Rukhsana Hamid vs State Of West Bengal & Ors on 13 August, 2025

0
6

Calcutta High Court (Appellete Side)

Rukhsana Hamid vs State Of West Bengal & Ors on 13 August, 2025

           IN THE HIGH COURT OF JUDICATURE AT CALCUTTA
                 CONSTITUTIONAL WRIT JURISDICTION
                          APPELLATE SIDE

                         RESERVED ON: 04.08.2025
                         DELIVERED ON: 13.08.2025

                             PRESENT:
               THE HON'BLE MR. JUSTICE GAURANG KANTH

                             WPA 18238 OF 2024

                            RUKHSANA HAMID
                                 VERSUS
                        STATE OF WEST BENGAL & ORS.

Appearance:-

Mr. Arup Krishna Das, Adv.
Mr. Rajarshi Ghosh, Adv.
                                          ...........................For the Petitioner

Mr. Dipanjan Datta, Adv.
Mr. Debangshu Mondal, Adv.
                                             ........................... For the State

Mr. Shounak Bhattacharya, Adv.
                                   ............................... For the Corporation
Mr. S.K. Mondal, Adv.
                                   ................... For the Private Respondent

                                   WITH

                             WPA 20449 OF 2024

                          RUKHSANA ZAKARIA KHAN
                                  VERSUS
                        THE STATE OF WEST BENGAL & ORS.

Mr. Srijib Chakraborty, Adv.
Mr. Subhajit Mukherjee, Adv.
                                      ..............................For the Petitioner

Mr. Malay Singh, Adv.
Ms. Neelam Singh, Adv.
                                      .................................... For the State
Mr. Shounak Bhattacharya, Adv.

                                       ......................... For the Corporation
Mr. S.K. Mondal, Adv.

                                       ............ For the Private Respondent
                                        2

                                   JUDGMENT

Gaurang Kanth, J. :-

1. The demolition order dated 04.03.2024 having Memo No.

3049/(12)/PW/Eng/24 passed by the Superintending Engineer, Asanasol

Municipal Corporation in connection with demolition of a certain portion of

the Nuruddin House having JL No. 20, Mouza Asanasol Municipality is in

consideration in both these matters. In WPA 20449/2024, the Petitioner is

challenging the said demolition order where as in 18238/2024, the

Petitioner is seeking the implementation of the said demolition order.

Hence this Court decided to dispose of both these matters with a common

order.

Facts as per WPS 18238/2024

2. The Petitioner claims to be one of the co-sharers of the premises in

question. Her case is that one Nuruddin Mistry was the original owner of

certain plots of land situated under Mouza- Asansol Municipality, JL No.

20, recorded in Khatian Nos. 8860, 8861, 8862, 13588, 13589, 10793,

10794, 10795, 10796, 10797, 10798, 8866, 8867, 8869, 8870, 8871,

8873-8877, 22250, 22242, 22256, 22255, 22251, 22241, 22243, 22252,

and 22254. The Petitioner is one of the successors-in-interest of the late

Shri Nuruddin Mistry. Nuruddin House is constructed over the said

property. After the death of Nuruddin Mistry, a partition suit, being Title

Suit No. 92 of 2023, was instituted and is presently pending before the

Court of the Civil Judge, Senior Division, Asansol, among the legal heirs of

the said late Nuruddin Mistry.

3

3. The Petitioner in WPA No. 18238 of 2024 (Rukhsana Hamid), contends that

private respondents Nos. 6 and 7, namely Abdulla Zakaria and Sulaiman

Zakaria, commenced unauthorised construction over a portion of the

aforesaid property without obtaining any valid sanctioned building plan.

Accordingly, she lodged a complaint dated 29.12.2023 before the Mayor,

Asansol Municipal Corporation. Pursuant to the said complaint, officials of

the Respondent Municipality carried out a spot inspection and issued a

“work stop” notice dated 09.01.2024 against the said private respondents.

4. Despite the issuance of the said notice, Abdulla Zakaria and Sulaiman

Zakaria continued with the unauthorised construction. Consequently, the

Petitioner lodged another complaint dated 12.02.2024. The Assistant

Engineer, Asansol Municipal Corporation, by letter dated 17.02.2024,

informed the Deputy Commissioner of Police (Central), Asansol-Durgapur

Police Commissionerate, to take appropriate action against the said private

respondents.

5. A hearing was thereafter conducted by the Respondent Municipality on

20.02.2024, which was attended by both the Petitioner and the private

respondents. As no sanctioned building plan was produced by the private

respondents, the Respondent Municipality passed a demolition order dated

04.03.2024, directing the said private respondents to demolish the

unauthorised construction within seven days, failing of which the

demolition would be carried out by the Municipality itself.

6. Notwithstanding the passing of the demolition order dated 04.03.2024, no

demolition was carried out, either by the private respondents or by the

Respondent Municipality. The Petitioner thereafter submitted a
4

representation dated 29.05.2025, requesting implementation of the said

demolition order.

7. Aggrieved by the continued inaction of the Respondent Municipality in

enforcing the demolition order dated 04.03.2024, the Petitioner has

preferred the present writ petition.

Facts as per WPA No. 20449/2024

8. The Petitioner is the recorded owner of the premises wherein the property

known as Nuruddin House is situated, her name being duly reflected in the

Record of Rights. On 24.07.2024, she was informed by officials of the

Respondent Municipality that a demolition order had been passed in

respect of a portion of Nuruddin House. Upon request, she was furnished

with a copy of the demolition order dated 04.03.2024, from which she

learnt that her sons, Abdulla Zakaria and Sulaiman Zakaria, had allegedly

carried out illegal and unauthorised construction in the said premises, and

that the order pertained to such alleged unauthorised construction.

9. The Petitioner states that the building in question originally belonged to the

great grandfather of her husband. She was married in the year 1975 and

has resided in the premises since then. According to her, Nuruddin House

is approximately 100 years old, and certain portions had, over time, fallen

into a dilapidated and ruinous condition, making them uninhabitable. She

asserts that only limited renovation work was undertaken to render those

portions habitable.

10. After the death of her husband in 2021, the Petitioner’s relationship with

her sons deteriorated, and she began to reside separately from them. She

avers that due to natural calamities, the portion of the building where she

currently lives has also become dilapidated, and she has carried out only
5

such renovation work as is permissible in law. The Petitioner contends

that, despite being the recorded owner of the premises, she was neither

afforded an opportunity of hearing nor served with any notice prior to the

passing of the demolition order. She further points out that the order does

not specify which portion of the building is alleged to be unauthorised.

11. Upon receiving the order, she addressed a letter dated 25.07.2024 to the

Respondent-Municipality seeking clarification and redress, but no action

was taken. Aggrieved by such inaction, the Petitioner has filed the present

writ petition.

Submission on behalf of the Petitioner in 20449/2024 (Rukhsana Zakaria
Khan)

12. Learned Counsel for the Petitioner submits that the Petitioner is the

recorded owner of the premises known as Nuruddin House, her name being

duly reflected in the Record of Rights. Despite this, the impugned

demolition order dated 04.03.2024 has been passed without serving any

notice upon her, without summoning her for spot inspection, without

issuing any “stop work” notice, and without affording her any opportunity

of hearing. It is contended that such omission strikes at the very root of

the proceedings and amounts to a clear violation of the principles of

natural justice, rendering the impugned order liable to be set aside on this

ground alone.

13. It is further submitted that the impugned demolition order has been issued

by the Superintending Engineer, Asansol Municipal Corporation. Section

266 of the West Bengal Municipal Corporation Act, 2006, expressly vests

the power to pass a demolition order in the Commissioner, and there is no

provision under the Act which permits delegation of such power to a
6

subordinate officer. The Petitioner therefore contends that the impugned

order has been passed wholly without jurisdiction and is void ab initio.

14. The Petitioner further argues that the impugned order suffers from

vagueness and ambiguity inasmuch as it does not specify the exact portion

of the premises alleged to be unauthorised. Nuruddin House is a large,

approximately 100 year-old building, and without a sketch map, site plan,

or any form of identification annexed to the order, the alleged illegal

construction cannot be precisely ascertained. In the absence of such

clarity, the order is incapable of lawful execution and stands vitiated in

law.

15. Learned Counsel also points out that the Petitioner has been residing

separately from her sons, Abdulla Zakaria and Sulaiman Zakaria, due to

their hostile behaviour and has no connection with any unauthorised

construction allegedly carried out by them. The portion of the premises

under her occupation had fallen into a dilapidated condition due to

natural calamities, and she undertook only lawful renovation work to

make it habitable. The demolition order, insofar as it affects her portion,

has therefore been passed on an erroneous assumption of fact and without

affording her an opportunity to contest the allegations.

16. In support of his submissions, learned counsel for the Petitioner places

reliance upon the following decisions:

             (i)      Gurunath Manohar Pavaskar         v.   Nagesh     Siddappa
                    Navalgund, AIR 2008 SC 901;
             (ii)      Chief General Manager (IPC), Madhya Pradesh Power

Trading Company Ltd. v. Narmada Equipments Pvt. Ltd.,
(2021) 14 SCC 548;

(iii) J.K. Cotton Spinning and Weaving Company Ltd. v. State
of U.P.
, AIR 1961 SC 1170;

7

(iv) Dharani Sugars and Chemicals Ltd. v. Union of India,
(2019) 5 SCC 480;

(v) Laddu Gopal Bajoria v. Kolkata Municipal Corporation,
2006 (3) CAL LT 50 (HC);

(vi) Dinanath Singh v. State of West Bengal, WPA 12318/2025;

(vii) Maniruddi Bepari v. Chairman of the Municipal
Commissioners
, reported as ILR (1936) 63 Cal 295; and

(viii) State of Odisha v. Satish Kumar Ishwardas Gajbhiye,
(2021) 17 SCC 90.

17. In light of these submissions, it is argued that the impugned demolition

order dated 04.03.2024 is illegal, arbitrary, without jurisdiction, violative

of the principles of natural justice, and vitiated by vagueness. The same is

therefore liable to be quashed and set aside by this Court.

Submission on behalf of the Petitioner in WPA 18238/2024 (Rukhsana
Hamid)

18. Learned Counsel for the Petitioner in WPA 18238/2024 submits that the

private respondents (Abdulla Zakaria and Sulaiman Zakaria) carried out

unauthorised and illegal construction in contravention of the West Bengal

Municipal Corporation Act, 2006. For the said construction work, no

building plan has been sanctioned by the Asanasol Municipal Corporation.

The Respondent Corporation has already passed the demolition order

dated 04.03.2024, however, till date is no action has been taken in

pursuance of the same.

19. Learned Counsel further submits that as per Section 266 of the West

Bengal Municipal Corporation of the Act, 2006, the commissioner is

empowered to delegate his power to his subordinate officers. Hence validly

passed the demolition order dated 04.03.2024.

8

20. Further as per the said Act, the notice is to be given to the ‘person at whose

instance’ the unauthorised construction is being carried out. Abdulla

Zakaria and Sulaiman Zakaria are the persons who have carried out the

said demolition work and hence the Respondent Corporation passed the

demolition order after affording an opportunity of hearing to the said

persons.

21. In view thereof, Learned Counsel for the Petitioner prays for the

implementation of the impugned demolition order dated 04.03.2024.

Submission on behalf of the Respondent Corporation

22. It is submitted by the Learned Counsel for the Respondent Corporation

that the Petitioner in WPA 18238/2024, namely, Rukhsana Hamid, lodged

a written complaint dated 29.12.2023 alleging that Abdulla Zakaria and

Sulaiman Zakaria were carrying out unauthorised construction at the

premises in question. Pursuant to the said complaint, the Respondent

Corporation issued a stop-work notice dated 09.01.2024 directing the said

persons to forthwith cease all construction activities. However, despite

service of the said notice, the unauthorised construction continued

unabated. Consequently, by letter dated 17.02.2024, the Respondent

Corporation requested the Deputy Commissioner of Police (Central),

Asansol Durgapur Police Commissionerate, to enforce the said stop-work

notice. Thereafter, a hearing was conducted by the Superintendent

Engineer, Asansol Municipal Corporation, wherein both the complainant

and the persons responsible for the unauthorised construction were

present. Upon their failure to produce any sanctioned building plan, the

impugned demolition order dated 04.03.2024 was passed, directing the

removal of the unauthorised construction.

9

23. The Respondent Corporation has placed on record the delegation of powers

issued by the Commissioner, Asansol Municipal Corporation, vide Memo

No. 707-G dated 09.02.2024, in exercise of powers conferred under Section

47(3)(b) of the West Bengal Municipal Corporation Act, 2006.

24. The Respondent Corporation further submits that no notice was required to

be issued to Rukhsana Zakaria Khan, Petitioner in WPA 20449/2024,

inasmuch as she is neither the owner of the premises in question nor the

person responsible for the unauthorised construction. The mere recording

of her name in the L.R. record-of-rights neither creates nor extinguishes

title, as is well-settled in law. Accordingly, her claim to notice is without

legal foundation.

25. It is further the specific case of the Respondent Corporation that WPA

20449/2024 is a proxy litigation instituted at the behest of Abdulla

Zakaria and Sulaiman Zakaria, in collusion with their mother, Rukhsana

Zakaria Khan, with the sole intent of frustrating and obstructing the lawful

demolition proceedings initiated by the Corporation.

26. In view of the aforesaid facts, submissions, and the record placed before

this Hon’ble Court, the Respondent Corporation respectfully prays that

WPA 20449/2024 be dismissed with costs.

Legal Analysis

27. This Court has heard the arguments advanced by the learned counsel for

both parties and has carefully perused the documents placed on record.

28. The principal contention advanced on behalf of Rukhsana Zakaria Khan,

(Petitioner in WPA 20449/2024), is that the Superintendent Engineer,

Asansol Municipal Corporation, was not competent to pass the impugned

demolition order dated 04.03.2024. It is submitted that, in terms of
10

Section 266 of the West Bengal Municipal Corporation Act, 2006, the

power to pass a demolition order is vested exclusively upon the

Commissioner. The Petitioner further submits that, under the provisos to

Section 266, the Commissioner may delegate only certain powers, namely,

under the first proviso, the power to issue notices and conduct hearings,

and under the second proviso, the power to issue stop-work orders, to

subordinate officers. However, the authority to pass a demolition order

itself cannot be delegated, as such delegation is not contemplated by

Section 266.

29. The learned counsel for the Respondent Corporation, however, strongly

disputes this interpretation and relies upon Section 47 of the West Bengal

Municipal Corporation Act, 2006, to contend that the Commissioner is

empowered to delegate even the power to pass demolition orders to

subordinate officers.

30. In order to properly evaluate the rival submissions, it is necessary to

examine the scope and interplay of Section 266 and Section 47 of the West

Bengal Municipal Corporation Act, 2006.

Section 266(1) of the West Bengal Municipal Corporation Act, 2006

“266. Order of demolition of building or stoppage of erection of
buildings in certain cases and appeal.

(1) Where the erection of any building or the execution of any work has
been commenced, or is being carried on, or has been completed
without or contrary to the sanction referred to in section 263 or in
contravention of any of the provisions of this Act or the rules and the
regulations made thereunder, the Commissioner may, in addition to
any other action that may be taken under this Act, make an order
directing that such erection or work shall be demolished’ by the
person at whose instance the erection or the work has been
commenced or is being carried on or has been completed within such
period, not being less than five days and more than fifteen days from
the date on which a copy of the order of demolition with a brief
statement of the reasons therefor has been delivered to such person,
as may be specified in the order:

11

Provided that no order of demolition shall be made unless such
person has been given, by means of a notice served in such manner as
the Commissioner may think fit, a reasonable opportunity of showing
cause why such order shall not be made:

Provided further that where the erection or the execution has not
been completed, the Commissioner may by the same order or by a
separate order, whether made at the time of the issue of the notice
under the first proviso or at any other time, direct such person to stop
the erection or the execution until the expiry of the period within which
an appeal against the order of demolition if made may be preferred
under sub-section (3).

Explanation. – In this chapter, “the person at whose instance”
shall mean the owner, occupier or any other person who causes the
creation of any building or execution of any work to be done, including
alterations or additions if any, or does it by himself.

Provided also that the Commissioner, by order, delegate his
powers and functions under the first and the second proviso of this
sub-section to the Special Officers, appointed by the Commissioner
with the approval of the State Government on such terms and
conditions as may be determined by the Corporation, and the
expenses for payment of such officers shall be borne from the
Municipal Fund.”

Section 47 of the West Bengal Municipal Corporation Act, 2006

“Delegation of powers and functions.

(1) The Board of Councillors may, by resolution, delegate, subject to such
conditions as may be specified in the resolution, any of its powers or
functions to the Mayor-in-Council.

(2) The Mayor-in-Council may, by order, delegate, subject to such
conditions as may be specified in the order, any of its powers or
functions to the Mayor or to the Commissioner.

(3) Subject to such standing orders as may be made by the Mayor-in-

Council in this behalf,-

(a) the Mayor may, by order, delegate, subject to such conditions
as may be specified in the order, any of his powers or
functions to the Deputy Mayor or to the Commissioner.

(b) the Commissioner may, by order, delegate, subject to such
conditions as may be specified in the order, any of his powers
or functions to any other officer or any employee of the
Corporation; and

(c) any officer of the Corporation either than the Commissioner
may. by order, delegate, subject to such conditions as may be
specified in the order, any of his powers or functions to any
officer subordinate to him.

(4) Notwithstanding anything contained in the foregoing provisions of this
section, the Mayor-in-Council, the Mayor, the Commissioner, or the
officer referred to in clause (c) of sub-section (3) shall not delegate-
12

(a) any of its or his powers or functions delegated to it or him
under this section, or

(b) such of its or his powers or functions as may be prescribed.”

31. A plain reading of Section 266 of the West Bengal Municipal Corporation

Act, 2006 indicates that the power to pass demolition orders in cases of

unauthorised construction is vested in the Commissioner. While the

provisos to Section 266 make specific reference to the delegation of certain

ancillary functions, such as issuing notices, conducting hearings, and

stopping work, the section does not contain any express prohibition

against the delegation of the power to issue demolition orders itself. The

absence of such a prohibition must be read in harmony with the general

delegation powers conferred under Section 47 of the said Act.

32. Section 47(3)(b) expressly empowers the Commissioner to delegate any of

his powers or functions under the Act to subordinate officers, subject to

such conditions as may be specified. This provision is couched in broad

terms and applies to all powers of the Commissioner, save and except

those for which the statute contains an express prohibition. Since Section

266 does not expressly restrict the delegation of demolition powers, the

enabling provision of Section 47(3)(b) must be given full effect.

33. A harmonious construction of Sections 266 and 47 reveals that while

Section 266 identifies the Commissioner as the primary authority

competent to issue demolition orders, Section 47 prescribes the procedural

mechanism by which such powers may be delegated to suitably empower

subordinate officers. The legislative intent underlying these provisions is to

ensure administrative efficiency and expeditious action against

unauthorised constructions, an objective that would be undermined if
13

every demolition order were required to be personally passed by the

Commissioner.

34. Furthermore, the first proviso to Section 266 vests the Commissioner with

the authority to conduct hearings in relation to demolition matters. If the

Petitioner’s argument were to be accepted, it would result in an

incongruous situation where the hearing is conducted by a subordinate

officer, yet the final demolition order is passed exclusively by the

Commissioner. Such a bifurcation of process is anomalous and contrary to

established principles of law.

35. It is a well settled principle of statutory interpretation that where two

provisions are capable of being read harmoniously, the interpretation that

gives full effect to both must be adopted. In the present context, Section

266 determines the source of the power, while Section 47 lays down the

mode of its lawful delegation. Accordingly, a demolition order passed by

the Superintendent Engineer pursuant to a valid written delegation from

the Commissioner under Section 47(3)(b), such as Memo No. 707-G dated

09.02.2024, is intra vires, lawful, and enforceable.

36. Learned Counsel for the Petitioner has placed reliance upon various

judgments referred to in paragraph 16 hereinabove. This Court, while

holding the legal principles enunciated therein in the highest regard and

being in respectful agreement with the propositions so laid down, it is of

the considered view that the present controversy hinges upon a core issue

which is materially distinct from the questions that fell for determination

in those cases. Consequently, the ratio of the cited decisions, though

instructive, cannot be applied in its entirety to the facts at hand.
14

37. The contention of the Petitioner that the power to issue demolition orders is

non-delegable is misconceived and contrary to settled legal principles. The

Supreme Court has consistently recognised that, unless expressly

prohibited, statutory powers including quasi-judicial powers may be

delegated to subordinate authorities where the enabling statute so

provides. In Gurunath Manohar Pavaskar (supra), the Hon’ble Court held

that delegation is permissible where the statute contains a general

provision authorising such delegation, provided that statutory safeguards

are preserved. Similarly, in State of Orissa v. Commissioner of Land

Records & Settlement, (1998) 7 SCC 162, it was held that when the

legislature confers a general power of delegation, it must be construed

broadly to encompass all powers unless expressly excluded.

38. In the municipal governance context, in Laddu Gopal Bajoria (Supra) this

Court, upheld the competence of subordinate municipal officers to act

pursuant to powers delegated by the Commissioner, provided the

delegation complies with the statute. The delegation effected through

Memo No. 707-G dated 09.02.2024 is a direct exercise of the

Commissioner’s powers under Section 47(3)(b) of the West Bengal

Municipal Corporation Act, 2006. In the absence of any express bar in

Section 266 against the delegation of demolition powers, the principle of

harmonious construction must prevail.

39. Consequently, the Superintendent Engineer, having acted under a valid

and duly notified delegation of authority, was fully competent to issue the

impugned demolition order dated 04.03.2024. The order cannot be

invalidated merely because it was not personally signed by the

Commissioner.

15

40. The second limb of the Petitioner’s argument in WPA 20449/2024 is that

she was not granted an opportunity of hearing prior to the issuance of the

impugned demolition order, which, according to her, constitutes a violation

of the principles of natural justice. The Respondent Corporation has

refuted this contention by asserting that the statutory requirement of

hearing was duly complied with, as the opportunity of hearing was

afforded to those directly responsible for the unauthorised construction,

namely, Abdullah Zakaria and Sulaiman Zakaria, the sons of the

Petitioner.

41. As per Explanation to Section 266, ‘the person at whose instance” shall

mean the owner, occupier or any other person who causes the creation of

any building or execution of any work to be done. Hence before issuing a

demolition order, the Commissioner must give a “reasonable opportunity of

being heard” only to the owner, occupier, or person responsible for the

unauthorised construction. The provision does not require the Corporation

to extend such an opportunity to every person with a tangential or indirect

interest in the property.

42. It is undisputed that “Nuruddin House” is an old structure, and the

complaint lodged by Rukhsana Hamid pertained solely to unauthorised

construction carried out by Abdullah Zakaria and Sulaiman Zakaria. The

demolition order concerns only this unauthorised portion and not the

original building. The Petitioner herself has consistently stated that she

resides separately from her sons and was unaware of the said

construction. Her only stated concern is that she should not be rendered

homeless as a result of the demolition.

16

43. It is also significant to note that Abdullah Zakaria and Sulaiman Zakaria,

who admittedly undertook the unauthorised construction, never

challenged the demolition order dated 04.03.2024. They participated in the

hearing conducted by the Respondent Municipal Corporation but failed to

produce any sanctioned building plan in respect of the disputed

construction. It is not even their case that they did not make the

unauthorised construction.

44. In these circumstances, the Petitioner, being merely the mother of the

persons responsible and having disclaimed any connection with the

unauthorised works, cannot claim to be aggrieved by the demolition order.

Since the action of the Respondent Corporation is confined to the

demolition of the offending structure raised by her sons, and the original

Nuruddin House remains unaffected, there is no infringement of her legal

rights, and the plea of violation of natural justice is without merit.

45. In view of the detailed discussion hereinabove, this Court finds no illegality,

irregularity, or infirmity in the impugned demolition order dated

04.03.2024. The factual matrix clearly establishes that Abdullah Zakaria

and Sulaiman Zakaria undertook unauthorised construction on the said

premises without obtaining any sanctioned building plan, in blatant

contravention of the provisions of the West Bengal Municipal Corporation

Act, 2006. The Respondent Municipal Corporation, upon due compliance

with the statutory mandate of affording an opportunity of hearing to the

persons responsible, has rightly directed demolition of the said

unauthorised structure.

46. The record reveals that the unauthorised construction is entirely

attributable to the said two individuals, who neither denied their role in its
17

execution nor produced any lawful sanction in support thereof. The

Petitioner, who claims to reside separately and disassociates herself from

the acts of her sons, has failed to demonstrate any infringement of her own

legal rights that could warrant judicial interference.

47. Consequently, WPA 20449/2024 is dismissed, as there are no sustainable

grounds for challenge.

48. WPA 18238/2024 is allowed. The Respondent Municipal Corporation is

directed to proceed forthwith with the demolition of the unauthorised

structure raised by Abdullah Zakaria and Sulaiman Zakaria, strictly in

accordance with law, and to ensure that the action is confined only to the

offending portion without disturbing the original old structure.

49. Urgent Photostat certified copy of this judgment, if applied for, be supplied

to the parties, expeditiously after complying with all necessary legal

formalities.

(Gaurang Kanth, J.)

SAKIL AMED (P.A)



Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here