Johnson Controls Hitachi Air … vs M/S. Shapoorji Pallonji And Company Pvt … on 23 April, 2025

0
43

Calcutta High Court

Johnson Controls Hitachi Air … vs M/S. Shapoorji Pallonji And Company Pvt … on 23 April, 2025

Author: Shampa Sarkar

Bench: Shampa Sarkar

     ORDER                                                            OCD-11
                      IN THE HIGH COURT AT CALCUTTA
                           COMMERCIAL DIVISION
                               ORIGINAL SIDE

                        AP-COM/315/2025
        JOHNSON CONTROLS HITACHI AIR CONDITIONING INDIA LTD.
                                VS
           M/S. SHAPOORJI PALLONJI AND COMPANY PVT LTD.

BEFORE:
The Hon'ble JUSTICE SHAMPA SARKAR
Date: 23rd April, 2025.
                                                                        Appearance:
                                                           Mr. Amit Kr. Ghosh, Adv.
                                                            Mr. A. Mukherjee, Adv.
                                                                    ...for petitioner.
                                                             Ms. Setu Das Roy, Adv.
                                                          Ms. Suranjana Nandi, Adv.
                                                                  ...for respondent.


1.   This is an application for appointment of a learned arbitrator by way a

     composite reference in respect of ten work orders, each of which contains

     a dispute resolution clause.      The dispute resolution clause reads as

     follows:-

       "18.1      All disputes or difference of opinions, on account of

       interpretation of clauses, technical specifications,etc. shall be resolved

       through direct and mutual discussions at site level.       In the case of

       difference of opinion still persisting then the matter shall be referred to

       Regional Head of the Contractor. However, in case parties fail to reach

       amicable settlement, the matter shall be referred to arbitration.

       However, Contractor reserves the rights to appoint Sole Arbitrator in
                                        2


       the case of dispute and the Arbitration proceedings shall be governed

       as per Indian Arbitration & Conciliation Act 1996 and shall be held in

       Kolkata."

2.   The petitioner contends that by a single Letter of Intent (LOI), the

     proposed work for design, supply, installation, testing and commissioning

     of HVAC System for five hospitals at West Bengal, viz., Jalpaiguri,

     Gopiballavpur, Egra, Panskura and Ghatal, was offered to the petitioner.

     A composite value for all the works at the five locations as offered by the

     petitioner to the tune of Rs.12,35,00,000/- was accepted by the

     respondent. Thus, it is submitted that although the LOI was followed by

     ten work orders, for all practical purposes the conduct of the parties

     would indicate that the works arose out of one LOI and were a part of one

     single business transaction. The petitioner raised certain disputes with

     regard to payments and/or delay in payments. The emails sent by the

     petitioner to the representative of the respondent have been brought to the

     notice of the Court, in support of the contention that negotiations for

     composite payments were going on and some payment was received. The

     various emails relied upon, according to the petitioner, indicate that

     negotiations were on with regard to the payments due and outstandings

     as per the petitioner's claim and part of such claims were also paid. Thus,

     it is submitted by the petitioner that further scope for an amicable

     settlement is unlikely. A composite notice invoking arbitration was also

     issued by the petitioner, which was received by the respondent.
                                          3


3.   Ms. Das Roy, learned advocate for the respondent, objects to the prayer

     for composite reference on the ground that ten separate work orders were

     issued and each of the work orders contains a specific dispute resolution

     clause. The sites where the works are to be executed were also different.

     Under such circumstances, separate references should be made.            The

     learned advocate also objects to the claim on the ground that most of the

     remaining claims are inadmissible. Reference has been further made to

     the reply to the notice of invocation. The respondent expressed the desire

     to appoint an arbitrator as per the terms separately, for each work order.

4.   Unilateral appointment of an arbitrator is not permissible in law.

5.   Reference is made to the following decisions Perkins Eastman Architects

     DPC and Another vs. HSCC (India) Ltd. reported in 2019 SCC OnLine

     SC 1517, and Central Organisation for Railway Electrification vs.

     ECI SPIC SMO MCML (JV) A joint Venture Company reported in 2024

     SCC OnLine SC 3219.

6.   The   Hon'ble   Apex   Court   in   Central   Organization   for     Railway

     Electrification (supra), held thus:-

        "73. The 2015 amendment has introduced concrete standards of
        impartiality and independence of arbitrators. One of the facets of
        impartiality is procedural impartiality. Procedural impartiality implies
        that the rules constitutive of the decision-making process must favour
        neither party to the dispute or favour or inhibit both parties
        equally.137 Further, a procedurally impartial adjudication entails
        equal participation of parties in all aspects of adjudication for the
        process to approach legitimacy.138 Participation in the adjudicatory
        process is meaningless for a party against whom the arbitrator is
        already prejudiced.139 Equal participation of parties in the process of
                                   4


   appointment of arbitrators ensures that both sides have an equal say
   in the establishment of a genuinely independent and impartial arbitral
   process.
   74. Under Sections 12(1) and 12(5), the Arbitration Act recognises
   certain mandatory standards of independent and impartial tribunals.
   The parties have to challenge the independence or impartiality of the
   arbitrator or arbitrators in terms of Section 12(3) before the same
   arbitral tribunal under Section 13.140 If the tribunal rejects the
   challenge, it has to continue with the arbitral proceedings and make
   an award. Such an award can always be challenged under Section 34.
   However, considerable time and expenses are incurred by the parties
   by the time the award is set aside by the courts. Equal participation of
   parties at the stage of the appointment of arbitrators can thus obviate
   later challenges to arbitrators.
   75. Independence and impartiality of arbitral proceedings and equality
   of parties are concomitant principles. The independence and
   impartiality of arbitral proceedings can be effectively enforced only if
   the parties can participate equally at all stages of an arbitral process.
   Therefore, the principle of equal treatment of parties applies at all
   stages of arbitral proceedings, including the stage of the appointment
   of arbitrators.
   ***

124. The doctrine of bias as evolved in English and Indian law
emphasizes independence and impartiality in the process of
adjudication to inspire the confidence of the public in the adjudicatory
processes. Although Section 12 deals with the quality of independence
and impartiality inherent in the arbitrators, the provision’s emphasis
is to ensure an independent and impartial arbitral process.”

In Perkins Eastman (supra), the Hon’ble Apex Court held thus :-

…”20. We thus have two categories of cases. The first, similar to the
one dealt with in TRF Ltd. [TRF Ltd. v. Energo Engg. Projects Ltd.,
(2017) 8 SCC 377 : (2017) 4 SCC (Civ) 72] where the Managing
Director himself is named as an arbitrator with an additional power
to appoint any other person as an arbitrator. In the second category,
the Managing Director is not to act as an arbitrator himself but is
empowered or authorised to appoint any other person of his choice or
discretion as an arbitrator. If, in the first category of cases, the
Managing Director was found incompetent, it was because of the
interest that he would be said to be having in the outcome or result of
the dispute. The element of invalidity would thus be directly relatable
5

to and arise from the interest that he would be having in such
outcome or decision. If that be the test, similar invalidity would
always arise and spring even in the second category of cases. If the
interest that he has in the outcome of the dispute, is taken to be the
basis for the possibility of bias, it will always be present irrespective
of whether the matter stands under the first or second category of
cases. We are conscious that if such deduction is drawn from the
decision of this Court in TRF Ltd. [TRF Ltd. v. Energo Engg. Projects
Ltd.
, (2017) 8 SCC 377 : (2017) 4 SCC (Civ) 72] , all cases having
clauses similar to that with which we are presently concerned, a
party to the agreement would be disentitled to make any appointment
of an arbitrator on its own and it would always be available to argue
that a party or an official or an authority having interest in the
dispute would be disentitled to make appointment of an arbitrator.

21. But, in our view that has to be the logical deduction from TRF
Ltd. [TRF Ltd. v. Energo Engg. Projects Ltd.
, (2017) 8 SCC 377 :

(2017) 4 SCC (Civ) 72] Para 50 of the decision shows that this Court
was concerned with the issue, “whether the Managing Director, after
becoming ineligible by operation of law, is he still eligible to nominate
an arbitrator” The ineligibility referred to therein, was as a result of
operation of law, in that a person having an interest in the dispute or
in the outcome or decision thereof, must not only be ineligible to act
as an arbitrator but must also not be eligible to appoint anyone else
as an arbitrator and that such person cannot and should not have
any role in charting out any course to the dispute resolution by
having the power to appoint an arbitrator. The next sentences in the
paragraph, further show that cases where both the parties could
nominate respective arbitrators of their choice were found to be
completely a different situation. The reason is clear that whatever
advantage a party may derive by nominating an arbitrator of its
choice would get counter-balanced by equal power with the other
party.But, in a case where only one party has a right to appoint a sole
arbitrator, its choice will always have an element of exclusivity in
determining or charting the course for dispute resolution. Naturally,
the person who has an interest in the outcome or decision of the
dispute must not have the power to appoint a sole arbitrator. That
has to be taken as the essence of the amendments brought in by the
Arbitration and Conciliation (Amendment) Act, 2015 (3 of 2016) and
recognised by the decision of this Court in TRF Ltd. [TRF
Ltd. v. EnergoEngg. Projects Ltd., (2017) 8 SCC 377 : (2017) 4 SCC
(Civ) 72]

24. In Voestalpine [Voestalpine Schienen GmbH v. DMRC, (2017) 4
SCC 665 : (2017) 2 SCC (Civ) 607] , this Court dealt with
6

independence and impartiality of the arbitrator as under : (SCC pp.
687-88 & 690-91, paras 20 to 22 & 30)
“20. Independence and impartiality of the arbitrator are the
hallmarks of any arbitration proceedings. Rule against bias is one of
the fundamental principles of natural justice which applied to all
judicial and quasi-judicial proceedings. It is for this reason that
notwithstanding the fact that relationship between the parties to the
arbitration and the arbitrators themselves are contractual in nature
and the source of an arbitrator’s appointment is deduced from the
agreement entered into between the parties, notwithstanding the
same non-independence and non-impartiality of such arbitrator
(though contractually agreed upon) would render him ineligible to
conduct the arbitration. The genesis behind this rational is that even
when an arbitrator is appointed in terms of contract and by the
parties to the contract, he is independent of the parties. Functions
and duties require him to rise above the partisan interest of the
parties and not to act in, or so as to further, the particular interest of
either parties. After all, the arbitrator has adjudicatory role to
perform and, therefore, he must be independent of parties as well as
impartial. The United Kingdom Supreme Court has beautifully
highlighted this aspect in Hashwani v. Jivraj [Hashwani v. Jivraj,
(2011) 1 WLR 1872 : 2011 UKSC 40] in the following words : (WLR p.
1889, para 45)
’45. … the dominant purpose of appointing an arbitrator or
arbitrators is the impartial resolution of the dispute between the
parties in accordance with the terms of the agreement and, although
the contract between the parties and the arbitrators would be a
contract for the provision of personal services, they were not personal
services under the direction of the parties.’

21. Similarly, Cour de Cassation, France, in a judgment delivered in
1972 in Consorts Ury [Fouchard, Gaillard, Goldman on International
Commercial Arbitration, 562 [Emmanuel Gaillard & John Savage
(Eds.) 1999] {quoting Cour de cassation [Cass.] [Supreme Court for
judicial matters] Consorts Ury v. S.A. des Galeries Lafayette, Cass.2e
civ., 13-4-1972, JCP, Pt. II, No. 17189 (1972) (France)}.] , underlined
that:

‘an independent mind is indispensable in the exercise of judicial
power, whatever the source of that power may be, and it is one of the
essential qualities of an arbitrator’.

22. Independence and impartiality are two different concepts. An
arbitrator may be independent and yet, lack impartiality, or vice
versa. Impartiality, as is well accepted, is a more subjective concept
as compared to independence. Independence, which is more an
objective concept, may, thus, be more straightforwardly ascertained
7

by the parties at the outset of the arbitration proceedings in light of
the circumstances disclosed by the arbitrator, while partiality will
more likely surface during the arbitration proceedings.

***

30. Time has come to send positive signals to the international
business community, in order to create healthy arbitration
environment and conducive arbitration culture in this country.
Further, as highlighted by the Law Commission also in its report,
duty becomes more onerous in government contracts, where one of
the parties to the dispute is the Government or public sector
undertaking itself and the authority to appoint the arbitrator rests
with it. In the instant case also, though choice is given by DMRC to
the opposite party but it is limited to choose an arbitrator from the
panel prepared by DMRC. It, therefore, becomes imperative to have a
much broadbased panel, so that there is no misapprehension that
principle of impartiality and independence would be discarded at any
stage of the proceedings, specially at the stage of constitution of the
Arbitral Tribunal. We, therefore, direct that DMRC shall prepare a
broadbased panel on the aforesaid lines, within a period of two
months from today…”

7. I have considered the rival contentions of the parties. It is not in dispute

that a single LOI was issued on November 16, 2015, whereby and

whereunder, the final offer of the petitioner with regard to the execution of

the work mentioned in the said LOI was accepted. The letter records that

the final offer by the petitioner was furnished by a single offer letter dated

November 5, 2015. A composite offer to the tune of Rs.12,35,00,000/-

inclusive of material, labourers, taxes, duties, provident fund, freight,

transit insurance, handling charges, cess, levies and other incidental

charges etc. except VAT and Service Tax was made by the petitioner, in

respect of the projects. By the said LOI, the petitioner was also asked by

the Project Director of the respondent to start the preliminary activities.

Thereafter, item-wise break-up was also asked in respect of individual
8

hospitals. It is clear from the said LOI that at the very initial stage, a

composite price was offered by the petitioner, as the sub-contractor and

the said composite price was accepted. Based on the said LOI,which was

issued in respect of all the five projects, preliminary activities commenced

from the side of the sub-contractor. From the stage of issuance of the said

LOI, it is evident that the respondent treated the projects at five different

locations as a single business transaction between the parties. The work

orders which followed the LOIspecified the terms and conditions of the

work orders. In each of the work orders the LOI was mentioned. The e-

mails which have been annexed to the application clearly indicate that

some consolidated payments were made in respect of some of the projects,

in spite of separate bills having been raised for each of the locations. The

replies of the respondent via e-mails, do not indicate that the respondent

had any objection when the negotiationstook place with regard to the

outstanding dues of all the five projects, in a composite manner. A

consolidated payment was also made.

8. The petitioner has relied on a decision of this court in the case of M/s.

Sauryajyoti Renewables Pvt. Ltd. vs. VSL RE Power Private Limited in

support of his contention that, this court haddirected such composite

reference in the matter, upon noting the communications between the

parties.

9. For the reasons which have been mentioned hereinabove, this court is of

the view that a composite reference will be beneficial for all the parties and
9

the same is permissible in the facts and circumstances of the case. The

very acceptance of the offer of the petitioner at the consolidated price in

respect of the works to be executed at five different locations, clearly

indicates that the parties, by conduct, had treated the offer of work as a

part of the single transaction and the negotiations were also going on for a

consolidated payment of total sum due. In any event, arbitrability of the

issues, admissibility of the claims, limitation, etc. should be raised before

the learned Arbitrator and the learned Arbitrator shall decide such issues

in accordance with law.

10. The application is disposed of by appointing Mr. Shashwat Nayak,

Advocate, Bar Library Club [M: 8910251490], to arbitrate upon the

disputes between the parties. This appointment is subject to compliance of

Section 12 of the Arbitration and Conciliation Act, 1996. The learned

Arbitrator shall fix his remuneration as per the Schedule of the Arbitration

and Conciliation Act, 1996.

11. Liberty is granted to the learned advocate for the respondent to file the

Vakalatnama within ten days from date.

(SHAMPA SARKAR, J.)

S. Kumar / pkd / JM / R.D. Barua

[ad_1]

Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here