Jpw Infratech Private Limited vs Bridge And Roof Co. (India) Limited And … on 11 August, 2025

0
15

[ad_1]

1. This is an application for appointment of a learned Arbitrator in terms of

Clause 78 of the General Conditions of Contract (GCC) of the respondent

no.1. Pursuant to a notice inviting e-tender dated May 13, 2022, the

petitioner was awarded the work as the L1 bidder. A Letter of Intent dated

July 26, 2022 was issued by the respondent no.3. The estimated value of

the work was Rs.31,04,10,086.95/-. The petitioner furnished a performance

bank guarantee (PBG) for a total sum of Rs.1,55,20,525/-.

2. According to the petitioner, men and machineries were deployed. However,

there were multiple hindrances at the site which resulted in slow progress of

the work. The petitioner contends that the hindrances immensely affected

the work and the respondents were responsible for the delay.