S.P. Singla Constructions Pvt. Ltd vs Union Of India on 29 April, 2025

0
48

[ad_1]

. The parties had entered into a written

agreement for construction of sub-structure above well

cap & super structure of South approach Rail via-duct in

connection with Ganga Rail-cum-Road Bridge Project,

Patna dated 05.07.2010. The agreement contained

clause No. 63 for settlement of disputes.

3. A communication was made by the

petitioner to the General Manager, East Central Railway

specifying the claims and the nature of dispute between

the parties, which communication was not responded by

the railways.

4. This Court, vide judgment dated

15.12.2021, referred to above, found that the conditions

of clause 63 were not fulfilled. It was also noted that the

Supreme Court in Central Organisation for Railway

Electrification vs. ECI-SPIC-SMO-MCML (JV) :