Mohammed Sabir vs Union Of India & Ors on 24 June, 2025

0
2

Calcutta High Court (Appellete Side)

Mohammed Sabir vs Union Of India & Ors on 24 June, 2025

                                           1



                      IN THE HIGH COURT AT CALCUTTA

                  (CONSTITUTIONAL WRIT JURISDICTION)

                                 APPELLATE SIDE

Present :

The Hon'ble Justice Partha Sarathi Chatterjee

                                 WPA 8641 of 2024

                                 Mohammed Sabir

                                         Vs.

                               Union of India & Ors.

For the petitioner                 : Mr. Milan Chandra Bhattacharjee, Ld. Sr. Adv,

                                    Ms. Sulagna Bhattacharya.




For the UOI                        : Mr. Soumik Nandi, Ld. Sr. Adv.,

                                    Mr. Pradyut Saha.




Heard on                           : 20.05.2025

Judgment on                        : 24.06.2025

Partha Sarathi Chatterjee, J.:-

Preface:

   1.         The present writ petition challenges the legality of the order of

        termination dated 06.06.2023 issued by the Railway Authority, which

        pertains to the contract entered into with the petitioner. The petition also

        questions the consequent forfeiture of the security deposit, the issuance of a
                                             2



        new work order dated 22.06.2023, and the publication of a fresh e-auction

        notice dated 18.08.2023 inviting quotations from interested traders.

        Additionally, the petitioner seeks a direction upon the respondents to allow

the petitioner to continue and complete the remaining scheduled trips under

the terms and conditions of the original contract relating to the parcel service

on Train No. 12311 Netaji Express (Ex-HWH to KLK, SLR).

Petitioner’s Case:

2. Sans unnecessary details, the necessitous facts, as unfurled in the writ

petition, that need to be adumbrated are as follows:

i) An e-auction was floated by the Eastern Railway authorities,

Howrah Division, on 06.06.2023 for the allotment of parcel

space in SLR-F1 of Train No. 12311, Netaji Express (Ex-Howrah

to Kalka), at the rate of Rs. 42,300/- per 4 MT for 7 days a week,

for a period of two years commencing from 22nd June 2023 to

21st June 2025, covering a total of 731 trips.

ii) The petitioner, having recently ventured into the field of

railway-based trading and having emerged as the successful

bidder, was allotted the parcel space, and a formal contract was

executed on the same date. The lease was governed by both the

Special Conditions and the Standard Conditions of Contract, as

stipulated in the bid documents.

iii) On 11.08.2023, during a scheduled trip en route to Kalka,

which was the 52nd of 731 scheduled trips, the Railway

authorities allegedly detected an overweight consignment

measuring 4,344 kg, purportedly identified at Deen Dayal
3

Upadhyaya Railway Station amid heavy rainfall. The goods,

comprising garments and flowers, which were perishable in

nature, were unloaded and weighed. The petitioner’s

representative promptly visited the station on 12.08.2023 and

deposited the penalty amount.

iv) However, on 17.08.2023, the petitioner was served with an

order indicating that, for the alleged overweight consignment, a

penalty of Rs. 1,29,371 was imposed. In addition, the contract

was terminated and the security deposit of Rs. 7,71,975/- was

forfeited. On the same date, a fresh e-auction was also floated for

allotment of the parcel space to a third party. These actions

compelled the petitioner to file the present writ petition.

3. The petitioner challenged the legality and fairness of the impugned

actions on multiple grounds. It was alleged that the goods were not weighed in

the presence of the petitioner, rendering the claim of overweight detection

arbitrary and baseless. Furthermore, the petitioner was neither given prior

notice nor afforded an opportunity to respond or present a defence before the

alleged weighment was conducted. This is particularly significant given that,

in accordance with Clause 27.8, the Railway authorities were obligated to

make a bona fide effort to conduct the weighment in the presence of the

concerned leaseholder. The failure to adhere to this requirement constitutes a

clear violation of the principles of natural justice.

4. According to the petitioner, although the Railway authorities terminated

the contract and forfeit the security deposit referring to clause 28.3 and Clause
4

17.3 of the terms and conditions of the contract, these two clauses did not exist

in the Special Conditions and Standard Conditions of the Contract.

5. Clause 14.3 of the Special Conditions of Contract provides that the

contract can only be terminated, with forfeiture of the security deposit, if

overloading beyond the permissible tolerance limit is detected on more than

two occasions. Therefore, even assuming overloading occurred in the present

case, it was the first instance, and the condition for termination has not been

met.

6. Clauses 16 and 16.1 of the Standard Conditions of Contract provide for

an appeal against the order of termination and forfeiture of the security

deposit, which must be filed within 30 days from the date of such order.

Furthermore, Clauses 17 and 17.1 stipulate that if, for any reason, it becomes

impossible for the contractor to continue with the contract, the contract may

be terminated by giving 30 days’ notice, provided that a minimum period of

six months under the contract has been completed. In such a case, the entire

security deposit is to be refunded. However, in the present case, before expiry

of that period, a fresh tender was floated prematurely on 18.08.2023. The

petitioner contended that, as a result of the actions undertaken by the Railway

authorities, he has suffered substantial financial loss.

7. The petitioner preferred an appeal under Clause 16 by submitting a

representation to the Chief Commercial Manager and Divisional Railway

Manager (DRM) on 21.08.2023. During pendency of the appeal, the petitioner

preferred a writ petition, WPA 21549 of 2023. Taking note of the fact that the

appeal had already been disposed of, a Co-ordinate Bench accordingly

disposed of the writ petition, granting liberty to the petitioner to pursue
5

appropriate remedies in the event he is aggrieved by the order passed by the

Appellate Authority.

8. However, according to the petitioner, the appellate process was vitiated

by procedural irregularities. Although a personal hearing was granted on

12.09.2023 and an order was subsequently passed by the Appellate Authority

on 11.10.2023, the said order was never served upon the petitioner.

9. The petitioner further contends that the Appellate Authority erroneously

relied on Clauses 17.3 and 28.3 of the terms and conditions of the contract and

incorrectly concluded that the petitioner’s consignment weighed 8,344 kg,

whereas the permissible limit was 4 metric tonnes, i.e., 4,000 kg.

10. In view of these facts, the petitioner, in essence, the petitioner prays

for restoration of the contract, refund of the security deposit and penalty

amount, compensation for loss of goods and business.

Respondents’ case:

11. At Pandit Deen Dayal Upadhyaya (PDDU) Railway station, the Train

Examiner observed that the buffer height of the overloaded wagon was

significantly lower than that of the locomotive, thereby posing a serious safety

threat. Such a discrepancy could have potentially resulted in a derailment or

an accident with severe consequences. Accordingly, the Train Examiner

advised that the consignment loaded in the overloaded FSLR-I compartment

be unloaded and re-weighed.

12. Thereafter, based on a joint report dated 11.08.2023 issued by the Chief

Loco Inspector, PDDU Station, Senior Section Engineer (Carriage & Wagon),

PDDU Station, Chief Parcel Supervisor, PDDU Station, and the Deputy

Station Superintendent, PDDU Station, the consignment was unloaded and
6

weighed in the presence of Parcel Staff, Railway Protection Force (RPF), and

the Chief Loco Inspector. The weight of the consignment was found to be

8,344 kg, as against the permissible carrying capacity of 4,000 kg. A joint

inspection report was prepared. In order to complete the entire process, the

passenger train was halted for duration of two hours.

13. The petitioner was permitted to load the FSLR-1 compartment up to a

maximum limit of 4,000 kg. However, he loaded 8,344 kg, exceeding the

permissible limit by approximately 134%. Such excessive overloading, being

more than double the designated carrying capacity of the rake

14. Clause 18.1 of the Standard Conditions of Contract, as outlined in Freight

Marketing Circular No. 11 of 2022, empowers the Railway authorities to

terminate the contract at any time, without prior notice, as a punitive measure

in the event of any violation of the contractual terms and conditions or any

serious misconduct. Such misconduct includes, but is not limited to, violations

of the Railway Act, 1989, commission of unlawful acts contrary to good

industry practices, or acts involving moral turpitude. In such cases, the

authorities are also entitled to forfeit the entire Earnest Money Deposit (EMD)

and Security Deposit (SD). In view of the petitioner’s alleged serious

misconduct, the Railway authorities invoked Clause 18.1, terminated the

contract, and proceeded to forfeit the EMD and SD.

15. The affidavit-in-opposition refuted the allegation that the Railway

Authority had fabricated a ‘gossip’ regarding a discrepancy in buffer height

between the Locomotive and the Front SLR-I with any ulterior motive. It

further denied that this purported discrepancy was used as a pretext to justify

the unloading and re-weighing of the goods. The petitioner paid the penalty
7

amount on 12.08.2023. Subsequently, an order of termination was issued and

served upon the petitioner on 17.08.2023. The petitioner filed an appeal

against the termination order on 21.08.2023. A personal hearing was granted

to the petitioner on 12.09.2023, and the appeal was ultimately disposed of by

an order dated 11.10.2023, which was duly send by speed post at the

petitioner’s address mentioned in that writ petition.

16. In accordance with Item No. 65 of the New Items in the Schedule of

Powers (SOP) 2018, Part-E – Commercial Matters, when a bid or agreement

awarded through the e-Auction mode is terminated due to non-performance

or for any other reason as per the terms of the contract, the Railway

Administration is required to re-invite bids immediately through e-Auction.

This is done to monetise the Railway asset and prevent any potential loss of

revenue. The revised reserve price for the re-auction shall be fixed at an

amount equivalent to the second-highest bid received in the previous e-

Auction, or the original/reassessed reserve price, whichever is higher.

Therefore, to monetise the Railway asset and prevent any potential loss of

revenue, the re-auction process was initiated. The petitioner was free to

participate in the re-auction held on 4.9.2023.

17. The petitioner cannot claim only his contractual rights: he had to

discharge his contractual obligations also. The petitioner violated the terms of

the contract and as such, suffered an order of termination of contract and

forfeiture of EMD/SD for which it was the petitioner who himself was to

blame. The advance fare of 4 trips were taken from the petitioner and the

same is under process of payment. The answering respondents took exception
8

of the fact in the writ petition, the Railway authority was called as ‘monster’ by

the petitioner, who by overloading put the life of thousand passengers at risk.

18. In terms of Clause 10 of FM Circular No. 12 of 2022, the responsibility

for loading and unloading operations of parcels in the leased parcel space at

the originating, destination, and intermediate stations lies with the contractor.

Further, Clause 9.7 of the same circular stipulates that the contractor is

responsible for ensuring that the total weight of consignments loaded in the

parcel space does not exceed the permissible carrying capacity of the

vehicle/unit leased to them at any point during its journey. The act of

overloading by 134% of the permissible carrying capacity constitutes a blatant

violation of the contractual provisions and thereby endangering the lives of

travelling passengers.

Contents of affidavit-in-reply of the petitioner:

19. There was no overloading in the FSLR-I of the rake, and the goods were

unlawfully unloaded and weighed in the absence of the petitioner. The

situation arose due to defective buffers installed by the Railway authorities.

The train itself was faulty and operated as a slow-moving train, lacking

modern equipment, including an advanced locomotive braking system. The

difficulty in train movement resulted from the jamming of the buffers–not

from any overloading which is substantiated by the Expert’s report.

Accordingly, the petitioner cannot be held responsible for the buffer jamming

incident.

20. On 12.08.2023, under threat of arrest, the petitioner was forced to sign

on the Delivery Registrar and pay the exorbitant amount of penalty in

contravention of the Clause 14-4 of the Freight Marketing Circular no. 12 of
9

2022 and the Appellate Authority also accepted such contention of the

petitioner. The Railway authorities did not specify which clause or clauses was

or were violated by the petitioner.

21. The clause 10.4 of the Special Conditions for Contract stipulates that

after putting the padlock by the contractor before the departure of the train,

Railway staff can complete other formalities including sealing of brake van

(SLR). Therefore, since the sealing is done and/or supervised by the Railway

staff, story of overloading is unbelievable. The Railway authorities acted

illegally by imposing three punishments.

Submissions:

22. Mr. Bhattacharya, the learned Senior Advocate representing the

petitioner, contended that the alleged weighment of the goods was carried out

in absence of the petitioner. He emphasized that no prior notice was issued to

the petitioner, nor was any opportunity granted to respond or present a

defence before the weighment took place. He submitted that under Clause

27.8, the Railway authorities were duty-bound to make a genuine effort to

ensure that the weighment was conducted in the presence of the leaseholder.

The failure to comply with this procedural requirement amounts to a blatant

breach of the principles of natural justice.

23. He further submitted that Clause 10.4 of the Special Conditions of

Contract clearly states that once the contractor secures the consignment with

a padlock prior to the train’s departure, the Railway staff are responsible for

carrying out the remaining formalities, including sealing the brake van (SLR).

Given that the sealing process is undertaken and/or overseen by Railway
10

personnel, the allegation of overloading appears implausible and lacks

credibility.

24. He argued that any disruption in the smooth operation of the train was

attributable to defective buffers installed by the Railway authorities. The train

in question was outdated and lacked modern equipment, including an

advanced locomotive braking system. The difficulty in movement was caused

by buffer jamming, not by any overloading of goods. Therefore, the petitioner

cannot be held liable for the incident involving the jamming of the buffers.

25. He further argued that under clause 14.3 of the Special Conditions,

termination of contract is warranted only after the third instance of

overloading. However, in the case at hand, the overloading, if any, was a first-

time occurrence. Therefore, according to him, the Railway authorities have

illegally terminated the contract and forfeited the contract.

26. On 12.08.2023, the petitioner was coerced into signing the Delivery

Register and paying an unreasonably high penalty under the threat of arrest,

in blatant disregard of Clause 14.4 of the Freight Marketing Circular No. 12 of

2022. In addition to this, the Railway authorities proceeded to terminate the

contract and forfeit the security deposit. According to the petitioner, this

amounted to being penalized three times for a single alleged offence.

27. To bolster his submission, he cited certain decisions, reported at (1993) 4

SCC 727 (Managing Director Ecil Hyderabad Etc. .. vs. B. Karunakar Etc.),

AIR 2011 SC 2709 (Kesar Enterprises Ltd. Vs. State of U.P. & Ors.), (2010) 4

SCC 785 (Assistant Commissioner, Commercial Tax Department, Works

Contract and Leasing, Kota vs. Shukla And Brothers), (2020) 16 SCC 489

(Silppi Constructions Contractors vs. Union of India & Ors.), (2021) 12 SCC
11

780 (Benedict Benis Kinny vs. Tulip Brian Miranda & Ors.) & (2021) 19 SCC

706 (State of Uttar Pradesh vs. Sudhir Kumar Singh & Ors.).

28. In response, Mr. Nandy, the learned Senior Advocate representing the

Railway authorities, contended that the train in question was a passenger

train, and one of its rakes had been leased to the petitioner for a duration of

two years, covering 731 trips. He further clarified that the maximum

permissible carrying capacity of the leased rake was 4 metric tonnes (i.e.,

4000 kilograms).

29. Mr. Nandy further stated that on 11.08.2023, the train driver

experienced difficulty in operating the train. Based on the driver’s report, the

train was halted at PDDU station and subsequently examined. During the

inspection, the Train Examiner observed that the buffer height of one of the

wagons identified as overloaded was significantly lower than that of the

locomotive. This discrepancy, he contended, posed a serious safety threat and

could have potentially caused a derailment or a major accident. As a result,

the Train Examiner recommended that the consignment loaded in the

overloaded FSLR-I compartment be offloaded and reweighed. He refuted the

allegation that the driver experienced difficulty in operating the train due to

its age or outdated condition.

30. He submitted that, following the incident, the consignment was

unloaded and weighed on the basis of a joint report dated 11.08.2023,

prepared by the Chief Loco Inspector, the Senior Section Engineer (Carriage &

Wagon), the Chief Parcel Supervisor, and the Deputy Station Superintendent,

all from PDDU Station. The weighment was conducted in the presence of the

Parcel Staff, RPF, and the Chief Loco Inspector. It was found that the
12

consignment weighed 8,344 kilograms, exceeding the permissible limit of

4,000 kilograms by approximately 134%. A joint inspection report was

accordingly prepared. To carry out this entire process, the passenger train had

to be halted for approximately two hours. He asserted that it would not be

practical to delay the train at the station solely to secure the presence of the

leaseholder for the purpose of re-weighing the goods.

31. He argued that overloading the goods by 134% beyond the permissible

limit posed a serious risk and could have led to a major accident with serious

consequences, including the potential loss of innocent lives. Therefore, such

an act, in his view, constituted serious misconduct. Accordingly, the Railway

authorities were justified in invoking Clauses 17.3 and 28.3 of the contract

terms, leading to the termination of the contract and forfeiture of the security

deposit.

32. He argued that although the rake was sealed by Railway staff, the

responsibility for proper loading of goods at the originating station rests solely

with the leaseholder. Therefore, the petitioner cannot put blame upon the staff

who merely sealed the rake. He further submitted that, in order to monetise

the Railway asset and prevent any potential loss of revenue, a fresh auction

process was initiated in accordance with the relevant rules. The petitioner was

at liberty to participate in that auction. In support of his submission, he relied

upon an unreported decision by a Hon’ble Bench headed by the Hon’ble the

Chief Justice in FMA 531 of 2024 (M/s. TOTCO vs. The Union of India &

Ors.).

13

Analysis:

33. Undeniably, it is a well-settled principle of law that the scope of judicial

review in contractual matters is limited. The writ remedy is essentially a

public law remedy, and for such remedy to be invoked, the action of the

authority must fall within the domain of public law. However, it is equally

recognized that the legal rights of an individual may arise from a contract or

an instrument that has the force of law. Interference in writ jurisdiction in

contractual matter is permissible only if public law element is involved

otherwise, the remedy is to seek damages or specific performance in civil

proceedings.

34. The State, or any of its corporations, instrumentalities, or agencies,

possesses the freedom to contract and is entitled to enter into agreements with

individuals of its choice. It may determine the terms and conditions of such

contracts and, at its discretion, decide the method and criteria for inviting

bids, including granting relaxation of certain conditions. However, once the

State or its agency lays down specific norms, procedures, and terms and

conditions, it is bound to adhere to them. Any deviation from those terms

must not be arbitrary or unreasonable.

35. It is well-established that even in contractual matters, a writ court is

entitled to interfere where it is found that the State or its agency, in entering

into a contract with an individual, has acted illegally, irrationally, or in a

manner that fails to withstand the test of reasonableness.

36. In the present case, it is an admitted position that a contract bearing No.

PCL-12311-F1-060623 dated 06.06.2023 was executed between the Howrah
14

Division-Commercial, Eastern Railway and Sabir Road Carriers, Delhi, for the

leasing of a parcel space in a Single Compartment SLR coach. The lease was

for a period of two years, commencing from 22.06.2023 to 21.06.2025

covering 731 trips @ Rs. 42,300/- per trip, pursuant to an e-auction held on

06.06.2023. The lease pertained to Train No. 12311, operating from Howrah

to Kalka, with the designated SLR compartment having a carrying capacity of

4 metric tonnes (MT). The contract was governed by the Special and Standard

Conditions of Contract.

37. In order to effectively address the contours of the controversy involved

in the writ petition, it is essential and indeed unavoidable to enumerate

certain relevant clauses from the Special Conditions, Standard Conditions,

and other applicable contractual provisions.

38. Clauses 10.1 and 10.2 of the Special Conditions of Contract (Annexure

P/2 to the writ petition) stipulate that the loading and unloading of parcels in

the leased parcel space at the originating, destination, and intermediate

stations must be carried out and completed by the contractor within the

available time. Clause 10.4 further provides that the contractor is required to

padlock the brake van before the departure of the train, after which the

Railway staffs are to carry out the remaining formalities, including sealing the

brake van (SLR). Additionally, Clause 10.5.1 prescribes that if a train is

detained beyond its scheduled stoppage time due to loading or unloading by

the contractor, a fine of Rs. 5,000 shall be imposed for each such instance.

Clause 14.1 specifies that loading/unloading will not be supervised by railway

staff.

15

39. Accordingly, the responsibility for carrying out loading and unloading

operations within the available time at the originating and destination

stations, rests solely with the contractor. The role of the Railway staff is

limited to sealing the brake van after the completion of these operations.

40. Clause 14.2 of the Special Conditions of the contract provides that

weighment of consignments loaded in leased SLRs and Parcel Vans shall be

governed by Freight Marketing Circular No. 07 of 2021 (issued via letter no.

2019/TC(FM)/11/10 dated 03.05.2021), as amended from time to time. Clause

14.3, which is central to the dispute in the writ petition, stipulates that if

overloading beyond the permissible tolerance limit–1.0 tonne for Parcel Vans

and 5% of the permissible carrying capacity for SLR compartments–is

detected more than twice under a single contract, the contract shall be

terminated and the security deposit forfeited. For clarity, the contract will be

terminated upon the third such instance of overloading.

41. Clause 18.8 of the Special Conditions stipulates that the contractor

shall be liable to make good any damage caused to the Brake Van, Parcel Van,

platform, or other Railway property during handling of parcels at any station.

Clause 18.10 empowers the Railway to impose penalties if a derailment is

proven to be caused by overloading. In such cases, the Railway may terminate

the contract, cancel the contractor’s registration depending on the severity of

the incident, and recover re-railment charges. The Railway also reserves the

right to open padlocks and seals in unavoidable situations such as accidents or

strikes etc. Annexure-2 to the Special Conditions requires the contractor to

make specific declarations on the reverse side of the Manifest, including a
16

statement that consignments loaded in leased SLRs or Parcel Vans shall not

exceed the permissible carrying capacity at any point during transit.

42. Clause 16.1 of the Standard Conditions provides for an appeal against

orders of contract termination and forfeiture of EMD/SD. Sub-Clause 17.3

empowers the Railway to terminate the contract at any time, without notice,

as a punitive measure for breach of terms of contract or serious misconduct.

Clause 18.1, which is also pivotal to the present dispute, reiterates this right by

allowing termination without notice for any violation of the contract, the

Railway Act, 1989, engagement in unlawful acts contrary to industry norms,

or acts involving moral turpitude, along with full forfeiture of the EMD/SD.

Clause 19 further authorizes the Railway to impose penalties on the contractor

for passenger inconvenience or other specified reasons, at the prescribed

rates.

43. The termination order dated 17.08.2023 records that on 11.08.2023,

an overloading of 4,344 kg exceeding the permissible limit of 4,000 kg, was

detected, leading to an unwarranted detention of the passenger train by 114

minutes. The Railway authorities viewed this as a serious misconduct, posing

risks to rolling stock, track, and the safety of passengers. Consequently,

invoking Clauses 28.3 and 17.3, the contract was terminated, the Security

Deposit forfeited, and a penalty of Rs. 1,29,371/- imposed. Clause 28.3 of

Freight Marketing Circular no. 11 of 2022 further provides that,

notwithstanding Clause 28.2, the Railway reserves the right to terminate the

contract without notice in cases of serious violation, illegal activity, or conduct

contrary to Good Industry Practices, along with forfeiture of the Security

Deposit.

17

44. Admittedly, this Court is not a fact-finding authority, and the scope of

judicial review is confined to examining the decision-making process. As

noted earlier, the petitioner availed the appellate remedy under Clause 16.1 of

the Standard Conditions. The appellate order, which was passed after granting

the petitioner an opportunity of hearing, recorded that the petitioner’s

representative, who arrived at PDDU station on 12.08.2023, did not request

re-weighment of the parcels in his presence.

45. The appellate order noted that, at the relevant time, the loco pilot refused

to start the train due to uneven coupling between the first SLR (No. ER

112736) and the engine (No. 37169), and requested inspection by the TXR

(Train Examiner) staff. Upon examination, the TXR staff found that

overloading in the SLR had caused a coupling mismatch, creating an unsafe

condition. Consequently, the TXR staff issued a memo directing the unloading

of packages from FSLR-I.

46. The contractor declared in the manifest dated 10.08.2023, which was

submitted in the Howrah Parcel Office, that there were 193 packages and 3990

Kgs. of consignment. The order mentioned that loading is not supervised by

the Railway authorities. However, after unloading the consignment, it was

found that there were 171 packages. Weighment was done in presence of

Parcel Staff, RPF and Chief Loco Inspector (CLI) of PDDU station. For

completion of unloading the parcels and re-weighment etc., the train which

was a passenger train was detained by 113/114 minutes.

47. The main thrust of the petitioner’s argument was that conducting the re-

weighment of parcels without his presence amounted to a serious violation of

the principles of natural justice. However, he failed to produce any material to
18

contradict the appellate order’s finding that his representative did not request

re-weighment on 12.08.2023. Additionally, he could not cite any contractual

provision mandating that re-weighment be carried out in the presence of the

contractor or his representative in cases where overloading necessitates

unloading at any intermediate station to ensure the safe operation of a

passenger train. It is a settled presumption that official acts are regularly

performed, and in the absence of compelling evidence suggesting mala fide

intent or procedural impropriety, this presumption remains unrebutted.

48. To invoke extraordinary jurisdiction of this Court under Article 226 of

the Constitution of India, one must show that he has existing fundamental or

legal rights and infraction of that right or rights has resulted in his personal

injury and prejudice. Breach of audi alteram partem rule, may claim

involvement of public law element. However, currently, there is a shift from

its earlier concept that even a small violation of natural justice shall result in

the order being rendered a nullity. Presently, a clear distinction has been

drawn between the cases where there was no hearing at all and the cases

where there was mere technical infringement of the principle [See, the

judgment of Sudhir Kumar Singh (supra)].

49. In the present case, Mr. Bhattacharya contended that the principles of

natural justice were violated, as the re-weighment was carried out in the

absence of the petitioner’s representative, and no prior notice was issued

before the termination of the contract and forfeiture of the Security Deposit

(SD). However, as previously noted, the petitioner’s representative did not

request that the re-weighment be conducted in his presence. Furthermore, it

is an admitted fact that, in accordance with the Standard Conditions of
19

Contract, the Railway authorities were vested with the right to terminate the

contract and forfeit the SD without prior notice.

50. It is well settled proposition of law that the principles of natural justice

cannot be put into a strait-jacket formula and that its application will depend

upon the fact situation obtaining therein. It cannot be applied in a vacuum

without reference to the relevant facts and circumstances of the case.

51. The present case serves as a reminder of the well-established principles of

law, as enunciated in Gorkha Security Services v. Government (NCT of Delhi),

(2014) 9 SCC 105. The Supreme Court observed that the rules of natural justice

are not embodied rules, nor are they elevated to the status of fundamental rights.

Their primary objective is to ensure justice and prevent its miscarriage. It is a

settled proposition of law that, unless a statutory provision expressly or by

necessary implication excludes them, the exercise of any power that prejudicially

affects an individual must conform to the principles of natural justice. It is

axiomatic that principles of natural justice do not supplant the law, but

supplement the law. Its application may be excluded wither expressly or by

necessary implication. (See, judgment of Dr. Umrao Singh Choudhary vs. State

of Madhya Pradesh, reported at (1994) 4 SCC 328). In the present case, as noted

earlier, the Railway authorities reserved its right to terminate the contract and

forfeit the SD without any notice. Taking note of this stipulation in the contract,

the petitioner entered into the contract.

52. The petitioner was granted a hearing by the Appellate Authority.

Notably, during the proceedings on 12.08.2023, the petitioner’s representative

did not allege any coercion by the Railway authorities regarding the penalty

payment, nor was any contemporaneous complaint filed with any authority.
20

Furthermore, the issue of lack of prior notice before termination of the

contract and forfeiture of the Security Deposit (SD) was not raised before the

Appellate Authority. In B. Karunakar (as cited in Sudhir Kumar Singh), the

Hon’ble Court held that in cases of alleged violation of natural justice, such as

non-supply of an enquiry report, the burden lies on the delinquent to

demonstrate that the omission caused prejudice and led to a miscarriage of

justice. Absent such a showing, the punitive order cannot be set aside merely

on procedural grounds.

53. In Sudhir Kumar Singh (supra), the Hon’ble Court ruled that no

prejudice arises from a breach of natural justice if the person concerned does

not dispute the case against him or it, whether through estoppel,

acquiescence, waiver, or failure to challenge or deny the facts. In that case, the

Court can held that no real prejudice was caused. In the present case, the

petitioner’s legal or fundamental rights, if any, arise from the terms of the

contract. Being fully aware that the Railway authorities had reserved the right

to terminate the contract and forfeit the Security Deposit (SD) in the event of a

breach, without any prior notice, the petitioner voluntarily accepted these

terms and entered into the agreement. Therefore, in light of the facts, it can be

concluded that no prejudice was caused to the petitioner either due to the

omission of re-weighment of parcels at PDDU station or the absence of any

prior notice before termination of the contract and forfeiture of the SD. It is

pertinent to note that the termination of the contract and forfeiture of the

Security Deposit did not debar the petitioner from participating in future

auction processes.

21

54. The next issue that survives for consideration is whether the Railway

authorities were justified in terminating the contract and forfeiting the

Security Deposit. As previously noted, Clause 14.3 of the Special Conditions of

Contract provides that if overloading beyond the permissible tolerance limit–

namely, 1.0 tonne for Parcel Vans and 5% of the permissible carrying capacity

for SLR compartments–is detected more than twice under a single contract,

the contract shall be terminated and the Security Deposit forfeited. It further

clarifies that termination will follow upon the third instance of overloading.

Therefore, Clause 14.3 applies in cases where overloading is within 5% of the

permissible carrying capacity for SLR compartments. In cases of overloading

by 134% of the permissible limit, this clause cannot be invoked.

55. An act of overloading to the extent of 8,344 kgs, where the permissible

tolerance limit was 4,000 kgs–amounting to over 134% of the allowable

limit–was considered by the Railway authorities as not being in line with

good industry practices and amounting to serious misconduct on the part of

the contractor. Experts opined that such excessive overloading could have led

to a serious accident involving the passenger train. Furthermore, the

contractor had furnished incorrect information in the manifest regarding the

number of packages and the weight of the parcels. Therefore, considering the

misconduct, I find no justification to hold that the decision was perverse or

that the punishment was disproportionate.

56. I have carefully considered the decisions cited on behalf of the petitioner.

While there is no dispute regarding the binding nature of those precedents,

they are factually distinguishable and do not come to the aid of the petitioner

in the present case.

22

Order:

57. Therefore, based on the discussions and reasons set out in the preceding

paragraphs, I am of the view that the petitioner’s contentions are without

merit. I find no infirmity in the decision-making process, nor any perversity in

the decision of the Railway authorities to terminate the contract and forfeit

the Security Deposit. Consequently, the writ petition is dismissed, however,

without any order as to costs.

(Partha Sarathi Chatterjee, J.)



Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here