land utilised for the very
same purpose but order so passed had been
complied with by the State by not only
initiating the proceedings but even determining
and paying compensation lawfully due and
payable to them. In the case of the appellant
also the State had on its own initiated
proceedings for acquisition of land but the
said proceedings were allowed to lapse ostensibly
because the road in question had subsequently
been taken over under the Pradhan Mantri
Gram Sadak Yojna which did not provide
for payment of compensation to the land
owners whose lands were utilised for such
projects. It was urged that the utilisation of
the land for construction of the road was
not in dispute before the High Court as was
evident from the counter affidavit filed to the
writ petition. There was therefore no question
of directing the appellant to approach the
Civil Court for adjudication of any disputed
question of fact. It was also submitted that
the transfer of the road to the Pradhan Mantri
Sadak Yojna for maintenance etc. was no
reason why the owners whose land had
been utilised should have been denied the
payment of compensation otherwise due to
them. It was urged that the State had never
claimed that the erstwhile owner of the land
and the predecessor in interest of the
appellant herein had made any formal or
informal donation of the land in favour
of the State to facilitate the construction
of the road. In the absence of even an
assertion that the road was constructed
on the invitation of the erstwhile owner,
the High Court was in error in declining
to grant relief to the appellant who had
lost his valuable land and thereby the
source of livelihood. The remedy in a civil
court was neither speedy nor efficacious. It

– 28 – ( 2025:HHC:5826 )

was urged that the appellant would be satisfied
in case the actual extent of land utilised
by the State out of his ownership is verified
by the Collector and compensation determined
in Kanwar Singh’s case under Award No. 10
of 2008 directed to be paid to the appellant
depending upon the classification of the
land that has been utilised by the State
Government. It is urged that the appellant
would keeping in view the intervening delay
give up his right to claim compensation for
the user of the land without acquisition and
payment of statutory interest recoverable
on the said amount. This would according
to the learned counsel not only serve the
ends of justice but also prevent any further
litigation in the matter. It was submitted that this
Court could in the peculiar facts and
circumstances of this case and with a view
to giving a quietus to the entire controversy
make a suitable order that would meet the
ends of justice.

There is in our opinion considerable
merit in the submission made by Mr. Nag.
It is true that the appellant had approached
the High Court rather belatedly inasmuch
the land had been utilised some time in
the year 1985-86 while the writ petition
was filed by the appellant in the year 2009.
At the same time it is clear from the
pleadings in the case at hand that the user
of the land owned by the appellant is
not denied by the State in the counter affidavit
filed before the High Court or that filed
before us. It is also evident from the
averments made in the counter affidavit
that the State has not sought any donation
in its favour either by the appellant or
his predecessor in interest during whose
life time the road in question was
constructed. All that is stated in the
counter affidavit is that the erstwhile owner
of the land “might have donated” the
land to the State Government. In the absence
of any specific assertion regarding any

– 29 – ( 2025:HHC:5826 )

such donation or documentary evidence
to support the same, we are not inclined
to accept the ipsit dixit suggesting any
such donation. If that be so as it indeed
is, we fail to appreciate why the State should
have given up the land acquisition proceedings
initiated by it in relation to the land of the
appellant herein. The fact that the State
Government had initiated such proceedings
is not in dispute nor is it disputed that the
same were allowed to lapse just because
the road had in the meantime been taken
under the Pradhan Mantri Gram Sadak Yojna.
It is also not in dispute that for the
very same road the land owned by Kanwar
Singh another owner had not only been
notified for acquisition but duly paid
for in terms of Award No. 10 of 2008.

7(iv). Plea of State Authorities that land was

utilized on the basis of the oral consent given by

land-owner(s) was negated by the Hon’ble Supreme

Court, in Vidya Devi versus State of Himachal

Pradesh and others, (2020) 2 SCC 569, which

reads as under:

12.7. In this case, the appellant could not
have been forcibly dispossessed of her property
without any legal sanction and without
following due process of law and depriving
her payment of just compensation, being a
fundamental right on the date of forcible
dispossession in 1967.

12.8. The contention of the State that the
appellant or her predecessors had “orally”

consented to the acquisition is completely
baseless. We find complete lack of authority
and legal sanction in compulsorily divesting
the appellant of her property by the

– 30 – ( 2025:HHC:5826 )

State.

7(v). In Sukh Dutt Ratra and another versus

State of Himachal Pradesh and others, (2022)

7 SCC 508, {i.e. CA No 2773 of 2022}, the Hon’ble

Supreme Court has held that in absence of any

material on record, the plea of verbal consent

or the fact that land owner did not raise any

objection cannot be used to deny compensation, in

the following terms:

21. Having considered the pleadings filed, this
court finds that the contentions raised by
the State, do not inspire confidence and
deserve to be rejected. The State has merely
averred to the appellants’ alleged verbal
consent or the lack of objection, but has not
placed any material on record to substantiate
this plea. Further, the State was unable to
produce any evidence indicating that the
land of the appellants had been taken over
or acquired in the manner known to law,
or that they had ever paid any compensation.

It is pertinent to note that this was the
State’s position, and subsequent findings of
the High Court in 2007 as well, in the other
writ proceedings.

22. This court is also not moved by the
State’s contention that since the property
is not adjoining to that of the appellants,
it disentitles them from claiming benefit on
the ground of parity. Despite it not being
adjoining (which is admitted in the rejoinder
affidavit filed by the appellants), it is clear
that the subject land was acquired for
the same reason-construction of the Narag

– 31 – ( 2025:HHC:5826 )

Fagla Road, in 1972-73, and much like the
claimants before the reference court, these
appellants too were illegally dispossessed
without following due process of law, thus
resulting in violation of Article 31 and
warranting the High Court’s intervention under
Article 226 jurisdiction. In the absence of
written consent to voluntarily give up their
land, the appellants were entitled to
compensation in terms of law. The need for
written consent in matters of land acquisition
proceedings, has been noted in fact, by
the full court decision of the High Court
in Shankar Dass (supra) itself, which is
relied upon in the impugned judgment.

7(vi). The judgement in the case of Sukh

Dutt Ratra (supra) was again taken in Review

Petition (Civil) Diary No. 7253 of 2023 titled as

The State of Himachal Pradesh and others

versus Sukh Dutt Ratra, resulting in dismissal of

review petition on 03.08.2023 in the following

terms:

Review Petition (Civil) Diary No 7253 /2023

“Delay condoned.

Instant petition has been filed by the petitioners
for review of order dated 6.4.2022 passed by
this Court in CA No 2773 of 2022.

Having carefully perused the petition for
review and the papers connected therewith,
we do not find any reason for reconsideration
of the above mentioned order.

The Review petition is accordingly dismissed.”

– 32 – ( 2025:HHC:5826 )

Thus, taking into account the material

on record in the writ proceedings and even in

instant Letters Patent Appeal, this Court is of

the considered view, that the State Authorities have

not placed any material on record to substantiate

the plea of verbal consent by writ petitioner(s)-

private land owner and in absence of any proof

of “consent on the basis of cogent and concrete

evidence-material” the action of the State Authorities

in depriving the landowner-writ petitioner of his

land(s) and in divesting a land owner of the right

to get compensation for his lands but in utilizing

such land for the construction of road, being

without sanction of law does not stands the test

of judicial scrutiny. In absence of any material,

the contention of Learned State Counsel is

misconceived on facts and also in view of the

mandate of law in the case of Shankar Dass, Raj

Kumar, Vidya Devi and Sukh Dutt Ratra (supra).

8. Second contention of the Learned State

Counsel that the Mahota-Bagshar Road was

– 33 – ( 2025:HHC:5826 )

constructed under Pradhan Mantri Gram Sadak

Yojna [in short PMGSY] under the package for

the year 2003-2004 and the land of the writ

petitioner and others was utilized but since there

is no provision in Pradhan Mantri Gram Sadak

Yojna [in short PMGSY] guidelines for acquiring

land and for payment of compensation, therefore,

compensation could not be given to the writ

petitioner.

8(i). The above plea of the Learned State

Counsel does not stand the test of judicial scrutiny

for the reason that a reference was formulated

as to whether a person whose land was utilized

for construction of road under Pradhan Mantri

Gram Sadak Yojna [in short PMGSY] is entitled

to compensation has been answered by the Full

Bench of this Court in LPA No. 33 of 2021,

State of Himachal Pradesh and others versus

Sita Ram, decided on 30.03.2022 in the following

terms:

26. In view of the afore discussed law,

– 34 – ( 2025:HHC:5826 )

it must be held that even after the right of
property enshrined under Article 19(I) (f) was
deleted by the 44th amendment to the
Constitution, Article 300A still retains the
right to property as the constitutional right
as well as legal right and mandates that no
person can be deprived of his property
except by authority in law. Action of the
State in dispossessing a citizen of his private
property, without following the due process
of law, would be violative of Article 300A
of the Constitution of India, as also
negate his human right. Right to property
has thus been acknowledged, not only
constitutional as well as statutory, but also
human right, to be construed in the realm
of individual rights, such as right to health,
livelihood, shelter, employment etc. in a
Welfare State. The State Authorities cannot
dispossess any citizen of his property except
in accordance with the procedure established
by law, that too by due process of law
and by acquiring land and paying adequate
compensation.

27. The PMGSY Guidelines issued in April,
2012 clearly envisaged that land has to
be provided by the State Authorities for
construction of roads under that Scheme,
but under PMGSY, no provision has been made
for payment of compensation or acquiring the
land. Either the State Government has to provide
land by acquiring the land out of its own
resources, or by persuading the citizens to
voluntarily donate land or provide the land
in exchange of some other land given to
them by the State or by devising any other
mechanism as may be considered appropriate
to ensure availability of the land. Even the
PMGSY Guidelines also do not envisage
taking possession of the land of the citizen
without his consent and without payment
of due amount of compensation. It is however
another matter if the citizen voluntarily
surrenders his land, but the factum of
voluntariness on his part and free consent

– 35 – ( 2025:HHC:5826 )

to part with possession of such land, has
to be established by cogent and reliable
material/evidence if and when such an
action is called in question. Whether or
not someone has voluntarily donated the
land or has given his land in exchange of
another land provided to him by the State
or parted with possession of the land by
any other mechanism, are all questions
to be decided on facts of each case.

30. The judgments of this Court in Laiq
Ram Dogra and Bhoop Ram, in the facts of
those cases have been decided correctly by
relying on the decision of Supreme Court
in Raj Kumar‘s case. The Supreme Court
in Raj Kumar was also dealing with
the case where initially the process for
acquisition of land was started, but the
proceedings were allowed to lapse, as
subsequently the road, in question, was taken
over under the PMGSY, which did not
provide for compensation for land owners,
if land was utilized for such projects. The
Supreme Court rejected the argument that
such land owners should be directed to
approach the Civil Court for adjudication
of the disputed questions of facts. It held
that there was no reason as to why the
owners whose land had been utilized for
construction of road under PMGSY should
be denied payment of compensation. The
Supreme Court in that case also observed
that the appellant had approached the High
Court rather belatedly inasmuch as the
land had been utilized sometime in the year
1985-1986 and the writ petition was filed
by the appellant in the year, 2009. But
at the same time, the Supreme Court noted
that the user of the land owned by the
appellant was not denied by the State
in the counter-affidavit filed before the High
Court or even before the Supreme Court.

The plea that the erstwhile owner of the
land might have donated the land to the
State Government, was not accepted in the

– 36 – ( 2025:HHC:5826 )

absence of any specific assertion regarding
any such donation or documentary evidence
to support the same. Against the backdrop
of these facts, the Supreme Court directed
the Collector Solan to verify the exact land
utilized for construction of road and determine
the amount of compensation and pay the
same to the land owners.

32. In view of above, the question referred
to by the Division Bench, is, therefore,
answered in the affirmative that a person
whose land has been utilized for construction
of road under PMGSY is entitled to
compensation unless it is proved to the
satisfaction of the Court that the land was
voluntarily donated or given by him willingly
with free will and consent for construction
of such road.

8(ii). Pursuant to Full Bench judgement in

LPA No. 33 of 2021 decided on 30.03.2022 in

the case of Sita Ram (supra) the Division Bench

of this Court, dismissed the state appeal titled

as State of Himachal Pradesh versus Sita Ram

on 3.11.2022, in the following terms:

4. During the course of hearing of the
appeal, one of the moot questions arose
as to whether a person(s) whose land(s)
has been utilized for construction of road
under ‘PMGSY’ is entitled to compensation
and upon noticing the conflicting opinions,
the issue was referred to Hon’ble Larger Bench
for authoritative pronouncement.

5. Now, the Hon’ble Larger Bench of this
Court vide its order dated 30.03.2022, has
answered the question in the affirmative and
held that the person(s) whose land(s) has

– 37 – ( 2025:HHC:5826 )

been utilized for construction of road under
‘PMGSY’ is entitled to compensation unless
it is proved to the satisfaction of the
Court that the land was voluntarily donated
or given by him willingly with free will
and consent for construction of such road.

8(iii). State Authorities assailed the judgement

in LPA No. 33 of 2021 before the Hon’ble Supreme

Court in SLP (C) Diary No. 31814 of 2023, titled

as The State of Himachal Pradesh & Ors versus

Sita Ram (since deceased) through LRs was also

dismissed on 3.10.2023, in the following terms:

1. Delay condoned.

2. We are not inclined to interfere with the
impugned judgment and order passed by the High
Court. The special leave petition is dismissed
accordingly.

3. Pending application(s), if any, stand
disposed of.

Thus, taking into account the mandate

of Full Bench in the case of Sita Ram (supra)

which has been upheld by the Hon’ble Supreme

Court in SLP referred to above, this Court upholds

the findings recorded by the Learned Single

Judge in the judgement dated 13.08.2024 in

question that even in case of construction or

– 38 – ( 2025:HHC:5826 )

utilization of road under the Pradhan Mantri Gram

Sadak Yojna [in short PMGSY], the land owner(s)

including the writ petitioner herein, is entitled for

acquisition and compensation for the land utilized

for construction of road by the State Authorities.

9. Third contention of Learned State Counsel

is that the process for utilization-construction

of the road relating to package 2003-04 was

started by State Authorities in the year 2005 and

the same was completed in February 2009 and

the writ petitioner approached this Court in June,

2022 and therefore, the claim suffer from delay

and laches and therefore, no relief could have

been granted to the writ petitioner by the Learned

Single Judge.

Above contention of State Authorities

invoking plea of delay and laches is untenable

for the reason, that the State Authorities took

possession and utilized the land belonging to

writ petitioner without any sanction of law as

mandated by the Honble Supreme Court in Tukaram

– 39 – ( 2025:HHC:5826 )

Kana Joshi and others versus Maharashtra

Industrial development Corporation and others,

(2013) 1 SCC 353, in the following terms:

9. There are authorities which state
that delay and laches extinguish the right
to put forth a claim. Most of these authorities
pertain to service jurisprudence, grant of
compensation for a wrong done to them
decades ago, recovery of statutory dues,
claim for educational facilities and other
categories of similar cases, etc. Though,
it is true that there are a few authorities
that lay down that delay and laches debar
a citizen from seeking remedy, even if his
fundamental right has been violated, under
Article 32 or 226 of the Constitution, the
case at hand deals with a different scenario
altogether. Functionaries of the State took
over possession of the land belonging to
the appellants without any sanction of
law. The appellants had asked repeatedly
for grant of the benefit of compensation.

The State must either comply with the
procedure laid down for acquisition, or
requisition, or any other permissible statutory
mode. There is a distinction, a true and
concrete distinction, between the principle of
“eminent domain” and “police power” of
the State. Under certain circumstances, the
police power of the State may be used
temporarily, to take possession of property
but the present case clearly shows that
neither of the said powers have been exercised.
A question then arises with respect to the
authority or power under which the State
entered upon the land. It is evident that
the act of the State amounts to encroachment,
in exercise of “absolute power” which in
common parlance is also called abuse of
power or use of muscle power. To further
clarify this position, it must be noted that
the authorities have treated the land owner

– 40 – ( 2025:HHC:5826 )

as a ‘subject’ of medieval India, but not
as a ‘citizen’ under our constitution.

9(i). Repelling the contention of delay and

laches or limitation the Honble Supreme Court

mandated that the defence of delay and laches

or limitation will not apply, if the case relates to

a continuing cause of action or if circumstances

shocks the conscious of the Court while exercising

constitutional jurisdiction so as to do substantial

justice in Vidya Devi versus State of Himachal

Pradesh and others, (2020) 2 SCC 569, in the

following terms:

12.12. The contention advanced by the State
of delay and laches of the appellant in moving
the Court is also liable to be rejected. Delay
and laches cannot be raised in a case
of a continuing cause of action, of if the
circumstances shock the judicial conscience
of the Court. Condonation of delay is a
matter of judicial discretion, which must be
exercised judiciously and reasonably in the
facts and circumstances of a case. It will
depend upon the breach of fundamental rights
and the remedy claimed and when and
how the delay arose. There is no period
of limitation prescribed for the courts to
exercise their constitutional jurisdiction
to do substantial justice.

12.13. In a case where the demand for justice
is so compelling, a constitutional court
would exercise its jurisdiction with a view
to promote justice, and not defeat it.

– 41 – ( 2025:HHC:5826 )

9(ii). Negativating the contention of delay and

laches in case a person was forcibly dispossessed

of private property without following due process

of law and by mandating that there cannot be

a limitation for doing justice the Hon’ble Supreme

Court has held in Sukh Dutt Ratra and another

versus State of Himachal Pradesh and others,

(2022) 7 SCC 508 after following the mandate

in the case of Vidya Devi (supra), in the following

terms:

“16. Given the important protection extended
to an individual vis-a-vis their private
property (embodied earlier in Article 31, and
now as a constitutional right in Article 300-A),
and the high threshold the State must
meet while acquiring land, the question
remains- can the State, merely on the ground
of delay and laches, evade its legal
responsibility towards those from whom
private property has been expropriated?
In these facts and circumstances, we find
this conclusion to be unacceptable, and
warranting intervention on the grounds of
equity and fairness.”

[Emphasis supplied]

22. This court is also not moved by the
State’s contention that since the property
is not adjoining to that of the appellants,
it disentitles them from claiming benefit
on the ground of parity. Despite it not being
adjoining (which is admitted in the rejoinder
affidavit filed by the appellants), it is clear
that the subject land was acquired for the

– 42 – ( 2025:HHC:5826 )

same reason-construction of the Narag Fagla
Road, in 1972-73, and much like the claimants
before the reference court, these appellants too
were illegally dispossessed without following
due process of law, thus resulting in violation
of Article 31 and warranting the High
Court’s intervention under Article 226
jurisdiction. In the absence of written consent
to voluntarily give up their land, the appellants
were entitled to compensation in terms
of law. The need for written consent in
matters of land acquisition proceedings, has
been noted in fact, by the full court decision
of the High Court in Shankar Dass (supra)
itself, which is relied upon in the impugned
judgment.

25. Concluding that the forcible
dispossession of a person of their private
property without following due process of
law, was violative of both their human
right, and constitutional right under Article
300-A
, this court allowed the appeal. We
find that the approach taken by this court
in Vidya Devi (supra) is squarely applicable
to the nearly identical facts before us in
the present case.

9(iii). A coordinate Division Bench of this Court

based on the mandate of the Hon’ble Supreme

Court in the case of Tukaram Kana Joshi, Vidya

Devi and Sukh Dutt Ratra (supra) had outlined

in LPA No. 54 of 2017, In re: State of Himachal

Pradesh and others versus Upender Kumar and

other connected matters decided on 27.3.2024 that

objection regarding limitation or delay and laches

– 43 – ( 2025:HHC:5826 )

cannot be permitted to come in the way so as

render do substantial justice when, the action of

forcible deprivation of private land owner from his

property was without sanction of law, resulting in

expropriation of property by State, resulting in

a continuing cause of action and/or such act

shocks the judicial conscience in the following

terms:

10. It is now trite law that in dealing
with constitutional rights in the exercise
of writ jurisdiction, one can no longer
apply mutatis mutandis, the time frame
stipulated in limitation law as if they
were attracted. The issue has been dealt
with time and again by the Hon’ble Supreme
Court, particularly in the context of land
acquisition.

11. In Tukaram Kana Joshi and others
through Power-of-Attorney Holder versus
Maharashtra Industrial Development Corporation
and others (2013) 1 SCC 353 (“Tukaram”),
the Hon’ble Supreme Court ruled that the
constitutional right to property could
not be defeated on technical grounds citing
delay. Though, in the case of State of
Maharashtra versus Digambar
(1995) 4 SCC
683 (“Digambar”) the Hon’ble Supreme
Court had denied relief to farmers on the
ground of delay, but delay was not simply
declared to be an absolute bar on filing
of a writ petition.

12. It cannot be disputed that while deciding
Tukaram’s case (supra), Digambar‘s case
(supra) had not been noticed, but the same
was later noticed by the Hon’ble Supreme

– 44 – ( 2025:HHC:5826 )

Court in a fairly recent case of Sukh Dutt
Ratra and another versus State of Himachal
Pradesh and others
(2022) 7 SCC 508
(“Sukh Dutt Ratra”) wherein the Hon’ble
Supreme Court has dealt with a number
of its judgments to emphasis that there can
be no “limitation” to do justice if it is
clear that the right to property has been
intruded into without due process of law.

The Hon’ble Supreme Court has repelled
the citation of delay and laches in enforcement
of the constitutional right to property in land.
The Hon’ble Supreme Court, as observed
above, has considered the case of
Digambar.

13. Thus, the law as stands today is that
the State cannot, on the ground of delay
and laches, evade its responsibility towards
those from whom private property has
been expropriated. In any case, what principles
a Court must apply while assessing whether
a writ petition is so hopelessly barred by
delays and laches that a remedy is not
worthy of consideration, is well articulated
in Maharashtra SRTC versus Balwant Regular
Motor Service
AIR 1969 SC 329 and these
principles stand extracted and endorsed by
the Hon’ble Supreme Court in Sukh Dutt
Ratra
‘s case (supra) wherein it was held
as under:

“16. Given the important protection
extended to an individual vis-a-vis their
private property (embodied earlier in
Article 31, and now as a constitutional
right in Article 300-A), and the high
threshold the State must meet while
acquiring land, the question remains-
can the State, merely on the ground of
delay and laches, evade its legal
responsibility towards those from
whom private property has been
expropriated ? In these facts and
circumstances, we find this conclusion
to be unacceptable, and warranting
intervention on the grounds of

– 45 – ( 2025:HHC:5826 )

equity and fairness.

17. When seen holistically, it is
apparent that the State’s actions, or
lack thereof, have in fact compounded
the injustice meted out to the appellants
and compelled them to approach this
court, albeit belatedly. The initiation of
acquisition proceedings initially in the
1990s occurred only at the behest of
the High Court. Even after such judicial
intervention, the State continued to
only extend the benefit of the court’s
directions to those who specifically
approached the courts. The State’s
lackadaisical conduct is discernible
from this action of initiating acquisition
proceedings selectively, only in respect
to the lands of those writ petitioners
who had approached the court in
earlier proceedings, and not other
land owners, pursuant to the orders
dated 23.04.2007 (in Anakh Singh v.
State of H.P., 2007 SCC Online HP

220) and 20.12.2013 (in Onkar Singh
vs. State, CWP No. 1356 / 2010)
respectively. In this manner, at every
stage, the State sought to shirk its
responsibility of acquiring land required
for public use in the manner prescribed
by law.

18. There is a welter of precedents
on delay and laches which conclude
either way-as contended by both sides
in the present dispute-however, the
specific factual matrix compels this
court to weigh in favour of the appellant-

land owners. The State cannot shield
itself behind the ground of delay and
laches in such a situation; there
cannot be a ‘limitation’ to doing justice.
This court in a much earlier case-

Maharashtra State Road Transport
Corporation v. Balwant Regular Motor
Service
(1969) 1 SCR 808, held:

– 46 – ( 2025:HHC:5826 )

“11……Now the doctrine of laches
in Courts of Equity is not an
arbitrary or a technical doctrine.
Where it would be practically
unjust to give a remedy, either
because the party has, by his
conduct, done that which might
fairly be regarded as equivalent
to a waiver of it, or where by
his conduct and neglect he has,
though perhaps not waiving that
remedy, yet put the other party
in a situation in which it would
not be reasonable to place him
if the remedy were afterwards
to be asserted in either of these
cases, lapse of time and delay
are most material.

But in every case, if an argument
against relief, which otherwise
would be just, is founded upon
mere delay, that delay of course
not amounting to a bar by any
statute of limitations, the validity
of that defence must be tried upon
principles substantially equitable.

Two circumstances, always
important in such cases, are, the
length of the delay and the nature
of the acts done during the
interval, which might affect either
party and cause a balance of
justice or injustice in taking the
one course or the other, so far
as relates to the remedy.”

14. By now, it is well settled that right
to property though no longer a fundamental
right and is otherwise a zealous possession
of which one cannot be divested save and except
by the authority of law as is enjoined by
Article 300A of the Constitution of India.
Any callous inaction or apathy of the State
and its instrumentalities, in securing just
compensation would amount to dereliction of

– 47 – ( 2025:HHC:5826 )

a constitutional duty justifying issuance of
writ of mandamus for appropriate remedial
directions.

9(iv). The judgement in Upender Kumar’s case

(supra) was taken by State Authorities in SLP (C)

No. 49057 of 2024, titled as The State of Himachal

Pradesh and others versus Upender Kumar wherein,

after cautioning the State Authorities with exemplary

costs, the SLP was dismissed on 22.11.2024, in

the following terms:

SPECIAL LEAVE PETITION (CIVIL) Diary No(s).

49057/2024

[Arising out of impugned final judgment and
order dated 27-03-2024 in LPA No. 54/
2017 passed by the High Court of Himachal
Pradesh at Shimla]

THE STATE OF HIMACHAL PRADESH &
ORS. Petitioner(s) VERSUS UPENDER KUMAR
Respondent(s)

1. Delay condoned.

2. We have come across several matters
wherein the State of Himachal Pradesh has
challenged the orders passed by the Division
Bench of the High Court of Himachal Pradesh,
thereby directing the compensation to be
paid to the respondent(s).

3. The writ petitioner(s) has approached
the High Court with a grievance that though
the possession of their lands were taken for
road construction, they did not receive
compensation.

4. By the impugned judgment and order,
the High Court has held that the State cannot

– 48 – ( 2025:HHC:5826 )

take possession of citizen land without
paying the compensation.

5. Although the right to property is no
longer considered a fundamental right, it is
still a constitutional right. The State cannot
be permitted to acquire citizen land without
paying appropriate compensation.

6. In these circumstances, it would have
been justified in dismissing the special leave
petition(s) with exemplary cost. However,
we refrain from doing so now and simply
dismiss these special leave petitions.

9(v). While dealing with a claim by landlord

for compensation, who was non suited on the

ground of delay and laches, the Hon’ble Supreme

Court allowed the compensation by negating the

plea of delay and laches, so as to rectify injustice

and moreso when, the right of an individual to

vindicate and protect private property could not be

brushed aside by invoking delay and laches in

Urban Improvement Trust versus Vidhya Devi

and others, Civil Appeal No. 14473 of 2024 decided

on 13.12.2024 in the following terms:

45. Having heard the learned counsels
appearing for the parties and having gone
through the materials on record, the following
questions fall for our consideration:

(i) Whether the High Court committed
any error in taking the view that

– 49 – ( 2025:HHC:5826 )

the respondents herein should be
non-suited on the ground of delay
and laches?

46. As regards the appellant’s challenge
to the inordinate delay of 21 years in filing
of the writ petitions by the respondents,
we are of the view that the same needs
to be considered in the facts and circumstances
of the case. While it is true that the
courts have consistently held that undue
delay in approaching the court can be a
ground for refusing relief, the courts have
also recognized that in exceptional cases,
where the impugned action is patently
illegal or affects fundamental rights, the
delay must be condoned.

47. It is pertinent for us to consider the
judgment of this Court in Vidya Devi v.
State of Himachal Pradesh
reported in
(2020) 2 SCC 569, wherein it was held, inter
alia, as follows:

12.13. In a case where the demand for
justice is so compelling, a constitutional
court would exercise its jurisdiction
with a view to promote justice, and
not defeat it. [P.S. Sadasivaswamy v.

State of T.N., (1975) 1 SCC 152 : 1975
SCC (L&S) 22]” [Emphasis supplied]

48. The aforesaid view has also been
reiterated by this Court in Sukh Dutt
Ratra v. State of Himachal Pradesh
reported
in (2022) 7 SCC 508 wherein the court
opined that there cannot be a ‘limitation’
to doing justice….”.

50. This Court in its decision in Ramchandra
Shankar Deodhar v. State of Maharashtra
,
reported in (1974) 1 SCC 317 held that:

“10. … There was a delay of more than
ten or twelve years in filing the
petition since the accrual of the cause
of complaint, and this delay, contended
the respondents, was sufficient to

– 50 – ( 2025:HHC:5826 )

disentitle the petitioners to any relief
in a petition under Article 32 of
the Constitution. We do not think
this contention should prevail with
us. In the first place, it must be
remembered that the rule which says
that the Court may not inquire into
belated and stale claims is not a
rule of law, but a rule of practice
based on sound and proper exercise
of discretion, and there is no inviolable
rule that whenever there is delay,
the Court must necessarily refuse
to entertain the petition. Each case
must depend on its own facts. The
question, as pointed out by Hidayatullah,
C.J., in Tilokchand Motichand v. H.B.
Munshi
[(1969) 1 SCC 110] “is one of
discretion for this Court to follow
from case to case. There is no lower
limit and there is no upper limit …. It
will all depend on what the breach
of the fundamental right and the
remedy claimed are and how the delay
arose”. …[ SCC para 11] …”

(Emphasis supplied)

51. The decisions of this Court have
consistently held that the right to property
is enshrined in the Constitution and requires
that procedural safeguards be followed to
ensure fairness and non-arbitrariness in
decision-making especially in cases of
acquisition by the State. Therefore, the delay
in approaching the court, while a significant
factor, cannot override the necessity to
address illegalities and protect right to
property enshrined in Article 300A. The
court must balance the need for finality
in legal proceedings with the need to
rectify injustice. The right of an individual
to vindicate and protect private property
cannot be brushed away merely on the
grounds of delay and laches.


                             {Emphasis Ours}
                                   - 51 -               ( 2025:HHC:5826 )



              Based     on    the     factual      matrix     and    the

legal mandate as discussed hereinabove, this Court

is of the considered view that once the State

Authorities have curtailed the constitutional right

of the writ petitioner i.e. by forcibly depriving

him of his property without sanction of law and

in depriving such land owner of the compensation

by utilizing the land of writ petitioner, even though

for a public purpose i.e. construction of road.

This action of the State Authorities has certainly

resulted in civil consequences, by depriving the

land owner-writ petitioner of his right to reap the

benefits accruing from his land resulting in

recurring loss and this action has shocked the

conscience of this Court. In these circumstances,

the plea of delay and laches cannot be permitted

to be raised by the State so as to safeguard

the rights of the writ petitioner so as to rectify

injustice and to enable the writ petitioner to get

compensation for his land, from which he was

– 52 – ( 2025:HHC:5826 )

forcibly and illegally dispossessed in the teeth of

Articles 14, 21 and 300-A of the Constitution of

India. Accordingly, in facts of this case, the plea

of delay and laches needs to be brushed aside so

as to rectify injustice and to render substantial

justice to writ petitioner. Accordingly, the contention

of Learned State Counsel based on delay and

laches does not stand the test of judicial scrutiny

and the same is rejected.

10. Fourth contention of Learned State Counsel

is that the judgement in the case of State of

Maharashtra versus Digambar (1995) 4 SCC 683

has not been considered by the Learned Single

Judge is misconceived when, the Learned Single

Judge had referred to the judgment in the case

of Sukh Dutt Ratra (supra), wherein, the judgement

in Digambar‘s case (supra) as discussed in the

case of Vidya Devi (supra) was relied upon and

based on aforesaid judgement(s), the plea of delay

and laches was negated by the Hon’ble Supreme

Court. Thus, in these circumstances, the contention

– 53 – ( 2025:HHC:5826 )

of Learned State Counsel does not stand test of

judicial scrutiny and is accordingly turned down.

11. Fifth contention of Learned State Counsel

is that the judgement in case of Rajiv versus State

of Himachal Pradesh has not been considered

by the Learned Single Judge. The above contention

is contrary to the records, when no such judgement

was made part of reply affidavit before the writ court

and even, in instant appeal, the aforesaid judgement

has neither been referred to. Even on a query

by this Court, Learned State Counsel was able to

point out the aforesaid judgement, as quoted in

grounds of appeal today.

12. Last contention of Learned State Counsel

is that the Full Bench judgement of this Court

[though not quoted as to which Full Bench

judgment] has been ignored. It appears that the

above plea has been set-up, just to delay the

implementation of Impugned judgement and to

prolong the release of actual compensation to the

land owner-writ petitioner. Moreover, the Learned

– 54 – ( 2025:HHC:5826 )

Single Judge has discussed the mandate of Full

Bench of this Court in the case of Sita Ram

Sharma (supra), in Paras 4 and 5 of the judgement

and has relied on the judgment in case of Sukh

Dutt Ratra, wherein another Full Bench judgement

in case of Shankar Dass has been duly relied

upon-approved by the Honble Supreme Court..

13. Notwithstanding the above, the instant

appeal needs to be tested from another angle

also. Admittedly, the State Authorities started the

construction of Mahota Bagshar Road with total

length of 00/00 to 17/00 upto village Telehan

under Pradhan Mantri Gram Sadak Yojna [in

short PMGSY] under package for the year 2003-04.

Land of the writ petitioner and other co-owners,

having adjoining lands namely Bhoop Ram and

Neem Chand were also utilized for the construction

of same subject road without sanction of law

by the State Authorities. Feeling aggrieved Bhoop

Ram filed CWP No. 2386 of 2009 and Neem Chand

filed CWP No. 3090 of 2009 and both these

– 55 – ( 2025:HHC:5826 )

writ petitions were allowed on 24.06.2016 and

5.7.2016 by the Learned Single Judge. These

judgement in the case of Bhoop Ram was taken

in LPA No. 79 of 2017 decided on 8.8.2017 wherein

the State Appeal was dismissed and CWP was

upheld. After decision in LPA, the State Authorities

as per material on record in the writ proceedings

started the acquisition proceedings on 6.12.2018,

by issuing notification under Section 11 of the

Right to Fair Compensation and Transparency in

Land Acquisition, Rehabilitation and Resettlement

Act, 2013 leading to the passing of Award by

Land Acquisition Collector, HPPWD (CZ), Mandi

on 22.02.2022 [Annexure P-2 colly]. After passing

of award in the case of Bhoop Ram and Neem

Chand, the writ petitioner submitted representation

on 21.04.2022 to State Authorities [Annexure P-3]

whereafter the Land Acquisition Collector requested

the Executive Engineer concerned on 27.4.2022

[Annexure P-4] to initiate appropriate action for

acquiring the land. Even Special Secretary (PW)

– 56 – ( 2025:HHC:5826 )

directed the concerned Executive Engineer and

Land Acquisition Collector on 4.5.2022 [Annexure P-5]

to take steps for payment of compensation to the

writ petitioner [Charan Dass]. Since nothing was

done therefore, the writ petitioner approached this

Court in CWP No. 4226 of 2022 on 14.06.2022.

In these circumstances, once the compensation has

been given to Bhoop Ram and Neem Chand

therefore, “Impugned Judgement dated 13.08.2024”,

In re: Charan Dass versus State of Himachal

Pradesh and others needs no inference so as to

ensure parity in treatment and to avoid the charge

of discrimination vis-à-vis other landowners of the

adjoining lands for same subject road. The

act of the State Authorities in compelling the writ

petitioner to face litigation, one after the other,

for his constitutional right to get compensation

from the State Authorities against the illegal and

forcible deprivation of his property without the

sanction of law, and that too by a mere executive

fiat, cannot be permitted to operate any longer.

– 57 – ( 2025:HHC:5826 )

In order to balance the need for finality in legal

proceedings, with the intent and object of need

to rectify injustice and to enable the writ petitioner

to vindicate and to protect his private property

therefore, this Court being a “sentinel of justice” of

constitutional right of property embodied in Article

300-A of the Constitution of India, when, benefit

of compensation stands given to other landowners

having adjoining lands for subject road as detailed

hereinabove establishes unfairness, unreasonableness,

discrimination and arbitrariness in State action,

which also is not in spirit of the litigation policy

of the State-Appellants. Accordingly, the Impugned

judgement passed by the Learned Single Judge

does not suffer from any illegality, infirmity or

perversity and therefore, the instant appeal, is devoid

of any merit.

14. Based on the factual matrix and the

mandate of law as discussed hereinabove, this

Court does not find any merit in the contentions

advanced by the Learned State Counsel, in the

– 58 – ( 2025:HHC:5826 )

instant appeal which are just a reiteration of

the pleas taken by the appellate-State Authorities

before the Writ Court. Accordingly, the contentions

of Learned State Counsel for appellants, are without

merit and the same are accordingly turned down.

CONCLUSION & DIRECTIONS:

15. In view of the above discussion and for

the reasons recorded hereinabove, the instant

Letters Patent Appeal sans merit, and is dismissed

in the following terms:-

(i). Impugned judgement passed by Learned
Single Judge, in CWP No. 4226 of 2022
decided on 13.08.2024 in Charan Dass
versus State of Himachal Pradesh and
others
, is upheld;

(ii). Respondents-State Authorities are directed
to initiate the acquisition proceedings
and/or to otherwise award compensation
to the writ petitioner [Charan Dass], on
same analogy it has been released to
land owners having adjoining lands i.e.
Bhoop Ram and Neem Chand [supra]
which was used for same subject road ;

with directions to complete entire process
expeditiously and not later than the
outer limit of one year as mandated

– 59 – ( 2025:HHC:5826 )

by Learned Single Judge in judgement
under reference.

16. Before parting with this case, this Court

observe that State Authorities have been filing appeals

notwithstanding the fact that benefit of acquisition

and/or compensation for utilization of lands of

landowner(s) by the State Authorities in identical

cases stands implemented. Yet, filing of instant appeal

reveals a sorry state of affairs, for which this

Court would have imposed exemplary costs. However,

without observing further and by refraining ourselves,

this Court hopes and trust that State Authorities

shall follow its litigation policy in letter and spirit

hereinafter, failing which we shall be constrained to

levy exemplary costs which shall be liable to be paid by

the officer concerned.

In aforesaid terms, the letters patent appeal

is dismissed in limine and pending miscellaneous

application(s), if any, shall also stand disposed of

accordingly.


( G. S. Sandhawalia )                        ( Ranjan Sharma )
  Chief Justice.                               Judge.
 March 1, 2025 [tm]
 

[ad_1]

Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here