Cesc Ltd vs Md Ali And Ors on 15 July, 2025

0
23

[ad_1]

1. The present appeal has been preferred by Calcutta Electric Supply

Corporation Limited (hereinafter referred to as CESC) challenging an

order dated 23rd April, 2025 passed by learned Single Judge in the writ

petition being WPO/122/2025. By the said order the learned Single

Judge directed the writ petitioner/respondent no.1 herein to pay

Rs.1,50,000/- within a period of 7 days along with reconnection charges

without prejudice to the rights and contentions of the parties. It was

also directed that upon such payment CESC will reconnect the

electricity connection of the writ petitioner and he shall go on paying the

current bills. It was further observed that the said interim order shall

remain in effect for a period of two months from date and that the

matter will be taken up for hearing after three weeks when CESC shall

produce the relevant records.