1. The present appeal has been preferred by Calcutta Electric Supply
Corporation Limited (hereinafter referred to as CESC) challenging an
order dated 23rd April, 2025 passed by learned Single Judge in the writ
petition being WPO/122/2025. By the said order the learned Single
Judge directed the writ petitioner/respondent no.1 herein to pay
Rs.1,50,000/- within a period of 7 days along with reconnection charges
without prejudice to the rights and contentions of the parties. It was
also directed that upon such payment CESC will reconnect the
electricity connection of the writ petitioner and he shall go on paying the
current bills. It was further observed that the said interim order shall
remain in effect for a period of two months from date and that the
matter will be taken up for hearing after three weeks when CESC shall
produce the relevant records.