Jana Construction vs Union Of India And Anr on 29 April, 2025

0
40

Calcutta High Court

Jana Construction vs Union Of India And Anr on 29 April, 2025

Author: Shampa Sarkar

Bench: Shampa Sarkar

OCD-14
                           AP-COM/283/2025
                    IN THE HIGH COURT AT CALCUTTA
                  ORDINARY ORIGINAL CIVIL JURISDICTION
                         COMMERCIAL DIVISON


                            JANA CONSTRUCTION
                                     VS
                           UNION OF INDIA AND ANR

 BEFORE:
 The Hon'ble JUSTICE SHAMPA SARKAR
 Date : 29th April, 2025.

                                                                            Appearance:
                                                                 Mr. S.N. Dhuria, Adv.
                                                                  . . .for the petitioner.

                                                           Mr. Dhruv Surana, Adv.
                                                           Ms. Sumita Sarkar, Adv.
                                                             . . .for the respondent.


    The Court:

    1. This is an application for appointment of an arbitrator under Clause

         25(ii) of the General Conditions of Contract For Central P.W.D. Works

         2014. The petitioner is a registered CPWD's enlisted government

         contractor.   Work was allotted to the petitioner by a letter dated

         September 12, 2018. An agreement was entered into by and between

         the parties pursuant to the said letter of allotment.

    2. According to the petitioner, the work was allegedly completed on April

         30, 2019.     The petitioner submitted his third and final bill for an

         amount of Rs.51,57,125/- on October 21, 2019. By a letter dated April

         19, 2022 the petitioner requested the respondent no.2 to release the

         third and final bill. The petitioner also submitted a statement of claim.
                                2


Once again the petitioner requested the respondent no.2 vide letter

dated May 17, 2022 for release of the amount claimed under the third

and final bill. The respondent no.2 did not take any steps. Thereafter,

by a letter dated June 16, 2022 the petitioner requested the respondent

no.1 to refer the dispute to the Dispute Resolution Committee (in Short

DRC). A revised claim was submitted before the respondent no.1. By a

letter dated June 21, 2022, the respondent no.1 referred the matter to

the Dispute Resolution Committee. The petitioner wrote a letter to the

respondent no.1, reminding him that the DRC should deliver the

decision within sixty days from the date of reference, and that not a

single meeting had been held by the DRC.         Later, an amount of

Rs.11,19,360/- was released against the final bill and the petitioner

accepted the same under protest. Thereafter, the petitioner requested

for release of the security deposit. By a letter dated October 14, 2022,

the respondent no. 2 informed the petitioner that the claims have been

settled.   Again the petitioner requested for release of the security

deposit, reimbursement of ESI and PF, compensation for increase in

labour charges, interest for delayed payment etc., by a letter dated

November 11, 2022.       Another claim was made by a letter dated

November 14, 2022, for escalation of labour charges.     The petitioner

submitted a brief statement of claim of Rs.16,80,013/- before the DRC.

The first meeting of the DRC was to be held on November 17, 2022. The

DRC delivered its final decision on November 30, 2022 and made

recommendations. According to the petitioner, he was not heard by the
                                  3


  DRC. The recommendation of the DRC was objected to and by a letter

  dated April 6, 2023 the petitioner requested the DRC to recall the

  decision. The petitioner filed objections to the final recommendation of

  the DRC before the Special Director General. The petitioner wrote to the

  respondent no.1 and 2, pointing out the discrepancies in the decision of

  the final recommendation and served a notice on March 7, 2024 along

  with a statement of claim, with a request for appointment of an in house

  Arbitrator. No steps were taken.

3. The petitioner once again requested the respondent no.1 to appoint an

  in house Arbitrator.   Thereafter, on January 18, 2025 the petitioner

  issued a notice invoking arbitration. The above correspondence clearly

  indicate that the pre-arbitration mechanism as required to be exhausted

  by the petitioner had been exhausted. The decision of the DRC was not

  accepted by the petitioner. The petitioner alleges of not being heard.

  The DRC was requested to recall the final recommendation. The DRC

  did not take any steps. Thus, the petitioner waited for some time before

  issuing the notice for appointment of a learned Arbitrator.

4. The petitioner also approached the Special Director General for

  appointment of an in house Arbitrator in terms of Clause 25(ii) but no

  such appointment was made. In any event, the mechanism provided for

  appointment of an Arbitrator under the GCC is no-longer permissible in

  law. The said clause provides that disputes which are not settled by the

  DRC or if the decision of the DRC does not become final and binding,
                                   4


  the same shall be settled by arbitration. The petitioner did not accept

  the decision of the DRC.

5. A person who is unable to act as an Arbitrator, cannot appoint an

  Arbitrator. That is the settled principal of law, as laid down in the

  decisions Perkins Eastman Architects DPC and Another vs. HSCC

  (India) Ltd. reported in 2019 SCC OnLine SC 1517, and Central

  Organisation for Railway Electrification vs. ECI SPIC SMO MCML

  (JV) A joint Venture Company reported in 2024 SCC OnLine SC

  3219.

6. The Hon'ble Apex Court in Central Organization for Railway

  Electrification (supra), held thus:-


    "73. The 2015 amendment has introduced concrete standards of
    impartiality and independence of arbitrators. One of the facets of
    impartiality is procedural impartiality. Procedural impartiality implies
    that the rules constitutive of the decision-making process must favour
    neither party to the dispute or favour or inhibit both parties
    equally.137 Further, a procedurally impartial adjudication entails
    equal participation of parties in all aspects of adjudication for the
    process to approach legitimacy.138 Participation in the adjudicatory
    process is meaningless for a party against whom the arbitrator is
    already prejudiced.139 Equal participation of parties in the process of
    appointment of arbitrators ensures that both sides have an equal say
    in the establishment of a genuinely independent and impartial arbitral
    process.
    74. Under Sections 12(1) and 12(5), the Arbitration Act recognises
    certain mandatory standards of independent and impartial tribunals.
    The parties have to challenge the independence or impartiality of the
    arbitrator or arbitrators in terms of Section 12(3) before the same
                                  5


arbitral tribunal under Section 13.140 If the tribunal rejects the
challenge, it has to continue with the arbitral proceedings and make
an award. Such an award can always be challenged under Section 34.
However, considerable time and expenses are incurred by the parties
by the time the award is set aside by the courts. Equal participation of
parties at the stage of the appointment of arbitrators can thus obviate
later challenges to arbitrators.
75. Independence and impartiality of arbitral proceedings and equality
of   parties   are   concomitant     principles.   The    independence        and
impartiality of arbitral proceedings can be effectively enforced only if
the parties can participate equally at all stages of an arbitral process.
Therefore, the principle of equal treatment of parties applies at all
stages of arbitral proceedings, including the stage of the appointment
of arbitrators.
***

124. The doctrine of bias as evolved in English and Indian law
emphasizes independence and impartiality in the process of
adjudication to inspire the confidence of the public in the adjudicatory
processes. Although Section 12 deals with the quality of independence
and impartiality inherent in the arbitrators, the provision’s emphasis
is to ensure an independent and impartial arbitral process.
***
In Perkins Eastman (supra), the Hon’ble Apex Court held thus

:-

…”20. We thus have two categories of cases. The first, similar to the
one dealt with in TRF Ltd. [TRF Ltd. v. Energo Engg. Projects Ltd.,
(2017) 8 SCC 377 : (2017) 4 SCC (Civ) 72] where the Managing
Director himself is named as an arbitrator with an additional power to
appoint any other person as an arbitrator. In the second category, the
Managing Director is not to act as an arbitrator himself but is
empowered or authorised to appoint any other person of his choice or
discretion as an arbitrator. If, in the first category of cases, the
Managing Director was found incompetent, it was because of the
interest that he would be said to be having in the outcome or result of
the dispute. The element of invalidity would thus be directly relatable
6

to and arise from the interest that he would be having in such
outcome or decision. If that be the test, similar invalidity would always
arise and spring even in the second category of cases. If the interest
that he has in the outcome of the dispute, is taken to be the basis for
the possibility of bias, it will always be present irrespective of whether
the matter stands under the first or second category of cases. We are
conscious that if such deduction is drawn from the decision of this
Court in TRF Ltd. [TRF Ltd. v. Energo Engg. Projects Ltd., (2017) 8
SCC 377 : (2017) 4 SCC (Civ) 72] , all cases having clauses similar to
that with which we are presently concerned, a party to the agreement
would be disentitled to make any appointment of an arbitrator on its
own and it would always be available to argue that a party or an
official or an authority having interest in the dispute would be
disentitled to make appointment of an arbitrator.

21. But, in our view that has to be the logical deduction from TRF
Ltd. [TRF Ltd. v. EnergoEngg. Projects Ltd., (2017) 8 SCC 377 : (2017)
4 SCC (Civ) 72] Para 50 of the decision shows that this Court was
concerned with the issue, “whether the Managing Director, after
becoming ineligible by operation of law, is he still eligible to nominate
an arbitrator” The ineligibility referred to therein, was as a result of
operation of law, in that a person having an interest in the dispute or
in the outcome or decision thereof, must not only be ineligible to act
as an arbitrator but must also not be eligible to appoint anyone else as
an arbitrator and that such person cannot and should not have any
role in charting out any course to the dispute resolution by having the
power to appoint an arbitrator. The next sentences in the paragraph,
further show that cases where both the parties could nominate
respective arbitrators of their choice were found to be completely a
different situation. The reason is clear that whatever advantage a
party may derive by nominating an arbitrator of its choice would get
counter-balanced by equal power with the other party.But, in a case
where only one party has a right to appoint a sole arbitrator, its choice
will always have an element of exclusivity in determining or charting
the course for dispute resolution. Naturally, the person who has an
interest in the outcome or decision of the dispute must not have the
power to appoint a sole arbitrator. That has to be taken as the essence
of the amendments brought in by the Arbitration and Conciliation
(Amendment) Act, 2015
(3 of 2016) and recognised by the decision of
this Court in TRF Ltd. [TRF Ltd. v. EnergoEngg. Projects Ltd., (2017) 8
SCC 377 : (2017) 4 SCC (Civ) 72]

24. In Voestalpine [VoestalpineSchienen GmbH v. DMRC, (2017) 4
SCC 665 : (2017) 2 SCC (Civ) 607] , this Court dealt with
independence and impartiality of the arbitrator as under : (SCC pp.
687-88 & 690-91, paras 20 to 22 & 30)
“20. Independence and impartiality of the arbitrator are the hallmarks
of any arbitration proceedings. Rule against bias is one of the
fundamental principles of natural justice which applied to all judicial
7

and quasi-judicial proceedings. It is for this reason that
notwithstanding the fact that relationship between the parties to the
arbitration and the arbitrators themselves are contractual in nature
and the source of an arbitrator’s appointment is deduced from the
agreement entered into between the parties, notwithstanding the same
non-independence and non-impartiality of such arbitrator (though
contractually agreed upon) would render him ineligible to conduct the
arbitration. The genesis behind this rational is that even when an
arbitrator is appointed in terms of contract and by the parties to the
contract, he is independent of the parties. Functions and duties
require him to rise above the partisan interest of the parties and not to
act in, or so as to further, the particular interest of either parties. After
all, the arbitrator has adjudicatory role to perform and, therefore, he
must be independent of parties as well as impartial. The United
Kingdom Supreme Court has beautifully highlighted this aspect
in Hashwani v. Jivraj [Hashwani v. Jivraj, (2011) 1 WLR 1872 : 2011
UKSC 40] in the following words : (WLR p. 1889, para 45)
’45. … the dominant purpose of appointing an arbitrator or arbitrators
is the impartial resolution of the dispute between the parties in
accordance with the terms of the agreement and, although the
contract between the parties and the arbitrators would be a contract
for the provision of personal services, they were not personal services
under the direction of the parties.’

21. Similarly, Cour de Cassation, France, in a judgment delivered in
1972 in Consorts Ury [Fouchard, Gaillard, Goldman on International
Commercial Arbitration, 562 [Emmanuel Gaillard & John Savage
(Eds.) 1999] {quoting Cour de cassation [Cass.] [Supreme Court for
judicial matters] Consorts Ury v. S.A. des Galeries Lafayette, Cass.2e
civ., 13-4-1972, JCP, Pt. II, No. 17189 (1972) (France)}.] , underlined
that:

‘an independent mind is indispensable in the exercise of judicial
power, whatever the source of that power may be, and it is one of the
essential qualities of an arbitrator’.

22. Independence and impartiality are two different concepts. An
arbitrator may be independent and yet, lack impartiality, or vice versa.
Impartiality, as is well accepted, is a more subjective concept as
compared to independence. Independence, which is more an objective
concept, may, thus, be more straightforwardly ascertained by the
parties at the outset of the arbitration proceedings in light of the
circumstances disclosed by the arbitrator, while partiality will more
likely surface during the arbitration proceedings.

***

30. Time has come to send positive signals to the international
business community, in order to create healthy arbitration
environment and conducive arbitration culture in this country.
Further, as highlighted by the Law Commission also in its report, duty
becomes more onerous in government contracts, where one of the
8

parties to the dispute is the Government or public sector undertaking
itself and the authority to appoint the arbitrator rests with it. In the
instant case also, though choice is given by DMRC to the opposite
party but it is limited to choose an arbitrator from the panel prepared
by DMRC. It, therefore, becomes imperative to have a much
broadbased panel, so that there is no misapprehension that principle
of impartiality and independence would be discarded at any stage of
the proceedings, specially at the stage of constitution of the Arbitral
Tribunal. We, therefore, direct that DMRC shall prepare a broadbased
panel on the aforesaid lines, within a period of two months from
today…”

7. Under such circumstances, the petitioner has rightly approached this

Court for appointment of an Arbitrator.

8. Under such circumstances, the Court appoints Mr. Shounak

Mukhopadhyay, learned Advocate (Mobile No. 8981772268) as the

Arbitrator, to arbitrate upon the disputes between the parties. This

order is subject to compliance of Section 12 of the Arbitration and

Conciliation Act, 1996.

9. The learned Arbitrator shall fix his own remuneration as per the

provisions of the Arbitration and Conciliation Act.

10. AP-COM 283 of 2025 is, accordingly, disposed of.

(SHAMPA SARKAR, J.)
sp/

[ad_1]

Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here