M/S Durga Enterprises vs Food Corporation Of India And Others on 30 June, 2025

0
4

Jammu & Kashmir High Court

M/S Durga Enterprises vs Food Corporation Of India And Others on 30 June, 2025

Author: Moksha Khajuria Kazmi

Bench: Moksha Khajuria Kazmi

        HIGH COURT OF JAMMU AND KASHMIR AND LADAKH
                         AT JAMMU

Case: WP(C) No. 1109/2023

Reserved on: 06.06.2025.
Pronounced on : 30.06.2025

M/S Durga Enterprises
M




                                                     ....Petitioner/Appellant(s)

                 Through :- Mr. P.N.Raina Sr. Advocate with
                            Mr. J. Hamal Advocate.


V/s

Food Corporation of India and others                         .....Respondent(s)

         Through :-          Mr. R.K.Gupta Sr. Advocate with
                             Mr. Ravi Abrol Advocate.
CORAM:
HON'BLE MS. JUSTICE MOKSHA KHAJURIA KAZMI, JUDGE

                                JUDGMENT

1 In this petition, the petitioner, herein, is seeking the following

reliefs:

(i) A Writ of Certiorari quashing order dated 09.06.2022 issued

by respondent No.1, insofar as it pertains to the petitioner, by
virtue of which the prayer of the petitioner against unlawful
recoveries made by the respondents pursuant to Road
Transport Contracts for FSD New Godown Jammu to FSD
Mirbazar, PEG Ramban, and RH Udhampur to PEG Doda has
been rejected by the respondents.

(ii) A Writ of Certiorari quashing order dated 16.10.2019
issued by respondent No.3, insofar as the same has been made
applicable to the pre-existing contracts i.e prior to 16.10.2019,
for FSD New Godown Jammu to FSD Mirbazar, PEG Ramban
and RH Udhampur to PEG Doda, by virtue of which arbitrary,
2

illegal and unwanted recoveries have been made by the
respondents from the running bills and security deposits of the
petitioner.

(iii) A Writ of Mandamus directing the respondents to release
the entire amount of Rs.76,92,578, with interest @ 20% per
month, from the date of deduction until the entire amount is
released in favour of the petitioner which has been illegally,
irrationally and arbitrarily deducted by the respondents while
settling the claims of the petitioner pursuant to contract for FSD
New Godown Jammu to PEG Ramban dated 16.03.2017, Rail
Head Udhampur to PEG Doda, dated 02.02.2018 and for FSD
New Godown Jammu to FSD Mirbazar, dated 02.08.2018
executed between the petitioner and the respondents.

(iv) Any other appropriate writ, direction, or relief as this Court
may deem just and fit.

Factual matrix:

2 The petitioner is one of the partners in a registered partnership firm

engaged in transport and carriage contracts, operating under the name and style

of M/s Durga Enterprise, having its registered office at 45/5, Transport Nagar,

Narwal, Jammu. The petitioner, being a partner in the aforementioned firm and

duly holding a power of attorney on behalf of the other partners, is competent

and authorized to file the present writ petition.

3 It is submitted that respondent No.1, through its official website,

issued e-tender notices dated 26.12.2016, 13.11.2017 and 22.06.2018, inviting

online tenders under the “two-bid system” for the appointment of road transport

contractors for the movement of food stocks from FSD New Godown, Jammu

to various destinations as detailed in the respective tender notices. Pursuant to
3

the issuance of the said e-tender notices, the petitioner submitted its bid and was

awarded contracts for transportation of stocks from FSD New Godown, Jammu

to PEG Ramban,Rail Head Udhampur to PEG Doda, and FSD New Godown,

Jammu to FSD Mir Bazar. Consequent to the acceptance of the petitioner’s

bids, the petitioner was duly appointed as Road Transport Contractor (RTC) for

the aforementioned routes. It is submitted that while issuing the said e-tenders,

respondent No.2 had specified certain parameters including distance in

kilometers, period of contract, estimated contract value, Earnest Money Deposit

(EMD), security deposit, etc., which formed the basis for evaluating bids.

Taking these parameters into consideration, the petitioner submitted its bid,

which was accepted, and the petitioner accordingly commenced transportation

work as per the work orders issued by the respondents.

4 The petitioner executed the awarded works and submitted freight

bills from time to time, which were duly verified and cleared by the respondents

in accordance with the distances mentioned in the tender documents and

appointment orders. It is submitted that till July 2019, the respondents complied

with all terms and conditions of the contracts. However, for the first time in July

2019 after the completion of the contract related to the route from FSD New

Godown, Jammu to PEG Ramban, respondents raised certain claims and

adjusted alleged recoveries against the running bills of the petitioner relating to

the FSD Mir Bazar contract. As per the petitioner firm, these deductions were

illegal, unwarranted, and arbitrary. It has been submitted that the Model Tender

Form (MTF) governing the contracts did not contain any clause permitting

remeasurement of distances during the currency of the contract. Moreover, the

respondents neither informed the petitioner regarding any remeasurement
4

exercise nor disclosed the methodology adopted for the same. Despite this, the

respondents, in a wholly arbitrary and unjustified manner, proceeded to deduct

substantial amounts from the petitioner’s freight bills on the alleged ground of

remeasurement of distances. It is submitted that, the respondents deducted an

amount of ₹76,92,578 from the petitioner’s freight bills and security deposits,

without providing any notice, opportunity of hearing, or explanation to the

petitioner. These deductions were allegedly based on the remeasurement of

distances for the following routes:

             (i)     FSD New Godown, Jammu to PEG Ramban,
             (ii)    FSD New Godown, Jammu to FSD Mir Bazar, and
             (iii)   Rail Head Udhampur to PEG Doda.

5            It is stated that such action on the part of the respondents is

arbitrary, violative of the principles of natural justice, and dehors the terms and

conditions of the contract, particularly in the absence of any provision

permitting unilateral remeasurement during the subsistence of the contracts. The

petitioner, vide representation dated 23.12.2019, addressed to Respondent No.3,

objected to the remeasurement of distances and its application to running

contracts on the ground that such action was arbitrary and beyond the scope of

the Model Tender Form (MTF). There exists no clause under the MTF that

provides for the remeasurement of distances during the subsistence of a running

contract. This objection was also brought to the notice of Respondent No.2

through a collective representation dated 13.06.2020 submitted by various Road

Transport Contractors (RTCs), including the petitioner herein. In response to

the said representation, respondent No.2, through a communication dated

05.06.2020 addressed to respondent No.1, categorically stated that tenderers

quote rates based on distances specified in the tender enquiry, and that reduced
5

variations in distance are not to be applied to running contracts. It was further

stated that even enhanced distances are not taken into consideration during the

subsistence of the contract, except in cases of infrastructural development where

the route change significantly impacts the distance. Respondent No.2 further

recommended that changes in distance should not be implemented in general

cases, and that such changes should be restricted to instances involving major

variations due to infrastructural developments such as new tunnels or alternate

routes. Despite this, respondent No.3, without seeking approval from the

competent authority, arbitrarily and suo motu applied revised distances to

ongoing contracts, effectively altering the terms of the Notice Inviting Tender

(NIT), which is an integral part of the MTF. Any change in the NIT amounts to

a modification of the MTF, which respondent No.3 was not competent to effect

unilaterally. Moreover, the respondents themselves admitted before the

Comptroller and Auditor General (CAG), in response to a query regarding

remeasurement of distances, that there was no clause in the contract (MTF) or

policy of FCI permitting remeasurement of distances during the term of the

contract, and that any modification must be supported by mutual agreement

between the parties.Despite this admission, the respondents subsequently

introduced a fresh clause in the later NITs providing for remeasurement of

distances in the last weeks of March and September each year clearly

demonstrating that such a clause was not part of earlier contracts like the one in

question. Therefore, it is evident that in the absence of such a clause in the

present case, the respondents could not have resorted to remeasurement of

distances.

6

6 It is further submitted that, under Section 62 of the Indian Contract

Act, novation of a contract requires mutual agreement between the parties. In

the present case, the petitioner was neither informed nor consulted regarding

any such remeasurement, rendering the unilateral imposition of revised

distances illegal. Consequently, the recoveries made on this basis are beyond

the scope of the contract and unsustainable in law. The distance mentioned in

the e-tender notice is a vital factor, as the estimated bid for transportation is

based on the specified distance. The rates quoted by an RTC account for the

entire transportation cost, including subcontractor charges, which are fixed

based on volume and distance. Any change in distance during the contract

period disrupts this arrangement, causing undue hardship to the contractor.

Aggrieved by the conduct of respondent No.3, the petitioner approached the

Grievance Redressal Cell (GRC) vide letter dated 26.05.2022. Although the

GRC’s decision dated 09.06.2022 acknowledged that distance is a critical factor

in quoting rates, yet it failed to address the petitioner’s core grievance i.e., the

legality of remeasuring distances during the currency of a contract. It is stated

that the action of respondent No.3 in imposing recovery is illegal, arbitrary, and

violative of the principles of natural justice. No prior notice or communication

was made to the petitioner either before or after the remeasurement. The GRC’s

finding is legally untenable, especially in light of categorical admissions made

by respondents No.1 and 2 through communications dated 03.09.2020 and

05.05.2020 respectively, wherein they confirmed that distance could not be

remeasured during the subsistence of a contract. Since there is no clause in the

MTF permitting remeasurement during the contract period, any such act is ultra

vires the contract and cannot form the basis of recovery. Section 62 of the
7

Indian Contract Act mandates that any amendment or novation of contract terms

requires consent from both parties which condition is clearly absent in this case.

7 In support of the petitioner firm’s case, Mr. P.N. Raina, learned

Senior Counsel appearing for the petitioner, relying upon the judgment of the

Supreme Court in Suresh Kumar Wadhwa vs. State of Madhya Pradesh and

others, (2017) 16 SCC 757, submits that a party to a contract has no right to

unilaterally alter the terms and conditions of the contract. He further submits

that additional terms or conditions can be added only if both parties agree to

such alterations or additions. In this context, he has referred to paragraphs 26

and 27 of the said judgment, which are reproduced hereunder:

“26. Equally well settled principle of law relating to contract is
that a party to the contract can insist for performance of only those
terms/conditions, which are part of the contract. Likewise, a party
to the contract has no right to unilaterally “alter” the terms and
conditions of the contract and nor they have a right to “add” any
additional terms/conditions in the contract unless both the parties
agree to add/alter any such terms/conditions in the contract.

27. Similarly, it is also a settled law that if any party adds any
additional terms/conditions in the contract without the consent of
the other contracting party then such addition is not binding on the
other party. Similarly, a party, who adds any such term/condition,
has no right to insist on the other party to comply with such
additional terms/conditions and nor such party has a right to
cancel the contract on the ground that the other party has failed to
comply such additional terms/conditions”.

8 Vide order dated 01.05.2023, this Court granted liberty to the

petitioner to submit a representation seeking review of the GRC’s decision

dated 09.06.2022 and the respondents were directed to consider the same.
8

9 The respondents have filed their objections/counter affidavit to the

present writ petition and submitted that the impugned order dated 16.10.2019

was issued by the Divisional Office, Jammu, conveying revised distances as per

the directions from the Regional Office, Jammu, vide communication dated

15.03.2019. The contracts awarded under the prevailing scheme of Road

Transport Contracts of FCI are on Rs./MT/KM basis. Therefore, it is essential

that distances are periodically reassessed to safeguard the financial interests of

the Corporation.

10 It is submitted that Clause XVIII (a)(v) of the Model Tender Form

(MTF) provides that distances will be reckoned as fixed by the Chief Engineer,

PWD, or an officer nominated by him, or by the General Manager, or verified

by an officer acting on his behalf, and rounded off to the nearest kilometer,

which shall be final and binding on the contractor and that FCI Zonal Office

(North), vide letter dated 23.01.2017, referring to FCI Headquarters’

instructions dated 21.07.2016, advised that the shortest motorable road between

the dispatch and receipt points should be regularly assessed at the time of

awarding contracts. The distance mentioned in the NIT was based on the

previous assessment.

11 It is further submitted that as per order issued by the FCI, the

measurement of distance is required to be conducted biannually (twice a year)

during the last weeks of March and September with the revised distances

becoming applicable from 1st April and 1st October, respectively. In special

circumstances, such as the opening of new tunnels or roads, revised distances

become applicable from the date of such developments. It is submitted that the
9

petitioner’s representation was considered by the Grievance Redressal

Committee (GRC), Zonal Office (North), in its meeting held on 09.06.2022.

The GRC noted that earlier, flat-rate contracts were floated irrespective of

distance; that post the 2011 revision of the MTF, contracts are awarded on per

MT/KM basis; that since rates are quoted per MT/KM, the distance is a critical

component in determining freight charges; that once remeasured, it is

incumbent upon the Corporation to regulate payments accordingly; and if

documentary evidence of structural changes is produced, the corresponding

revised distance may be applied from the date of such changes.

12 It is submitted by the respondents that the price bid under the MTF

format contains a column for rate per MT/KM but does not mention distance.

The contracts are awarded and accepted on that basis alone. The revised

distances were adopted to reflect route changes, including new roads and

tunnels, and not implementing them would have caused financial loss to the

Corporation. According to the respondents, the total recovery of Rs. 5,75,322/-

in respect of the contract from FSD New Godown Jammu to PEG Ramban (for

the period 16.03.2017 to 15.03.2019) was made. This included Rs. 4,78,177/- in

compliance with a CAG audit para; andRs. 97,145/- on account of revised

distances, which was recovered from the bills of another contract (FSD NG

Jammu to FSD Mirbazar) as the original contract had expired. It is submitted

that the FCI regularly measures distances through its internal committees to

ensure compliance with MTF provisions and to prevent undue enrichment of

contractors due to outdated distances. The measurement is carried out without

the need for contractor involvement as per the terms of the contract. The

communication dated 05.06.2023 merely apprised higher authorities of the
10

variance in distances. It also clarified that distances in the NIT were indicative,

used solely for calculating the value of the contract and EMD/Security Deposit.

This was not a recommendation to alter the Regional Office’s decisions. It is

further submitted that the communication dated 03.09.2022 from Zonal Office

(North) regarding insertion of a clause in the NIT for six-monthly measurement

did not nullify the decision of the Regional Office, Jammu. The GRC remained

the competent authority for deciding such matters and that the decision of the

GRC dated 09.06.2022 clearly held that revised distances would be applicable

from the date of re-measurement, unless a structural change is documented for a

prior period. In such case, the change in distance would apply from the date of

the change itself.

13 It has been submitted that the petitioner was informed to submit

claims, if any, in accordance with the GRC decision vide letter dated

12.01.2023, but no claim was filed by the petitioner thereafter and that the

decision of the GRC was implemented uniformly for all contractors to

safeguard public funds. No mala fide or arbitrary action was taken.

Communication dated 16.10.2019 conveyed the revised distances to all

concerned contractors. Clause XX(f) of the MTF provides the procedure for

filing grievances, which the petitioner firm followed by filing representations

dated 26.05.2022 and 13.05.2023. The same were duly considered and rejected

by passing speaking orders. The order dated 25.05.2023 disposing of the

petitioner’s second representation has not been challenged in the present writ

petition, rendering the petition infructuous. The respondents have submitted

that the reliance on the NIT distances is misconceived. These distances are not

binding for payment calculation but are only indicative. The actual payment is
11

determined on the Rs./MT/KM rate and the shortest motorable road, as per the

MTF and FCI guidelines.

14 It is submitted that the operations of different FCI regions are not

comparable. Jammu & Kashmir is a consuming region with limited dispatch

centers, whereas Punjab is a procuring region with multiple dispatch centers.

Consequently, the operational logistics and tendering procedures necessarily

vary from region to region and that the decision to revise the distances was

implemented uniformly across all contractors operating during the relevant

period. No individual contractor, including the petitioner, was singled out for

differential treatment. The allegations of arbitrariness or discrimination are

misconceived and baseless. According to the respondents, the writ petition is

liable to be dismissed, as it challenges a policy decision taken in public interest

and in accordance with the terms of the contract. Furthermore, the petitioner has

failed to assail the final order dated 25.05.2023, passed by the GRC in response

to the petitioner’s representation, rendering the petition legally untenable.

15 Learned counsel for the respondents, in support of their case, has

relied upon a decision dated 06.03.2018 rendered by this Court in OWP No.

1370/2017, titled M/s S. Surinder Singh & Another v. FCI & Others and

connected matters, which is squarely applicable to the present case.In the said

case, a similar issue regarding the re-measurement and revision of

transportation distances has been considered. This Court, while referring to the

decisions of the Supreme Court in Kerala SEB v. Kurien E. Kalathil, (2000) 6

SCC 293, and Central Bank of India v. Devi Ispat Ltd., (2010) 11 SCC 186,

has held that the interpretation and implementation of contractual clauses
12

cannot be the subject matter of a writ petition. The Supreme Court emphasized

that disputes concerning the interpretation of the terms and conditions of a

contract must be adjudicated by a civil court or through arbitration, if such a

mechanism is provided under the contract. Further, the writ Court also relied

upon the decision in Rajasthan State Industrial Development and Investment

Corporation v. Diamond and Gem Development Corporation Ltd., (2013) 5

SCC 427, reiterating that contractual disputes fall outside the scope of writ

jurisdiction. The Court observed that the impact of distance reduction could be

better examined by an expert committee.It has been reported that the decision

rendered in the aforesaid case has not been challenged before any forum and

has, therefore, attained finality.

16 In Surinder Singh‘s case (supra), while dismissing the writ

petition, this Court noted that the petitioners had the remedy of approaching the

Grievance Redressal Committee (GRC). Paragraphs 17 and 18 are relevant to

the context and are reproduced below:

“17) In view of the aforesaid order dated 04.08.2017, the meeting
of the Grievance Redressal Committee was held on 13.11.2017 by
which the claim of the petitioner was rejected by the respondents.

However, the fact remains that the aforesaid order has been passed
by the Grievance Redressal Committee without affording
opportunity of hearing to the petitioners. The petitioners had a
remedy to approach the Grievance Redressal Committee under
Clause XX of the contract. However, instead of resorting to the
aforesaid remedy, the petitioners have rushed to this Court.
Therefore, it is not necessary to deal with other contentions made
by the parties.

13

18) In view of the preceding analysis, no interference is called for
with the decision of the respondents. However, it would be open to
the petitioners to approach the Grievance Redressal Committee, if
they so advised in terms of Clause XX of the agreement. Needless
to say that in case the petitioners approach the Grievance
Redressal Committee, the aforesaid Committee shall decide the
dispute by a speaking order within a period of three weeks from
today”.

17 Pursuant to the order dated 22.05.2025, the respondents have filed

an affidavit stating that the petitioner firm participated in the tendering process

initiated through e-NIT dated 26.12.2016 for transportation of food grains from

FSD New Godown, Jammu to PEG Ramban. The petitioner’s bid was accepted

vide order dated 17.03.2017, and the contract period was from 16.03.2017 to

15.03.2019. Initially, the distance from FSD New Godown, Jammu to PEG

Ramban was shown as 170 km. However, this distance was revised to 139 km

vide order dated 29.05.2017, which was accepted by the petitioner firm, and

bills were raised accordingly. Subsequently, as per the Corporation’s circulars,

guidelines, and instructions, the distance to PEG Ramban was remeasured by a

committee on 12.09.2018, in pursuance of the direction dated 10.09.2018. The

revised distance was found to be 137 km due to road realignment, construction

of flyovers, and new culverts caused by the ongoing construction of the four-

lane National Highway. Thereafter, payment was made to the petitioner at the

revised distance of 137 km. However, the petitioner had continued raising bills

based on the earlier distance of 139 km. As a result, the Corporation recovered a

total amount of ₹5,75,322 in two instalments,Rs.4,78,177 based on a CAG

report and Rs.97,145 for the period from 12.09.2018 to 15.03.2019.As per the

decision of the Grievance Redressal Committee (GRC), the revised distance
14

was to be applied from the date of remeasurement, not from the beginning of

the contract. Therefore, the petitioner is entitled to a refund of ₹4,78,177 for

transportation from FSD New Godown, Jammu to PEG Ramban. It is further

submitted that the petitioner also participated in another e-NIT for

transportation of food grains from FSD New Godown, Jammu to FSD Mir

Bazar. Upon being declared successful, the petitioner was appointed as the

regular RTC vide order dated 14.08.2018 for the contract period from

14.08.2018 to 13.08.2020. Initially, the distance was shown as 220 km. During

the contract, the Corporation remeasured the distance as per applicable

circulars, guidelines, and the MTF, and found it reduced to 211 km due to

similar reasons i.e realignment, flyovers, and culverts related to highway

expansion. The Corporation applied the revised distance of 211 km with effect

from 01.04.2019 and continued till 16.06.2020. Consequently, it recovered

₹55,05,197 from the petitioner. However, as per the GRC’s directions, the

revised distance should have been implemented from the date of actual

remeasurement, i.e., 19.05.2019. Therefore, the petitioner is entitled to a refund

of ₹2,87,477 for the period from 01.04.2019 to 18.05.2019.Further, the

petitioner also participated in the tender for transportation of food grains from

Railhead Udhampur to PEG Doda and was appointed as the RTC vide order

dated 26.02.2018 for the contract period from 02.02.2018 to 01.02.2020. The

original distance was recorded as 105 km. Upon remeasurement on 26.04.2019,

the distance was found to be reduced to 102 km due to road changes. However,

recoveries were made with effect from 01.04.2019, which is prior to the

remeasurement date. It is submitted that in line with the GRC decision, the

revised distance should be applicable from 26.04.2019. Hence, the petitioner is
15

entitled to a refund of Rs.27,802 for the period from 01.04.2019 to

25.04.2019.The total recovery affected by the Corporation from the petitioner’s

freight bills and security deposits is Rs.65,10,874. As per the order dated

16.10.2019, the Corporation recovered Rs.59,35,552 for revised distances

concerning FSD Mir Bazar and PEG Doda with effect from 01.04.2019.

However, as per the GRC’s decision, the revised distances must be applied from

the date of re-measurement and not from 01.04.2019. Accordingly, the

petitioner is entitled to a total refund of Rs7,93,456.It is further submitted that

the amount of ₹5,75,322 for PEG Ramban was recovered prior to the issuance

of the order dated 16.10.2019, since the contract for Ramban had already

expired on 15.03.2019.

18 Heard learned counsel for the parties and perused the material on

record including the record produced by the respondents.

19 From the pleadings of the parties and upon perusal of the material

on record, the following issues arise for consideration:

Issue No. (i): Whether the remeasurement of distances during the currency
of the contracts was contrary to the terms of the contract (MTF)?

20 The petitioner’s case rests heavily on the contention that there is no

express clause in the Model Tender Form (MTF) permitting unilateral

remeasurement of distances during the subsistence of a contract. However, the

respondents have relied upon Clause XVIII(a)(v) of the MTF, which stipulates

that the distance shall be reckoned as fixed by the Chief Engineer, PWD, or an

officer nominated by him, or by the General Manager or an officer acting on his

behalf, and that such measurement, once verified and rounded off to the nearest
16

kilometer, shall be final and binding on the contractor. Furthermore, the

Grievance Redressal Committee (GRC), vide its decisions dated 09.06.2022 and

25.05.2023, has upheld the authority of the Food Corporation of India (FCI) to

periodically reassess distances in view of infrastructural developments and

relevant policy circulars. Therefore, when Clause XVII(a)(v), Note (2) of the

tender document, and the applicable guidelines are read in conjunction, the

remeasurement of distances is not outside the scope of the contract. Moreover,

as per the order dated 16.10.2019 issued by the Divisional Office, Jammu,

revised distances were conveyed pursuant to the Regional Office’s directions

dated 15.03.2019. For clarity, it is appropriate to reproduce the communication

dated 15.03.2019 addressed by the General Manager, FCI to the Execution

Director (North) FCI Zonal Office, Noida, which provided directions regarding

the remesaurement of distances:

“The Executive Director (North)
Food Corporation of India
Zonal Office(North), Noida.

Subject: – Regular assessment of road distances for the purpose of
payment of road freights to transport contractors- reg.

Ref: – 1. FCI ZO(N), letter no.S&C/15(6)/GRC/Cont/NZ/2017/27dated
17.10.2017.

2. FCI ZO(N), letter no. S&C/32(19)/Misc./Cont/NZ/14 dated 23.01.2017.

Madam,

Kindly refer to FCI ZO(N) communications cited under reference
above in references to FCI Hqrs letter dated 21.07.2016 regarding
enhancement/reduction in distances of road transport contracts where it has
been mentioned that “shortest motorable road between dispatch and
receipt point is required to be assessed regularly while awarding the
contracts”. Further, vide letter dated 17.10.2017, it has been advised that
concern of reduction/enhancement in distance of road transport contract may
be finalized at RO level. However, no specific time period or interval has been
specified for measuring the distances.

Due to on going process of development and re-alignment of highways,
regular changes are observed in distances on fresh measurements due to which
17

need has been felt to fix some regular interval during contract period for
measurement of distances in order to reduce the complexities and disputes.

Accordingly, the matter has been examined in this office in consultation with
finance division and below guidelines have been issued to all D.Os in J&K
region for strict compliance. The same note shall also be appended in all
tender notices now onwards for clarity to bidders: –

“Under the provisions of clause XVIII.a.v. of the MTF, District Office
concerned shall get the distances measured by committee of officers in the
last weeks of March and September every year and the same shall be
applicable for freight payments from the 1st April and 1st October resp. In
case of special circumstances like opening of new tunnels of roads, the
new distances shall be measured immediately and applicable from the
date of opening of such roads/tunnels.”

Further, it is also suggested that similar procedure should be followed in other
regions as well and Z.O/HQ may consider issuing necessary direction to this
effect.

Dy. General Manager
For General Manager(J&K)

21 Under the current scheme of Road Transport Contracts awarded by

the FCI, where contracts are executed and payments made on per Rs./MT/KM

basis, periodic reassessment of distances is imperative to safeguard the financial

interests of the Corporation and to ensure equitable payment corresponding to

actual distances. On a plain reading of Clause XVIII(a)(v) of the MTF, the

consistent decisions of the GRC, and the above authoritative circular, it is clear

that the FCI is legally entitled and contractually authorized to remeasure and

revise road distances during the contract period.

22 The original distance from FSD New Godown, Jammu to PEG

Ramban was 170 kilometers. This was later revised to 139 kilometers due to

road realignment. The petitioner accepted this revised distance without protest

and submitted bills accordingly. This indicates the petitioner’s acceptance of the

revised measurement and reduced freight charges. Subsequently, the distance

was again revised from 139 kilometers to 137 kilometers. Although the
18

petitioner objected to this second revision, the earlier conduct of accepting a

similar revision without protest amounts to acceptance of FCI’s authority under

the contract to remeasure distances. The legal position is clear that a party

cannot accept benefits under a contract and later challenge its terms. In

Rajasthan State Industrial Development and Investment Corporation v.

Diamond & Gem Development Corporation Ltd., (2013) 5 SCC 470, and in

State of Maharashtra v. Digambar, (1995) 4 SCC 683, the Supreme Court

has held that once a party accepts the contractual terms and derives benefit, it is

estopped from later challenging them. In Union of India v. N.K. (P) Ltd.,

(1972) 1 SCC 858, the Supreme Court has held that the conduct of parties is

significant in interpreting commercial contracts.

23 Accordingly, the petitioner’s earlier conduct of accepting the

revised distance and corresponding freight charges constitutes a waiver and

legal estoppel. Therefore, the present challenge to the recovery orders, based on

a similar revision in distance, is not sustainable. Since the contracts were

awarded on a per MT/KM basis, the respondent-FCI was empowered to

remeasure the distances. It was incumbent upon the respondent-FCI to do so in

order to safeguard the public exchequer. Accordingly, the petitioner’s challenge

to the remeasurement of distances during the currency of the contracts is devoid

of merit and is hereby rejected.

24 Regarding the judgment cited by Mr. P.N. Raina in Suresh Kumar

Wadhwa‘s case (supra), there is no dispute about the legal proposition that a

party to the contract can insist on performance only of those terms and

conditions which are part of the contract. Likewise, a party has no right to
19

unilaterally alter or add terms or conditions without mutual agreement.

However, in the present case, there is no alteration of the terms and conditions

of the contract. Clause XVIII (a)(v) specifically states that the distance will be

reckoned as fixed by the Chief Engineer, PWD, or an officer nominated by him,

or by the General Manager, or verified by an officer acting on his behalf, and

rounded off to the nearest kilometer, which shall be final and binding on the

contractor. Moreover, the distance from FSD New Godown, Jammu to PEG

Ramban was initially 170 kilometers and was subsequently revised to 139

kilometers due to road realignment. The petitioner accepted this revised

distance without protest and submitted bills accordingly. This conduct clearly

indicates the petitioner’s acceptance of the revised measurement and the

resultant reduced freight charges. Therefore, the legal proposition laid down in

Suresh Kumar Wadhwa‘s case (supra) is not applicable to the present case.

Issue No. (ii): Whether the recoveries made retrospectively, i.e., for
periods before the actual remeasurement, were legal and
justified ?

25 The respondents, in their affidavit and counter submissions, have

admitted that recoveries in certain cases were made from 01.04.2019, even

though the remeasurement was carried out at later dates. The GRC, in both its

decisions, has clearly held that revised distances should be applied only from

the date of actual remeasurement, unless there is concrete evidence of earlier

structural changes. Accordingly, the respondents have conceded that the

following amounts were erroneously recovered prior to the remeasurement

dates:

20

Route Date of Period of contract Period of excess Amount to be
remeasurement recovery refunded
FSD Jammu 12.09.2018 16.03.2017 to 12.09.2018 to Rs.4,78,177
to PEG 15.03.2019 15.03.2019
Ramban
FSD Jammu 19.05.2019 14.08.2018 to 01.04.2019 to Rs.2,87,477
to FSD Mir 13.08.2020
Bazar 18.05.2019
Railhead 26.04.2019 02.02.2018 to 01.04.2019 to Rs.27.802
Udhampur to 01.02.2020 25.04.2019
PEG Doda
Total refund Rs.7,93,456

26 Since the recoveries made prior to the actual remeasurement dates are

contrary to the GRC’s findings and policy guidelines, as such the petitioner is entitled

to refund of Rs.7,93,456.

27 In view of the above findings, there is no perversity in the impugned

orders. However, since it is established and admitted by the respondent-FCI that an

excess amount of Rs. 7,93,456/- was recovered prior to the respective remeasurement

dates, this Court deems it appropriate to dispose of the writ petition by directing the

respondent-FCI to refund to the petitioner a sum of Rs. 7,93,456/- (Rupees Seven

Lakh Ninety Three Thousand Four Hundred Fifty Six only), being the excess amount

recovered. Ordered accordingly. The said amount shall be paid to the petitioner

within a period of six (6) weeks from the date of this judgment. In case of failure, the

amount shall carry interest at the rate of 6% per annum from the date of this judgment

until actual payment.

Record produced by the respondents in terms of order dated 22.05.2025 be

returned back.

(MOKSHA KHAJURIA KAZMI)
JUDGE

Jammu
30.06.2025.

Sanjeev
Whether order is reportable: Yes/No



Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here