Vijay Shankar Patil Decd Thru Lhrs And … vs Uco Bank Thr Its Divisional Manager on 25 March, 2025

0
126

Bombay High Court

Vijay Shankar Patil Decd Thru Lhrs And … vs Uco Bank Thr Its Divisional Manager on 25 March, 2025

2025:BHC-AS:14286
             NEETA SAWANT                                                          WP-18098-2024-FC



                        IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                CIVIL APPELLATE JURISDICTION

                                      WRIT PETITION NO. 18098 OF 2024


               1. Vijay Shankar Patil, since deceased
               through Legal Heirs
               1a. Priyanka Vijay Patil
               1b. Mukesh Vijay Patil
               1c. Yogesh Vijay Patil

               2. Dilip S. Kotharkar, since deceased
               through Legal Heirs
               2a. Deepali Dilip Kotharkar
               2b. Harshikesh Dilip Kotharkar
               2c. Gautami Dilip Kotharkar                                       ....Petitioners

                    : Versus :
               UCO Bank, through its Divisional
               Manager                                                           ....Respondent



               Mr. Ashok T. Gade with Ms. Riya John, for the Petitioners.

               Mr. Ashok D. Shetty, with Mr. Swapnil P. Kamble, Ms. Rita K. Joshi, Mr.
               Rahul P. Shetty and Mr. Shashikant D. Patil, for Respondent.


                                                     CORAM : SANDEEP V. MARNE, J.

                                                    Judgment Reserved on : 19 March 2025.
                                                    Judgment Pronounced on : 25 March 2025.


               JUDGMENT :

1) Petitioners have filed this petition challenging the
judgment and order dated 29 August 2024 passed by the Presiding
Officer, Central Government Industrial Tribunal-II, Mumbai to the

Page No.1 of 23
25 March 2025
::: Uploaded on – 27/03/2025 ::: Downloaded on – 27/03/2025 21:36:09 :::
NEETA SAWANT WP-18098-2024-FC

extent of denial of interest on the legal dues payable towards
implementation of the Award dated 16 September 1999.

2) Two workmen-Vijay Shankar Patil and Dilip S. Kotharkar
were working with the Respondent-Bank and were terminated from
service. At their instance, Reference CGIT No.2/13 of 1999 relating to
their demand for reinstatement was registered with Central
Government Industrial Tribunal-II, Mumbai (CGIT). The Reference
was answered by the CGIT in favour of the workmen by setting aside
their termination and directing their reinstatement with full backwages
w.e.f. 29 May 1997 alongwith continuity of service. The Bank filed Writ
Petition No.4510/2000 in this Court challenging the Award dated 16
September 1999. The Petition came to be dismissed by the order of the
learned Single Judge dated 30 August 2000. The Bank filed Letters
Patent Appeal challenging the order of the learned Single Judge dated
30 August 2000, which was registered as LPA No.37/2013. The Appeal
Court dismissed the Appeal by judgment and order dated 10 June 2014.
It appears that simultaneously, the workmen had filed Writ Petition
No. 8402 of 2012 seeking implementation of the Award dated 16
September 1999. By separate order passed on 10 June 2014, the Division
Bench disposed of the said Petition reserving liberty for the workmen
to exercise appropriate remedy for enforcement of Award before the
CGIT.

3) The two workmen accordingly filed Application No.2/06
of 2014 before the CGIT under the provisions of Section 33-C(2) of the
Industrial Disputes Act, 1947 (I. D. Act) seeking recovery of amount of
Rs.27,55,500/-. The Application was resisted by the Respondent-Bank
by filing Written Statement. The Bank contended that it had offered
amount of Rs.1,99,280/- by demand draft dated 23 December 2014
which was returned by the workmen. That Shri. Vijay Patil never

Page No.2 of 23
25 March 2025
::: Uploaded on – 27/03/2025 ::: Downloaded on – 27/03/2025 21:36:09 :::
NEETA SAWANT WP-18098-2024-FC

reported for duties and Shri. D.S. Kotharkar reported for duties as daily
wager in July 2010 and continued to work till August 2015 after which
he abandoned the service.

4) It appears that during pendency of the Application, the
dues payable in respect of the two workmen were amended and scaled
down to Rs.8,58,825/- each. The CGIT has partly allowed the
application by directing that the amount of Rs.8,58,825/- be paid to the
legal heirs of late, Dilip Kotharkar within a period of 2 months, failing
which the said amounts would carry interest at the rate of 6% from the
date of the order till realisation. The CGIT has however rejected the
prayer for payment of 9% interest on the amount from the date of the
Award. The legal heirs of the two workmen are aggrieved by the
impugned order of the CGIT to the limited extent of denial of interest
on the amount of wages and has accordingly filed the present petitions.

5) Mr. Gade, the learned counsel appearing for the Petitioners
would submit that the award for reinstatement and backwages was
passed on 16 September 1999 and the same was not implemented by
the Respondent-Bank for a considerable period of time. That the Award
has been upheld both by the learned Single Judge as well as by the
Division Bench of this Court. Since the Award is upheld, the Petitioners
must necessarily be paid interest on the amounts arising out of
implementation of the Award. That Petitioners are not seeking interest
in respect of the period prior to 16 September 1999. However, what
becomes payable from 16 September 1999 and what is actually paid
after the impugned order dated 29 August 2024 must necessarily carry
interest.

6) Mr. Gade would submit that the CGIT has erred in holding
that the award of interest would amount to creation of new right

Page No.3 of 23
25 March 2025
::: Uploaded on – 27/03/2025 ::: Downloaded on – 27/03/2025 21:36:09 :::
NEETA SAWANT WP-18098-2024-FC

beyond the Award. He would rely upon judgment of this Court in Mrs.
Prabhavati Ramgarib B. Versus. Divisonal Railway Manager, Western
Railway Manager1 in support of his contention that the Labour Court
has power of awarding interest while deciding the application under
Section 33-C(2) of the I.D. Act. He would submit that the view taken by
this Court in Prabhavati Ramgarib B. (supra) has been approved by
the Hon’ble Supreme Court in its judgment in Dushyant N. Dalal and
Another Versus. Securities and Exchange Board of India 2. He would
also rely upon judgment of this Court in Lintas India Pvt. Ltd. Versus.
Bharatiya Kamgar Sena Praphulban Soc. and Ors. 3, Mr. Prabhakar
Kisan Magar Versus. The Divisional Railway Manager, Western
Railway, Mumbai Central, Mumbai4 and Swan Mills Limited and
another Versus. Sakharam Dhondu Panchal and others5. Mr. Gade
would accordingly pray for setting aside the impugned order of CGIT
to the extent of denial of interest and would pray for award of interest
at the rate of 9% p.a. on amounts arising out of implementation of the
Award dated 16 September 1999 till the actual date of payment.

7) The petition is opposed by Mr. Shetty, the learned counsel
appearing for the Respondent-Bank. He would submit that jurisdiction
of industrial adjudicator under the provisions of Section 33-C(2) of the
I. D. Act is in an extremely narrow compass. That in exercise of that
jurisdiction, it is beyond the competence of CGIT to add anything to the
Award already made. He would submit that law in this regard is well
settled in several judgments and would accordingly rely upon
following judgments :

1

2010 (4) Mh.L.J. 691
2
(2017) 9 SCC 660
3
Writ Petition No. 2522/2021 decided on 23 March 2023
4
Writ Petition No. 8129/2009 decided on 18 April 2022
5
(2005) 1 LLJ 990

Page No.4 of 23
25 March 2025
::: Uploaded on – 27/03/2025 ::: Downloaded on – 27/03/2025 21:36:09 :::
NEETA SAWANT WP-18098-2024-FC

(i) Municipal Corporation of Delhi Versus. Ganesh Razak &
Anr.6

(ii) State Bank of India Versus. Ram Chandra Dubey & Ors. 7

(iii) The Central Bank of India Ltd. Versus. P.S. Rajagopalan. 8

(iv) Bombay Gas Co. Ltd. Versus. Gopal Bhiva & Ors.9

(v) State Bank of Bikaner and Jaipur Versus. Khandelwal
(R.L.)10

(vi) Central Inland Water Transport Corporation Ltd. Versus.

The Workmen & Anr.11

(vii) Mining Engineer East India Coal Co. Ltd. Versus.

Rameswar & Ors.12

8) Without prejudice, Mr. Shetty would submit that
immediately after the order of the Division Bench dated 10 June 2014,
the Bank had called upon both the workers to collect Demand Drafts of
Rs.1,99,280/- and to report for duties. However, by letter dated
10 January 2015, the workmen returned the draft on the pretext that the
amount was not as per the Award. That the workman-Vijay Patil did
not report for duty till his death, whereas the workman-D.S. Kotharkar
reported for duties as daily wage worker in July 2010 and continued to
work till August 2015 and drew wages of Rs.3,35,800/-. That therefore
on facts, Petitioners are not entitled to the relief of payment of interest.
He would accordingly pray for dismissal of the petition.

9) Rival contentions of the parties now fall for my
consideration.

6

1995 I CLR S.C. 171
7
2000 II LLJ 1660
8
[1964] 3 S.C.R. 140
9
[1963] 3 S.C.R. 709
10
1967 SCC Online SC 373
11
[1975] 1 S.C.R. 153
12
[1968] 1 S.C.R. 140

Page No.5 of 23
25 March 2025
::: Uploaded on – 27/03/2025 ::: Downloaded on – 27/03/2025 21:36:09 :::
NEETA SAWANT WP-18098-2024-FC

10) The main issue that arises for consideration is whether
CGIT has the jurisdiction to award interest on amount arising out of
implementation of the Award dated 16 September 1999. It is an
admitted position that though the Award dated 16 September 1999 was
not stayed by any higher Court, the same was not implemented by the
Respondent-Bank till the Appeal got dismissed on 10 June 2014. It is the
case of the Respondent-Bank that on 6 January 2015, they issued letters
to both the workmen to collect amounts of Rs.1,99,280/- and also called
them upon to report for duties. It is Bank’s claim that the worker-Vijay
Patil never reported for duty. However, though the letter calling upon
the workmen to report for duties was allegedly issued on
6 January 2015, the Bank pleaded in its Written Statement that the
worker Dilip S. Kotharkar had reported for duties as daily wager in
July 2010 and continued to work as such till August 2015 and drew
wages of Rs.3,35,800/-. This shows that during pendency of the Appeal
before the Division Bench, Shri. Kotharkar was permitted to report for
duties and that he actually worked from 2010 till 2015. In the Written
Statement, the Respondent-Bank claimed that the total amount due to
Shri. Vijay Patil from 29 May 1997 to 10 June 2014 was Rs.1,99,280/-,
whereas, the amount due to Shri. Kotharkar from 29 May 1997 to
7 August 2010 was Rs. 1,58,000/-. Despite this, it is their claim that both
the workers were offered amount of Rs.1,99,280/- which was declined
by them.

11) It appears that the workers initially claimed higher
amounts of Rs.27,55,500/-. However, during the course of pendency of
proceedings before the CGIT, the claim was amended by restricting the
same to Rs. 8,58,825/- in respect of each of the workmen. The CGIT has
accordingly upheld the claim of Rs.8,58,825/- in respect of the
workman-Shri. Vijay Patil, whereas, it has deducted the wages drawn
by Shri. D.S. Kotharkar after July 2010 and has sanctioned his claim at

Page No.6 of 23
25 March 2025
::: Uploaded on – 27/03/2025 ::: Downloaded on – 27/03/2025 21:36:09 :::
NEETA SAWANT WP-18098-2024-FC

Rs.5,53,162/-. The claim for interest is however denied by the CGIT by
recording following reasons :

As regards the Interest, it is contended on behalf of the opponent that,
the deceased applicants are not entitled for Interest. In my opinion
also Tribunal cannot create a new right of parties beyond the award.
In the decision of A. F. R. Neutral Citation No.20/24 relied by the
opponent, it has been held that, the Labour Court completely mislead
in granting Interest as it was beyond the competence and scheme of
Sec. 33 (C) 2 of ID Act therefore the heirs of the deceased applicants
are not entitled for Interest from the date of award as claimed. In
short, the Legal heirs of the deceased applicants are entitled for the
amount of Rs. 8,58,825/- and Rs. 5,53,162/-respectively, hence, I
answer this point in the affirmative.

12) The CGIT has relied on judgment of the Allahabad High
Court in Executive Engineer Electricity Transmission Division Versus.

Mahesh Chandra & Anr13. It is held in para-18 of the said judgment as
under :

18. Thus, in view of the above, I find that Labour Court was
completely misled in granting interest @ 18% for the delayed
payment. It was beyond the competence of Labour Court to have
awarded interest, as under the scheme of Section 33C(2) granting of
interest does not find any place.

13) Thus, the learned Single Judge of the Allahabad High
Court appears to have taken a view that it is impermissible for the
Labour Court to grant interest on delayed payment in exercise of
jurisdiction under Section 33-C(2) of the I.D. Act.

14) However, the issue of jurisdiction of Labour Court to
award interest in exercise of jurisdiction under Section 33-C(2) arose
before this Court in Prabhavati Ramgarib B. (supra). In para-4 of the

13
2024 SCC OnLine All 1214

Page No.7 of 23
25 March 2025
::: Uploaded on – 27/03/2025 ::: Downloaded on – 27/03/2025 21:36:09 :::
NEETA SAWANT WP-18098-2024-FC

judgment, the Coordinate Bench of this Court formulated the issue for
consideration as under :

4. Mr. Patil’s fifth defence raises a question of law of some importance.

The question of law that arises is whether the Labour Court has power
under section 33-C(2) to order an employer to pay the employee
interest for the period between the date of an order of a Court or
Tribunal or authority for payment and the date of payment.

I have answered the question in the affirmative upholding the claim
for interest in such cases on four grounds – under sections 3(1)(a) and

(b) and 4 of the Interest Act, 1978, and in exercise of powers under
Article 226 of the Constitution of India. A view to the contrary would
lead to a total miscarriage of justice and disastrous consequences not
merely in this matter but for bona-fide and innocent employees in
general. It would put a premium on an employer disregarding orders
of Courts, Tribunals and other authorities. Worse still, it would
encourage an employer to refuse payments under such orders for as
long as possible, rendering them virtually meaningless.

15) The reasonings adopted by this Court while upholding the
claim for interest for the period between the date of order of a Court till
the date of payment are as under :

24. Mr. Shaikh also relied upon the judgment of a learned single Judge of this
Court in Swan Mills Ltd. v. Sakharam Dhondu Panchal, 2004 (12) LJSOFT 56 :

2004 (III) CLR 870 where it was held:–

“12. The next issue is awarding of interest. In the instant case, no
interest has been awarded on the amount of wages awarded. What
the Labour Court has done is merely to award interest subsequent to
the orders in the event, the employer fails to pay the amount
determined. It is therefore, not a case of awarding interest but merely
awarding an interest on the amount awarded on failure to pay the
amount already quantified. The learned counsel has placed reliance in
the judgment of Payal Electronics v. Arun Vasant Pawar, 2002 (III) CLR
328 to contend that the Labour Court has no jurisdiction and power to
grant any interest on the determined amount as due from the
employer. In that case, interest at the rate of 15% p.a. was ordered to
be paid on unpaid overtime wages. The learned Single Judge of this
Court proceeded to hold that there was no existing right to get the
interest on the amount of dues and as the Executing Court, the labour
Court cannot add anything more than the amount of money due.

There can be no dispute with the proposition in the said judgment. As
an Executing Court what the Court can do is to execute the
awards/order and not grant anything beyond the said order. In the
instant case also no interest has been awarded on the unpaid amount. It is
only on failure to pay the amount that interest has been awarded from a

Page No.8 of 23
25 March 2025
::: Uploaded on – 27/03/2025 ::: Downloaded on – 27/03/2025 21:36:09 :::
NEETA SAWANT WP-18098-2024-FC

future date. Though the principles of section 34 of the Civil Procedure Code
cannot be said to be conferred on the Labour Court, still it will be open to a
Civil Court and the Labour Court is a Civil Court to award the interest on
the amount already computed and not paid from the date of this order in
terms of section 34 of Civil Procedure Code. That is what the Labour Court
has done. It therefore, cannot be said that the same is without jurisdiction.
That contention must therefore, be rejected.”

(emphasis supplied)

25. The judgment is binding on me. I am, in any event, in respectful
agreement with the judgment for the reasons I have stated earlier insofar as it
relates to the maintainability of a claim for future interest. In the case before
me also, the interest claimed is not on the amounts unpaid upto the date of
the order of the Labour Court dated 30th September, 1992, but in respect of
the amounts awarded from a future date. Future interest could always have
been granted when the order dated 30th September, 1992, was passed. For
the reasons stated earlier, there is nothing that prevented the petitioner from
claiming it by a separate application. The petitioner was not bound to
presume that the respondent would not honour an order of a competent
Court. Indeed the petitioner, like any other citizen, is justified in assuming
that orders would be obeyed.

26. I am in respectful agreement with the conclusion of the Division Bench of
the Punjanb and Haryana High Court and of the learned Single Judge of this
Court. I would, however, furnish my reasons for the same.

27. The claim for interest is, as I said earlier, maintainable under subclauses

(a) and (b) of sub-section (1) of section 3 and under section 4 of the Interest
Act, 1978. A Court in exercise of powers under Article 226 can also grant
interest in a case such as this. Section 3(1) of the Interest Act, 1978 is as under:

“3.Power of Court to allow interest. — (I) In any proceedings for the
recovery of any debt or damages or in any proceedings in which a
claim for interest in respect of any debt or damages already paid is
made, the Court may, if it thinks fit, allow interest to the person
entitled to the debt or damages or to the person making such claim, as
the case may be, at a rate not exceeding the current rate of interest, for
the whole or part of the following period, that is to say,–

(a) if the proceedings relate to a debt payable by virtue of a
written instrument at a certain time, then, from the date when
the debt is payable to the date of institution of the proceedings;

(b) if the proceedings do not relate to any such debt, then, from
the date mentioned in this regard in a written notice given by
the person entitled or the person making the claim to the
person liable that interest will be claimed, to the date of
institution of the proceedings:

Provided that where the amount of the debt or damages has
been repaid before the institution of the proceedings interest
shall not be allowed under this section for the period after such
repayment.”




                                         Page No.9 of 23
                                         25 March 2025
     ::: Uploaded on - 27/03/2025                             ::: Downloaded on - 27/03/2025 21:36:09 :::
 NEETA SAWANT                                                             WP-18098-2024-FC



28. Firstly, the Interest Act, 1978 is applicable to a Labour Court and an
Industrial Tribunal under the ID Act.

(A) Section 3 of the Interest Act refers to the powers of “the Court”.
Section 2(a) of this Act defines “Court” to include a Tribunal and an
Arbitrator. The ambit of the term “Court” in the Interest Act is, therefore,
wide. There is no warrant for excluding a Labour Court from the ambit of
that expression in the Interest Act. Thus, a Labour Court is entitled to exercise
power by awarding interest under the Interest Act.

(B) Secondly, the application in this case was a proceeding in which a
claim for interest in respect of a debt already paid was made. The amount
directed to be paid by the order dated 30th September, 1992, was a debt.
Section 2(c) defines a debt thus:–

“debt” means any liability for an ascertained sum of money and includes a
debt payable in kind, but does not include a judgment debt;”. The claim for
interest in this case was not in respect of a judgment debt.

29. I have come to the conclusion that the petitioner is entitled to interest
from 30th December, 1992 itself in view of the provisions of section 3(1)(a).
The order dated 30th September, 1992, falls within the ambit of the
expression “written instrument” in section 3(1)(a) of the Interest Act. There is
neither any warrant nor justification for limiting the scope of this expression.
In Savitribai v. A. Radhakishan, AIR 1948 Nagpur 49, a Division Bench held
that a decree is an instrument within the meaning of the Interest Act, 1839.
Paragraph 5 of the judgment reads as under:

“5. The only question which arises here and which did not arise in the
other cases relates to the plaintiff’s claim for interest. It is relevant to
note that interest was decreed in the previous suits which the plaintiff
was forced to file. It is said that this operates as res judicata, but we
need not proceed on that ground because we agree with 15 Luck. 537,
that the Interest Act of 1839 applies. As the learned Judges said there:
“The claim in the present case is for a certain sum payable at a certain
time that is monthly allowance of quzera impliedly payable at some
time in every month for that month,”

and again,

“In our opinion a monthly maintenance or allowance payable under a
compromise in a suit comes within the scope of this provision.”

It was argued that a decree is not an “instrument” within the meaning of the
Act. We find, however, that the word “instrument” is used in various senses,
in some it includes a decree, in others it does not. Thus, section 17(1)

(b), Registration Act makes non testamentary “instruments” of the
type set out there compulsorily registerable. Sub-section (2) exempts a
number of documents, deeds and so forth from the scope of section
17(1)(b), among them certain decrees in sub-cl. (v). There would have
been no need to exclude this decrees if the word “instrument” did not
cover a decree. It is to be observed that certain compromise decrees
are not exempted. Therefore, they are “instruments” for the purpose
of the Registration Act. We see no reason why we should limit the use of
the word in the Interest Act. Accordingly, we hold that the term is wide
enough to cover a decree.”



                                        Page No.10 of 23
                                         25 March 2025
     ::: Uploaded on - 27/03/2025                            ::: Downloaded on - 27/03/2025 21:36:09 :::
 NEETA SAWANT                                                           WP-18098-2024-FC



30. I am in respectful agreement with the judgment. On a parity of reasoning
I would apply the ratio of the judgment to all orders of Courts, Tribunals or
other authorities, including a Labour Court exercising powers under section
33-C(2).

31. To the illustration furnished by the Nagpur High Court, I would only add
the provisions of the Bombay Stamp Act.

(A) Under section 3 of the Bombay Stamp Act, every instrument
mentioned in Schedule I, except those specified therein shall be chargeable
with duty of the amount indicated in Schedule I. Article 25 of Schedule I
refers to a conveyance other than a transfer charged or exempted under
Article 59. Clause (da) of Article 25 relates inter alia, to the order of a High
Court in respect of the amalgamation or reconstruction of companies under
section 394 of the Companies Act 1956. Thus, an order of a Court has been
considered by the Legislature to be an instrument.

(B) Article 60 Schedule I is as under:–

“60. TRANSFER OF LEASE by way of assignment and not by way of
under lease or by way of decree or final order passed by any Civil Court
or any Revenue Officer.”

Here again, a decree passed by a Civil Court or even an order of a
Revenue Officer has been considered by the Legislature to be an instrument.
This is so, both by considering such instruments as being liable to stamp duty
as also excluding them from the necessity of being stamped.

32. In the circumstances, the term “instrument” in section 3(1)(a) of the
Interest Act is wide enough to include a decision by the Labour Court under
section 33-C(2). Accordingly, interest would be payable on the said sum from
30th December, 1992 till payment and/or realisation. There is no dispute
regarding the computation.

33. Even assuming that the order dated 30th September, 1992 is not a written
instrument and the petitioner is therefore not entitled to payment of interest
under section 3(1)(a), she would be entitled to the same under section 3(1)(b).

By the order dated 30th September, 1992 the Labour Court upheld
the petitioner’s deceased husband’s claim and directed the payment thereof
within three months i.e. on or before 30th December, 1992. The respondent
failed to do so. By a letter dated 26th February, 1996, the petitioner’s advocate
called upon the respondent to pay the amount pursuant to the order dated
30th September, 1992 with interest at 12 per cent per annum. The petitioner
would, therefore, be entitled to interest under section 3(1)(b) if section 3(1)(a)
did not apply. Thus, the petitioner would, in any event, be entitled to interest,
at least from 26th February, 1996 under section 3(1)(b).

However, as I have held earlier, the petitioner is entitled to interest
under section 3(1)(a).

34. The petitioner’s claim is also sustainable under section 4 of the Interest
Act which reads thus:–

Page No.11 of 23

25 March 2025
::: Uploaded on – 27/03/2025 ::: Downloaded on – 27/03/2025 21:36:09 :::
NEETA SAWANT WP-18098-2024-FC

4.Interest payable under certain enactments. — (1) Notwithstanding
anything contained in section 3, interest shall be payable in all cases in
which it is payable by virtue of any enactment or other rule of law or
usage having the force of law.

(2) Notwithstanding as aforesaid, and without prejudice to the
generality of the provisions of sub-section (1), the Court shall,
in each of the following cases, allow interest from the date
specified below to the date of institution of the proceedings at
such rate as the Court may consider reasonable, unless the
Court is satisfied that there are special reasons why interest
should not be allowed, namely:–

(a) where money or other property has been deposited as
security for the performance of an obligation imposed by law
or contract, from the date of the deposit;

(b) where the obligation to pay money or restore any property
arises by virtue of a fiduciary relationship, from the date of the
cause of action;

(c) where money or other property is obtained or retained by
fraud, from the date of the cause of action;

(d) where the claim is for dower or maintenance, from the date
of the cause of action.

35. The petitioner’s claim for interest would fall within the ambit of the words
“or other rule of law” in section 4(1). The other rule of law being on grounds
of equity. Even under the Interest Act, 1839, interest was payable under the
proviso to section 1 which reads:”Provided that interest shall be payable in
all cases in which it is now payable by law.” Interest was payable by law
under that Act in equity. This was recognized in a series of judgments. For
instance in Trojan and Co. v. Nagappa Chettiar, (1953) 1 SCC 456 : 1953 SCR 789.
The Supreme Court, in paragraph 23 observed that it was well settled that
interest is allowed by a Court of equity in the case of money obtained or
retained by fraud. Interest was, therefore, awarded in equity.

36. The position is not different under the Interest Act, 1978. The words, in
section 4(1) “or other rule of law” would include interest payable in equity. In
fact, interest has been awarded by our Courts in equity as well as on
principles analogous to section 34 of the Code of Civil Procedure on the basis
that section 34 is based upon principles of justice, equity and good
conscience.

37. It is important to note that there is no legal provision or any other rule of
law that prohibits the grant of interest for the period during which a debtor
fails to comply with an order of payment passed by a Court, Tribunal or any
other competent authority. This enables, therefore, the application of the
common law principles relating to equity.

48. I have also held in the petitioner’s favour on the basis of a judgment of a
Division Bench of this Court in the case of Dilip T. Khandar v. State of
Maharashtra
, 2006 (2) Mh.L.J. 781 : 2006 (2) LJSOFT 12 : 2006 (1) Bom.C.R. 721.

In that case, the complaints filed by the workmen under the MRTU
and PULP Act
were allowed and recovery certificates were issued by
the Industrial Court for recovery of salary and other reliefs. The
Collector granted the employer instalments and did not recover

Page No.12 of 23
25 March 2025
::: Uploaded on – 27/03/2025 ::: Downloaded on – 27/03/2025 21:36:09 :::
NEETA SAWANT WP-18098-2024-FC

interest. It was contended on behalf of the respondents that the
Labour Court/Industrial Court had not directed payment of interest
and hence there was no clause relating to payment of interest in the
recovery certificates. The Division Bench referred to section 50 of the
MRTU and PULP Act and expressly observed that the provisions
thereof were similar to section 33-C of the ID Act. Section 50 of the
MRTU and PULP Act also provides that where money is due to an
employee from an employer in the circumstances mentioned therein,
the Court shall issue a certificate for that amount to the Collector who
shall proceed to recover the same in the manner as an arrear of land
revenue. The Division Bench rejected the contention that merely
because the Labour Court/Industrial Court had not directed payment
of interest and the recovery certificate also did not refer to interest, no
interest was payable. The judgment was also based on section 33-C(1)
read with section 267 of the Maharashtra Land Revenue Code.

16) In Prabhavati Ramgarib B., this Court has relied upon
judgment of Coordinate Bench in Swan Mills Limited (supra), para-12
whereof has already been reproduced in the judgment of Prabhavati
Ramgarib B.

17) It appears that while deciding an unrelated issue of interest
on unpaid amount of penalty arising out of Securities and Exchange
Board of India Act, 1992
and Income Tax Act, 1961, the Apex Court has
considered the judgment of this Court in Prabhavati Ramgarib B. and
has agreed with the view taken therein. In paras-31 and 32 of the
judgment in Dushyant Dalal, the Apex Court has held as under :

31. We find that a learned Single Judge of the Bombay High Court has,
in Prabhavati Ramgarib B. v. Divl. Railway Manager [Prabhavati Ramgarib
B. v. Divl. Railway Manager, 2010 SCC OnLine Bom 171 : (2010) 4 Mah LJ 691] ,
specifically held as follows: (SCC OnLine Bom paras 35-36 : Mah LJ pp. 702-
03, paras 35-36)
“35. The petitioner’s claim for interest would fall within the ambit of
the words “or other rule of law” in Section 4(1). The other rule of law
being on grounds of equity. Even under the Interest Act, 1839, interest
was payable under the proviso to Section 1 which reads:

‘Provided that interest shall be payable in all cases in which it is now
payable by law.’
Interest was payable by law under that Act in equity. This was
recognised in a series of judgments. For instance in Trojan and
Co. v. Nagappa Chettiar [Trojan
and Co. v. Nagappa Chettiar, (1953) 1 SCC

Page No.13 of 23
25 March 2025
::: Uploaded on – 27/03/2025 ::: Downloaded on – 27/03/2025 21:36:09 :::
NEETA SAWANT WP-18098-2024-FC

456 : 1953 SCR 789 : AIR 1953 SC 235] , the Supreme Court, in para 23,
observed that it was well settled that interest is allowed by a court of
equity in the case of money obtained or retained by fraud. Interest
was, therefore, awarded in equity.

36. The position is not different under the Interest Act, 1978. The
words, in Section 4(1) “or other rule of law” would include interest
payable in equity. In fact, interest has been awarded by our courts in
equity as well as on principles analogous to Section 34 of the Code of
Civil Procedure on the basis that Section 34 is based upon principles
of justice, equity and good conscience.”

32. We agree with the aforesaid statement of the law. It is clear, therefore,
that the Interest Act of 1978 would enable Tribunals such as SAT to award
interest from the date on which the cause of action arose till the date of
commencement of proceedings for recovery of such interest in equity. ….

(emphasis added)

18) Thus, Coordinate Benches of this Court have held in Swan
Mills Limited and in Prabhavati Ramgarib B. that interest on delayed
payment can be awarded in exercise of jurisdiction under Section 33-
C(2) of the I.D. Act. The judgment in Prabhavati Ramgarib B. has been
followed by another Coordinate Bench in Prabhakar Kisan Magar
(supra) in which it is held in paras 16 and 17 as under :

16. Be that as it may, the issue is no more res integra and the controversy in
the present proceedings is squarely covered by the decision of this Court in
Prabhavati Ramgarib’s case (supra) as rightly contended by Mr.Salvi. In such
case, in an identical controversy, learned Single Judge of this Court
considering the defence as advanced on behalf of the respondent, negatived
the findings of the Industrial Court while holding that the petitioner therein
(Prabhavati) was entitled to claim interest on such delayed payment as
claimed by Prabhavati before the Industrial Court in her application which
was rejected by the Industrial Court. The petitioners’ claim before the
Industrial Court was exactly similar to the one as made in Prabhavati’s case.

The relevant paragraphs in the said decision are required to be noted which
read thus:-

xxx xxx xxx

17. I am in complete agreement with the above reasoning and conclusion of
the learned Single Judge of this Court in Prabhavati Ramgarib’s case. In my
opinion, it is clear that the judgment of this Court in Prabhavati Ramgarib’s
case squarely covers the issues as arising in the present writ petitions.





                                       Page No.14 of 23
                                        25 March 2025
      ::: Uploaded on - 27/03/2025                          ::: Downloaded on - 27/03/2025 21:36:09 :::
 NEETA SAWANT                                                             WP-18098-2024-FC



19)              Division Bench of Delhi High Court in Bhim Singh Bajeli

Versus. P. O. Central Government Industrial Tribunal 14 has considered
the judgment of this Court in Prabhavati Ramgarib B. and had held
that if not under Section 33-C(2), but under Article 226 the High Court
can award interest on delayed amount arising out of implementation of
Award. The Division Bench held as under :

7. As previously mentioned, even though the structure of Section 33C(2)
does not confer jurisdiction to the Labour Court to grant interest, in the
facts and circumstances of the case, the fact remains that the employee had
approached this Court under Article 226 of the Constitution of India,
complaining that his rights had been defeated by non-implementation of
substantive award and subsequent award. At least in these proceedings, it
was open for this Court to have directed payment of interest even if it were
of the opinion that the Tribunal did not possess the primary jurisdiction to
do so. Although the management has relied upon the decision of this Court
in Central Government Industrial Tribunal (supra), at the same time, the
Court is mindful of certain other decisions of the Bombay High Court in Mrs.
Prabhavati Ramgarib B. vs. Divisional Railway Manager, Western Railway
Manager 2010 (5) SLR 683 (W.P.(C) 5529/2009) and of the Punjab and
Haryana High Court in State of Haryana v. Hisam Singh & Anr. 1999 (2) LLJ
335, where the Court relied on a larger equitable principle, as well as the
public interest underlying Section 3 of the Interest Act and drawing analogy
from Section Section 34 of the Civil Procedure Code (CPC), and upheld the
jurisdiction of the authority under Section 33C(2), to award interest, having
regard to the circumstances.

(emphasis added)

20) In M. M. Joseph Vs. Labour Court and others 15, the Kerala High
Court has also followed the Judgment of this Court in Prabhavati
Ramgarib B. The issue taken up for consideration by the Court has
been summarized in the opening Paragraph of the judgment as under :

A question of seminal importance, as to whether under Section 33C(2)
of the Industrial Disputes Act, 1947 (for short the “I.D. Act“), the
Labour Court is empowered to award interest, which has not been
specifically granted in an award passed under the I.D. Act, is raised
herein. When computation in terms of money is sought on the basis of
a legal entitlement or on the basis of an award or settlement, and there
is no specific provision to grant interest, could the principles of equity
be invoked? When the claim is based on an award, will not the grant
of interest be regulated by the award and will not an award; silent on
14
2013 SCCOnLine Del 338
15
2015 SCCOnline Ker 9802

Page No.15 of 23
25 March 2025
::: Uploaded on – 27/03/2025 ::: Downloaded on – 27/03/2025 21:36:09 :::
NEETA SAWANT WP-18098-2024-FC

that aspect be deemed to be a refusal of interest? The question is
raised on the well established principle, that the Labour Court, under
Section 33C(2), exercises power akin to an execution court as
contemplated under the Civil Procedure Code, 1908 [for brevity
CPC“].

21) The Kerala High Court answered the issue by observing as
under:

21. The learned counsel for the petitioner has placed before me a
decision of the High Court of Judicature at Mumbai in W.P(C). No.
5529/2009 [Prabhavati Ramgarib B v. Divisional Railway Manager].

The learned Single Judge in the said decision found on a an elaborate
consideration of the various provisions of the Industrial Disputes Act,
Civil Procedure Code and the Interest Act that the High Court has
power under Article 226 to grant interest in appropriate cases. While
agreeing with the said proposition, this Court would go a step further
to find that the Labour Court examining an issue under Section 33C(2)
could also exercise discretion insofar as the award of interest looking
at the facts and circumstances of the case.

29. Principles of equity definitely, commend grant of interest when the
management choses not to comply with an award of the Labour Court
on the basis of valid proceedings before a higher forum. There can be
no question, that the management is entitled to challenge orders
adverse to itself, before the appropriate forum in appeal or revision as
provided by law. The specific provisions for grant of an interim order,
is also based on the principles of equity since the party approaching
the higher forum should not be prejudiced insofar as having to
comply with an order, which he expects to get overturned in an
appeal. By rote, the specific averments made in every affidavit
accompanying an interim application for stay, is that “the applicant
has a reasonable belief of success in the appellate forum and hence the
appellant would be prejudiced insofar as the compliance is enforced
when the challenge against the order is pending”. The undisputed
corollary would be that, when against the reasonable expectation of
the appellant, the appellate forum upholds the impugned order,
necessary consequences would follow.

30. The reasonable belief stands dispelled by the appellate order and
the reasonable expectation of the opposite party, who was deprived of
the fruits of the order, at the proper time, would be; some
compensation for the delay caused, by an unsuccessful appellate or
revisional proceeding. “He who seeks equity must do equity”. The
grant of interest compensates the loss caused to the workman and
repairs the injury occasioned by deprivation of lawful employment
and wages due at a distant, earlier point of time. Equity is not a one
way street, nor are benefits legally admissible always found between
the pages of an enactment/legislation. The guiding principles in

Page No.16 of 23
25 March 2025
::: Uploaded on – 27/03/2025 ::: Downloaded on – 27/03/2025 21:36:09 :::
NEETA SAWANT WP-18098-2024-FC

Section 34 of the CPC would be the grant of interest, to a person who
is made to wait, to reap the benefits of an order; by reason of the
opposite party having availed an appellate remedy. [2002 (2) KLT SN
6 (Case No. 6) (Co-operative Sugars Ltd. v. Noorudeen)].

31. On the above reasoning, this Court finds that the claim of interest
made by the petitioner is to be allowed.

22) While considering the pari materia provisions of Section 50
of the Maharashtra Recognition of Trade Unions and Prevention of
Unfair Labour Practices Act, 1971, another Coordinate Bench of this
Court in Lintas India Pvt. Ltd. (supra) has held in paras-45, 46, 47 and
48 as under :

45. Lastly, a feeble attempt was made on behalf of the petitioner to urge that
the learned Member Industrial Court could not have awarded interest on the
due amount. The submission is required to be stated to be repelled. Interest
on the delayed payment of wages due to an employee is a well recognized
mode of compensating the employee, who has been kept away from
legitimate dues.

46. In the case of Dilip T. Khandar (supra), a Division Bench of this Court
awarded interest on the amount, for which a recovery certificate was granted
under Section 50 of the Act, 1971. The Division Bench had drawn support
from provisions contained in Section 267 (1) of the Maharashtra Land
Revenue Code, 1966, under which the amount is to be recovered as an arrear
of land revenue. The Court thus awarded interest on the amount due under
the recovery certificate at the rate of 6% p.a.

47. An issue which merits consideration is the rate at which the interest is
awarded by the Industrial Court. Interest has been ordered to be paid from
the date of the judgment in complaint (ULP) No. 1161 of 1989 till the date of
realisation. The said period exceeds 20 years. It is common knowledge that
interest rate moves in cycles. It is rarely static for even a couple of years.

48. In the totality of the circumstances, in my view, it would be appropriate to
modify the rate of interest awarded by the learned Member Industrial Court.

A direction for payment of interest at the rate of 8% p.a. would be just and
equitable.





                                       Page No.17 of 23
                                        25 March 2025
      ::: Uploaded on - 27/03/2025                         ::: Downloaded on - 27/03/2025 21:36:09 :::
 NEETA SAWANT                                                                WP-18098-2024-FC



23)              In M/s. Standard Pharmaceuticals Ltd. Versus. State of

West Bengal & Ors.16 Calcutta High Court has held that interest would
also be covered under the ambit of the term ‘benefit’ as under :

11. With due respect to the judgments delivered by the Madras High Court I
feel that this aspect of the matter has not been argued and, accordingly, not
considered. Any other narrow interpretation of the word ‘benefit’ in the facts
of the case would render Section 33C(2) otiose and a dead letter. Interest is a
benefit, which is capable of being computed in terms of money if the
management fails to act in terms of the award and awarded sum is not paid
in accordance with Section 17A of the Industrial Disputes Act. If the
workman is required to enforce the award, his right to claim interest as a
benefit cannot be denied. The Labour Court has already adjudicated the main
reference and has passed an award in favour of the petitioner. The failure on
the part of the management to calculate the back wages and left it to the
Labour Court to calculate the same in a proceeding initiated by the workman
and thereafter to come with a plea that the Labour Court cannot
grant interest on such awarded sum, in my view, is clearly unsustainable.

Any other interpretation denying the right to claim interest for belated
payment of the awarded sum would only result in manifest justice. The
Court exists to do justice between the parties. Injustice would be caused to
the petitioner in the event such interest is not allowed in favour of the
petitioner which, in my view, is in consonance with the provisions of the
Industrial Disputes Act, 1947.

24) On the other end of the spectrum, there appears to be few
judgments holding that it is impermissible for Labour Court to award
interest in exercise of jurisdiction under Section 33-C(2) of the ID Act. In
Municipal Council, Bhandara Versus. Vimal wd/o Sadaram Kodape 17 a
coordinate bench of this Court has held as under :

9. There is an order of award of interest at the rate of twelve per cent per
annum from the date of application, i.e., 7th October, 1999. The proceedings
u/s 33-C(2) of the Industrial Disputes Act are in the nature of execution
proceedings only and there is no provision therein to award interest on the
amount found due. Hence Labour Court does not have the jurisdiction
to award interest on the amount found due. In my opinion, grant
of interest at the rate of twelve per cent per annum would be penalizing the
Municipal Council.

10. This Court having noticed that there is no power in the Labour Court
acting u/s 33C(2) of Industrial Disputes Act, finds that it is necessary to
make some observations in the present matter. The application u/s 33C(2)

16
2014 (2) CalLJ 616
17
(2014) 5 AIR Bom. R 377

Page No.18 of 23
25 March 2025
::: Uploaded on – 27/03/2025 ::: Downloaded on – 27/03/2025 21:36:09 :::
NEETA SAWANT WP-18098-2024-FC

was filed on 7th October, 1999 and the decision was made on 5th July,
2002. Section 33C(2) reads thus:-

33C. Recovery of Money Due from an Employer.-

(1)…..

(2) Where any workman is entitled to receive from the employer any
money or any benefit which is capable of being computed in terms of
money and if any question arises as to the amount of money due or as
to the amount at which such benefit should be computed, then the
question may, subject to any rules that may be made under this Act,
be decided by such Labour Court as may be specified in this behalf by
the appropriate Government within a period not exceeding three
months.

It is seen that the outer limit for decision is three months. But in this case the
decision came late by more than two years due to transfer of Presiding
Officer or for want of notification conferring power. Thus, the applicant has
lost the interest on the due amount. But as found above, there is no power
to award interest, as the proceedings have been held to be in the nature of
execution proceedings. It is a matter of common experience that these
summary proceedings of execution are not decided within three months.
Hence this Court finds that the Labour Court acting u/s 33C(2) of Industrial
Disputes Act should be empowered to award interest.

(emphasis added)

Thus in the judgment of this Court in Municipal Council, Bhandara
Versus. Vimal wd/o Sadaram Kodape the coordinate bench, after
noticing absence of provision for award of interest under Section 33-
C(2), has made an observation that such provision needs to be made
especially where the proceedings under Section 33-C(2) itself takes long
time to decide, contrary to statutorily prescribed period of 3 months.
This Court did observe that award of interest was actually warranted,
but on account of absence of statutory provision, this Court felt that the
same could not be awarded. Also, it appears that attention of this Court
was not drawn to the judgment in Prabhavati Ramgarib B. while
deciding the case Municipal Council, Bhandara Versus. Vimal wd/o
Sadaram Kodape.





                                      Page No.19 of 23
                                       25 March 2025
     ::: Uploaded on - 27/03/2025                          ::: Downloaded on - 27/03/2025 21:36:09 :::
 NEETA SAWANT                                                        WP-18098-2024-FC



25)              Thus, following the judgment of this Court in Prabhavati

Ramgarib B. various High Courts have taken a view that interest can be
awarded on delayed payment of dues arising out of implementation of
Award. The view expressed by coordinate bench in Prabhavati
Ramgarib B. is held to be good law by the Apex Court in Dushyant
Dalal. In some judgments, it is held that the award of interest can be in
exercise of jurisdiction under Section 33-C(2) of the I.D. Act, whereas in
some judgments, it is held that even if there is absence of provision for
award of interest under Section 33-C(2) of the ID Act, High Court can
always award interest if it notices delay in implementation of award.

26) Mr. Shetty has relied upon various judgments in support of
his contention that in a limited remit of enquiry under Section 33-C(2),
the Labour Court can only compute pre-existing right or benefit and
cannot add anything to the Award. The law appears to be fairly well
settled that the Labour Court has no jurisdiction to first decide
workmen’s entitlement and then proceed to compute the benefit so
adjudicated on the basis of exercise of its power under Section 33-C(2)
of the Act. It is only when the entitlement has been earlier adjudicated
or recognised by the employer, jurisdiction under Section 33-C(2) can
be exercised merely as an executing court by leaving ambiguity if any
in exercise of power to interpret the decree. However, none of the
judgments relied upon by Mr. Shetty deal with the issue of payment of
interest on account of delay on the part of the employer to implement
the Award. Therefore, none of the judgments relied upon by Mr. Shetty
have any remote application to the facts of the present case. It is
therefore considered unnecessary to discuss the ratio of judgments
relied on by Mr. Shetty.





                                     Page No.20 of 23
                                      25 March 2025
      ::: Uploaded on - 27/03/2025                      ::: Downloaded on - 27/03/2025 21:36:09 :::
 NEETA SAWANT                                                        WP-18098-2024-FC



27)              Turning to the facts of the present case, the Award was

made on 16 September 1999. It directed reinstatement of the two
workmen with continuity and full backwages w.e.f. 29 May 1997.
Respondent-Bank went on litigating before this Court in two rounds of
litigation and apparently did not implement the Award till its Appeal
came to be dismissed by the Division Bench on 10 June 2014. It is only
on 6 January 2015 that the Respondent-Bank offered amount of
Rs.1,99,280/- to each of the two workmen and also called upon
Mr. Vijay Patil to report for duties. It appears that Shri. Kotharkar had
already reported for duties in July 2010. The issue here is whether the
Bank should be permitted to take advantage of its own wrong by not
implementing the Award for over 17 long years. As a matter of fact, the
said delay of 17 years latter escalated to 26 years as the final order for
payment of dues came to be passed by the CGIT on 29 August 2024.
The issue therefore is whether the employer can escape the liability to
pay interest on amount which was payable 24 years ago ? The answer
to the question, to my mind, appears to be in emphatic in the negative.
The facts of the present case are such that this Court would be
otherwise justified in awarding interest in exercise of its extraordinary
jurisdiction, if not under Section 33-C(2) of the ID Act.

28) Having held that the Petitioners would be entitled for
award of interest, the next issue is the rate of interest and the period for
which the same is to be awarded. The calculation of amount of Rs.
8,58,525/- in respect of both the employees would indicate that the
same is towards wages for the period from 1998 to 2014. This shows
that the CGIT has not awarded any sum towards backwages after
issuance of letter dated 6 January 2015 by the Bank offering backwages
and calling upon Shri. Vijay Patil to report for duties. Since Shri.
Kotharkar had already reported for duties in July 2010, the salary

Page No.21 of 23
25 March 2025
::: Uploaded on – 27/03/2025 ::: Downloaded on – 27/03/2025 21:36:09 :::
NEETA SAWANT WP-18098-2024-FC

drawn by him after July 2010 is deducted and his claim is upheld only
for Rs.5,53,162/-. Thus, what was payable in the year 1998 was partly
offered to the workers in January 2015 and would now be ultimately
paid as a result of order dated 29 August 2024 passed by the CGIT. The
amount of Rs.1,98,280/- offered towards backwages by Respondent-
Bank does not match with the figure of Rs.8,58,825/- ultimately
accepted by the CGIT for the period from 1998 to 2014. Therefore, the
employees had rightly refused to accept the amount of Rs.1,98,280/-
offered to them in January 2015. Considering the facts and
circumstances of the present case where part sums were offered to the
workmen by the employer in January 2015, in my view, award of
interest at the rate of 6% p.a. on the amount of backwages till the date
of actual payment would be appropriate. Such interest will have to be
calculated for the period when the amounts became due till the same is
actually realised. For ease of calculations, the amount of wages payable
in respect of each year be considered as payable in December of that
year and interest thereon be calculated from first day of January of
following year till the date of actual payment of the said amount. To
illustrate, in respect of Shri. Vijay Patil, wages of Rs.28,600/- were
payable for the entire year 1998. Therefore, the said amount of
Rs.28,600/- shall carry interest at the rate of 6% p.a. from 1 January 1999
till the date of actual payment. Similarly, in respect of wages for the
period 1999, an amount of Rs. 31,350/- simple interest at the rate of 6%
p.a. would be payable from 1 January 2000 till the date of actual
payment. This is how the interest payable on the delayed payment of
interest of simple interest of 6% p.a. is required to be computed and
paid to the legal heirs of the concerned workers.





                                    Page No.22 of 23
                                     25 March 2025
     ::: Uploaded on - 27/03/2025                      ::: Downloaded on - 27/03/2025 21:36:09 :::
                 NEETA SAWANT                                                         WP-18098-2024-FC



                29)               The petition accordingly succeeds, and I proceed to pass
                the following order:


                           (i)     The Petitioners would be entitled to simple interest of

6% p.a. on the amount awarded by the CGIT, which is to
be computed in accordance with the methodology
suggested above.

(ii) The Respondent-Bank shall pay the amount of interest to
the Petitioner within a period of two months.

30) With the above directions, the petition is allowed and disposed
of. There shall be no order as to costs.




         Digitally
         signed by                                                [SANDEEP V. MARNE, J.]
         NEETA
NEETA    SHAILESH
SHAILESH SAWANT
SAWANT Date:
         2025.03.25
         16:01:03
         +0530




                                                      Page No.23 of 23
                                                       25 March 2025
                      ::: Uploaded on - 27/03/2025                       ::: Downloaded on - 27/03/2025 21:36:09 :::
 

[ad_1]

Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here