Atul Projects India Private Limited vs Nima Developers Private Limited on 23 July, 2025

0
54

[ad_1]

Bombay High Court

Atul Projects India Private Limited vs Nima Developers Private Limited on 23 July, 2025

   2025:BHC-OS:11633


                                                                                      CARBP-35274-2024=IA=F.docx



                                    IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                        ORDINARY ORIGINAL CIVIL JURISDICTION
                                             IN ITS COMMERCIAL DIVISION

                           COMMERCIAL ARBITRATION PETITION (L) NO. 35274 OF 2024
         Digitally
         signed by
         SHRADDHA
SHRADDHA KAMLESH
KAMLESH  TALEKAR
                       Atul Projects India Pvt. Ltd.                               ...Petitioner
TALEKAR  Date:
         2025.07.23          Versus
         15:52:20
         +0530
                       1. Nima Developers Private Limited
                       2. India Farmers Private Limited                            ... Respondents
                                                 WITH
                                INTERIM APPLICATION (L) NO. 1461 OF 2025
                                          [FOR INTERVENTION]
                                                   IN
                           COMMERCIAL ARBITRATION PETITION (L) NO. 35274 OF 2024

                       Oberoi Realty Limited                                ... Applicant / Intervenor
                       In the matter between :
                       Atul Projects India Private Limited                  ... Petitioner
                             Versus
                       Nima Developers Private Limited & Anr.               ... Respondents


                       Mr. P. Chidambaram, Senior Advocate a/w Dinyar Madon, Senior
                       Advocate, Cyrus Ardeshir, Senior Advocate, Kausar Banatwala, Ziyad
                       Madon, Manini Roy, Neuty N. Thakkar, Vaishali Dedhia, Nisha
                       Waghmare, Dipsy Sequiera, i/b Tushar Goradia, for Petitioner.

                       Mr. Aspi Chinoy, Senior Advocate a/w, Mr. Rohaan Cama a/w Pheroze
                       Mehta, Krishna Balaji Moorthy, Bhakti Mehta, Letishiya Chaturvedi, i/b
                       Wadia Gandhi & Co., for Applicant.

                       Mr. Darius Khambata, Senior Advocate, a/w Karl Tamboly, Karan
                       Rukhana, Deeksha Jani, Niket Jani, i/b Jani & Parikh, for Respondents.



                                      CORAM                : SOMASEKHAR SUNDARESAN, J.

                                      Reserved on          : March 17, 2025

                                      Pronounced on        : July 23, 2025
                                                             Page 1 of 70
                                                            July 23, 2025
            Shraddha




                            ::: Uploaded on - 23/07/2025                          ::: Downloaded on - 23/07/2025 22:25:57 :::
                                                                    CARBP-35274-2024=IA=F.docx




           JUDGEMENT :

Context and Factual Background:

1. This Petition is an appeal filed under Section 37 of the Arbitration and

Conciliation Act, 1996 (“the Act”) impugning an Order dated October 24,

2024 (“Impugned Order”) passed by the Learned Arbitral Tribunal refusing

to grant interlocutory relief to the Petitioner.

2. The Petitioner, Atul Projects India Pvt. Ltd. (” Atul”) entered into a

Memorandum of Understanding dated November 29, 2014 (” Atul MoU”)

with Respondent No. 1, Nima Developers Pvt. Ltd. (” Nima”) to develop

5,00,000 square feet of residential area on 12.5 acres of land that Nima was

entitled to in Village Marve, Malvani and Aksa (” Subject Land”). The Subject

Land forms part of a larger tract of 100 acres of land (” Larger Land”), which

had been leased to Nima by Respondent No. 2, India Farmers Pvt. Ltd.

(“India Farmers”) by a sub-lease dated one day before the date of MoU i.e. on

November 28, 2014 (“Sub-Lease Deed”).

3. India Farmers, in turn, had been a lessee of ~114 acres of marshy land

for 999 years demised to it by the Governor of Bombay Presidency

(predecessor to the State of Maharashtra), pursuant to a reclamation lease

deed dated July 7, 1956 (“Lease Deed”). The Lease Deed had stipulated
Page 2 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

targets for reclamation of marshy land, with stipulated deadlines, for

cultivation of agriculture.

4. The history of events in between the Lease Deed and the Atul MoU

would matter for appreciation of the core controversy between the parties in

these proceedings. This is outlined below:-

A) The Collector, Mumbai Suburban District sought to

terminate the Lease Deed on April 26, 1993;

B) The Additional Commissioner, Konkan Division set aside

the termination by the Collector by an Order dated March

30, 1994;

C) The Revenue Minister, State of Maharashtra set aside the

Additional Commissioner’s revocation of the termination by

an Order dated May 18, 1998 (“Revenue Minister Order”),

thereby confirming the termination effected by the Collector

on April 26, 1993;

D) India Farmers filed Writ Petition No. 1029 of 1998 (” WP

1029″) challenging the Revenue Minister Order;

E) A Show Cause Notice dated March 19, 2002 (“2002 SCN”)

Page 3 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

was issued to India Farmers during the pendency of WP

1029 and that too was challenged by amending WP 1029;

F) WP 1029 was allowed by a Learned Single Judge of this

Court by an Order dated March 23, 2004 (“SB Judgement”),

setting aside the Revenue Minister Order and the 2002

SCN;

G) The SB Judgement was appealed by the Government of

Maharashtra in Appeal No. 766 of 2004 (“Appeal 766”);

H) The Atul MoU was executed on November 29, 2014 during

the pendency of Appeal 766. The Atul MoU explicitly

records that Atul has been shown all the litigation over the

Larger Land and that Nima has title to such land. However,

Clause 3 explicitly provided that the parties would convince

the Government of Maharashtra to withdraw Appeal 766.

On the withdrawal or disposal of Appeal 766, the Atul MoU

would become binding. If Appeal 766 were to not get

disposed in six months, Atul would be entitled to a refund of

the amounts spent or, at its option, continue with the

arrangement set out in the Atul MoU until such time as it

deems fit. Once India Farmers and Nima received a clear

Page 4 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

title with a favourable Order, the Atul MoU would be

incapable of termination unless any default in obligation is

committed;

I) Under Clause 4 of the Atul MoU, the parties agreed that

Atul would have a right to develop 5,00,000 square feet of

residential area on 12.5 acres of land. On the remaining

part of the Larger Land, Atul would have a right of first

refusal (“ROFR”) in relation to any development, such

ROFR being exercisable within one month of the offer for

development being made by Nima;

J) Various milestones were agreed under Clause 6 of the Atul

MoU. In the first stage, the parties were to first take efforts

to get the Government of Maharashtra to withdraw Appeal

766 and get clear and marketable title to the land. The

parties also agreed to fence the property and register the

Sub-Lease Deed and the Development Agreement. The

layout of 100 acres was to be prepared. In the next stage,

the parties were to work on obtaining permits for

development of residential property with the applicable

approvals being obtained. It is in the final stage that the

Page 5 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

parties would make a layout of the land and demarcate

portions of land for specific purposes;

K) Under Clause 7 of the Atul MoU, Atul was to pay Rs. 43

crores to Nima in three stages – the first payment of Rs. 3

crores on signing of the Atul MoU; the next Rs. 12 crores on

the withdrawal of Appeal 766 or a favourable decision in the

matter i.e. “on obtaining absolute clear title”. Other

milestones were agreed, both for payment and for taking

actions – effectively, the execution of a Development

Agreement was envisaged at a later stage;

L) On December 1, 2014, the parties agreed to a higher

payment at specific stages supplementing the Atul MoU;

M) On November 2, 2015 (a year after the Atul MoU), Atul,

Nima and India Farmers executed a Deed of Confirmation,

a tripartite document (“Confirmation Deed”) binding all

three parties. Mr. Manish Majithia, director of both Nima

and India Farmers, duly authorised to bind both the

Respondents, appears to have represented that within six

months, there would be clear title to the Larger Land and

Atul would be put in joint possession of 12.5 acres;

Page 6 of 70

July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

N) In Clause 6, the Confirmation Deed makes an explicit

reference to a plan for joint development. Should the area

shown in the plan fall under any reservation, any residential

zone equivalent to the same area reserved would be

provided by the Respondents to Atul touching the proposed

road out of the 114-acre plot;

O) Clause 9 of the Confirmation Deed provides that if after the

payment of Rs. 5 crores by Atul, there is no significant

progress, Atul has the option of withdrawing from the

project with refund along with interest at 18% after the first

month, and a bungalow worth Rs. 15 crores would be

mortgaged to Atul and interest at the rate of 18% would kick

in from the expiry of six months until clear title is obtained;

P) Finally, in Clause 11 of the Confirmation Deed, it is made

clear that India Farmers and Nima cannot terminate any of

the documents or terms unless there is a payment default

on Atul’s part;

Q) At Exhibit J to the Petition, a map indicating the layout of

the Subject Land is enclosed – this would come in for some

controversy as would be seen later;

Page 7 of 70

July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

R) It is apparent from the record that Appeal 766 was first

allowed and the SB Judgement was set aside by a Learned

Division Bench of this Court. That was carried by Nima in

Civil Appeal 5947 of 2007 to the Supreme Court, which

remanded the case back to this High Court by an Order

dated February 24, 2011. That eventually came to be dealt

with by a judgement dated October 1, 2019 (“DB

Judgement”), in which a Learned Division Bench of this

Court took note of the Government of Maharashtra’s efforts

to monitor reclamation work through the decades and its

allegations of breach of the lease conditions by allegedly not

adhering to the end-use of the lease, and upheld the SB

Judgement to the extent of finding that the Revenue

Minister Order ought to be set aside;

S) However, the DB Judgement found that 2002 SCN ought

not to have been quashed since it raised an independent

issue of mortgaging government land to banks to raise

finances. Instead, the DB Judgement held, the Respondents

ought to have been asked to respond to the 2002 SCN.

Therefore, effectively the DB Judgement confirmed the

quashing of the adverse findings starting with the
Page 8 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

Collector’s adverse Order dated April 26, 1993 culminating

in the Revenue Minister Order, but revived the 2002 SCN

that had been quashed in the SB Judgement. The 2002

SCN also had a direction not to create any interest in the

land without the prior permission of the Government of

Maharashtra – these are the proceedings that were revived

by the DB Judgement;

T) On July 28, 2020 (nearly ten months later), Nima would

write to Atul stating that the DB Judgement had confirmed

that the proceedings based on allegations of violation of the

lease deed stood quashed and that Nima’s title was now

clear. The DB Judgement had not been challenged in the

Supreme Court by the Government of Maharashtra.

Therefore, the letter asserted that Indian Farmer’s rights to

the land stood firmly established, and called on Atul to pay

the Rs. 12 crore payable as a non-refundable security

deposit under the Atul MoU within 14 days, failing which it

would be presumed that Atul was not interested in pursuing

the Atul MoU, which would stand terminated;

U) On August 24, 2020, Atul replied to Nima asserting that

Page 9 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

merely because the Government of Maharashtra did not file

a special leave petition in the Supreme Court it could not be

said that Indian Farmer’s title is clear;

V) Neither of the aforesaid two letters made a reference to the

2002 SCN having been revived or its status. On September

7, 2020, Nima replied to Atul calling upon Atul to perform

the Atul MoU and ended by hoping that wiser counsel

would prevail and Atul would comply with the Atul MoU (in

paragraphs 6 and 9);A little before this exchange of

correspondence between July 2020 and September 2020,

proceedings under the 2002 SCN had been underway. On

November 27, 2019, written submissions of India Farmers

had been filed before the Collector, Mumbai Suburban

District and a personal hearing had been conducted on

December 16, 2019. It appears that on September 18, 2020,

less than ten days after Nima had called on Atul to perform

the Atul MoU, the Collector, Mumbai Suburban District

passed an Order dealing with the 2002 SCN and holding

India Farmers guilty of violating the lease conditions by

mortgaging the property in favour of Indian Bank, which

had led to recovery proceedings – contrary to India
Page 10 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

Farmers’ assertion that the loan had been repaid. The

Collector held that the land had been given for reclamation

with the sole objective of making it cultivable. That not

having been done and the land having been mortgaged

without the consent of the Government, the lease was

forfeited and re-possession was directed;

W) On September 23, 2020, it is apparent that re-possession

was attempted. This led to Writ Petition (L) No. 3607 of

2020 (“WP 3607”) being filed by India Farmers. As it now

transpires, on September 23, 2020, the property cards were

mutated to record the name of Government of Maharashtra

as the owner of the Larger Land;

X) On September 24, 2020, noting that legal possession was

with the Government of Maharashtra while physical

possession was still with India Farmers, this Court directed

that status quo be maintained until the next date;

Y) In these proceedings, Atul would claim that these

developments were entirely behind its back and the

Respondents had not extended the courtesy of intimating

Atul. On the contrary, the Respondents had been asserting

Page 11 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

that the title was completely in the clear and called upon

Atul to pay another Rs. 12 crores;

Z) On October 16, 2023, India Farmers took two simultaneous

actions. It executed a Memorandum of Understanding with

Oberoi Realty Ltd. (“Oberoi MoU”) for development of the

Subject Land under Regulation 33(8) of the Development

Control Promotion Regulation, 2034 (” DCPR 2034″) made

under the Maharashtra Regional and Town Planning Act,

1956 by the Municipal Corporation of Greater Mumbai

(“MCGM”) or under the Information Technology (“IT”)

policy entailing development for IT and IT-enabled service

(“ITES”) units as well as for non-IT and non-ITES units;

AA) On the same date i.e. on October 16, 2023, a three-way

instrument was executed internally among India Farmers,

Nima and Mr. Manish Majithia, purporting to terminate the

Sub-Lease Deed (“Sub-Lease Termination Deed”) – Mr.

Majithia himself purporting to sign on behalf of each of the

three parties. The upshot of this action is that Nima’s

entitlement to the Larger Land was meant to be cut out of

the linkage to India Farmers’, thereby leaving Atul with no

Page 12 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

basis to claim performance from Nima. It is seen from the

record that it was on April 9, 2024, that the fact of this

purported cancellation was intimated to Atul by advocates

of Nima in the course of trading notices to each other;

BB) On December 18, 2023, Nima wrote to Atul purporting to

terminate the Atul MoU on account of non-payment of the

sum of Rs. 12 crores by Atul pursuant to the demand made

on July 28, 2020 and September 7, 2020. This letter made

no mention of Nima no longer having a sub-lease in its

name and that the Atul Transaction Documents had been

frustrated. By this letter, Nima stated that the Atul MoU had

been terminated on July 28, 2020 and it was ” once again”

being terminated “with immediate effect”. The amount of

Rs. 5.51 crores paid until then by Atul to Nima was refunded

by a cheque enclosed with the letter;

CC) On December 28, 2023, the Government of Maharashtra

issued a notification changing the status of the land to a No-

Development Zone (“NDZ Land”);

DD) Atul invoked arbitration under Clause 19 of the Atul MoU

on February 21, 2024, and filed a Section 9 Petition on May

Page 13 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

29, 2024, which was converted into an Application under

Section 17 by an Order of a Learned Single Judge dated July

24, 2024. It is in disposal of the Section 17 Application that

the Impugned Order was passed on October 24,

2024;Meanwhile, by an Order dated September 19, 2024

(“New Revenue Minister Order”), it is stated the then

incumbent Revenue Minister, Government of Maharashtra

passed an Order leading to a closure of the 2002 SCN and

the consequent proceedings to take possession of the Larger

Land in favour of India Farmers;

EE) The Impugned Order was challenged by way of this Petition.

A Learned Single Judge (R.I. Chagla J.) took note of the

Respondents’ submissions that contentions raised in this

Petition by Atul had not been raised before the Learned

Arbitral Tribunal. The matter was stood over to December

4, 2024 for consideration of ad interim relief, permitting an

Affidavit from the Respondents. On December 3, 2024 (the

eve of the next hearing date) the Respondents served the

Revenue Minister’s Order dated September 19, 2024 on

Atul;

Page 14 of 70

July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

FF) On December 4, 2024, the matter was stood over to

December 11, 2024. On that date, the Learned Single Judge

arrived at a prima facie view that the Oberoi MoU had been

executed before the Atul MoU had been terminated. Taking

note of the submission that the Oberoi MoU that had been

tendered during the Section 17 proceedings before the

Learned Arbitral Tribunal had been substantially redacted

(portions not intended to be read being masked), Atul had

been unable to assail the Oberoi MoU in that forum, the

Learned Single Judge was pleased to direct that the Oberoi

MoU be tendered in this Court in a sealed cover, and that

until the Petition was disposed of, the Oberoi MoU shall not

be acted upon;

GG) On January 17, 2025, the Petition came up before me.

Oberoi Realty Ltd. (“Oberoi”) moved Interim Application

(L) No. 1461 of 2025 (“Intervention Application”) seeking to

be impleaded in the Petition. Essentially, Oberoi’s

contention was that its interests were hampered by the

Learned Single Judge’s restraint on the Oberoi MoU being

acted upon. Oberoi was desirous of filing a Reply to the

Petition. I passed an Order stating that the non-redacted
Page 15 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

Oberoi MoU that was in a sealed envelope would be

examined by me in Chambers, after which a view would be

taken on whether to issue notice on the Interim Application;

HH) On February 10, 2025, I passed an Order inter alia stating

the following:

Having considered the MoU, prima facie, in the interest of
transparency and access of all parties to all the material on record, I
am inclined to:-

(a) issue notice to the Petitioner on the Intervention Application;

and

(b) issue notice to the Respondents in the Section 37 Appeal to let
the Petitioner have access to the MoU so that the Section 37 Appeal
can be considered with full transparency and access to all relevant
material by all parties.

[Emphasis Supplied]

II) Atul filed an Affidavit in Reply to the Intervention

Application taking the stance that Oberoi was not related to

Nima and India Farmers and that applying the principles

laid down in Cox and Kings1, it was not necessary to make

1
Cox and Kings v. SAP India Pvt. Ltd. & Anr. – 2023 INSC 1059
Page 16 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

Oberoi a party. It was contended by Atul that it was not

necessary to implead Oberoi and that Oberoi was not a

party to the arbitration proceedings;

JJ) Thereafter, when the proceedings were taken up, consensus

appeared to have evolved among the Learned Senior

Counsel for the parties to address the Court on the main

Section 37 Petition. The matter was then heard on multiple

dates with all parties, including Oberoi being present on all

dates;

Section 17 Application – Reliefs Sought:

5. At the threshold, it would be instructive to notice the reliefs sought by

Atul in the Section 17 Application. Atul desired a direction to Nima, India

Farmers and Mr. Manish Majithia, to deposit a sum of Rs. 10 crores; and to

stay the effect and operation of the purported termination of the Atul MoU,

the letter dated December 1, 2014 and the Confirmation Deed (collectively,

“Atul Transaction Documents”), by way of the letters dated July 28, 2020 and

December 18, 2023 and to injunct the Respondents from communicating the

purported termination to third parties. Atul also sought a full disclosure of

the nature of the third party rights purported to have already been created (as

communicated by Advocates of Nima by letter dated April 9, 2024). Atul also

Page 17 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

prayed for tendering of the Sub-Lease Termination Deed. Another prayer

was for disclosure of every document and deed executed in respect of the land

since April 1, 2020. Finally, it was prayed that the Respondents be injuncted

from presenting any proposal for development of the land.

Impugned Order:

6. The Learned Arbitral Tribunal was satisfied on a number of counts for

refusing relief in the Section 17 Application. They may be summarized thus:-

A) The Learned Arbitral Tribunal was satisfied that the Larger

Land came to be classified as a No Development Zone (” NDZ”).

The Learned Arbitral Tribunal ruled that since no residential

development could at all take place on the Larger Land, there is no

scope for specific performance. The Learned Arbitral Tribunal also

ruled that it would not be possible to direct Nima and India

Farmers to effect development for IT and ITES purposes on the

Larger Land to suit the requirements of Atul. It was held that no

interim relief could be granted since no such final relief was

possible, since the designated user of the land had totally changed;

B) The second view of the Learned Arbitral Tribunal was that

prima facie, Atul was not ready and willing to perform on the Atul
Page 18 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

MoU. Atul was to make a non-refundable deposit of Rs. 43 crores

in stages – the first payment of Rs. 3 crores was made and Rs. 12

crore was payable when the revenue matter was resolved in Court.

The letter dated December 1, 2014 entailed a further sum of Rs. 18

crores. The Confirmation Deed entailed payment of Rs. 2 crores on

its execution and another Rs. 3 crores against ” almost work of title

by Revenue Department and / or by Court is clear [sic]”. The

Learned Arbitral Tribunal held that both these were to be done

within six months. However, the Learned Arbitral Tribunal found

that Atul had only paid a total of Rs. 5.51 crores and defaulted on

paying the further amounts when due. Considering the transcript

of an exchange that took place on October 17, 2019 on WhatsApp,

the Learned Arbitral Tribunal found that Atul had indicated the

need to reduce the area, and the Respondents had even proposed

to go with the reduction, but Atul did not react further. The upshot

of this analysis is that Atul’s conduct was not equitable by not

taking any action for long and allowing another to deal with the

property, disentitling relief at this stage on equity grounds under

Section 17 of the Act;

C) The Learned Arbitral Tribunal also found that the precise

Page 19 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

area of 12.5 acres on the Larger Land had not been identified and

marked by the parties. Citing a few judgements, the Learned

Arbitral Tribunal held that where the exact area is not identified

and the boundaries were unclear, no decree could lie. The upshot

appears to be that no relief would be forthcoming under the Atul

Transaction Documents, which are lacking a crystallised bargain in

material particular, since the area of 12.5 acres has not been

specifically marked on the 100 acres of the Larger Land. The

Learned Arbitral Tribunal has specifically held that Atul had no

rights over the Larger Land and therefore it could not have been

given land for residential use. Effectively, the view appears to be

that the Atul Transaction Documents do not lend themselves to

specific performance and therefore the Section 17 Application

would not get any traction;

D) The Learned Arbitral Tribunal has also ruled that the letter

of July 28, 2020 is a termination letter rather than a notice to

terminate, and to consider whether it was waived by issuance of the

letter dated September 7, 2020 (which called for performance),

there ought to have been a pleading claiming waiver. The Learned

Arbitral Tribunal held that the Atul MoU had been terminated on

Page 20 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

July 28, 2020 and Atul did not react until it invoked arbitration on

February 21, 2024;

E) The Learned Arbitral Tribunal accepted the statement

made by Counsel for the Respondents that third party rights had

already been created. The Learned Arbitral Tribunal held that

third parties who are not party to the arbitration agreement could

not be added in the arbitration proceedings. The Learned Arbitral

Tribunal held that it could not pronounce upon the validity of the

Oberoi MoU since Oberoi was not a party;

F) The Learned Arbitral Tribunal held that the restoration of

the 2002 SCN and the direction contained therein, not to deal with

the Larger Land without the prior consent of the Government of

Maharashtra, cannot be regarded as a stay on creation of third

party rights by a court of law. The mere issuance of a Show Cause

Notice is not a fetter, and it is only when there is an outcome in the

proceedings pursuant to the Show Cause Notice that there could be

a fetter. However, if Atul was of the view that the 2002 SCN was a

fetter on title, that alone would be ground for not being able to

enforce the Atul Transaction Documents since there would be a

fetter on implementing them;

Page 21 of 70

July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

G) In view of such findings, the Section 17 Application was

comprehensively and completely dismissed without any relief.

Analysis and Findings:

7. Mr. P. Chidambaram, Learned Senior Counsel made submissions on

behalf of Atul; Mr. Darius Khambata, Learned Senior Counsel on behalf of

the Respondents and Mr. Aspi Chinoy, Learned Senior Counsel represented

Oberoi. Each of Mr. Chidambaram and Mr. Khambata has presented written

notes in aid of their submissions – and the exchange went on up to the stage

of a written response even to the written submissions in sur-rejoinder.

8. These proceedings have been very intensely contested with

submissions by Learned Senior Counsel for both sides over multiple rounds,

each seeking to raise a plethora of nuanced points, with accommodation of

time being sought by each side after each round of submissions by the other.

Submissions were made on four different dates of hearing, lasting between

February 26, 2025 and March 17, 2025. To be fair, the issues raised by them

involve consideration of a long and complicated history of factual

developments, and indeed nuanced consideration of inter-related facets of

the matter that were pleaded or argued by each side at different stages of this

litigation.

Page 22 of 70

July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

9. I have had the benefit of their well-referenced written notes on

arguments to navigate the voluminous record generated by the parties in the

proceedings before the Learned Arbitral Tribunal. I find that apart from the

issues presented to the Learned Arbitral Tribunal and the manner of decision

on them, the parties have also serious disputes over whether Atul has

presented moving targets for the Respondents to meet in the manner in

which contentions were presented to the Learned Arbitral Tribunal and to

this Court.

10. For ease of structure to my opinion, I have dealt with the issues in the

same sequence as has been dealt with by the Learned Arbitral Tribunal, as

summarized above. Multiple strands of contentions have been presented and

the response to each need not necessarily have a direct and independent

bearing on the final outcome. I would therefore deal with the implications of

the findings on these strands in a cumulative and holistic analysis at the end

of the judgement.

11. At the threshold, it must be stated that Section 17 of the Act enables

protection and preservation of the subject matter of the arbitration. The Atul

Transaction Documents reduced to writing the terms on which the parties

would pursue development of residential units on the Subject Land. For
Page 23 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

purposes of the jurisdiction under Section 37 of the Act, which is a statutory

appeal over decisions taken under Section 17 of the Act, the core question to

ask is whether any of the material findings in the Impugned Order are

summary in nature and defiant of reason, as discernible from the record.

Whether the view of the Learned Arbitral Tribunal is a reasonable and

plausible view or whether it is implausible or perverse on any facet would

need to be seen.

12. In the peculiar facts of this case, such consideration would also extend

to whether the Learned Arbitral Tribunal was presented with all that had to

be considered in order to return reasonable findings, or whether the

Impugned Order is not a duly informed decision in view the Learned Arbitral

Tribunal not having had access to the necessary material. This facet would

gain significance, particularly in the context of the Oberoi MoU. A connected

issue would be whether the Learned Arbitral Tribunal ought to have asked for

a greater disclosure of the Oberoi MoU before arriving at the decision that it

was not relevant.

No Development Zone and its implications:

13. At the threshold, the Learned Arbitral Tribunal was pleased to return a

finding that the designation of the Larger Land as NDZ undermined

everything that the Atul Transaction Documents stood for. The change of
Page 24 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

status of the Larger Land as a NDZ with effect from December 28, 2023

would, at first blush appear to undermine the Atul Transaction Documents,

which was essentially meant for carrying out redevelopment for residential

purposes.

14. However, it is indeed clear from the material on record that the NDZ

status does not mean the end of road for residential development of any

nature whatsoever. Rule 8.1.3 of DCPR 2034 indeed provides for

development of IT and ITES units to be developed on NDZ land. The

Impugned Order records that the Learned Counsel for Atul failed to show any

provision of law that would enable residential development in NDZ land. This

perhaps led to the Learned Arbitral Tribunal not having assistance on the

nuance in this regard, but what is clear is that development of an IT park in

NDZ also entails “allied services” and “support services”, which include the

need for those working in the IT park to have access to residential

accommodation and to allied commercial establishments.

15. This facet of the matter has not been noticed or rather can be said to

have escaped attention in the analysis contained in the Impugned Order.

Therefore, in my opinion, it cannot be ruled out that the Atul Transaction

Documents being a commercially-agreed transaction to develop residential

accommodation could have potentially been accommodated and reconciled
Page 25 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

with the NDZ classification. Suffice it to say, the NDZ classification by itself

would not be the end of the for the Atul Transaction Documents. Therefore,

this element of the analysis can be said to be inaccurate.

16. Notably, the Oberoi MoU would itself deal with this very facet of the

policy going by its description of the transaction. However, the Oberoi MoU

was, for all practical purposes, not shared with the Learned Arbitral Tribunal.

The manner of redacting of the Oberoi MoU is dealt with subsequently in this

judgement. Suffice it to say, had the Oberoi MoU been available to the

Learned Arbitral Tribunal, I have no doubt in my mind that the Learned

Arbitral Tribunal would not have returned the findings that it did on the NDZ

issue or at least in the manner that it has done.

Was Atul Ready and Willing to Perform?

17. Whether Atul was truly ready and willing to perform the Atul

Transaction Documents is a key element in resolving the issues raised in

these proceedings. Atul’s key contention is that the obligation to pay Rs. 12

crores did not arise at all until there was clear and marketable title to the

Subject Land, which could have only been achieved if there was a resolution

of Appeal 766 in favour of India Farmers and Nima, or if they managed to

convince the Government of Maharashtra to change its stance and

perspective on the merits of pursuing those proceedings. Having examined
Page 26 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

the record, the key driver for the Learned Arbitral Tribunal to take a view on

whether there is a failure on Atul’s part to demonstrate readiness and

willingness to complete the Atul Transaction Documents is the reliance

placed on a transcript of WhatsApp messages exchanged between Mr. Atul

Patel and Mr. Manish Majithia on October 17, 2019. The Learned Arbitral

Tribunal has examined the transcript produced in the proceedings (Page 502)

to arrive at a view that Atul was not really ready and willing to perform the

Atul Transaction Documents and had sought accommodation on its terms in

view of the financial and market conditions prevalent in October 2019 after

the DB Judgement came about.

18. Atul would contend that the WhatsApp transcript would only show

negotiations and discussions and unless a firm position came about, the

terms of the Atul Transaction Documents would have continued. The

Respondents would contend that the issue at hand was not whether the Atul

Transaction Documents were amended but whether Atul was ready and

willing to perform the Atul Transaction Documents in the terms contracted.

19. Mr. Chidambaram would brand the WhatsApp chat transcript as

“gibberish” that is unworthy of consideration as evidence, bearing in mind

that at the stage of Section 17 proceedings, the Learned Arbitral Tribunal

ought to have only examined how to preserve the subject matter of
Page 27 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

arbitration rather than render firm findings on whether a party is ready and

willing to perform. Mr. Khambata would contend that the WhatsApp

conversation speaks to Atul’s own desire to renegotiate the transaction and

the difficulties he was then facing in the market, which would then point to

the Learned Arbitral Tribunal’s view on the absence of readiness and

willingness on Atul’s part to perform the contract was a reasonable and

plausible view.

20. The transcript is evidently colloquial, with a strong vernacular

rendition of the English language, but that is an element that afflicts even the

Confirmation Deed (recall the reference to ” almost work of title being clear”.

This Court cannot undermine the ability of the Learned Arbitral Tribunal to

exercise its discretion in discerning a prima facie position on whether Atul

was ready and willing to perform the Atul Transaction Documents in the very

same terms as contracted. Whether the Atul Transaction Documents was

amended is not the point in issue – whether it was Atul’s desire to have the

Atul Transaction Documents modified to enable him to still get some part of

the bargain, is a question that the Learned Arbitral Tribunal is entitled to

consider. However, what needs to be considered is whether the stage at

which the WhatsApp conversation was had, was a stage when Atul was

obliged to make payments on the premise that the title was absolutely clear.

Page 28 of 70

July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

21. While the WhatsApp transcript alone may not have a definitive bearing

to render all other areas of consideration irrelevant, but discounting for the

colloquial usage of English, it would be totally open to the Learned Arbitral

Tribunal to draw a reasonable inference on the readiness and willingness to

perform. The transcript would indicate, a prima facie position (a firm final

conclusion can be drawn in arbitration proceedings eventually) that Mr. Patel

was open to scaling down the area of development to reduce the financial

burden at that time, which Mr. Majithia too was willing to consider. The

WhatsApp transcript also shows that the parties had disagreement even on

that very day about whether Nima and India Farmers could be said to have

clean title. Atul presented a dual proposition – if the title were not clear, then

nothing would be payable, and if title were clear, then the ” problem is market

& payment”. He would say “if due & not payable then will agree to reduce my

area….but can’t commit nowadays”. To my mind, going by the style of

conversation, the words “not payable” indicates that if Atul is unable to pay,

he would agree to reduce his area, but it was difficult to commit. However, he

did reject the proposition that the milestones for him to pay, had been

reached.

22. In my opinion, no fault can be found with the Learned Arbitral

Tribunal in interpreting this conversation on WhatsApp, which is in fact in

Page 29 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

writing. When dealing with the conduct of commercial parties, one must

have regard to reading the language deployed by men of commerce in a

manner that they would have meant. It would not be appropriate to bring to

bear standards of legally-drafted correspondence when interpreting what is a

ready indicator of the state of mind of the person authoring such a message.

In my opinion, no fault can be found with the Learned Arbitral Tribunal’s

reliance on the WhatsApp message or in its interpretation of the same. This

element would go into the mix of what is to be considered in the course of an

appropriate decision under Section 17 of the Act. The readiness and

willingness to perform has indeed been shown as eroded, in about a fortnight

after the DB Judgement. Whether the DB Judgement actually firmly and

clearly lifted the cloud on title is a separate issue and that is dealt with

separately.

Was Precision of Subject Matter Absent?

23. One of the key findings of the Learned Arbitral Tribunal is that the

instruments constituting the Atul Transaction Documents are agreements to

agree and not a firm and crystallised agreement. Towards this end, one key

area of controversy is whether the 12.5 acres of land on which residential

development was to take place in terms of the Atul Transaction Documents

had been identified and marked on a layout for the parties to know what

Page 30 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

precisely was the area on which they would effect residential development.

Towards this end, the parties have had bitter disputes about the existence of a

layout plan. Atul would contend that the layout was well known to the parties

and had been identified. The contention is that Atul’s advocates

inadvertently did not append it to the Section 17 Application (the Section 9

Petition originally filed) but were willing to tender it in the arbitration

proceedings but the Learned Arbitral Tribunal simply refused to let them

tender it.

24. In my opinion, the material on record would not lend itself to a

sweeping conclusion that there was nothing earmarked in the instruments

constituting the Atul Transaction Documents. Clause 6 of the Confirmation

Deed records that the plot area of 50,500 square metres “as shown in plan” is

for joint development. Should any portion of it fall in a reservation when

town planning takes place, the Respondents would provide any residential

zone area of the same size touching the proposed road. A plain reading of

Clause 6 of the Confirmation Deed would indicate that there was a plan and

that did indicate the area.

25. That apart, the role of an architect, one Mr. Ashwin Zhaveri and M/s

H.M. Zaveri & Sons is writ large on the Confirmation Deed. It appears

unlikely that a commercial party would agree to part with serious money for a
Page 31 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

residential development without so much as a plan to indicate the layout of

the Larger Land and which part of the Larger Land would comprise the

Subject Land, and where to locate the residential development. The value of

development, particularly for residential units could vary widely when one is

considering the sizeable value of monies contracted to be parted with

between the parties.

26. Whether there was an identified plan and earmarked land would

certainly present a question of fact, and to my mind it cannot be summarily

concluded that the Atul MoU or the Confirmation Deed was simply without

any idea whatsoever of where the 12.5 acres of land would lie on the Larger

Land. Evidence would need to be led – perhaps of Mr. Zaveri too and not just

the contesting parties. Whether the plan sought to be exhibited by Atul is the

plan that was referred to in Clause 6 of the Confirmation Deed would have

been a matter of evidence. Answering that would call for a more detailed

probe at the stage of the final hearing. Pending that, what interim

arrangements are needed ought to have been considered. Therefore, to my

mind, the Atul Transaction Documents cannot be entirely wished away as

being so inchoate and vague that it would not lend itself to enforcement and

execution, even if such a statement were to be made purely as a prima facie

finding.

Page 32 of 70

July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

27. A letter from the solicitors to the Respondents dated April 9, 2024

would come in for some analysis across the issues involved in this judgement.

In Paragraph 24 of that letter, it is asserted on behalf of the Respondents that

Atul was to fence and build a compound wall but defaulted in doing so. If

there had been a contracted obligation to fence an area and build a

compound wall, it would stand to reason that the area of land to be fenced

would have to be identified. That too would reasonably point to it being more

probable than not, that the parties knew which precise piece of land would

constitute the Subject Land. Therefore, it does not appear reasonable to wish

away the Atul Transaction Documents away as a bunch of documents with no

clue as to which parts of the Larger Land would constitute the Subject Land.

If the fencing was to be of the Larger Land, and that too by Atul, it would beg

the question as to whether Atul’s claim for protection on the Larger Land,

premised that it had a ROFR on it, would have carried greater weight than

what has been ascribed to the issue by the Learned Arbitral Tribunal.

28. Another relevant element is whether the subject matter of protection is

just the Subject Land or the Larger Land. Atul would contend that it has a

ROFR over development of the Larger Land. This is seen in Clause 4 of the

Atul MoU. Therefore, when presented with a prayer for preservation of the

subject matter of the dispute that is subject to arbitration, Atul would

Page 33 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

contend, the subject matter of protection includes its entitlement to the

Larger Land and the ROFR it enjoys on it. This too is not an argument that

can be summarily wished away. However, whether interim relief, when

moulded, must cover only the Subject Land or the Larger Land is entirely a

matter in the discretion of the Learned Arbitral Tribunal based on its

perception of the strength of the view on the prima facie case, perception of

grave injury and balance of convenience.

29. If it was found that there was hesitation in performing even the

obligations in relation to the Subject Land, due to financial and market

constraints, and that Atul was seen as being willing to truncate its

entitlements even to the Subject Land, it would be totally open to make no

interlocutory arrangements, subject of course, to whether the time to perform

had arrived and the pre-conditions to performance obligations had been met.

Was the Atul Transaction Documents Terminated on July 28, 2020?

30. One area of hot contest between the parties is whether the Atul

Transaction Documents was terminated on July 28, 2020. The Learned

Arbitral Tribunal has returned a summary view that they were terminated on

that date. The Respondents hope to have a declaration of Atul being

hopelessly barred by limitation by indicating that the termination took effect

on July 28, 2020 and arbitration was invoked only on February 21, 2024.
Page 34 of 70

July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

The April 9, 2024 letter from the solicitors of the Respondents asserts so in

so many words. The effect of suspension of limitation periods between

March 15, 2020 and February 28, 2022 at the instance of the Supreme Court

in Suo Motu Writ Petition 3 of 2020 does not seem to have been factored in.

31. That apart, leaving limitation aside, the perceived delay could influence

a reasonable assessment of whether interim protection ought to be granted.

With that in mind, I have examined the assertion of termination having been

effected way back on July 28, 2020. It is clear from the letter issued on that

date (and this was nearly ten months after the DB Judgement) that Atul was

called upon to pay a sum of Rs. 12 crores failing which there would be an

automatic termination of the Atul Transaction Documents. This letter called

upon Atul to perform within 14 days and did sound an ultimatum. However,

this letter also invited Atul for a conversation on the subject. Atul did not

accept the position that the conditions to be met for payment obligations to

be triggered had been met. Atul replied on August 24, 2020 denying that the

stage for payment of Rs. 12 crores had arrived.

32. Thereafter, Nima issued another letter dated September 7, 2020 which

would indicate, prima facie, that the Respondent did not intend (then) for the

July 28, 2020 letter to have been a termination letter. This letter again called

upon Atul to perform the Atul Transaction Documents. It was stated
Page 35 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

explicitly that Nima hoped wiser counsel would prevail on Atul and it would

perform the obligations demanded of it in accordance with terms agreed

between the parties. If the July 28, 2020 letter was an inexorable

termination, there would have been no room for the letter dated September 7,

2020 asking for compliance. Neither had Atul performed the actions

demanded within 14 days of July 28, 2020 nor was Nima’s letter dated

September 7, 2020 (in response to Atul’s letter of August 24, 2020) in the

vein of asserting that the Atul Transaction Documents already stood

terminated. On the contrary, the threat of legal action if wiser counsel did

not prevail on Atul, could point to potential action for specific performance

being initiated by the Respondents not being ruled out.

33. Therefore, in my opinion, it cannot be reasonably held with the

certitude found in the Impugned Order that that there had been a

termination of the Atul Transaction Documents on July 28, 2020, or for that

matter, on September 7, 2020. Indeed, it was on December 18, 2023 that

Nima actually terminated the Atul Transaction Documents and enclosed a

cheque for the Rs. 5.51 crores received until then from Atul. By this time, the

Respondents had achieved the commercial and financial security from the

Oberoi MoU (executed in October 2023). It was on December 18, 2023 that

the election to terminate was clearly made and the potential to litigate for

Page 36 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

specific performance was conclusively shelved. Arbitration was invoked by

Atul in February 2024 and in the interregnum, mediation was attempted for

what was evidently a commercial dispute. Both parties could equally be

accused of remaining silent for three years since July / September 2020. The

Respondents, of course, were battling a renewed effort by the Government of

Maharashtra to take possession of the Larger Land – indeed, far from

absolute title, even mutation entries indicating taking of possession on paper

were passed, taking back the land in purported cancellation of the Lease

Deed. The Oberoi MoU was executed in October 2023 and the Atul

Transaction Documents were explicitly terminated in December 2023.

34. It appears to me that the reference to these dates by the Learned

Arbitral Tribunal is in the context of articulating the fact that Atul sought to

invoke arbitration much later (in February 2024 – perhaps after becoming

aware of the risk that the ship was sailing), and this weighed with the

Learned Arbitral Tribunal on the decision not to grant interim relief. That is

understandable. However, it cannot be ruled at this stage for any purpose of

the arbitration proceedings that the Atul Transaction Documents stood

terminated on July 28, 2020.

Page 37 of 70

July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

Relevance of the Oberoi MoU:

35. The Oberoi MoU is a very important element of these proceedings. The

Oberoi MoU was executed on October 16, 2023 along with the Sub-Lease

Termination Deed. The two instruments executed simultaneously on the

same day appear to be a device structured to bring to an end, the interests of

Atul. The Sub-Lease Termination Deed (signed by Mr. Majithia for himself;

for Nima and for India Farmers) was a self-executed instrument that would

enable the Respondents to contend that Nima had no title to the Larger Land,

which was part of the land leased by the Government of Maharashtra to India

Farmers and sub-leased by India Farmers to Nima. Third party interest in

the hands of Oberoi was created in parallel.

36. In the letter written by solicitors of the Respondents on April 9, 2024,

there is an assertion that the Sub-Lease Termination Deed had been

executed. The effect of the Sub-Lease Termination Deed would be an internal

document executed to be self-serving to one of the parties to the instruments

constituting the Atul Transaction Documents.

37. One of the reliefs sought in the Section 17 Application is a full

disclosure of all documents executed in relation to the land covered by the

Atul Transaction Documents. There is no doubt that the execution of the

Oberoi MoU was necessarily required to be part of the assessment and
Page 38 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

adjudication by the Learned Arbitral Tribunal. A redacted version of the

Oberoi MoU was purportedly brought on record by the Respondents –

“purportedly” because, in my opinion, the document tendered by the

Respondents was as good as not producing anything at all.

38. I have already outlined the flow of events in these proceedings before

my predecessor who had called for the Oberoi MoU to be produced without

any masking for consideration by the Court, but in a sealed cover i.e. not for

being shared with Atul. As stated earlier, I have gone through it. I am left

with no doubt in my mind that if this document had been called for by the

Learned Arbitral Tribunal just like my predecessor had called for it, the

Learned Arbitral Tribunal would have taken a significantly different view of

the matter. A number of conclusions drawn by the Learned Arbitral

Tribunal, in my opinion, would have well stood undermined, had the Learned

Arbitral Tribunal seen the Oberoi MoU in its entirety. That the Learned

Arbitral Tribunal had been prevented from getting a full picture is evident

from the manner in which a glimpse of the Oberoi MoU was purported to be

provided to the Learned Arbitral Tribunal, if the manner of redacting could

even be regarded as leading to even a “glimpse”.

Page 39 of 70

July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

39. A careful examination of the redacted Oberoi MoU would show that

what was a 33-page document was presented as a six-page document. Of the

four pages of recitals that are replete with the history of the transactions over

the same land, just one page with a large black patch on it was filed. The

provisions, including the definitions and the operative provisions contain

references to the Atul Transaction Documents. These ought to have been

part of the mix for consideration by the Learned Arbitral Tribunal so that it

could consider an appropriate relief even if it were to be of the view that

prima facie, Atul has not been able to show a strong demonstration of having

been ready and willing to perform. Unfortunately, the end result is that the

entire evidence that would have enabled an informed decision by the Learned

Arbitral Tribunal had been kept away from the Learned Arbitral Tribunal.

40. Indeed, Section 19 of the Act makes it clear that arbitral tribunals are

free to conduct proceedings in such manner as they deem appropriate. This

would include the power to determine admissibility, relevance, materiality

and weight of any evidence. Since Section 37 envisages a statutory right to

appeal from decisions refusing to grant an interim measure, if it appears to

the Section 37 Court that a certain decision on the manner of allowing

evidence has been unreasonable or implausible, leading to a rejection of the

interim relief under Section 17, an intervention may be made. It is apparent

Page 40 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

that the Learned Arbitral Tribunal took a view on the basis of the redacted

Oberoi presented by the Respondent – six out of 33 pages, of which two are

title pages and two are the signature pages and one page is the schedule to

show that a third party interest has been created on the same land. By

adopting such an approach, the Learned Arbitral Tribunal was led to believe

that the rest of the Oberoi MoU would be totally irrelevant to a decision

under Section 17 of the Act. In my opinion, the contrary is true.

41. The situation in hand is not even that the Learned Arbitral Tribunal

was fully shown what the Oberoi MoU entailed, with an application being

made for keeping it confidential – neither the Learned Arbitral Tribunal nor

Atul were any wiser about the contents of the Oberoi MoU and its import for

the matter at hand. This is not to suggest that the Learned Arbitral Tribunal

must necessarily have seen the Oberoi MoU behind the back of Atul. Dealing

with a similar situation in a writ petition involving development of property,

the declaration of the law by a Learned Division Bench of this Court, in the

case of Sonali Ashok Tandle2 would be apt to cite:

2

Sonali Ashok Tandle vs. Rannka Lifestyle Ventures – 2023 SCC OnLine Bom 1918
Page 41 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

18. Pausing briefly for a moment, we note that the previous
Division Bench accepted without comment the tendering of some
documents in sealed cover by the 1 st Respondent. This Court has
previously thoroughly deprecated this practice. 1 So has the
Supreme Court, most recently in Madhyamam Broadcasting
Ltd. v. Union of India2 We
specifically disapprove of this and do
not permit it. It undermines the legitimacy of the adjudication
process in any system based on an adversarial proceeding. The
simplest general principle is that anything that the Court can see,
the opposing party must be allowed to see. Any exceptions must be
narrowly tailored, whether under the Evidence Act or some other
governing law. Nothing in this matter invites a single one of the
exceptions in the Evidence Act regarding privilege, i.e., immunity
from disclosure. In other jurisdictions, most particularly in the UK
limited disclosures or non-disclosures are permitted. But such
‘Closed Material Proceedings’ are now governed by statute and
always subject to judicial oversight. They are mostly in cases of
national security, immigration, etc. It is never for a party to decide
for itself what it will or will not disclose — most especially when
there is an order of the Court ordering and compelling disclosure
on affidavit. Where there are private disputes between two parties
and a Court has ordered a party to make a disclosure on Affidavit
of some material, there is simply no question of that party putting
in anything ‘in sealed cover’. As a matter of law, that is non-

compliance with a judicial order. In a given case, it will invite
action in contempt. If immunity from disclosure is sought, that is
an application that must be made to a court and must receive a
judicial order. No litigant can disadvantage the opponent by
Page 42 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

squirrelling some information into the court record ‘in sealed
cover’. No party is entitled can rely on such ‘sealed cover
material’ to the prejudice of the other side, and no court should
permit it. To do so flies in the face of every concept of fair justice
and openness and transparency in the decision-making process. It
is time to bury this thoroughly pernicious practice.

42. Madhyamam Broadcasting3 referred to by the Learned Division Bench

was a case of denial of reasons for refusal to provide approval for

broadcasting of a television channel on the ground of national security. The

facts involved in this Appeal involve no element of national security – it is a

private dispute between two builders about the manner of dealing with

development of the land. The land covered by their agreement forms subject

matter of another agreement, which is alleged to have been executed when

their agreement subsisted. There is nothing sensitive about the content that

would impinge on public interest, necessitating hiding of the same.

43. Therefore, in my view, the Learned Arbitral Tribunal was deprived of a

full picture by the manner of redacting of the Oberoi MoU. It is only

appropriate that the Learned Arbitral Tribunal and Atul should know what is

in the Oberoi MoU, since the contents speak for themselves. There are

provisions in it that actually relate to the Atul Transaction Documents.
3
Madhyamam Broadcasting Ltd. Vs. Union of India – (2023) 13 SCC 401

Page 43 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

Perusal of these provisions would have enabled Atul to make submissions on

the state of mind of the Respondents and the appropriate interlocutory

measures necessary in the circumstances. The Learned Arbitral Tribunal

would have benefitted from the contents of the Oberoi MoU to discern the

precise factual position involved and the Respondents’ own position on

whether Atul had any rights over the Subject Land or the Larger Land. All of

this has escaped adjudicatory attention because of the approach adopted.

44. Another facet of the Oberoi MoU is whether it could have at all been

executed without violating a requirement of law. This facet is integrally

connected to whether the 2002 SCN posed a fetter on free and marketable

title to the Larger Land. I have dealt with that facet where I deal with the

import of the 2002 SCN, which in turn is directly linked to whether the DB

Judgement resulted in free, marketable and clear title to the Larger Land. All

of these have been dealt with in the next section.

Did the 2002 SCN Constitute a Fetter on Title?

45. It is apparent that under the Atul Transaction Documents, until the

cloud over Nima’s title to the Subject Land was lifted, no further payments in

addition to the monies already paid, were due. Equally, the Atul Transaction

Documents were incapable of termination only after the title became free and
Page 44 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

marketable and the parties registered a proper development agreement.

46. The key issue that arises for consideration is whether the DB

Judgement comprehensively enabled free and marketable title to the Subject

Land in Nima’s possession as a sub-lessee. Clause 4 of the Confirmation Deed

(executed on November 2, 2015) has weighed with the Learned Arbitral

Tribunal. Clause 4 is a follow-on provision to Clause 3, which provides that

Nima has undertaken work to clear the title to the Subject Land such that

possession of the entire land with title would be clear for submissions to be

made to the MCGM for the redevelopment. For carrying out such work (to

have title cleared), Atul was to pay Rs. 2 crores on execution of the

Confirmation Deed and Rs. 3 crores ” against almost work of title by revenue

department and / or by court is clear”. Clause 4 goes on to say that Nima has

promised that the procedure would be completed in six months with clear

title and then the parties would execute registered documentation for the

development.

47. The DB Judgement indeed struck down the earlier view of the

Collector, which had been endorsed in the Revenue Minister Order, that in

terms of the factual matrix set out in these instruments, the Lease Deed had

been violated. The DB Judgement, however, restored the 2002 SCN. In

doing so, the DB Judgement did not effect any carve-out to the terms on
Page 45 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

which the 2002 SCN stood entirely revived.

48. A careful reading of the 2002 SCN would show that apart from it being

a show cause notice, it also doubled up as an interim order that contained

prohibitions on alienating any portion of the Larger Land without the

consent of the Government of Maharashtra. Therefore, it would not be

possible to state that the DB Judgement emphatically cleared all cloud over

title. It did clear the cloud arising of the Collector’s original view that had

been expressed on April 26, 1993 and had culminated in the Revenue

Minister Order of May 18, 1998. However, the DB Judgement revived the

2002 SCN. Indeed, the 2002 SCN dealt with alienation that arose by way of

creation of encumbrances on the land in favour of Indian Bank, without

permission of the Government of Maharashtra. On this ground too, the

Lease Deed could have been cancelled, as indeed occurred later, in fact,

contemporaneously with the September 7, 2020 Notice to Atul asserting that

the title was clear. However, the 2002 SCN having doubled up as interim

order containing prohibitions on dealings in the land, and specifically having

been revived by the DB Judgement, contained a direction, which too was

revived, not to deal freely with the Larger Land. Therefore, in my opinion, it

would not be possible to hold with any certitude that the DB Judgement

cleared all cloud over title to the Subject Land.

Page 46 of 70

July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

49. The language of the Confirmation Deed has to be seen in the light of

the aforesaid facts. The usage of the words ” almost work of title….is clear”

would indicate that the commercial agreement between the parties was that if

a substantial element of the title being clear was achieved, the payment under

Clause 4 would be triggered. This is the nature of the language used through

the Atul Transaction Documents (in one place “lapse” is spelt as “laps”) and

the authors of these instruments have presented the Learned Arbitral

Tribunal with a serious challenge in interpreting their true intent just as they

did with their WhatsApp chats.

50. It would be a plausible and reasonable prima facie finding that while

the DB Judgement did not result in a full, free and clear title to the Larger

Land, it did potentially present a situation where the title was almost clear,

triggering the payment instalment due under Clause 4 of the Confirmation

Deed. However, the payment of Rs. 12 crores due under Clause 7 of the Atul

MoU was linked to “obtaining absolute clear title”. Certainly, the DB

Judgement, which revived the 2002 SCN could not be regarded as conferring

absolute clear title. Prima facie, the Confirmation Deed supplemented the

Atul MoU and did not override the Atul MoU. This facet of nuance does not

appear to have been presented to the Learned Arbitral Tribunal and analysis

of this nature is not found in the Impugned Order. Therefore, the view that

Page 47 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

the DB Judgement rendered absolute clear title appears to me as being

summary in nature, particularly since the 2002 SCN containing a prohibition

on dealing with the land was explicitly revived by the DB Judgement.

51. In the ordinary course, it would be trite to say that the mere issuance of

a Show Cause Notice is not a fetter unless an adjudication is made on such

notice. However, where the Show Cause Notice doubles up as an interim

order, and what is revived by an explicit Court Order (that remained

unchallenged) is the entire Show Cause Notice without pruning the fetter on

free and marketable title, with the greatest respect to the Learned Arbitral

Tribunal, it would not be possible to concur that the DB Judgement led to

conferment of absolute and clear title on Nima for the Larger Land, and

thereby the Subject Land.

52. Indeed, the 2002 SCN could be said to have been pruned in its content

in relation to its basis – the creation of encumbrance in favour of banks

without consent of the Government of Maharashtra. On the remaining facts

that formed subject matter of the Revenue Minister Order, there was an

adjudication already by the DB Judgement. However, it is reasonable to

attribute the retention of the directions (not to transact in the land without

government approval) to the remaining basis i.e. the creation of

encumbrance without consent. That residual basis too could still have led to
Page 48 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

cancellation of the Lease Deed (as it indeed would later). In short, at this

stage, the factual developments that transpired later would show that Atul

had made a fair point – that the amount of Rs. 12 crore under the Atul MoU

was not due since absolute title had not been obtained.

53. When the first purported termination letter dated July 28, 2020 was

issued, the situation had not changed. Similar was the case on September 7,

2020, when Nima hoped better sense would prevail and again called upon

Atul to perform on the Atul Transaction Documents. Worse, an adverse

order was actually passed by the Collector on September 18, 2020, ten days

after the letter dated September 7, 2020, calling upon Atul to perform the

payment obligation. In fact, it is an admitted position that on September 23,

2020, the State officials attempted to take physical possession even while

they took paper possession by making mutation entries actually changing the

title to the Larger Land to the name of the Government of Maharashtra.

54. Looking at these contemporaneous developments, it would be

impossible to hold that in July 2020 or in September 2020, Nima and India

Farmers had clear title to the Larger Land. On September 24, 2020, this

Court had directed in WP 3607 that status quo be maintained. While it is

trite law that a mutation entry would not necessarily be determinative of title

in a conclusive manner, and admittedly, physical possession was in the hands
Page 49 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

of the Respondents, the status quo that was to continue would at best have

been the status quo obtaining after giving effect to the DB Judgement.

Therefore, it cannot be said that absolute and clear title in favour of the

Respondents was in existence.

55. The Oberoi MoU and the self-executed tripartite Sub-Lease

Termination Deed of October 16, 2023 would follow three years later. The

final clearance of the fetter on free and marketable title would cease only on

September 19, 2024 when the then incumbent Revenue Minister would

discharge the 2002 SCN and hold emphatically in favour of the Respondents.

Curiously, this Order of the Revenue Minister putting a final end to the

controversy (for the first time) was not even placed before the Learned

Arbitral Tribunal, which only had the DB Judgement and the redacted Oberoi

MoU to go by.

56. There has been a dispute during this Appeal about Atul’s access to the

Order of the Collector passed on September 18, 2020. This document was

indeed handed in by the Respondents as part of their Compilation of

Documents in the course of the arbitration proceedings. Mr. Khambata

would place strong reliance on the fact that Atul did not rely on the aforesaid

Order dated September 18, 2020 despite it being available during the

arbitration. In my opinion, at worst one could draw a conclusion of poor
Page 50 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

strategy or even folly for not relying on that Order in the proceedings.

However, that instrument and the consequential action to take possession

and the direction to maintain status quo are all part of the record. Whether

Atul failed to make a better argument in the arbitral proceedings by relying

on this Order would not change the legal position and status of whether there

was absolute clear title when the Oberoi MoU was executed. The Order of

September 18, 2020 was to the knowledge of the Respondents on September

24, 2020, when they informed this Court in WP 3607 that the Order had not

even been served on the Respondents. Atul was not informed about these

developments at that time. Had he been informed and yet kept quiet, the

analysis would change. Yet, the Respondents had contended before the

Learned Arbitral Tribunal that they had validly terminated the Atul

Transaction Documents on July 28, 2020 for non-payment of the Rs. 12

crores, which was payable against absolute and clear title being available.

57. The Order of September 18, 2020 and the attempt at taking possession

on September 23, 2020 and the Order in WP 3706 on September 24, 2020

are all part of one continuum of events and form an integral part of the

material on record. Atul not having made submissions based on these

developments, which only came in through a Compilation of Documents,

cannot render this Court handicapped when dealing with whether there was

Page 51 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

absolute and clear title. If Atul did not rely on them in the proceedings and

only relied on the revival of the 2002 SCN, these developments were a

consequence of the revived 2002 SCN.

58. Indeed, the sequence of events set out by Mr. Khambata in his written

submissions are instructive. After the status quo order in WP 3706, the

Additional Commissioner, Konkan Division passed an Order dated October

15, 2020 staying the Collector’s Order dated September 18, 2020. This Order

staying the Collector’s Order was set aside by the Divisional Commissioner on

June 25, 2021. In fact, the Collector was directed to hear the matter afresh

and take into account a Government Resolution dated June 26, 2018 to

examine if unauthorised mortgages could be regularised by paying twice the

prescribed charges.

59. On January 19, 2022, the Collector ruled that such Government

Resolution would not apply. This Order was upheld by the Additional

Commissioner on July 4, 2022. The matter meandered on without there

being absolute and clear title until October 31, 2023, when the then

incumbent Revenue Minister passed the New Revenue Minister Order to

aside the Additional Commissioner’s Order dated July 4, 2022, thereby

bringing to an end the Collector’s Orders dated January 19, 2022 and

September 18, 2020. This was a comprehensive closure for the first time to
Page 52 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

the cloud on the title. The events of this period explain the silence on the

Respondents’ part, with Atul, from following through on the letters dated

July 28, 2020 and September 7, 2020.

60. What is piquant is that the New Revenue Minister Order was passed a

fortnight after the Oberoi MoU was executed on October 16, 2023. Therefore,

when the Oberoi MoU was executed, the cloud had continued, but within a

fortnight of the execution of the Oberoi MoU, immediately after its execution,

this new position was secured by way of the New Revenue Minister Order

dated October 31, 2023. Therefore, prima facie, it can be said that the cloud

posed by the 2002 SCN came to an end on October 31, 2023 while the truly

effective termination by the Respondents, with the refund cheque of Rs. 5.51

crores took place only thereafter, on December 18, 2023.

61. By this time, indeed it could be said that there was absolute and clear

title for the first time, although a review petition was also filed before the

Revenue Minister, which was disposed of finally on September 19, 2024. It is

this Order of September 19, 2024 that was not at all available to the Learned

Arbitral Tribunal and was given to Atul for the first time on December 3,

2024.

Page 53 of 70

July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

Conclusions and Directions:

62. Based on the aforesaid analysis, a conspectus of the inter-play of the

various findings, and their relevance for the final outcome, would be

necessary. Needless to say, every single observation set out above is prima

facie in character. In my opinion, on a number of facets the Impugned Order

contains summary findings, primarily because the Learned Arbitral Tribunal

appears to have been handicapped by not having had access to the Oberoi

MoU. Therefore, I have been persuaded that the Impugned Order deserves to

be set aside by way of a remand, with the provision of the Oberoi MoU,

appropriately redacted. This is the only course that would be appropriate

and meet the ends of justice and fairness. In my opinion, the summary nature

of many critical findings that have come about, would warrant a remand. I

have given my anxious consideration as to whether this Court could itself

take a view, but I am constrained to note that a number of inter-connected

facets have emerged in this case, not all of which can appropriately be dealt

with for the first time by the appeal court without the benefit of analysis and

findings from the forum of the first instance.

63. In my opinion, the Oberoi MoU must necessarily be handed over in an

appropriately redacted form (as directed below) to the Learned Arbitral

Tribunal. As regards commercial interests of Oberoi, I have taken care to

Page 54 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

stipulate below what must be redacted in the Oberoi MoU, and what must

not be redacted:-

A) Nothing in the Recitals A to O shall be redacted;

B) Nothing in the Definitions Section shall be redacted;

C) Nothing in Clause 2 (Transaction) shall be redacted;

D) In Clause 3.1 (Clause 3.1.1 to Clause 3.1.9) the

amounts denominated in rupees in figures and words

shall be redacted, and nothing else shall be redacted;

E) In Clause 3.2 (Clause 3.2.1 to Clause 3.2.7) the

references to the percentages of revenue sharing shall be

redacted, and nothing else shall be redacted;

F) In Clause 4 (Clause 4.1 to Clause 4.6.4) and in

Clause 5 (Clause 5.1 to Clause 5.6) all amounts

denominated in rupees in figures and words, and to

percentages of revenue sharing shall be redacted, and

nothing else shall be redacted;

G) In Clause 6 (Clause 6.1 to Clause 6.8), nothing shall

be redacted except for the percentages of expense

sharing, which corresponds with the percentage of

revenue sharing. It is made clear that the percentages

relating to anything other than the aforesaid shall not be

Page 55 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

redacted; and

H) Nothing in Clause 7 and Clause 8 shall be redacted.

64. An authenticated copy of such redacted Oberoi MoU conforming to the

foregoing shall be filed before the Learned Arbitral Tribunal by the

Respondents and a copy shall be served on Atul within a period of four weeks

from the upload of this judgement on the website of this Court. Atul shall be

entitled to file an application seeking interim reliefs of such nature as advised

on the basis of its review of such redacted Oberoi MoU having become

available to it, and the Learned Arbitral Tribunal shall consider the same and

deal with such application, uninfluenced by whatever has been held in the

Impugned Order.

Summary of Conclusions:

65. A summarisation of my findings, to provide a comprehensive prima

facie thesis underlying my opinion that setting aside coupled with a remand

is necessary, is set out below:-

A) The land leased by the Government of Maharashtra to India

Farmers was over ~114 acres, of which India Farmers leased

100 acres to Nima, which in turn executed the Atul

Transaction Documents for 12.5 acres towards residential

development;

Page 56 of 70

July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

B) It is difficult to conclude in the manner done in the

Impugned Order that there was no earmarking whatsoever

of the 12.5 acres of land that constituted the Subject Land.

The Confirmation Deed in particular, refers to a plan. The

Atul Transaction Documents entail involvement of an

architect. Atul has annexed a map at Exhibit J and claims

that inadvertently the plan was not annexed to the Section 9

Petition, which was converted into the Section 17

Application. The Respondents contest the very existence of

such a plan. This dichotomy in positions would have led to

a triable issue and that would have to be dealt with in the

arbitration proceedings after examining evidence. However,

the Respondents have persuaded the Learned Arbitral

Tribunal to conclusively hold that there was no plan

whatsoever. In my opinion, such a firm conclusion even on

a prima facie basis would not tenable. It would not be

possible to conclude that the Atul Transaction Documents

were an inchoate set of instruments with no clarity

whatsoever on where the Subject Land was meant to be

located within the Larger Land, with serious monies

changing hands. For dealing with the Section 17

Page 57 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

Application, in my opinion, a greater scrutiny of this issue is

warranted – the conclusion appears to be summary;

C) The Notice of termination dated July 28, 2020 called upon

Atul to pay Rs. 12 crores within 14 days, failing which

termination would take place. That very letter called for a

conversation. Atul denied the contents of that letter on

August 24, 2020. On September 7, 2020, yet another letter

was issued by Nima calling upon Atul to perform and

hoping better sense would prevail to avoid unnecessary

litigation. This letter, inherently calling for performance,

would indicate at least prima facie, that the July 28, 2020

letter was not a conclusive termination. The copious

deliberations on the purported absence of a pleading on

waiver of the termination are, in my opinion, unnecessary.

These two letters speak for themselves. The Respondents

did not have an evident intent to terminate the Atul

Transaction Documents at that time, and could have even

sued for specific performance, particularly when the

September 7, 2020 letter actually called upon Atul to

perform. In their eventual termination letter dated

Page 58 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

December 18, 2023, the Respondents claim to have

terminated the Atul Transaction Documents “once again”

and with “immediate effect”. This is untenable. For the

reasons set out above, the clear and comprehensive

termination took place only on December 18, 2023, when a

cheque for refund of Rs. 5.51 crores was enclosed. It is

evident that this firm step of termination was taken only

after securing the New Revenue Minister Order, which too

had followed a fortnight after the Oberoi MoU was

executed;

D) The DB Judgement of October 1, 2019 revived the 2002

SCN, which was not merely a Show Cause Notice but also a

direction prohibiting dealing with the Larger Land without

government approval. This is clearly not consistent with a

position of absolute and clear title. The Atul MoU required

payment of Rs. 12 crore only on obtaining absolute and

clear title. The Confirmation Deed used the ambiguous

“almost….clear” language, which has led to an inference by

the Learned Arbitral Tribunal that the DB Judgement

conferred clear title. Be that as it may, on neither of the two

dates competing for the termination date, namely, July 28,

Page 59 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

2020 and September 7, 2020, did absolute and clear title

exist. Therefore, the obligation to pay Rs. 12 crores on either

of these dates cannot be said to have arisen;

E) The actual termination was effected on December 18, 2023,

with a refund of Rs. 5.51 crores being enclosed. However,

by this time, the Oberoi MoU was already executed on

October 16, 2023. Therefore, prima facie, the Oberoi MoU

was executed before the Atul Transaction Documents were

effectively terminated. This would have necessitated a

closer examination of what kind of interim relief would be

appropriate. However, with the Oberoi MoU not having

been given to the Learned Arbitral Tribunal except in such a

redacted form that rendered it meaningless in substance,

the range of facts that ought to have been analysed has

missed adjudication;

F) The cloud over title appears to have been truly lifted on

September 1, 2023 and eventually on October 31, 2023.

Indeed, the Oberoi MoU was executed on October 16, 2023,

and the clearing of the cloud took place in a fortnight

thereafter. The Learned Arbitral Tribunal not having had

the benefit of seeing any provision worth its name in the

Page 60 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

Oberoi MoU, the Impugned Order has no analysis on the

validity of executing the Oberoi MoU. Such execution was

effected during the subsistence of the Atul Transaction

Documents as also during the subsistence of the status quo

order of this Court passed in WP 3607. The Impugned

Order has simply recorded that the Learned Arbitral

Tribunal has accepted the statement made by Respondents’

counsel, on instructions, that third party rights had already

been created. After the Oberoi MoU, redacted as above, is

made available, the Learned Arbitral Tribunal would be able

to revisit this facet and take a clear view;

G) The Oberoi MoU, with the specific redacting directed earlier

in this judgement must be released to Atul and to the

Learned Arbitral Tribunal within a period of four weeks

from the upload of this judgement on the website of this

Court. Atul shall be entitled to file an application seeking

appropriate reliefs after having examined the Oberoi MoU

as directed above;

H) Whether the NDZ classification of the Larger Land has an

inexorable necessary implication of no residential

development at all being possible is a question that the

Page 61 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

Learned Arbitral Tribunal has to consider. The finding that

the NDZ could never entail residential development at all

appears to be inaccurate. Indeed, the DCPR 2034 enables

residential development although incidental to development

for IT and ITES units. Indeed, the Oberoi MoU entails

elements of non-IT and non-ITES development and indeed

residential development. These facets would need a non-

summary examination and towards this end, the provision

of the Oberoi MoU would enable the Learned Arbitral

Tribunal to examine how residential development is still

possible and has actually been envisaged;

I) The WhatsApp chat transcript does indicate that on October

17, 2019, Atul appears to have expressed apprehension

about having to pay Rs. 12 crore and was willing to prune

the size of his entitlements under the Atul Transaction

Documents. However, at this stage, absolute and clear title

had not been obtained – the DB Judgement revived the

2002 SCN and with it, the fetter on dealing with the Larger

Land. There is nothing wrong with the Learned Arbitral

Tribunal seeking to interpret the WhatsApp chat and it

cannot be totally dismissed as “gibberish”. However, the

Page 62 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

very same WhatsApp chat transcript also contains Atul’s

assertion that the milestone to pay the Rs. 12 crores had not

been reached. Therefore, the parties were engaged in a fluid

conversation, and greater scrutiny of the factual position

obtaining then would be necessary, without which the

adverse inference drawn from the WhatsApp chat transcript

would be summary in character. In view of the other

findings such as the implication of the DB Judgement, this

facet would need to be revisited more comprehensively.

66. I have given my anxious consideration to the standard of review to be

adopted in exercise of the jurisdiction under Section 37 when considering a

challenge to an Order passed under Section 17 of the Act. I am conscious of

the light-touch approach necessary in this jurisdiction. The state of the law

has been summarised succinctly by a Learned Single Judge of this Court

(Manish Pitale J.) in Paragraph 27 to Paragraph 29 of Max Healthcare

Institute Ltd. Vs. Touch Healthcare Private Ltd. & Ors. 4 Even while the scope

for interference would be tempered and measured, also bearing in mind the

legislative objective of limited interference by the Court under the Act, if the

Impugned Order misses considering material facets of the matter, or

4
Commercial Arbitration Petition (L) No. 20533 of 2023.
Page 63 of 70

July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

considers what must not be considered, the scope of review would lend itself

to examining the perversity that may emerge from the Order impugned.

67. For the reasons set out above, it is apparent that on multiple counts,

the views taken in the Impugned Order are implausible. The contents of the

multiple termination letters from the candidates speak for themselves, and

yet a firm view has been arrived at that the Atul Transaction Documents were

terminated on July 28, 2020. The Oberoi MoU, presented in the manner it

was, clearly indicates that there was significantly more than what met the

eye. The full document now having been seen by me, I would be remiss if I

did not take note of its contents and refrained from taking the consequential

action from what is disclosed in it. The status quo directed by this very Court

having been in operation when the Oberoi MoU was signed, also cannot be

ignored. The sweeping conclusion about residential development being

impossible on NDZ land adds to the mix above. Therefore, for the various

reasons articulated in this judgement, I am of the view that there is no option

but to interfere with the Impugned Order.

Oberoi’s Intervention Application:

68. I am also conscious that the Learned Arbitral Tribunal has held that it

has no jurisdiction to hear contentions of Oberoi, which would be necessary
Page 64 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

for considering the Oberoi MoU. Oberoi has sought to be impleaded in these

appellate proceedings, which have led to a remand. Therefore, Oberoi is

willing to subject itself to the proceedings so that it can be heard and the

manner of impact on its interests can also be considered. Curiously, Atul has

opposed allowing impleadment of Oberoi stating that it is not a party to the

arbitration agreement – curious because Atul seeks reliefs that would have an

impact on Oberoi, and it would only be appropriate that Oberoi is heard.

69. Meanwhile, the law on the power of the Learned Arbitral Tribunal to

join veritable parties has made a significant forward movement in a recent

judgement of the Supreme Court in ASF Buildtech5. It has been made clear

even that the Learned Arbitral Tribunal can implead a non-signatory party,

without the role of a reference court, on its own motion, if the requisite

factors are found.

70. In the instant case, the Oberoi MoU has interceded into the subject

matter of the Atul Transaction Documents before they were terminated. The

execution of the Oberoi MoU has been followed by the resolution of the

dispute with the Government of Maharashtra as envisaged therein, within a

fortnight. This is precisely the approach that had been envisaged in the Atul

Transaction Documents as well, but with a six-month expectation from Nima,

5
ASF Buildtech Pvt. Ltd. Vs. Shapoorji Pallonji and Co. Pvt. Ltd. – 2025 INSC 616 – See
Section C(ii)
Page 65 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

the deadline being extendable by Atul.

71. Oberoi has volunteered to be impleaded in this Appeal, and disposal of

this Appeal has led to a remand. Therefore, this is not a case where an

arbitral tribunal is seeking to bind a third party to its proceedings – instead,

the third party is volunteering to join the proceedings.

72. The Oberoi MoU is being directed to be introduced into the evidence

before the Learned Arbitral Tribunal, with appropriate redacting as directed

above. The Learned Arbitral Tribunal would have the benefit of getting a

complete and holistic picture with Oberoi’s participation. In any case,

Oberoi’s entry into the fray has led to Oberoi’s interests being aligned with

the interests of the Respondents in the very same subject matter of the

arbitration agreement. The Oberoi MoU makes many references to the Atul

Transaction Documents and to Atul – not just recitals of history. Therefore,

making Oberoi a party, and directing the Oberoi MoU to be considered

without the inhibition of Oberoi being a non-signatory, would meet the ends

of justice and would also not hurt Atul. Atul, of course, is dominus litis. If

the impleadment had been permitted by this Court, Oberoi would have been

heard in these appellate proceedings. Oberoi not having participated in the

Section 17 proceedings, and coming in the appellate stage would have skewed

the position. However, going by the same framework in which the Learned

Page 66 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

Arbitral Tribunal considered the matter, this judgement has been rendered.

Since a remand is being directed, it is only appropriate that the Learned

Arbitral Tribunal considers Oberoi’s Impleadment Application too and takes

an appropriate view.

73. Section C(ii) in ASF Buildtech is a comprehensive summary of the law

on the subject, but in this regard, just the following extracts are noteworthy :-

123. What can be discerned from the above is that the

recourse to doctrine of implied powers would be permissible,

if without it, it is impossible to effectuate a final power, and

such exercise of implied power would effectuate and advance

the object of the legislation.

124. Cox and Kings (I) (supra) has elaborately acknowledged

the unique complexities posed by contemporary business

transactions to the traditional framework of arbitration.

Historically, arbitration gained prominence in the context of

straightforward and linear bilateral transactions under the

mercantile system of law. While over the past century, the

nature of modern commercial transactions has undergone a

profound transformation with the involvement of

multifaceted obligations between multiple parties and

Page 67 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

complex contractual structures more sophisticated than the

linear parent- subsidiary type of organization, that has

rendered the traditional dyadic paradigms of business

obsolete, particularly in areas such as construction contracts,

financing transactions, reinsurance contracts, the framework

of arbitration has, to a significant extent remained

unchanged, leading to a mismatch between procedural form

and commercial substance.

125. For arbitration to remain a viable and effectively

alternative mechanism for dispute resolution, it is

imperative to ensure that commercial reality does not

outgrow this mechanism. The mechanisms of arbitration

must be sufficiently elastic to accommodate the complexities

of multi-party and multi-contract arrangements without

compromising foundational principles such as consent and

party autonomy. The approach of courts and arbitral

tribunal in particular must be responsive to the emerging

commercial practices and expectations of the parties who

submit themselves to it.

[Emphasis Supplied]

Page 68 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

74. In view of the foregoing, in my opinion, this is a fit case for the

Impugned Order to be set aside with a remand for a reconsideration on

merits on the basis of the findings rendered above. On remand, with the

benefit of the Oberoi MoU, to be redacted in the manner directed above, the

Learned Arbitral Tribunal would be in a better position to consider whether

and what appropriate interim reliefs are warranted.

75. With the aforesaid conclusions and directions, this Appeal is finally

disposed of. I am conscious that the parties will need some time to assess the

findings in this judgement and consider their respective positions. Therefore,

I have provided a period of four weeks from the upload of this judgement on

this Court’s website for the Oberoi MoU, redacted as directed above, to be

provided by the Respondents to Atul and to the Learned Arbitral Tribunal.

76. The protective arrangement obtaining as of today in favour of Atul

shall continue for a further period of two weeks from the expiry of the

aforesaid four-week period, within which the appropriately redacted Oberoi

MoU is required to be sent to Atul. This would enable Atul to review the same

and make an appropriate application to the Learned Arbitral Tribunal within

such period.

Page 69 of 70

July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::
CARBP-35274-2024=IA=F.docx

77. The issue of costs for this round of litigation is deferred for

consideration by the Learned Arbitral Tribunal when it hears the arbitration

proceedings finally.

78. All actions required to be taken pursuant to this order, shall be taken

upon receipt of a downloaded copy as available on this Court’s website.

[ SOMASEKHAR SUNDARESAN, J.]

Page 70 of 70
July 23, 2025
Shraddha

::: Uploaded on – 23/07/2025 ::: Downloaded on – 23/07/2025 22:25:57 :::

[ad_2]

Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here