Anamika Enterprises vs Union Of India on 4 August, 2025

0
2

Calcutta High Court

Anamika Enterprises vs Union Of India on 4 August, 2025

Author: Shampa Sarkar

Bench: Shampa Sarkar

OC 54

                             ORDER SHEET
                           AP-COM/405/2025
                    IN THE HIGH COURT AT CALCUTTA
                         COMMERCIAL DIVISION
                             ORIGINAL SIDE


                         ANAMIKA ENTERPRISES
                                  VS
                            UNION OF INDIA



  BEFORE:
  The Hon'ble JUSTICE SHAMPA SARKAR
  Date: 4th August, 2025.




                                                                     Appearance:
                                                    Ms. Sristi Barman Roy, Adv.
                                             Mr. Kamal Kr. Chattopadhyay, Adv.
                                                    Mr. Aurin Chakraborty, Adv.
                                                       Ms. Rimi Chatterjee, Adv.
                                                               ...for the petitioner

                                                 Mr. Shiv Chandra Prasad, Adv.
                                                       Ms. Sumita Sarkar, Adv.
                                                                   ...for CPWD




    The Court:

    1. This is an application for appointment of an arbitrator upon recording

        termination of the mandate of the sole arbitrator, who was appointed

        from the panel of Arbitrators maintained by the CPWD. The petitioner

        was all along willing to cooperate and participate in the arbitral

        proceedings which was being conducted by an Arbitrator chosen by the
                                  2

  respondent. The petitioner invoked arbitration sometime in 2024 with

regard to a dispute which arose in 2022. Without having any

knowledge about the modification of Clause 25 of the GCC of 2020, the

petitioner prayed for constitution of a Dispute Redressal Commission for

adjudication of the claim, as a precursor to the invocation of the

arbitration clause. The respondent constituted the DRC. As the claims

remained unresolved, the petitioner invoked arbitration in terms of the

erstwhile clause 25 of the 2020, GCC.

2. The challenge is that, the appointment was violative of the procedure

prescribed in the modified GCC. The appointment was unilateral and

the petitioner was not given a chance to choose an arbitrator from the

panel maintained by the CPWD. The petitioner’s choice of a retired

officer from the panel maintained by the CPWD was ignored and the

Chief Engineer referred the dispute to a person of his own choice,

without any consent from the petitioner.

3. That participation in an arbitral proceeding would not debar the

petitioner from challenging the jurisdiction of the arbitrator on the

ground that the arbitrator was de jure unable to perform on account of

severe infractions of the law and the GCC.

4. During the pendency of the arbitration, the petitioner wanted to amend

the statement of claim, by incorporating further claims towards

escalation charges and compensation. Such prayer was disallowed by

the learned Arbitrator on the ground that the claim could not be

entertained and the statement of claim could not be amended. Only
3

those disputes which were referred by the Chief Engineer of the

concerned department could be taken up by the arbitrator for

adjudication. After the order was passed, the petitioner came to know

that the Clause 25 of the GCC of 2020 was amended and the said

relevant clause discussed above had been done away with. The

procedure for dispute redressal through a DRC was deleted. Reference

of the dispute to conciliation was permitted only on limited grounds and

the same was not mandatory. The clause that, the arbitrator could

adjudicate only those disputes referred to him by the appointing

authority had been deleted, prior to the dispute having arisen between

the parties. Neither the arbitrator, nor the respondents had applied the

correct provisions of the GCC and the petitioner was misled. The

amended provisions stated that if the claim was below Rs.100 crores, a

sole arbitrator would be appointed. A party could also opt for

appointment of an Arbitrator from the Ministry of Housing and Urban

Affairs. In case, the party seeking arbitration applied for appointment of

an arbitrator from the Ministry of Housing and Urban Affairs, then an

express agreement towards waiver of Section 12(5) of the Arbitration

and Conciliation Act, 1996 was to be entered into. If the party did not

opt for an arbitrator of the Ministry of Housing and Urban Affairs or did

not submit the waiver agreement, the appointing authority was to

propose five arbitrators from the list of CPWD’s empanelled arbitrators

to the party seeking arbitration. The party seeking arbitration was to

give his choice for one of them within 15 days of receiving the notice and
4

the arbitrator appointing authority was to appoint the chosen person as

the sole arbitrator within 15 days of the receipt of choice. The above

provisions were not followed. The appointment was not only contrary to

the modified conditions of clause 25 of the GCC, but also contrary to

law.

5. The relevant provisions are quoted below :-

“25.2 Arbitration: If the aforesaid conciliation proceedings fail or the
Conciliator fails to give proposal for settlement within the aforesaid
period, either party may promptly give notice in the proforma prescribed
in Appendix XVIII, under intimation to the other party, to the Chief
Engineer or the Superintending Engineer concerned with the work (as
applicable), hereinafter referred to as the Arbitrator Appointing
Authority as indicated in Schedule F. for appointment of Arbitrator.
However, a party may seek appointment of Arbitrator without taking
recourse to the process of conciliation mentioned in sub-clause 25.1
above.

In the event of either party giving a notice to the Arbitrator Appointing
Authority for appointment of Arbitrator, the said Authority shall appoint
Arbitrator as per the procedure given below and refer such disputes to
arbitration.

(a) Number of Arbitrators: If the contract amount is lass than Rs.100
crore, the disputes may be referred for adjudication by a sole Arbitrator.

If the contract amount is Rs. 100 crore or more, the disputes may be
referred to an Arbitral Tribunal of three Arbitrators.

(b) Qualification of Arbitrators: It is a term of this contract that each
member of the Arbitral Tribunal shall be Graduate Engineer with
experience in execution of public works engineering contracts, and he
should have worked earlier at a level not lower than the Chief Engineer
(equivalent to level of Joint Secretary to the Government of India).
The aforesaid educational qualification and work experience shall be
mandatory for appointment as Arbitrator.

The age of Arbitrator at the time of appointment shall not exceed 70
years. An Arbitrator may be appointed notwithstanding the total
number of active arbitration cases with him.

(c) Parties to select Arbitrator: Based on the criteria specified above, a
list of empaneled Arbitrators has been prepared in CPWD, and the
parties shall have option to select an Arbitrator from the list sent to
them.

25.3 Appointment of Sole Arbitrator: The parties may opt for
appointment of the Arbitrator of the Ministry of Housing and Urban
Affairs. In such cases, the party seeking arbitration has to submit án
express agreement in writing as per Appendix XIX towards waiver of
5

Section 12(5) of the Arbitration and Conciliation Act, 1996 along with
the notice for appointment of Arbitrator in the proforma prescribed in
Appendix XVIII. under intimation to the other party. The Arbitrator
Appointing Authority shall, within 30 days of receipt of the said notice,
appoint Arbitrator of the Ministry of Housing and Urban Affairs as
Arbitrator in the matter, provided the other party also submits waiver of
Section 12(5), ibid in Appendix XIX within 7 days of the receipt of the
said notice.

Where any one of the parties does not opt for the Arbitrator of the
Ministry of Housing and Urban Affairs, or does not submit the waiver
agreement, the Arbitrator Appointing Authority shall propose five
Arbitrators from the list of CPWD Empaneled Arbitrators 10 the party
seeking arbitration under intimation to the other party within 15 days of
receiving the notice. The party seeking arbitration shall give his choice
for one of them within 15 days of receiving the list, and the Arbitrator
Appointing Authority shall appoint the chosen personas the Sole
Arbitrator within 15 days of the receipt of choice.
It is a term of this arbitration agreement that if the parties fail to select,
within the period prescribed above, an Arbitrator of their choice from
the list of CPWD Empaneled Arbitrators forwarded to them, the
Arbitrator Appointing Authority shall himself select and appoint
Arbitrator from the said list.”

6. In view of the above non-compliances and also because the appointing

authority unilaterally appointed the arbitrator, the mandate must be

terminated. It is submitted by the petitioner that upon coming to know

of the amendment, the petitioner realized that the procedure followed by

the authority was vitiated and the learned arbitrator could not continue

as he was de jure unable to perform his duty in terms of Section 12(5) of

the Act and modified provision of the GCC. Even if the GCC was not

known to the petitioner, the authority being aware of such fact, should

not have misguided the petitioner. The amended provision is also

inoperative to the extent that the petitioner cannot be forced to chose

from the list of five arbitrators to be supplied by the respondents, unless

the petitioner chooses voluntarily.

6

7. The court records termination of the mandate.

8. This Court appoints a substitute arbitrator from the list provided by the

petitioner. The petitioner submits before this Court that a retired officer

from the CPWD’s panel should be appointed as the dispute arises out of

a construction contract, which requires intricate measurements to be

carried out by experts.

9. Under such circumstances, I do not find that the respondent should

have any objection at all if one of their own retired engineers is

appointed. Sri Sansar Pattanayak (Mobile: 7504213002; Email ID:

[email protected]) is appointed as a substitute arbitrator. The

proceedings shall continue before the substitute arbitrator from the

stage it was last held. The award shall be published within one year

from the date of communication of this order. The petitioner may pray

for amendment of the statement of claim before the newly appointed

arbitrator. Such prayer will be considered in accordance with law. Both

the parties shall pray for return of the arbitral records from the

erstwhile learned arbitrator.

10. All points are left open, to be agitated before the learned arbitrator.

The fee of the learned arbitrator shall be as per schedule of rates

prescribed by CPWD.

11. Liberty is granted to file the affidavit in opposition in the department.

12. The application is disposed of.

(SHAMPA SARKAR, J.)
B.Pal/S.Kumar



Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here