Haldia Development Authority vs M/S. Konarak Enterprise on 17 January, 2025

0
115

Calcutta High Court

Haldia Development Authority vs M/S. Konarak Enterprise on 17 January, 2025

Author: Sabyasachi Bhattacharyya

Bench: Sabyasachi Bhattacharyya

                  IN THE HIGH COURT AT CALCUTTA
                  Ordinary Original Civil Jurisdiction
                         Commercial Division

The Hon'ble Justice Sabyasachi Bhattacharyya

                          AP-COM No.229 of 2024
                        (old no. AP No.464 of 2021)
                            IA NO: GA 1 of 2021

                     Haldia Development Authority
                                  Vs
                       M/s. Konarak Enterprise

                                   With

                         AP-COM No.255 of 2024
                        (old no. AP No.95 of 2022)

                       M/s. Konarak Enterprise
                                  Vs
                     Haldia Development Authority


 For the petitioner in
 AP-COM No.229 of 2024 and
 For the respondent in
 AP-COM No.255 of 2024              :     Mr. Swarajit Dey, Adv.
                                          Ms. Debarati Das, Adv.

 For the respondent in
 AP-COM No.229 of 2024 and
 For the petitioner in                    Mr. Subhabrata Dutta, Adv.
 AP-COM No.255 of 2024              :     Ms. Munmun Tiwary, Adv.


 Hearing concluded on               :     13.12.2024

 Judgment on                        :     17.01.2025

 Sabyasachi Bhattacharyya, J:-


1. Both the above applications under Section 34 of the Arbitration and

Conciliation Act, 1996 (for short, “the 1996 Act”), having arisen out of
2

the self-same award, as subsequently corrected under Section 33 of

the 1996 Act, are taken up together for analogous hearing.

2. The genesis of the case is a work order awarded to the contractor,

M/s. Konarak Enterprise (hereinafter referred to as the „claimant‟) by

the Haldia Development Authority (hereinafter referred to as the

„respondent‟), on the basis of a tender in which the claimant came out

successful, for construction of a road from Gholpukur to Tekhali

Bridge via Amdabad High School, Haldia and maintenance of the said

road.

3. Disputes having arisen between the parties arising out of the said

contract, the claimant referred the matter to arbitration, seeking

refund of security deposit and earnest money which was deposited at

the inception by it, whereas the respondent filed a counter claim

before the Arbitral Tribunal for recovering the risk and cost expenses,

which was the balance amount paid to the subsequent contractor for

completion of the work left unfinished by the claimant.

4. The Tribunal directed the earnest money and security deposit to the

tune of Rs.9,06,091.44p to be refunded to the claimant. The risk and

cost claim of the respondent was partially allowed, to the tune of

Rs.18,00,163/-.

5. Learned counsel appearing for the respondent argues that the refund

of security deposit and earnest money as directed by the Tribunal was

not permissible, since the work was not completed by the claimant.

The completion certificates issued to the claimant at various stages of

the work, it is argued, were restricted to the partial work completed
3

upto each such stage and did not pertain to the completion of the

entire work.

6. It is further argued that in view of the three additional years of

maintenance of the construction of road having not been completed,

the claim of refund was premature.

7. Thirdly, it is contended that the claim of refund of security deposit

was barred by limitation, since the work was completed on September

24, 2010 and the claim was made sometime in the year 2016.

8. Learned counsel also contends that the risk and cost expenses

awarded by the Tribunal ought to have been enhanced. The value of

the total work was calculated to be Rs.1,96,49,202/-. The work

actually done by the claimant and paid for was subsequently corrected

under Section 33, on the application of the claimant, and increased

from the original awarded amount of Rs.1,41,39,493/- to

Rs.1,74,05,144/-. As a logical corollary thereto, the work left

unfinished should have been decreased to Rs.22,44,058/-, in view of

the same being the difference between the total contract value and the

work actually done. However, such prayer of the respondent was

refused by the Arbitral Tribunal on the ground that no independent

application under Section 33 of the 1996 Act had been filed by the

respondent, overlooking that no further application by the respondent

was necessary in that regard, since the enhancement of the value of

work done would automatically entail a decrease of the work left

unfinished. Instead of decreasing the said amount, which would

require mere mathematical calculation, to Rs.22,44,058/-, which is
4

the difference between the total contract value and the enhanced

value of work done, the Tribunal retained the value of the unfinished

work at Rs.55,09,759/-, thereby committing a patent error of law

apparent on the face of the corrected award.

9. In support of his contentions, learned counsel cites Indian Oil

Corporation Limited v. Shree Ganesh Petroleum Rajgurunagar, reported

at (2022) 4 SCC 463, for the proposition that if the Arbitral Tribunal

passes an award contrary to the specific terms of the contract between

the parties, the same is tainted by patent illegality and can be set

aside under Section 34 of the 1996 Act.

10. Learned counsel for the respondent next relies on Associate Builders v.

Delhi Development Authority, reported at (2015) 3 SCC 49, for the

proposition that perverse and patently illegal judgments, overlooking

vital evidence and/or contrary to the materials on record, can be set

aside under Section 34 of the 1996 Act.

11. Learned counsel next places reliance on Delhi Metro Rail Corporation

Ltd. v. Delhi Airport Metro Express Pvt. Ltd., reported at 2024 SCC

OnLine SC 522 for the self-same proposition.

12. The respondent next cites Oil and Natural Gas Corporation Limited v.

Western Geco International Limited, reported at (2014) 9 SCC 263 and

Madhya Pradesh Power Generation Company Limited and another v.

Ansaldo Energia SPA and another, reported at (2018) 16 SCC 661, in

both of which cases the Supreme Court had modified the award.

Accordingly, it is submitted that it is well within the powers of this

Court under Section 34 to modify the award. It is further contended
5

that the parts of the award which are impugned herein by the

respondent are segregable from the rest of the award, and thus may

be interfered with by this court.

13. Learned counsel appearing for the claimant argues that the risk and

cost claim made by the respondent in its counter claim ought not to

have been granted. It is contended that the respondent/employer did

not impose any penal measure on the claimant for non-completion of

the work. Furthermore, the Tribunal itself directed security deposit to

be refunded to the claimant, thus accepting the argument that the

work was duly completed by the claimant.

14. It is contended that the probative value of the measurement books

override that of the letters issued by parties. Hence, proceeding on

such premise, the inevitable conclusion is that the work was duly

completed by the claimant.

15. Moreover, it is submitted that the work awarded to the subsequent

contractor on March 3, 2016 was six years after completion of the

contractual work done by the claimant in the year 2010. That apart,

the said work awarded to the subsequent contractor was merely in the

nature of repair, as opposed to constructional work covered by the

contract with the claimant. Hence, it is argued that the work awarded

to the second contractor was different from that awarded to the

claimant and an entirely new work. As such, the respondent‟s claim

that the same constituted the unfinished work left by the claimant is

not tenable and, accordingly, the respondent is not entitled to any risk

and cost expenses on such score.

6

16. Learned counsel for the claimant also controverts the argument of the

respondent on limitation regarding the claim of refund of security

deposit. It is submitted that since the final bill was prepared and

passed on May 18, 2016, whereas the demand for refund of security

deposit with interest was raised on November 11, 2016, the claim was

well within the limitation period as stipulated in Article 137 of the

Limitation Act.

17. It is further argued on behalf of the claimant that none of the

measures as contemplated under Section 3 of the Conditions of

Contract were taken by the respondent, which might have rendered

the claimant liable to pay compensation. Hence, the respondent was

not entitled to compensation on account of risk and cost principle as

envisaged under Section 3(c) of the Conditions of Contract.

18. It is argued that it is a well-settled proposition of law that an award

cannot be modified in exercise of jurisdiction under Section 34 of the

1996 Act.

19. Lastly, it is argued that the counter claim component of the award is

severable and, as such, can be set aside.

20. Upon hearing learned counsel for the parties, the following issues fall

for consideration:

(i) Whether the claimant is entitled to refund of security

deposit;

(ii) Whether compensation can be awarded to the respondent

on the risk and cost principle;

7

(iii) Whether the Arbitral Tribunal could enhance the amount of

risk and cost liability component payable to the respondent

by modifying the same even in the absence of any

independent application to such effect being filed by the

respondent for correction of the award under Section 33 of

the 1996 Act.

21. The above issues are decided as follows:

(i) Whether the claimant is entitled to refund of security deposit

22. The respondent has argued that the claim for refund of security

deposit is barred by limitation. However, such contention is

contradictory with the arguments of the respondent itself. On the one

hand, the limitation ground is taken on the premise that the work was

completed in the year 2010 but the claim was made only in 2016 and

on the other, the respondent argues that the claim for refund of

security deposit is premature, as the three years maintenance period

after the completion of the work has not elapsed after the final bill was

raised in the year 2016.

23. Even apart from such inherent contradiction in the limitation

argument raised by the respondent, the claim for refund of security

deposit cannot be held to be barred by limitation, since the final bill

was admittedly prepared and passed only on May 18, 2016 whereas

the claim for refund of security deposit was made on November 11,

2016, that is, well within the limitation period for making such a
8

money claim. Thus, the objection as to limitation taken by the

respondent is turned down.

24. The next objection taken by the respondentto the claim of refund of

security deposit is premised on the ground that the claimant did not

complete the work awarded under the concerned contract and as

such, Clause 3(a) of the Conditions of Contract could have been

invoked, thereby forfeiting the security deposit.

25. Such argument, however, cannot be accepted for several reasons.

26. First, there was no termination of the contract at any point of time.

Clause 3(a) provides that the security deposit of the contractor shall

stand forfeited and be absolutely at the disposal of the Authority only

upon the Authority rescinding the contract. There is nothing on

record to indicate that the contract was ever rescinded. Hence, the

forfeiture provision under Clause 3(a) could not have been invoked by

the respondent at all.

27. On the contrary, instead of terminating the contract, the respondent

went on passing bills till the final bill on May 18, 2016 and continued

to make payments to the claimant from time to time at the different

phases of the work, upon bills being raised for such work by the

claimant.

28. Secondly, completion certificates were issued for different phases of

the work and payments were also made accordingly by the

respondent. Thus, the respondent is estopped from arguing that the

entire work was not done, only in which case the security deposit

could have been forfeited.

9

29. The letters issued by the claimant, which are sought to be relied on by

the respondent, were only restricted to a part of the work having not

been completed. However, the measurementbooks, which

aredocuments admitted by both parties, clearly indicate that a

substantial portion of the work was actually completed and final bills

raised, passed and paid for such components of the work.

30. Hence, Clause 3(a) of the Conditions of Contract could not be invoked

at all. Thus, the principle laid down in Indian Oil Corporation Limited

(supra) is not applicable to the present case, as the Tribunal did not

act contrary to the contract between the parties in directing refund of

security deposit.

31. The proposition enunciated inAssociate Builders (supra) is also not

applicable, as the impugned award, to the extent of granting refund of

security deposit, is not perverse. The letters of the claimant, even if

considered, would not make a difference since they only reflected that

a part of the work was not completed. Thus, it cannot be said that

vital evidence was overlooked by the Tribunal.

32. Insofar as the argument of the respondent that the claim for refund of

security deposit is premature, we find from the materials on record

that the work was completed in several phases, for which completion

certificates were issued at different stages. Moreover, since the work

was substantially completed, the claim for refund of security deposit

was justified.

33. Another aspect of the matter ought also to be considered. Clause 3, in

sub-clauses (a), (b) and (c), provides different alternative measures
10

which could have been taken by the respondent in case of non-

completion of the work by the claimant. Since the respondent has

invoked Clause 3(c) by awarding the work to a second contractor, it

cannot be said that it would be entitled to forfeit the security deposit

as well. Such an approach would defeat the claim of the risk and cost

expenses made by the respondent in its counter claim. The above view

being one of the plausible ones, the Arbitral Tribunal cannot be

faulted for directing refund of security deposit to the claimant while

granting the risk and cost expenses to the respondent.

34. Accordingly, this Court comes to the conclusion that the claimant was

entitled to refund of security deposit along with earnest money and

the Tribunal was justified in granting the same.

35. This issue is, thus, decided in favour of the claimant.

(ii) Whether compensation can be awarded to the respondent on

the risk and cost principle

36. The claim of the respondent on the principle of risk and cost has been

sought to be resisted by the claimant on three grounds.

37. First, it is argued that no penal measure was imposed on the claimant

to justify the risk and cost component.

38. However, Clause 3 of the Conditions of Contract makes it a pre-

requisite for imposition of risk and cost composition merely that the

“contractor shall have rendered himself liable to pay compensation

amounting to the whole of his security deposit”. Thus, no imposition

of penalty has been contemplated as a pre-requisite of such liability.
11

In the present case, security deposit of Rs.9,06,091.44p has been

directed to be refunded. The claim of compensation on the risk and

cost principle made by the respondent far exceeds the said amount.

Hence, the contractor made himself liable to pay compensation

amounting to the whole of security deposit and as such, the

respondent-Authority acted well within its jurisdiction to invoke

Clause 3(c) on the principle of risk and cost liability. Non-imposition

of penal measure is, thus, a non-issue in the context.

39. The second ground on which the risk and cost claim has been resisted

it that security deposit was directed to be refunded, indicating that the

work was completed by the claimant.

40. However, the remedy of refund of security deposit under the contract

is independent of the claim of risk and cost compensation. In any

event, under Clause 3, any of the alternative measures under sub-

clauses (a), (b) and (c) could be invoked. Even if security deposit was

not forfeited under clause (a) but directed to be refunded, the same

could not be sufficient ground to defeat the claim of risk and cost

liability made by the respondent under clause (c).

41. The claimant thirdly argues that the work awarded to the second

contractor was on March 3, 2016, that is, six years after completion of

the claimant‟s work on 2010 and, thus, such work was a new project

unconnected with the work awarded to the claimant.

42. Yet, such argument is mutually contradictory, since the respondent‟s

argument of limitation for the claim of refund of security deposit is

resisted by the claimant on the ground that the final bill was passed
12

on May 18, 2016. It is evident, thus, that the work was not completed

at the juncture when the second contractor was awarded the balance

work on March 3, 2016.

43. Furthermore, from both the measurement books and the letters

written by the claimant itself, it is evident that the total work awarded

to the claimant/contractor was not completed. Hence, the respondent

was justified under Clause 3(c) of the Conditions of Contract to

measure up the work of the contractor and to hand over the

unexecuted portion of the work to a subsequent contractor. The

materials on record sufficiently show that such measuring up was

duly done by the respondent and, as such, the award of the work to

the second contractor attracted the risk and cost principle under

Clause 3(c) of the Conditions of the Contract.

44. The claimant argues that the work awarded to the second contractor

pertains to repair work and is not constructional in nature. However,

the tender on the basis of which the original work was awarded to the

claimant was not restricted to construction of the road but also

included subsequent maintenance work for three years and the work

awarded to the subsequent contractor was primarily for repair of the

road, which comes under the broader purview of „maintenance‟. That

apart, it is evident from the nature of the work awarded to the

subsequent contractor (including repair work) that the same also

pertained to construction of the balance portion of the road

contemplated by the contract between the claimant and the

respondent. Hence, there is no occasion for this Court, under Section
13

34 of the 1996 Act, to enter into a re-appreciation of evidence and

interfere with the view of the Arbitrator that the respondent is entitled

to the risk and cost claim. Since the ratio of the impugned award for

grant of the risk and cost expenses was one of the plausible views on

the facts of the case and clause 3 (c) of the Conditions of Contract

permitted the respondent to claim the same, there is no scope for this

Court to substitute its own views for that of the Arbitral Tribunalin the

factual matrix of the case.

45. Hence, this issue is decided against the claimant and in favour of the

respondent, by holding that the Tribunal was justified in awarding

risk and cost compensation to the respondent.

(iii) Whether the Arbitral Tribunal could enhance the amount of

risk and cost liability component payable to the respondent

by modifying the same even in the absence of any

independent application to such effect being filed by the

respondent for correction of the award under Section 33 of

the 1996 Act

46. The respondent has raised a vital question as to whether, in the

absence of an independent application by the respondent under

Section 33 of the 1996 Act, the Arbitrator had the power to enhance

the risk and cost component payable by the claimant to the

respondent.

47. The Arbitral Tribunal proceeded on the premise that it did not, since

the respondent had not filed any such independent application under
14

Section 33 of the 1996 Act, and restricted its correction to the prayer

made by the claimant in its application under the said provision.

48. However, such view of the Arbitral Tribunal is patently illegal, being in

contravention of Section 33(3) of the 1996 Act. The said provision

empowers the Arbitral Tribunal to correct any error of the type

referred to in Clause (a) of sub-section (1) on its own initiative within

30 days from the date of arbitral award.

49. Clause (a) of sub-section (1) of Section 33 provides inter alia that the

Arbitral Tribunal may correct any computation errors and the error

pointed out by the respondent pertains to simple calculation.

50. Admittedly, in the present case, the Tribunal allowed the application

of the claimant under Section 33 and altered the second component of

the risk and cost claim. This Court is required to delve a bit more into

the said aspect of the matter.

51. For considering the risk and cost counter claim, the Tribunal

enumerated three components.

52. The first of such components was the total contract value, which was

assessed at Rs.1,96,49,202/-, to which there is no demur from either

side.

53. The second component was the work actually done by the claimant

and paid for. In the initial award, the said amount was computed by

the Tribunal to be Rs.1,41,39,493/-. Subsequently, on the application

of the claimant, the second component was enhanced to

Rs.1,74,05,144/-, to which the respondent did not have any objection.
15

54. Notably, the third component, that is, the unfinished work of the

claimant, for which he was obviously not paid, was retained by the

Tribunal at Rs.55,09,759/-, as calculated in the original award.

55. However, such approach is perverse, since, even by a logical deduction

on application of rudimentary arithmetic, the third component ought

to have automatically decreased upon the second component being

increased, since the third component was the difference between the

first and the second.

56. If the first component, that is the total contract value, is taken to be of

value „A‟ and the second component, that is, work done by the

claimant as „B‟,then the third component, that is, the unfinished work

of the claimant is of value „C‟, which is equal to the figure: (A – B).

57. The value of „A‟ was an agreed and fixed amount and remained the

same as the original award even after correction. However, „B‟ was

increased from Rs.1,41,39,493/- to Rs.1,74,05,144/- after the original

award was corrected under Section 33 at the behest of the claimant.

58. By basic mathematics, if figure C = (A – B), and „B‟ is increased, „C‟

automatically comes down.

59. As per the original award, C = (1,96,49,202 – 1,41,39,493) =

Rs.55,09,759.

60. However, after correction of the award, „B‟ was changed to

1,74,05,144. Accordingly, C should have been equal to (1,96,49,202 –

1,74,05,144) = Rs. 22,44,058.

61. For arriving at such figure, no further correction on merits or

reappreciation of any legal or factual facet of the matter was
16

necessary. The said change was a logical and inevitable corollary of

the correction effected to component „B‟ by the Tribunal.

62. The Tribunal had proceeded to calculate the risk and cost

compensation payable to the respondent by deducting the figure „C‟

from the total amount paid to the subsequent contractor that is

Rs.73,09,922/-.

63. Accordingly, the amount payable to the respondent on such count was

calculated to be Rs.18,00,163/- = (73,09,922 – 55,09,759).

64. However, since the figure „C‟ would have to be reduced upon the

correction from Rs.55,09,759/- to Rs.22,44,058/-, the automatic

effect of the correction would be that the amount payable under the

head of “Risk and Cost Liability” by the claimant to the respondent

would become Rs.(73,09,922 – 22,44,058) = Rs.50,65,864/-.

65. Accordingly, even if the Tribunal merely allowed the Section 33

application of the claimant, as a logical result thereof, the risk and

cost amount payable to the respondent would increase to

Rs.50,65,864/- even without any further application by the

respondent being necessitated.

66. Even otherwise, as discussed above, Section 33(3) empowers the

Tribunal to suo moto correct any computation error as envisaged

under Section 33(1)(a). Having not done so within the statutory 30

days, it was incumbent upon the Arbitral Tribunal to suo moto correct

such error, at least as a resultant effect of the correction done by it on

the application of the claimant under Section 33 of the 1996 Act.
17

67. Thus, the refusal of the Arbitral Tribunal to correct the award insofar

as the risk and cost element of the award was concerned and to

enhance the risk and cost compensation payable to the respondent to

Rs.50,65,864/- is patently illegal and perverse, being contrary to its

own corrected award and as such, amenable to being set aside under

Section 34 of the 1996 Act. The proposition laid down in Delhi Metro

Rail Corporation Ltd. (supra) is apt in the context.

68. In Oil and Natural Gas Corporation Limited (supra) and Madhya

Pradesh Power Generation Company Limited (supra) the Supreme

Court had modified the respective awards therein. In the present case

as well, the refusal to enhance the risk and cost counter claim can be

segregated from the rest of the claims. Hence, by the own correction

effected by the Tribunal itself, the risk and cost awarded to the

respondent ought to have been enhanced to Rs.50,65,864/-. Since

such patent illegality hits at the root of the counter claim, the said

refusal can very well be set aside under Section 34 of the 1996 Act by

this Court, which would not tantamount to or be restricted merely to a

modification of the award.

69. Hence, this issue is decided in favour of the respondent and against

the claimant.

70. In fine, on the basis of the considerations above, this Court is of the

opinion that the component of the award of the claim for refund of

security deposit and earnest money to the claimant does not call for

any interference under Section 34 of the 1996 Act.
18

71. However, insofar as the risk and cost counter claim is concerned,

although the Tribunal was justified in granting the same, the

quantum of such counter claim amount ought to have been

Rs.50,65,864/-.

72. Accordingly, AP-COM No.255 of 2024 (old no. AP No.95 of 2022),

preferred by the claimant M/s Konarak Enterprise, is dismissed on

contest.

73. AP-COM No.229 of 2024 (old no. AP No.464 of 2021) is allowed on

contest in part, thereby granting the respondent its counter claim on

account of risk and cost principle to the tune of Rs.50,65,864/-.

Hence, the balance amount, after deducting the amount of claim of

security deposit and earnest money awarded to the claimant from the

counter claim awarded to the respondent to the tune of

Rs.50,65,864/-, comes to Rs.41,59,772.56p, which shall be paid by

the claimant to the respondent/Haldia Development Authority within

February 28, 2025.

74. IA No. GA 1 of 2021 is also disposed of accordingly.

75. There will be no order as to costs.

76. Urgent certified server copies, if applied for, be issued to the parties

upon compliance of due formalities.

( Sabyasachi Bhattacharyya, J. )



Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here