1. This Appeal, under Section 54 of the Land Acquisition Act,

1894 [hereinafter referred to as “the LA Act”], is filed by the Acquiring

Body and the State against the Judgment and Award dated 20.02.2013,

passed by the learned 4th Joint Civil Judge, Senior Division, Osmanabad

[hereinafter referred to as ‘the Reference Court’], in Land Acquisition

Reference No. 23 of 2006. The operative order of the said Judgment

reads as under : –

“ORDER

1. The references are partly allowed.

2. The respondents shall pay the claimants in all the LAR
enhanced compensation at the rate of Rs. 73,750/- per
acre for their acquired seasonally land along with all
statutory benefits. The amount of compensation which
is already withdrawn by the claimants under protest be
deducted by the enhanced amount of compensation.