Bharath Heavy Electricals Ltd vs Tirupati Earth And Project Works Pvt Ltd on 23 January, 2025

0
80

Bangalore District Court

Bharath Heavy Electricals Ltd vs Tirupati Earth And Project Works Pvt Ltd on 23 January, 2025

      KABC170013822024                          Digitally signed
                                                by SUDINDRA
                                 SUDINDRA       NATH S
                                 NATH S         Date:
                                                2025.01.28
                                                18:00:01 +0530

IN THE COURT OF LXXXIII ADDL. CITY CIVIL & SESSIONS JUDGE,
          COMMERCIAL COURT, BENGALURU (CCH-84)
            Present: Sri S. Sudindranath, LL.M., M.B.L.,
                      LXXXIII ADDL. CITY CIVIL & SESSIONS JUDGE
                                 BENGALURU.

                         COM.A.P.No.73/2024

             Dated on this 23rd day of January 2025

      Petitioner/s   1.    Bharath Heavy Electricals
                           Limited
                           Having its Office at IISc Post,
                           Prof. CNR Rao Circle, Malleshwaram,
                           Bengaluru - 560 012.
                           Represented by General Manager (PG III)

                           (By Sri.Aditya Narayana, Advocate)

                           // versus //

      Respondent/s 1.      Tirupati Earth & Project Works
                           Private Limited
                           Having its registered office at
                           No.3, Sadashiv Properties
                           Katras Road, Dhanbad - 826 001.
                           Represented by its Managing
                           Director

                     2.    Justice N. Kumar
                           Former Judge, High Court of Karnataka,
                           Arbitration & Conciliation Centre,
                           Bengaluru (Domestic & International)
                           3rd Floor East Wing, Khanija Bhavana,
                           Race Course Road, Bengaluru,
                                      2
                                    CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024




                          Karnataka - 560 001.

                          (R1 By Sri.Clive Johns, Advocate)

Date of institution of suit               :         28/05/2024
Nature of suit                                Arbitration Suit under
                                          :
                                                 Arbitration Act
Date of commencement                 of
                                          :                -
recording of the evidence
Date on which the judgment
                           :                        23/01/2025
was pronounced
                                              Year/s Month/s Day/s
              Total duration              :
                                               00          07      26


                          JUDGMENT

This is a petition under Section 34 of the Arbitration

and Conciliation Act, filed by the respondent before the

Arbitral Tribunal, challenging the Arbitral Award dated

24-01-2024, passed by Learned Sole Arbitrator,

Respondent No. 2 herein, in AC 18 of 2021, whereby the

Learned Arbitrator partly allowed the claims of the

claimant / Respondent No. 1 herein, and dismissed all

the counterclaims of the petitioner.
3

CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

2. On issuance of notice of the present petition,

Respondent No. 1 [claimant before the learned arbitral

tribunal], has entered appearance through counsel and

filed detailed objections to the present petition. The

notice to the learned arbitrator, Respondent No. 2, is

dispensed with.

3. Thereafter, I have heard the arguments of both

sides and perused the records of the case.

4. The only point that arises for my consideration is :-

Whether the impugned arbitral award

dated 24-01-2024, passed by Respondent

No. 2 in AC 18 of 2021, calls for

interference under Section 34 of the

Arbitration and Conciliation Act?

5. My answer to the above point is in the negative for

the following :-

4

CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

REASONS

6. At the outset, before considering the present

petition on merits, it is necessary to ascertain whether

the present petition is filed within the period of limitation

prescribed under Section 34 [3] of the Arbitration and

Conciliation Act. The impugned Arbitral Award is dated

24-01-2024. The present petition is filed on 27-05-2024.

On 28-06-2024, counsel for petitioner filed a memo

producing extract of the Register of Copy Applications of

the Arbitration Centre, disclosing that the award was

obtained by the petitioner on 01-02-2024. Under Section

34(3) of the Arbitration and Conciliation Act, the

limitation of three months begins to run from the date on

which the petitioner obtained the original award. Since

the original award was obtained on 01-02-2024, the

period of three months’ limitation would expire on 01-05-

2024, which falls within civil vacations. Therefore, the

petition filed on the reopening day, i.e., 27-05-2024,

is within the period of limitation.

5

CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

7. In the course of this judgment, for the sake of

convenience, Respondent No. 1 herein is referred to as

the claimant, and the petitioner is referred to as

BHEL.

8. The facts in brief are that, the claimant is a

company in the construction business. BHEL is a

Government of India undertaking. BHEL was engaged by

National Thermal Power Corporation to construct and set

up a Super Thermal Power Project in the state of

Jharkhand. In connection with the said project, BHEL

awarded the contract for setting up coal handling plant

and administrative buildings, to the Claimant. Later on,

additional work of the ash handling plant was also

awarded to the claimant. The letter of Award was dated

13-03-2015.

9. It was the responsibility of BHEL to acquire the land

where the said work had to be carried out, level the
6
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

same, and hand over possession of the same to the

claimant for the purpose of carrying out its work. The

time stipulated for completion of the said work was 30

months, which would expire on 12-09-2017. The work

was not completed within the stipulated period of 30

months, and therefore, the claimant sought an extension

of 18 months. By letter dated 26-12-2017, BHEL

extended the time for completion of the work by 12

months, observing that the delay was not attributable to

the claimant, and thereby the time was extended till 12-

09-2018.

10. By letter dated 31-10-2018, the claimant sought a

second extension of time for six months. There was no

response by BHEL to the said letter, and BHEL neither

extended the time nor terminated the contract. In view of

the same, the claimant continued the work. By letter

dated 05-04-2019, the claimant sought a third extension

of time for nine months. Again, there was no response,
7
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

and neither was the time extended nor the contract

terminated.

11. In June 2019, the workers of the claimant were

stopped at the gate and were prevented from entering the

work site. Therefore, the claimant wrote a letter dated 25-

06-2019, requesting issuance of an extension letter and

issuance of gate pass. BHEL provisionally amended the

work order by extending the time up to 31-07-2019.

However, the workers were allowed to enter the work site

only after 07-08-2019.

12. In view of these facts, disputes arose between the

parties under the contract, which contained an

arbitration clause. After issuance of a Section 21 notice,

the claimant approached the Hon’ble High Court for

appointment of a learned arbitrator, and the Hon’ble

High Court of Karnataka, vide order dated 23-01-2020 in

CMP 344 of 2019, appointed Respondent No. 2 as the
8
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

learned sole arbitrator to decide the dispute between the

parties.

13. On the learned arbitrator entering upon the

reference, the claimant filed a detailed statement of

claim, reiterating the above facts. Further, in the

statement of claim, the delay in completion of the work

was attributed solely to BHEL on the following grounds:

 Failure to hand over the site.

 Delay in providing requisite drawings for various

structures of CHP and AHP and repeated revision of

drawings.

 Delay in providing free issue materials, delaying

contract execution.

 Restrictions at the site gates towards ingress of the

claimant’s labor and material, causing inordinate

delay.

 Delay in progressive inspection of work and

stoppage of work.

9

CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

 Delay in payments against the claimant’s bills and

unwarranted deductions made therefrom.

 Delay caused by other agencies of BHEL.

 Closure of designated sources for material

procurement.

 Non-provision of electricity by BHEL as per Clause 8

of the technical conditions of the contract.

14. The claimant contended that although the delay

was solely attributable to BHEL and in fact, the first

extension of 12 months (from 12-09-2017 to 12-09-2018)

was given by BHEL with a specific observation that the

delay was not attributable to the claimant, on completion

of said extended time period, BHEL neither responded to

the claimant’s second and third requests for extension of

time nor terminated the contract. Instead, all of a

sudden, BHEL unilaterally terminated the contract by

letter dated 26-08-2019, and thereby, the claimant
10
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

contended that the termination of the contract is wholly

illegal.

15. The following claims were raised in the statement of

claim:

 Claim No. 1 : Towards unpaid value for works

done, sum of Rs. 29,46,418, consisting of principal

sum of Rs. 21,66,484, and interest component of

Rs. 7,79,934.

 Claim No. 2 : Refund of retention money :- Rs.

3,09,43,957, consisting of principal sum of Rs.

1,75,64,825, together with interest component of

Rs. 1,33,79,132.

 Claim No. 3 : Price variation amount of Rs.

4,60,85,671, consisting of principal sum of Rs.

2,57,86,951, and interest component of Rs.

2,02,98,720.

 Claim No. 4 : Additional costs incurred due to

prolongation of the contract. Under this claim,
11
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

Subclaim 4A was for Rs. 49,24,306 towards

additional cost incurred for retention of equipment

due to prolongation. Subclaim 4B was for Rs.

5,42,45,038/= for additional overhead cost during

the extended period. Subclaim 4C was for Rs.

5,38,913 towards bank guarantee extension charges

during the prolongation period.

 Claim 5 was for loss on account of wrongful

termination of the contract and consisted of the

following subclaims. Subclaim 5A was for Rs.

3,18,22,570 towards illegal confiscation of the

claimant’s plant, machinery, and equipment

immediately after termination of the contract.

Subclaim 5B was for Rs. 2,45,22,272 for refund of

the performance bank guarantee which had been

encashed by BHEL. Subclaim 5C was for a total

sum of Rs. 5,38,61,424 towards loss of overheads

and profits due to the illegal termination of the

contract.

12

CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

 Claim No. 6 was for Rs. 1,68,09,355 towards

enhanced cost for labour due to a change in the

law.

 Claim No. 7 was for interest on delayed payments

of Rs. 21,81,610.

16. Thereby, the claimant laid claim for a total sum of

Rs. 28,20,29,687 and also sought the grant of the cost of

arbitration.

17. To the above statement of claim, BHEL filed a

detailed statement of defence along with the

counterclaim. In the statement of defence, the awarding

of the work under the letter of award dated 13-03-2015

to the claimant was admitted. It was also admitted that

the work had to be completed within a period of 30

months, which would expire on 12-09-2017. It was

contended that in the event of delay, liquidated damages

of 0.5% per week of delay subject to a ceiling of 5% of the
13
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

total work order value was to be levied. It was contended

that the delay in completion of the work within the fixed

period of 30 months was due to lapses on the part of the

claimant, due to not bringing sufficient raw material and

not deploying adequate labour force. And in fact, the

claimant admitted that this was due to financial

constraints faced by the claimant at that point in time.

Thereby, it was contended that from January 2016, that

is, much before the completion date of 30 months, letters

were issued highlighting the delay in completion of the

work due to insufficient labour and tools and machinery.

It was contended that the first extension granted of 12

months was granted in the interest of the project,

although the delay was due to inaction and under-

deployment by the claimant. After the extension of time,

there was a delay on the part of the claimant in

completing the work, which constrained BHEL to issue

letters dated 17-01-2018 and 01-02-2018. The quality of

the work was also not as per the specifications. Although
14
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

the delay in completion was due to the default on the

part of the claimant, the claimant sought a further

extension of six months by letter dated 03-10-2018, and

as on that date, only 41% of the contract work was

completed. BHEL issued letters dated 12-01-2019, 18-

01-2019, and 21-01-2019 to the claimant requesting the

expedition of the work. BHEL issued letters dated 25-01-

2019, 18-06-2019, and 25-06-2019 regarding the poor

quality of the work. In the meantime, on 05-04-2019, the

claimant had issued another letter seeking an extension

of time by nine months. Since there was continuous

default on the part of the claimant in completing the

work, the respondent issued notice dated 17-07-2019

stating that in the event of the claimant’s failure to

complete the work as per the schedule, the contract

would be terminated. Since the claimant neither

completed the contract work nor responded to the said

letter, BHEL was constrained to terminate the contract

by letter dated 26-08-2019 and awarded the balance
15
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

work to an alternative contractor at the risk and cost of

the claimant. As a result of this, the performance bank

guarantee was encashed. Thereby, BHEL took the stand

that the termination was perfectly in accordance with the

law and due to the default on the part of the claimant

and, on this basis, denied all the claims raised by the

claimant. In addition, the following counterclaims were

raised by BHEL;

Counter-Claim 1 was for a sum of Rs. 15,98,82,197

towards the differential value of the contract given to an

alternative contractor at the risk and cost of the

claimant.

Counter-Claim 2 was for a sum of Rs. 2,16,25,276

towards liquidated damages for violation of the contract

by the claimant under clause 7, which, as already noted

supra, provided for levying of liquidated damages at the

rate of 0.5% per week of delay subject to a maximum of

5% of the contract value.

16

CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

Counterclaim No. 3 was for a sum of Rs. 5,85,03,549

towards recovery of money for failure to reconcile free

issue material.

Counterclaim No. 4 was for a sum of Rs. 43,59,550 for

estimated expenditure to be incurred by BHEL due to the

wrong location of concreting work by the claimant.

Counterclaim No. 5 was for a sum of Rs. 4,78,500

towards costs incurred towards the demolition of the

office building, cement stores, QA and QC labs, etc.,

constructed by the claimant for the purpose of its own

works, which had to be demolished by BHEL after

termination of the contract.

18. Thereby, counterclaim was raised for a total sum of

Rs. 24,48,49,072 along with interest.

19. The claimant filed detailed objections to the

counterclaim and also filed a rejoinder to the statement
17
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

of objections. BHEL, in turn, filed its rejoinder to the

same and additional rejoinder also.

20. On completion of pleadings of both sides, the

learned arbitrator framed the following issues:

1) Whether the termination of the contract on 26-08-

2019 by the letter of the respondent was arbitrary,

illegal, and unjustified?

2) Whether the claimant proves that they are entitled

to a sum of Rs. 21,66,484 towards the unpaid value

of the work done together with interest at 15%

compounded monthly, amounting to Rs.

7,79,934.40, in all a total amount of Rs.

29,46,418.40?

3) Whether the claimant proves that the respondent is

liable to refund a sum of Rs. 1,75,64,825.30

towards the amount deducted towards retention

money security from the bills of the claimant, along

with interest at a rate of 15 percent compounded
18
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

monthly, amounting to Rs. 1,33,79,132.64, in all a

total amount of Rs. 3,09,43,957.67?

4) Whether the claimant proves that the respondent is

liable to pay an amount of Rs. 2,57,59,951 against

the price variation in terms of Clause 2.17.9 of

GCC, along with interest at a rate of 15%

compounded monthly, amounting to Rs.

2,02,98,750, in all a total amount of Rs.

4,60,85,671?

5) Whether the claimant is entitled to the additional

cost incurred due to prolonged retention of the

equipment during the extended period, amounting

to Rs. 36,45,717.50, along with interest at 15%

compounded, amounting to Rs. 12,78,589/= in all a

total amount of Rs. 49,84,306.50?

6) Whether the claimant is entitled to the additional

overhead cost during the extended period of the

contract, amounting to Rs. 542,45,038.99, along
19
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

with applicable interest amounting to Rs.

1,30,18,809.12?

7) Whether the claimant is entitled to the cost incurred

for the extension of bank guarantees during the

extended period, amounting to Rs. 5,38,913.60,

along with applicable interest amounting to Rs.

1,29,339?

8) Whether the claimant is entitled to a sum of Rs.

2,56,63,633, with applicable interest amounting to

Rs. 61,59,207.12, in all a sum of Rs.

3,18,22,570.12, towards illegal confiscation of

claimant’s plant, machinery, and equipment by the

respondent immediately after illegal termination of

the contract?

9) Whether the claimant is entitled to claim towards

refund of the performance bank guarantee illegally

encashed by the respondent in the sum of Rs.

1,97,76,026, along with applicable interest
20
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

amounting to Rs. 47,46,246, in all an amount of Rs.

2,45,22,272?

10) Whether the respondent is liable to pay

towards loss of overheads and profits in the sum of

Rs. 4,34,36,632.92, along with interest at 18%,

calculated up to 30-11-2020, amounting to Rs.

1,04,24,791.90, and in all a sum of Rs.

5,38,61,424.82?

11) Whether the respondent is liable to pay

enhanced cost for labour due to change in law,

calculated up to 30-11-2020, in a sum of Rs.

1,20,23,874.06, with applicable interest in a sum of

Rs. 47,85,481.19, in all a sum of Rs.

1,68,09,355.25?

12) Whether the claimant is entitled to interest on

delayed payment in a sum of Rs. 21,81,610.57?

13) Whether the claimant proves that, in all, he is

entitled to an amount of Rs. 20,70,29,436.94, with

interest up to 30-11-2020 amounting to Rs.
21

CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

7,50,250.0037, in all a sum of Rs.

28,20,,29,681.31?

14) Whether the claimant is entitled to pendente

lite and future interest at 18%?

15) Whether the claimant is entitled to the cost of

arbitration?

Counterclaim Issues

16) Whether the respondent is entitled to a sum of

Rs. 15,98,82,197 towards the differential value of

the orders placed on alternate vendors by invocation

of the risk and cost clause along with departmental

charges at 15%, as per Clause 10 of the CTC, along

with interest at the rate of 18% per annum on Rs.

15,98,82,197 calculated from the date of invocation

of the risk and cost clause until the date of filing of

this statement of defence?

17) Whether the respondent is entitled to interest

at the rate of 18% per annum on Rs. 15,98,82,197
22
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

during the pendency of this arbitration until the

award is passed or any such amount that may be

awarded to the respondent?

18) Whether the respondent is entitled to

liquidated damages at 5% of the contract value,

being Rs. 2,16,25,276.28, along with interest at the

rate of 18% per annum on Rs. 2,16,25,276.28,

calculated from the date of invocation of the risk

and cost clause, i.e., 26-08-2019, till the date of

filing of this statement of defence, i.e., 29-03-2021?

19) Whether the respondent is entitled to interest

at the rate of 18% per annum on Rs. 2,16,25,276.28

during the pendency of this arbitration until the

award is passed or any such amount that may be

awarded to the respondent?

20) Whether the respondent is entitled to Rs.

3,25,61,588.50 towards the cost of unaccounted

free issue material for non-reconciled free issue

items, along with interest at a rate of 18% per
23
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

annum on Rs. 3,25,61,588.50 calculated from the

date of invocation of the risk and cost clause, i.e.,

26-08-2019, till the date of filing of the statement of

defence, i.e., 29-03-2021?

21) Whether the respondent is entitled to adjust

the sum of Rs. 32,80,470 from retention monies

withheld by the respondent in respect of the project

and under the contract?

22) Whether the aforesaid adjustment sought by

the respondent is barred by law?

23) Whether the respondent is entitled to interest

at the rate of 18% per annum on Rs. 5,85,03,549

during the pendency of this arbitration until the

award is passed, or any such amount that may be

awarded to the respondent?

24) Whether the respondent is entitled to Rs.

43,59,550.18 towards expenditure to be incurred by

the respondent for demolition and reconstruction of

wrongly located TR4-5 of BCN5A-B by the claimant,
24
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

along with interest at a rate of 18% per annum on

Rs. 43,59,550.18 calculated from the date of

invocation of the risk and cost clause, i.e., 26-08-

2019, till the date of filing of the statement of

defence, i.e., 29-10-2019?

25) Whether the respondent is entitled to interest

at the rate of 18% per annum on Rs. 43,59,550.18

during the pendency of this arbitration until the

award is passed, or any such amount that may be

awarded to the respondent?

26) Whether the respondent is entitled to Rs.

4,78,500 towards dismantling the site office and

allied constructions of the claimant, removal and

disposal of the debris, along with interest at the rate

of 18% per annum on Rs. 4,78,500 calculated from

the date of invocation of the risk and cost clause,

i.e., 26-08-2019, till the date of filing of the

statement of defence, i.e., 29-03-2021?
25

CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

27) Whether the respondent is entitled to interest

at the rate of 18% per annum on Rs. 4,78,500

during the pendency of this arbitration until the

award is passed or any such amount that may be

awarded to the respondent?

28) Whether the respondent is entitled to future

interest from the date of the award on the aforesaid

claims as awarded at such rate of interest as this

Hon’ble Tribunal may deem fit till the date of

realization thereof?

29) Whether the respondent is entitled to the costs

of these arbitral proceedings?

21. In the inquiry before the learned arbitrator, the

authorized representative of the claimant was examined

as PW1 and got marked Ex. C1 to C686. On behalf of

BHEL, the authorized representative was examined as

RW1 and got marked Ex. R1 to R221.

26

CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

22. After hearing both sides, on Issue No. 1, the learned

arbitrator held that the termination of the contract by the

BHEL by letter dated 26 August 2019 is contrary to law

and illegal. In respect of Claim No. 1, as against the

claimed sum of Rs. 29,46,418, the Learned Arbitrator

awarded Rs. 21,66,484, along with interest at 10% from

the date of termination till the date of claim petition. In

respect of Claim No. 2, as against the claimed sum of Rs.

3,09,43,957.67, the Learned Arbitrator awarded a sum of

Rs. 1,75,64,825.30 along with interest at 10% from the

date of termination of the contract till the date of claim.

The Learned Arbitrator rejected Claim No. 3 and Claim

No. 4, which consisted of three sub-claims. In respect of

Claim No. 5A, as against the claimed sum of Rs.

3,18,22,570.12, the Learned Arbitrator awarded Rs.

1,92,47,725 without pre-claim interest. In respect of

Claim 5B, as against the claimed sum of Rs. 2,45,22,272,

the Learned Arbitrator awarded Rs. 1,97,76,026 along

with interest at 8% per annum. In respect of Claim 5C,
27
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

the learned arbitrator awarded Rs. 2,17,18,316.46. The

learned arbitrator rejected Claim No. 6 and Claim No. 7.

23. Insofar as the counterclaims, the learned arbitrator

rejected all the counterclaims. On the sums awarded to

the claimant, the learned arbitrator awarded pendente

lite interest at 10% from the date of claim petition till the

date of award and future interest at the rate of 12% from

the date of award till the date of realization. The Learned

Arbitrator also awarded the proportionate cost of the

proceedings to the claimant. Since all the counterclaims

were rejected, the claim for interest on the counterclaims

also stood rejected. The respondent was held not entitled

to any cost of the proceedings.

24. Aggrieved by this arbitral award, the BHEL, which

was the respondent before the learned arbitrator, is

before this court under Section 34 of the Arbitration and

Conciliation Act.

28

CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

25. In support of the petition, Learned Counsel for the

Petitioner vehemently argued that the primary finding of

the learned arbitrator that the termination of the contract

by letter dated 26-08-2019 is illegal and contrary to law

is itself perverse, riddled with contradictions, and

erroneous on the very face of the award. He submitted

that the learned arbitrator ought to have considered the

case in the background of the fact that the work awarded

to the claimant was a crucial part of the total project for

setting up the thermal power project at the site, and

therefore, any delay on the part of the claimant in

completing the work and any non-adherence to the time

schedule would have adverse and cascading effects upon

the completion of the entire project. In this background,

he submitted that several letters were addressed to the

claimant to pick up the pace of the work and to rise to

the occasion. In particular, emphasis was placed upon

the letters at Ex. R57, R64 and R66. It was argued that,
29
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

in spite of all these letters and communications directing

the claimant to expedite the work, when the claimant did

not rise to the occasion and continued to work in a

slipshod manner, the BHEL had no option but to

terminate the contract under the Letter dated 26-08-

2019.

26. He further argued that the learned arbitrator has

contradicted himself by holding in one place that time is

not the essence of the contract and, at another place,

when Section 46 of the Contract Act was invoked, holding

that time is the essence of the contract. Thereby, it was

argued that the entire finding of the learned arbitrator

regarding the termination of the contract besides being

illegal is riddled with contradictions and suffers from

errors apparent on the face of the record, making it liable

to be set aside.

30

CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

27. It was argued that once this finding is set aside,

most of the claims will also have to go, and insofar as a

few other claims, such as the claim towards unpaid value

of work, such claims are allowed without any material in

support thereof, and therefore, the award is also liable to

be set aside on this ground.

28. It was further argued that, once the finding of the

Learned Arbitrator regarding the illegal termination of the

contract is set aside and it is held that the contract was

lawfully terminated by the BHEL, without being left with

any other option due to default on the part of the

claimant in carrying out the work, then the

counterclaims will have to be allowed. Apart from these

arguments, the Learned Counsel for the Petitioner has

reiterated all the contentions taken in the grounds of the

present petition.

31

CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

29. Per contra, Learned Counsel for Respondent No. 1

[claimant before the arbitral tribunal], supported the

impugned arbitral award.

30. Having considered the rival contentions, at the

outset, the admitted facts may be taken note of. It is

admitted that certain work, which was part of the overall

project of setting up a super thermal power project in the

state of Jharkhand, was awarded by BHEL to the

claimant by the letter of award dated 13-03-2015.

31. Admittedly, the stipulated period for completion of

the works was 30 months, which expired on 12-09-2017.

Admittedly, the works were not completed within the said

period of 30 months, as a result of which, on 04-09-

2017, the claimant sought an extension of 18 months,

and BHEL, on 26-12-2017, by way of Amendment No. 2

to the work order, extended the time from 12-09-2017 to

12-09-2018, that is, an extension of 12 months. It is the
32
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

specific finding of the learned arbitrator at paragraph 50

of the Award that when this extension of time was

granted up to 12-09-2018 as per Ex. C 186, it is clearly

mentioned that the delay is not attributable to the

contractor. This finding of fact is not challenged before

me, and even otherwise, this is a fact borne out from the

records of the case.

32. Therefore, what emerges is that, at the time of

granting the extension of time by 12 months, there is a

specific admission by the BHEL that the delay is not

attributable to the claimant herein. Thereafter, since the

work was not completed even within the extended period

of time of 12-09-2018, the claimant sought two more

extensions of time, namely, on 03-10-2018, wherein the

claimant sought an extension by six months, and on 05-

04-2019, wherein the claimant sought an extension of

time by nine months. Admittedly, the BHEL neither
33
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

granted the extension of time nor disallowed the same

nor terminated the contract on ground of lapse of time.

33. In this background, the legality of the termination

by the letter dated 26-08-2019 has been decided by the

learned arbitrator. The findings of the learned arbitrator

in this regard are in paragraph 46 to 56 of the award.

Essentially, the findings of the Learned Arbitrator are

that time was not the essence of the contract because the

contract provided for extension of time and acting on

such clause, in fact, BHEL had extended the time in the

first instance from 12-9-2017 to 12-9-2018, by making a

specific admission that delay is not attributable to the

contractor. When the extended time expired on 12-09-

2018 and the contractor sought for two more extensions

of time, the same was not rejected, but the contractor

was permitted to continue with the work. Thereby, the

learned arbitrator recorded a specific finding that, far
34
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

from time being the essence of the contract, time for

completion was set at large.

34. In this background, the learned arbitrator

considered the question whether, when on 17-07-2019,

BHEL issued a letter to the claimant which was a prelude

to the termination letter dated 26-08-2019, whether the

time fixed was reasonable for completion. The Learned

Arbitrator noted that in the said letter dated 17-07-2019,

BHEL asked the claimant to rise to the expected level of

progress within 14 days, failing which they will be left

with no option but to get the work done by other agency

at risk and cost of the claimant. It is to be noted that, in

the said letter, the contractor was called upon to raise to

the expected level of progress within 14 days without

clarifying what is the expected level. This letter was

followed by the termination letter dated 26-08-2019. The

Learned Arbitrator has held that when 49% of the work

took 4 years and 9 months, giving 14 days to complete
35
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

the remaining 51% of the work is totally unreasonable

and therefore held that the termination of the contract is

illegal.

35. Another ground on which the termination of the

contract was set aside was that as per the terms of the

contract, any notice to the other party had to be issued

by RPAD and the contract also required 2 weeks notice

before termination. In the case on hand, the notice giving

2 weeks pre-termination notice [dated 17-07-2019] was

issued by email. Learned Arbitrator held that, when the

contract provides for the doing certain things in a certain

manner, the parties are expected to comply with the

same. Therefore, the Learned Arbitrator held at

paragraph 56 of the award that, admittedly, the notice at

Ex.R 66 [letter dated 17-07-2019] giving 2 weeks notice

having not been sent by RPAD as provided under clause

2.7.2 of the GCC, compliance of which was a condition
36
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

precedent for valid termination, the notice of termination

is contrary to the agreed terms and therefore illegal.

36. This finding of the Learned Arbitrator that, the

termination of the contract was illegal, forms the fulcrum

of the entire award, since most of the claims and

counterclaims are decided on the basis of this finding.

Therefore, this finding has been vehemently attacked in

the present petition. Grounds attacking this finding

regarding termination of contract being illegal are at

paragraph 19 to 60 of the grounds of the present petition.

37. It is firstly contended that the learned arbitrator

erroneously held that time is not the essence of the

contract. Considering the background in which the LOA

was awarded, that is, the works awarded to the claimant

forms part of the larger work of setting up the thermal

power plant and any delay would have cascading effect

upon the completion of the entire project, it is contended
37
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

that this finding of the learned arbitrator that time is not

the essence of the contract is erroneous. This contention

cannot be accepted because, the contention that, time

was essence of the contract is falsified by the very act of

BHEL in granting first extension of time from 12-09-2017

to 12-09-2018 by admitting that the delay is not

attributable to the claimant. More importantly, when the

extended time came to an end and the work had not yet

been completed, if really time was the essence of the

contract, then certainly the BHEL ought to have

immediately terminated the contract on the ground that

work is not completed within the stipulated period.

Instead, BHEL permitted the claimant to continue to do

the work without either extending the time nor

terminating the contract. This clearly indicates that even

BHEL accepted that time is not the essence of the

contract and that is the reason it permitted the

contractor to continue the work in spite of the stipulated

extended period having come to an end. In this
38
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

background, the finding of the learned arbitrator that

time was not the essence of the contract is certainly in

accordance with law and does not call for interference.

38. The finding of the learned arbitrator that the time

for performance having been set at large all of a sudden

by the letter dated 17-07-2019, the BHEL expected the

contractor to finish 51% of the work in 14 days which is

totally unreasonable and on that ground holding the

termination of the contract by letter dated 26-08-2019 is

illegal is attacked in the present petition at paragraph 28

and 29 by relying upon Ex. R-57 and R-64, to contend

that under the letters at Ex. R-57 and R-64 specific time

frame was given to complete a specific work for which the

work front was given, that is, the contractor was called

upon to complete such portion of its work that was

required for achieving boiler light up in September 2019

and it was also specifically stated that in case of failure

to meet the said deadline, the BHEL will be constrained
39
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

to terminate the contract. Thereby, it is contended that

since the said time frame fixed for completion of boiler

light up was reasonable and on failure to comply with

said time frame, the contract was terminated and this

vital evidence has escaped the notice of the learned

arbitrator and therefore the award suffers from

perversity. It is further argued that under the letter at Ex.

R-66 dated 17-07-2019, the BHEL called upon the

contractor to rise up to the occasion and to expedite the

work and it is not as if the BHEL expected the contractor

to complete 51% of the work within 14 days. Since the

work was not expedited and the claimant did not rise up

to the occasion, the BHEL had no option but to terminate

the contract. On these grounds, it is contended that the

finding of the Learned Arbitrator that the termination is

illegal, requires to be set aside.

39. Although reappreciation of evidence is

impermissible in a Section 34 petition, for the sake of
40
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

completeness, I have looked into the afore stated Ex. R-

57, R-64, R-66, and also Ex R-67 (termination letter).

40. If Ex. R57 dated 17-04-2019 is looked into, it is

seen that, no doubt, at Page 1, it is stated that BLU

[boiler light-up] has been planned for September 2019,

but in conclusion of the said letter, the demand upon the

claimant is to achieve target in “reasonable / schedule

time”. Therefore, no specific timeframe was fixed even

under Ex. R57 for completion of any stage of the work.

Under Ex. R64, which is dated 25-06-2019, it is stated

that boiler light-up is scheduled in October 2019, which

is contrary to the statement made in Ex. R57 that boiler

light-up / BLU is scheduled in September 2019. This

shows that BHEL itself was not clear about the schedule

and even in Ex. R64, no specific timeframe is given for

completion of the work and only the direction is made to

submit plan and deploy resources to meet the schedule

and reserving the right to terminate the contract. Even in
41
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

Ex. R66, which is the letter dated 17-07-2019, again no

specific targets or dates are furnished but it is only

demanded that, the contractor should raise up to

expected level of progress within 14 days. In Ex.R 67

dated 26-08-2019 which is the termination letter, no

reference is made to violating the timeframe for

completion of BLU [boiler light-up] within September or

October 2019. Instead, general allegations are made that

during the original contract period and extended period,

execution of the contract was not on expected lines. It is

stated that since the contractor is not in a position to

continue and expedite the work, BHEL chose not to

extend the contract further, which is solely due to

inadequate manpower deployment and other resources,

including delay in non-submission of bank guarantee. It

is stated that the contractor has ignored the notice dated

17-07-2019 wherein BHEL had given a final chance to

come out with an action plan and schedule for

completion of the balance work. However, it is crucial to
42
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

note that in Ex. R66 dated 17-07-2019, the contractor is

only demanded to rise to the expected level of progress

within 14 days, failing which the contract will be

terminated. But, under the said letter, nowhere was the

contractor demanded to come up with an action plan and

schedule for completion of the balance work.

41. Therefore, it becomes clear that the BHEL initially

granted one-year extension from 12-9-2017 to 12-9-2018

by categorically admitting that the delay is not

attributable to the contractor. But then, after the lapse of

the extended time period, the contractor was permitted to

continue to do the work and BHEL neither granted

extension explicitly when the second and third

extensions of time were sought by the contractor, and

neither did the BHEL terminate the contract on 12-09-

2018 when the extended time period came to an end. At

no point of time, BHEL in its subsequent letters has fixed

any deadline for completion of work by the contractor. All
43
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

of a sudden, on 17-07-2019 a letter was issued calling

upon the contractor to rise to the expected level of work.

On 26-08-2019, the contract is terminated on the ground

that the work is not expedited. This is precisely the

reason why the learned arbitrator has held that, having

set the time for performance at large, out of the blue,

BHEL suddenly fixed unreasonable timeframe of 14 days

for completion and for non-adherence to such

unreasonable time frame, BHEL could not have

terminated the contract. On this ground, the learned

arbitrator has held that termination of the contract is

illegal and contrary to law. For the reasons noted supra,

the above findings of the Learned Arbitrator are perfectly

in accordance with law and do not call for interference.

This is because in all the letters relied upon by BHEL at

Ex. R57, 64, and 66, nowhere was a timeframe fixed for

the contractor to complete the work. Having earlier

extended the work and having not terminated the

contract when the extended time period came to an end
44
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

and instead, having allowed the contractor to continue

with the work, BHEL could again terminate the contract

only after fixing a reasonable time for completion. Having

not done so and instead having abruptly terminated the

contract on 26-08-2019, the termination of the contract

was rightly held to be illegal by the learned arbitrator.

42. At paragraph 40 of the grounds of the present

petition, reliance is placed upon clause 2.7.2 of the GCC,

which gives the right to BHEL to terminate the contract

by giving a two-week notice. However, this is not an

unqualified and unrestricted right, but BHEL can

terminate the contract by two weeks notice only for

contractors’ continued poor performance, contractors’

inability to progress the work as depicted in the contract,

or for poor quality of the work. Be it noted that in the

termination letter dated 26-08-2019 at Ex. R67, poor

quality of work is not raised as a ground for termination.

Only two grounds are raised, that is, non-furnishing of
45
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

the bank guarantee within time and failure to complete

the work within the stipulated period. However, insofar

as failure to complete the stipulated work is concerned,

as already noted, supra, after having extended the time

and having set the time for completion at large, it was

expected of BHEL to fix a reasonable time for completion

and only on failure to adhere to the reasonable timeline

could the contract have been terminated, which has not

been done in the present case. Therefore, clause 2.7.2

will not come to the aid of BHEL to terminate the

contract.

43. One of the principal grounds argued by Counsel for

Petitioner was that there is an inherent contradiction in

the award since in one place the learned arbitrator holds

that time is not the essence of the contract and in

another place holds that time is, in fact, the essence of

the contract, and on this ground, the award is liable to be

set aside. In this regard, it is to be noted that the so-
46

CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

called contradiction highlighted by the Counsel for

Petitioner is that in paragraph 49, the learned arbitrator

records the specific finding that in view of the clauses of

the agreement providing for extension of time, time is not

the essence of the contract. Whereas, at paragraph 53,

the learned arbitrator holds that this is not a contract

where no time is specified and hence section 46 has no

application to the contract in question. However, in my

view, there is no contradiction because these two

observations are made by the learned arbitrator in

different contexts. The learned arbitrator after analyzing

the provisions of the agreement in view of the extension

of time for the first time by clearly admitting that delay is

not attributable to the contractor and then allowing the

contractor to continue to do the work even after lapse of

extended time held that time is not the essence of the

contract. The observation at paragraph 53 that section

46 has no application since this is not a contract where

no time is specified has to be viewed in the context of the
47
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

fact that this observation is made in response to the

contention raised by BHEL that under section 46 of the

Contract Act, even if time is not the essence of the

contract, the work should have been completed within a

reasonable time. This contention has been answered by

holding that after setting the time for completion at large,

no reasonable time was fixed for completion of the work

because the BHEL expected the contractor to complete

51% of the work in 14 days. Having recorded the said

finding, at paragraph 51, at paragraph 53, a passing

observation is made that section 46 has no application

since this is not a case where no time was specified.

What the learned arbitrator has held is that, originally

time was specified and thereafter time was set at large

and therefore in order to terminate the contract it was

again necessary for the BHEL to fix reasonable time for

completion of the work. It is this principle which is

applicable and not the general principle of section 46

which requires the promiser to complete the work within
48
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

reasonable time. It is in this context that the above

observations of the Learned Arbitrator have to be

understood and therefore the contention that there is a

contradiction in the award is unacceptable and

accordingly rejected.

44. Against the finding of the Learned Arbitrator that

termination of the contract was illegal, it is next

contended that the Learned Arbitrator has ignored the

slow progress of the work made by the contractor. It is to

be noted that the Learned Arbitrator has analyzed the

various reasons for delay and in certain cases attributed

the delay to BHEL and in certain cases, attributed the

delay to both the parties. These findings are found at

paragraph 155 of the award. These are factual findings

which cannot be interfered in Section 34 petition.

However, these findings will not have any bearing on the

question of legality of the termination of the agreement

because ultimately although the Learned Arbitrator has
49
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

held that on certain aspects the delay was also

attributable to the claimant, the fact remains that the

finding of the Learned Arbitrator that time was not the

essence of the contract is unassailable and essentially

the termination of the contract is held to be invalid

because after having set the time for performance at

large, no reasonable time was fixed for completion and

abruptly the contract was terminated. Therefore, the fact

that the learned arbitrator has held against the claimant

on some grounds of delay and held that the claimant was

equally responsible for delay on some aspects will not

have a bearing insofar as the finding of the learned

arbitrator holding that the termination of the contract

was illegal, is concerned.

45. It is then contended at paragraph 59 of the grounds

of the petition that in the statement of admission and

denial of the claimant, the letter dated 17-07-2019 is

admitted. Therefore, the finding of the Learned Arbitrator
50
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

at paragraph 56 that, since said letter was issued by

email and not by RPAD, the termination of the contract is

not as per the terms of the contract is unsustainable.

What has been held by the learned arbitrator at

paragraph 56 of the award is that, as per the terms of the

contract, any notice to the other side has to be issued by

registered post. Further 2 weeks notice had to be issued

before termination. Whereas in the case on hand, the

pre-termination notice is issued by email and therefore,

the requirement of giving 2 weeks notice before

termination is not satisfied and this is another ground to

hold the termination to be illegal. It is to be noted that,

even if the receipt of the pre-termination notice is

admitted, the fact is that, when the contract requires a

party to do a certain act in a certain manner, it was

expected of BHEL to comply with the same. Therefore,

when the contract requires the notice to be issued by

RPAD, BHEL cannot issue the same by email and

contend that it is in compliance with the terms of the
51
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

contract. This is precisely what has been held by the

Learned Arbitrator by holding that clause 2.7.2 required

the letter giving 2 weeks notice of termination to be

issued by RPAD and compliance of this requirement is a

condition precedent for valid termination and this

condition precedent having not been complied, even on

this ground the termination is illegal.

46. Therefore, in conclusion, I hold that for all the

reasons noted supra, the finding of the Learned

Arbitrator holding the termination of the contract by

the BHEL as illegal, is perfectly in accordance with

law and certainly cannot be interfered in a section 34

petition.

47. Let me now consider the findings of the Learned

Arbitrator on each claim and counter-claim to determine

whether the same calls for interference in any manner.
52

CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

48. The first claim raised by the claimant is for unpaid

value of work which is claimed on the ground that there

were certain unjustifiable deductions from the RA bills of

the claimant. The Learned Arbitrator has held at

Paragraph 61 that, it is an admitted fact that Rs.

21,66,484 has been deducted from the RA bills and it is

the case of BHEL in written arguments at paragraph 303

that any and all deductions from RA bills have been

made in accordance with the terms of the contract. The

finding of the learned arbitrator at Paragraph 63 is that,

the reason why the amounts have been deducted is not

forthcoming and BHEL has also not produced any

evidence to show why this amount is not payable and

therefore, Learned Arbitrator has held that the claimant

is entitled to recover the said sum. This finding of the

Learned Arbitrator being a purely factual finding cannot

be interfered with in a section 34 petition.
53

CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

49. Insofar as another sum of Rs 7,85,519 is concerned,

which is deducted from the RA bill, it is the case of BHEL

that it is towards liquidated damages due to delay in

work. The finding of the Learned Arbitrator in this regard

is that there was extension of time for completion of work

by BHEL itself by admitting that delay is not attributable

to the contractor and also, time is not the essence of the

contract and the second and third extension of time

sought for by the contractor was not outrightly rejected

but the contractor was permitted to do the work. On this

ground, the Learned Arbitrator has held that, there

cannot be any deduction on the ground of liquidated

damages for delay in the work and therefore ultimately

the Learned Arbitrator has held that the claimant is

entitled to the principal sum due under this claim of Rs.

21,66,484 but in so far as interest component is

concerned, only awarded interest at rate of 10% percent

on the principal sum from date of termination till date of

claim petition. This finding of Learned Arbitrator also
54
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

cannot be interfered with, since, once it is held that,

BHEL set at large the time for completion of the contract

by not terminating the contract on lapse of time on 12-

09-2018 and permitted the claimant to continue the work

and also did not reject the request of claimant for II and

III Extension of time, it was impermissible for BHEL to

levy liquidated damages on ground of delay in the work.

50. Claim No. 2 which has been awarded is for recovery

and refund of retention money. In this regard the

Learned Arbitrator has held that the retention money

becomes payable on successful completion of the

contract and since the claimant has been prevented from

completing the contract due to illegal termination of the

contract, the claimant is entitled to recovery of the

retention money. This finding essentially depends upon

the finding regarding termination of the contract. Once it

is held that the finding of the learned arbitrator that the

contract was illegally terminated is in accordance with
55
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

law, it follows that since the contract was illegally

terminated and thereby, claimant was prevented from

completing the work by the illegal act of the BHEL, BHEL

cannot take advantage of its own wrong and hold on to

the retention money on the ground that, work was not

completed. Therefore, BHEL is bound to refund the

retention amount to the claimant. Therefore this finding

of the Learned Arbitrator also does not call for

interference.

51. Claim No 3 and 4A to 4C have been rejected and

therefore it is not subject matter of the present petition

since the claimant has not filed independent section 34

petition challenging that portion of the award rejecting

these claims.

52. Claim No. 5 consists of subclaims 5A to 5C. Sub-

claim 5A has been allowed towards illegal confiscation of

the claimants Plaint, machinery and equipment. In this
56
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

regard, the Learned Arbitrator has held at paragraph 100

of the award that, from the correspondence on record, it

is forthcoming that, after termination of the contract on

26-08-2019, the officers and workers of the claimant

were denied access to the work site and therefore the

claimant’s entire tools and machinery were lying in the

custody and care of the BHEL, for which BHEL is only

accountable. At paragraph 103, page 71 of the award, the

Learned Arbitrator has recorded the factual finding that

it was only in December 2020 that claimant was issued

gate pass and permitted to remove its equipment from

the work site. Although the claimant had claimed Rs 2.56

crores under this sub-claim, ¼ of the said amount was

deducted towards salvage value of the plant and

machinery and rent received from leasing out the same to

subsequent contractor and on this basis the Learned

Arbitrator has awarded Rs. 1,92,47,725. It is to be noted

that no interference is called for with the said finding of

the Learned Arbitrator because admittedly the contract
57
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

was abruptly terminated when the claimant was

proceeding with the work on 26-08-2019 and on the very

next day the claimant’s workmen were denied access to

the work site. Therefore obviously all the plant and

equipment which were being used for doing the work

were left lying at the work site. And the factual finding of

the Learned Arbitrator is that, from the date of

termination of contract on 26-08-2019 up to December

2020 that is for a period of nearly 1 year and 3 months,

the claimant could not have access to the plant and

machinery and in the meantime, the plant and

machinery would have deteriorated due to lack of timely

maintenance and therefore only the salvage value of the

same could be obtained. In the meantime, during the

said period, the said plant and machinery were leased

out by the claimant to subsequent contractor. After

deducting the salvage value and the rents that would

have been received, 3/4th of the claimed amount is

awarded. In the present petition, this finding is
58
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

challenged on the ground that, without any material

being produced by the claimant, the said sum has been

awarded. The above findings are recorded by the learned

arbitrator on the appreciation of the material on record

and the law is settled that in a section 34 petition, re-

appreciation of evidence is barred. Therefore, when these

findings are based on material on record and cannot be

said to be perverse, this finding of the Learned Arbitrator

does not call for interference.

53. Claim 5B which has been awarded is for refunding

of the performance bank guarantee. When the

termination of the contract is held to be illegal, it follows

that the BHEL could not have encashed the performance

bank guarantee and the reasons noted in respect of

Claim No. 2 [retention amount] are equally applicable to

this claim also and therefore the Learned Arbitrator was

perfectly justified in awarding this claim and this does

not call for interference.

59

CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

54. Claim 5C is for loss of overheads and profits due to

termination of the contract. The Learned Arbitrator has

relied upon the ruling of Hon’ble Apex Court in A.T. Brij

Paul Singh v. State of Gujarat, (1984) 4 SCC 59,

wherein it held that, “where in a works contract, the party

entrusting the work commits breach of the contract, the

contractor would be entitled to claim damages for loss of

profit which he expected to earn by undertaking the works

contract.”

55. However, the learned arbitrator has not granted

any amount under head of loss of overhead charges.

Insofar as loss of profit is concerned the Learned

Arbitrator has noted that even as per the say of the

BHEL, 49% of the work was completed which means that

59% of the work was pending and if the contract had not

been terminated the contractor could have performed the

remaining 59% of the work and earned proportionate
60
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

profit. Thereby, for the remaining 59% of the work, 10%

of the value of the balance work is awarded under the

head of the loss of profit. This finding is challenged at

paragraph 79 of the grounds of present petition by

contending that there is no reasoning whatsoever for

arriving at 10% as reasonable profit and the impugned

award does not rely on any formula to justify such

percentage. Conventionally, the contractor’s profit margin

is fixed at 10% of the contract value and therefore it

cannot be said that the finding of the learned arbitrator

awarding loss of profit at 10% of the value of the balance

work is either contrary to law or perverse. Therefore, this

finding of the learned arbitrator does not call for

interference.

56. Claim No. 6 and 7 have been rejected and

therefore, need not be considered in the present petition

since claimant has not filed any separate petition

challenging rejection of those claims.
61

CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

57. Now turning to the counterclaims, Counterclaim

No. 1 is for differential value of orders placed on

alternate vendors by invoking the risk and cost clause.

Once it is held that the termination of the contract was

illegal, it follows that, BHEL cannot impose the risk and

cost of award of balance work to subsequent contractor,

on the claimant. Therefore, BHEL is not entitled to

counterclaim No. 1 and Learned arbitrator was perfectly

justified in rejecting the same.

58. The counter-claim No. 2 is for liquidated damages

at 5% of the contract value. As already noted supra, the

contract provides for liquidated damages at the rate of

0.5% of the contract value per week of delay subject to

maximum of 5% of the contract value. In this regard, as

already noted at paragraph 155 of the award, the

Learned arbitrator has analyzed in detail the various

causes for delay and in respect of failure to hand over the
62
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

site, the Learned arbitrator has held that the claimant

cannot be held responsible for the delay on said ground.

In respect of delay in supply of duly approved

construction drawings the Learned Arbitrator has held

that the drawings were not furnished by BHEL and

claimant also did not execute the work even after

handing over the said drawings and thus, both parties

are equally responsible for the delay. In respect of non

availability and delay in issuance of free issue material,

the Learned arbitrator has held that though there was

some delay in supplying the cement, claimant had

requisite free issue materials to take up construction. In

respect of delay due to introduction of gate pass and

biometric confirmation by NTPC at the entry gate, it is

held that both parties are equally responsible for the said

delay. In respect of delay in progressive inspection, again

it is held that both parties are equally responsible for the

delay. In respect of delay in making payment against

claimant’s RA bills, it is held that neither party can be
63
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

held responsible for the said delay. Therefore, the

Learned Arbitrator has essentially held that both parties

were responsible for delay. This is a purely factual finding

which cannot be interfered in a Section 34 petition.

Therefore, when delay is not attributable solely to the

claimant, the BHEL cannot seek to levy liquidated

damages against the claimant on ground of delay.

Further, the Learned Arbitrator held that, although the

contract provided for liquidated damages, the same is

subject to proof of actual loss or damage suffered by

BHEL. In this regard, the Learned Arbitrator has relied

upon the law laid down by Hon’ble Apex Court in the

case of Kailash Nath Associates v. DDA, (2015) 4 SCC

136, wherein it is held that, where a sum is named in a

contract as a liquidated amount payable by way of

damages, the party complaining of a breach can receive

as reasonable compensation such liquidated amount

only if it is a genuine pre-estimate of damages fixed

by both parties and found to be such by the court. Else,
64
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

proof of damage or loss caused is a sine qua non for

award of damages. The Learned Arbitrator has held at

Paragraph 160 that, BHEL has failed to prove the loss or

damage caused to it, since, the documents produced

clearly demonstrate that, no L.D. [liquidated damages]

was deducted from the invoices of BHEL in respect of

subject contract by NTPC. Therefore, when loss or

damages suffered is not proved, no liquidated damages

can be awarded. These findings are factual findings

based on material on record and after appreciating the

documents relied upon by BHEL to show loss / damage

suffered and therefore, these factual findings which are

in consonance with the material on record cannot be

interfered, under Section 34 of the Act and therefore, the

finding of Learned Arbitrator rejecting this counter-claim

does not call for interference.

59. Counter claim No. 3 is for unaccounted free issue

material. In this regard, the Learned Arbitrator has held
65
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

that the free issue material would be at the work site and

once the contract was terminated, the claimant was

denied access to the work site. Therefore, there was no

chance of the claimant taking out the free issue material

from the work site and therefore the free issue material

would be utilized by the subsequent contractor and on

this ground denied this counterclaim. These findings

being factual findings and based on material on record

cannot be interfered in section 34 petition.

60. The next counterclaim raised is for charges for

demolition and reconstruction of wrongly located TR45

by the claimant. In this regard, the finding of the Learned

Arbitrator is that no material is produced to show that

the work was wrongly located by the claimant and no

material is produced to show the amount, if any, paid to

subsequent contractor for such demolition and

reconstruction and therefore disallowed this

counterclaim. Again, this finding is based on material on
66
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

record and purely factual finding and hence cannot be

interfered in section 34 petition.

61. The last counterclaim is towards dismantling site

office and allied construction of the claimant and even

this counterclaim is rejected for want of material in

support thereof and being a factual finding cannot be

interfered in the present petition. The other

counterclaims are only for interest and the cost of

arbitration and when all the counterclaims have been

rejected the question of awarding the cost of arbitration

or interest does not arise and therefore they were rightly

rejected by the Learned Arbitrator.

62. Therefore, in conclusion, the finding of the Learned

Arbitrator partly awarding the claims and rejecting the

counterclaims in toto does not call for interference in the

present petition.

67

CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

63. Before parting, the citations relied upon by Learned

counsel for petitioner needs to be taken note of. Reliance

is placed upon the following rulings in support of

propositions of law, as to when time can be considered

the essence of the contract; that when there is a promise,

there is obligation on the promisor to perform the

promise within reasonable time, even if time is not the

essence of the contract; that time can be made essence of

the contract by notice and even without notice, the

promisor is bound to perform the promise within

reasonable time under Section 46 of the Contract Act;

that Section 55 and Section 73 of the Indian Contract Act

are part of public policy and therefore, any findings

contrary thereto can be set aside under Section 34 on the

ground that the award is in conflict with the public policy

of India;

 AIR 1984 AP 110

 ILR 2008 Del 353

 2018 SCC Online Del 8913
68
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

 1998 (2) Mad LJ 751

 2002 (1) SCC 134

 AIR 1981 Pat 69

 1969 SCC Online Cal 40

 (1993) 1 SCC 519

 2003 SCC Online Ker 323

 1949 SCC Online MP 22

 1979 (2) SCC 70

 1983 SCC Online Del 236

 1957 SCC Online Pun 137

 AIR 1962 Pat 155

 2015 (4) SCC 136 – Kailashnath Associates case

which is already referred to supra.

 2010 SCC Online Del 821

 2021 SCC Online Del 4699

 2019 SCC Online Del 9037

 2024 SCC Online Del 5435
69
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

64. However, all these rulings are not applicable

because in the peculiar facts and circumstances of this

case, as already noted supra, BHEL initially extended the

contract by admitting that delay is not attributable to the

contractor and thereafter did not terminate the contract

when the extended time period came to an end, but

allowed the contractor to continue to and thereby setting

time for performance at large (in the words of the learned

arbitrator). And thereafter when although the claimant

sought for two additional extensions of time the BHEL

neither terminated the contract nor explicitly granted

extension and thereafter abruptly issued the notice dated

17-07-2019 calling upon the contractor to show progress

in 14 days and thereafter abruptly terminated the

contract and in this background on facts the Learned

Arbitrator has held that after setting at large the time for

performance of the contract thereafter no reasonable time

was fixed and no reasonable schedule was given for

completion of the work and therefore the abrupt
70
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

termination of the contract is illegal. The facts of the

present case being peculiar, the aforestated citations will

not come to the aid of the petitioner in the present case.

65. Reliance is also placed upon Batliboi

Environmental Engineers Ltd. v. Hindustan

Petroleum Corpn. Ltd., (2024) 2 SCC 375 and Unibros

v. All India Radio reported in 2023 SCC Online 1366

regarding computation of loss of profit.

66. In Batliboi Environmental Engineers Ltd. v.

Hindustan Petroleum Corpn. Ltd., (2024) 2 SCC 375 :

2023 SCC OnLine SC 1208 at page 399, it is held as

follows;

23. Ordinarily, when the completion of a
contract is delayed and the contractor
claims that s/he has suffered a loss arising
from depletion of her/his income from the
job and hence turnover of her/his business,
and also for the overheads in the form of
workforce expenses which could have been
deployed in other contracts, the claims to
bear any persuasion before the
71
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

arbitrator or a court of law, the
builder/contractor has to prove that
there was other work available that he
would have secured if not for the delay,
by producing invitations to tender
which was declined due to insufficient
capacity to undertake other work. The
same may also be proven from the
books of accounts to demonstrate a
drop in turnover and establish that
this result is from the particular delay
rather than from extraneous causes. If
loss of turnover resulting from delay is not
established, it is merely a delay in receipt of
money, and as such, the builder/contractor
is only entitled to interest on the capital
employed and not the profit, which should
be paid.

(Emphasis Supplied)

67. In Unibros v. All India Radio reported in 2023

SCC Online 1366, it is held as follows;

16. To support a claim for loss of profit
arising from a delayed contract or
missed opportunities from other
available contracts that the appellant
could have earned elsewhere by taking
up any, it becomes imperative for the
claimant to substantiate the presence of
a viable opportunity through compelling
evidence. This evidence should convincingly
demonstrate that had the contract been
executed promptly, the contractor could have
72
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

secured supplementary profits utilizing its
existing resources elsewhere.

17. One might ask, what would be the
nature and quality of such evidence? In our
opinion, it will be contingent upon the facts
and circumstances of each case. However, it
may generally include independent
contemporaneous evidence such as other
potential projects that the contractor
had in the pipeline that could have been
undertaken if not for the delays, the
total number of tendering opportunities
that the contractor received and
declined owing to the prolongation of
the contract, financial statements, or
any clauses in the contract related to
delays, extensions of time, and
compensation for loss of profit. While this
list is not exhaustive and may include any
other piece of evidence that the court may
find relevant, what is cut and dried is that in
adjudging a claim towards loss of profits, the
court may not make a guess in the dark; the
credibility of the evidence, therefore, is the
evidence of the credibility of such claim.

18. Hudson’s formula, while attained
acceptability and is well understood in
trade, does not, however, apply in a
vacuum. Hudson’s formula, as well as other
methods used to calculate claims for loss of
off-site overheads and profit, do not directly
measure the contractor’s exact costs.
Instead, they provide an estimate of the
losses the contractor may have suffered.
While these formulae are helpful when
needed, they alone cannot prove the
contractor’s loss of profit. They are useful
73
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

in assessing losses, but only if the contractor
has shown with evidence the loss of profits
and opportunities it suffered owing to the
prolongation.

19. The law, as it should stand thus, is
that for claims related to loss of profit,
profitability or opportunities to succeed,
one would be required to establish the
following conditions : first, there was a
delay in the completion of the contract;
second, such delay is not attributable to the
claimant; third, the claimant’s status as
an established contractor, handling
substantial projects; and fourth,
credible evidence to substantiate the
claim of loss of profitability. On perusal
of the records, we are satisfied that the
fourth condition, namely, the evidence to
substantiate the claim of loss of profitability
remains unfulfilled in the present case.
(Emphasis Supplied)

68. On this basis, it was argued for BHEL that without

evidence adduced by the claimant to show that the

claimant could have earned elsewhere by taking up any

other project, and evidence regarding other potential

projects the claimant had in the pipeline that could have

been undertaken if not for the delays, the total number of

tendering opportunities that the claimant received and
74
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

declined owing to the prolongation of the contract,

financial statements, etc., the claim for loss of profits

could not have been awarded by the Learned Arbitrator.

It is to be noted that, on facts, both the above rulings of

the Hon’ble Apex Court dealt with a fact situation where

the contractor was constrained to remain at the site

beyond the contract period and hence loss of profit was

sought for period beyond the contract period. In these

circumstances, Hon’ble Apex Court has said that for

such a claim it is necessary for the contractor to prove

that there were other contracts which the contractor had

to miss out on due to being stuck in the same project.

69. However, the case on hand is distinguishable, in

that, loss of profit is being claimed not for being at the

site beyond the contract period but for being unable to

complete the project and earn the estimated profit, due to

illegal termination of the contract. In this regard, the

Learned Arbitrator has relied upon A.T. Brij Paul Singh
75
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

v. State of Gujarat, (1984) 4 SCC 59 at page 63, as

follows;

8. Once it is held that the respondent was
guilty of breach of works contract, part of
which was already performed and for
performing which the appellant, a Poona
based contractor had transported machinery
and equipment from Poona to the work site
near Rajkot in Saurashtra, certainly he would
be entitled to damages. One of the heads of
damages under which claim is made is “loss
of expected profit in the work”. The claim
under this head as canvassed before the High
Court was in the amount of Rs 4,30,314.

9. It was not disputed before us that
where in a works contract, the party
entrusting the work commits breach of
the contract, the contractor would be
entitled to claim damages for loss of
profit which he expected to earn by
undertaking the works contract. What
must be the measure of profit and what proof
should be tendered to sustain the claim are
different matters. But the claim under this
head is certainly admissible. Leaving aside
the judgment of the trial court which rejected
the claim for want of proof, the High Court
after holding that the respondent was not
justified in rescinding the contract proceeded
to examine whether the plaintiff contractor
was entitled to damages under the head “loss
of profit”. In this connection, the High Court
referred to Hudson’s Building and
76
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

Engineering Contracts (1970), tenth edition
and observed that “in major contracts subject
to competitive tender on a national basis, the
evidence given in litigation on many occasions
suggests that the head-office overheads and
profit is between 3 to 7 per cent of the total
price of cost” which is added to the tender. In
other words, the High Court was of the view
that the claim under this head was
admissible. The High Court, however,
addressed itself to the question whether
adequate proof is tendered to sustain the
claim. In this connection, it was observed that
the loss of profit when it is sought to be
recovered on the percentage basis has to be
proved by proper evidence. Having settled the
legal position in this manner, the High Court
proceeded to reject the claim observing that
the bare statement of the partner of the
contractor’s firm that they are entitled to
damages in the nature of loss of profit at the
rate of 20 per cent of the estimated cost is no
evidence for the purpose of establishing the
claim. The High Court further observed that
the appellant has not proved by any primary
documents the basis of its pricing for the
purpose of quotation in reply to the tender
and more so when it has quoted at 7½ per
cent less than the original estimated cost and
in this view of the matter the claim for loss of
profit is unsustainable.

11. Now if it is well-established that the
respondent was guilty of breach of
contract inasmuch as the rescission of
contract by the respondent is held to be
unjustified, and the plaintiff contractor
77
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

had executed a part of the works
contract, the contractor would be
entitled to damages by way of loss of
profit. Adopting the measure accepted by
the High Court in the facts and
circumstances of the case between the
same parties and for the same type of
work at 15 per cent of the value of the
remaining parts of the work contract, the
damages for loss of profit can be
measured.

(Emphasis Supplied)

70. Reference may also be made to MSK Projects (I) (JV)

Ltd. v. State of Rajasthan, (2011) 10 SCC 573 :

(2012) 3 SCC (Civ) 818 : 2011 SCC OnLine SC 986 at

page 586, wherein it is held as follows;

38. In common parlance, “reimbursement”
means and implies restoration of an
equivalent for something paid or expended.
Similarly, “compensation” means anything
given to make the equivalent. (See State of
Gujarat v. Shantilal Mangaldas
[(1969) 1 SCC
509 : AIR 1969 SC 634] , TISCO Ltd. v. Union
of India [(2001) 2 SCC 41 : AIR 2000 SC
3706] , GDA [(2004) 5 SCC 65 : AIR 2004 SC
2141] and HUDA v. Raj Singh Rana [(2009)
17 SCC 199 : (2011) 2 SCC (Civ) 136 : AIR
2008 SC 3035] .)
However, in Dwaraka
Das v. State of M.P.
[(1999) 3 SCC 500 : AIR
1999 SC 1031] it was held that a claim by
78
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

a contractor for recovery of amount as
damages as expected profit out of
contract cannot be disallowed on ground
that there was no proof that he suffered
actual loss to the extent of amount
claimed on account of breach of contract.

39. In A.T. Brij Paul Singh v. State of
Gujarat
[(1984) 4 SCC 59 : AIR 1984 SC 1703]
, while interpreting the provisions of Section
73
of the Contract Act, 1972, this Court held
that damages can be claimed by a
contractor where the Government
is proved to have committed breach by
improperly rescinding the contract and
for estimating the amount of damages,
the court should make a broad
evaluation instead of going into minute
details. It was specifically held that where in
the works contract, the party entrusting the
work committed breach of contract, the
contractor is entitled to claim the
damages for loss of profit which he
expected to earn by undertaking the
works contract. Claim of expected
profits is legally admissible on proof of
the breach of contract by the erring
party. It was further observed that : (SCC pp.
64-65, para 10)

“10. … What would be the measure of profit
would depend upon the facts and
circumstances of each case. But that there
shall be a reasonable expectation of profit is
implicit in a works contract and its loss has to
be compensated by way of damages if the
79
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

other party to the contract is guilty of breach
of contract cannot be gainsaid.”

(Emphasis Supplied)

71. From the above law laid by Hon’ble Apex Court, it is

clear that the contractor is entitled to claim loss of profits

for failure to earn the profit as a result of the fault of the

employer. If the contractor claims loss of profit for period

beyond the contract period after completing the project

and the loss of profit is claimed for the period of

prolongation, then as per the law in Batliboi

Environmental Engineers Ltd. (supra) and Unibros

(supra), it will be necessary for the contractor to prove

that the contractor missed out on other projects due to

being stuck in the earlier project. However, where the

contractor claims loss of profit not for the period of

prolongation but on the ground that due to the fault of

the employer, the contractor could not complete the

project and earn the estimated profit, then it will not be
80
CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

necessary for the contractor to prove that there were

other projects which the contractor was unable to take

up due to being stuck in the current project. Therefore,

in the present case, even without adducing evidence and

proof of other projects which the claimant was unable to

take up, the Learned Arbitrator was perfectly justified in

awarding the claim of loss of profits.

72. For all the reasons noted supra, I hold that the

impugned arbitral award does not call for interference in

any manner and accordingly, answering the point for

consideration in the negative, I proceed to pass the

following :-

ORDER.

The petition under section 34 of the

Arbitration and Conciliation Act is

dismissed, with cost.

81

CT 1390_Com.AP 73-2024_Judgment.doc
KABC170013822024

Office to issue soft copy of this

judgment to both sides by email if

furnished.

[Dictated using Dragon Professional Speech Recognition
Software Version 15.3, transcript revised, corrected,
signed and then pronounced by me in open court on this
the 23rd day of January, 2025]

(Sri. S. SUDINDRANATH)
LXXXIII ADDL.CITY CIVIL AND SESSIONS JUDGE,
COMMERCIAL COURT, BANGALORE.

[ad_1]

Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here