Bharat Petroleum Corporation Limited vs Haldia Petrochemicals Ltd on 19 June, 2025

0
1


Calcutta High Court

Bharat Petroleum Corporation Limited vs Haldia Petrochemicals Ltd on 19 June, 2025

Author: Shampa Sarkar

Bench: Shampa Sarkar

                                                                        2025:CHC-OS:91



                  IN THE HIGH COURT AT CALCUTTA
               ORDINARY ORIGINAL CIVIL JURISDICTION
                       COMMERCIAL DIVISON



BEFORE :-
THE HON'BLE JUSTICE SHAMPA SARKAR


                            AP- 338 of 2022
                            GA COM 2 of 2024

                BHARAT PETROLEUM CORPORATION LIMITED
                                 VS
                     HALDIA PETROCHEMICALS LTD.


     For the Petitioner           :     Mr. Tilak Kr. Bose, Sr. Adv.
                                        Ms. Trisha Mukherjee, Adv
                                        Mr. Chetan Kr. Kabra, Adv.


    For the Respondent            :     Mr. Sabyasachi Chaudhury, Sr. Adv.
                                        Mr. Rajarshi Dutta, Adv.
                                        Mr. Shounak Mukhopadhyay, Adv.
                                        Mr. Debargha Basu, Adv.



     Hearing concluded on         :     21.03.2025



     Judgment on                  :     19.06.2025


Shampa Sarkar, J.

1. GA COM 2 of 2024 is an application filed by HPL (the award holder) for

certain reliefs and directions. The award holder prayed for a direction

upon the Registrar Original Side, High Court at Calcutta to
2
2025:CHC-OS:91
encash/invoke the bank guarantee for a sum of Rs. 15,65,50,000/-

furnished by the award debtor/BPCL and to transmit the entirety of the

amount of Rs. 15.5 crores under the bank guarantee, in favour of the

award holder. The award holder also undertook to furnish adequate

security. In effect, a modification of the order dated June 23, 2022

passed in AP 338 of 2022 was prayed for. Further direction was sought

upon the award debtor to furnish additional security of Rs. 2.3 crores.

This court had directed filing of affidavits to the said application and

proceeded to hear out the application for setting aside the award.

2. AP – 338 of 2022, is the application for setting aside the Award dated

December 30, 2021 passed by an Arbitral Tribunal, comprising of three

retired Hon’ble Judges. The petitioner (BPCL) was the claimant and the

respondent (HPL) was the respondent in the arbitral proceeding. The

parties entered into an Agreement for Sale and purchase of Naphtha on

May 25, 2017. The terms and conditions of sale and supply were clearly

specified in the agreement. Both the parties were signatories to the said

agreement. BPCL was the seller and HPL was the buyer.

3. Disputes and differences arose between the parties when HPL did not pay

the balance price of the goods sold and delivered between July 29, 2017

and August, 2017. The balance price was calculated by BPCL on the

average quotes of August, 2017, treating August as the loading month.

The justification was that the loading was completed on August 1, 2017

and a single Bill of Lading (B/L) was also generated at the request of HPL
3
2025:CHC-OS:91
in August, 2017. HPL had made payment on August 18, 2017, on the

basis of the split B/Ls which were provisionally raised in July and

August, 2017. According to BPCL, the price of the liquid cargo was to be

calculated on Free on Board (FOB) basis. The delivery of goods was

complete as soon as the cargo was dispatched in the vessel i.e. in August,

2017. HPL made a payment of Rs. 1,07,40,802.96/-. BPCL claimed a

further sum of Rs. 10,69,81,787.05/-. The agreement was to remain in

force for a period of one year starting from May 1, 2017 to April 30, 2018,

for supply of 240 TMT +/- 10% of Naphtha per annum.

4. Clause 18 of the agreement provided that any dispute or difference of any

nature whatsoever, any claim, cross-claim or set off or any dispute with

regard to rights and liabilities, omission and action of the parties arising

out of the agreement, were to be resolved through arbitration. The

tribunal would comprise of three arbitrators, one to be appointed by each

party and the third arbitrator to be appointed by the two arbitrators in

accordance with the Arbitration and Conciliation Act, 1996 (in short ‘A &

C Act’). The place of the proceedings was agreed to be Kolkata.

5. The case as run by BPCL, in the statement of claim is as hereunder :-

a. HPL being a naphtha based petro-chemical industry engaged in

the production of polymers and chemicals, including linear low density

polyethylene, High Density Polyethylene, Polypropelene, Benzene,

Butadiene, Cyelopentane, C4 Hydrogenated (LPG), Pyrolysis Gasoline,

Carbon Black Feedstock, Motor Spirit, etc., requested BPCL for supply
4
2025:CHC-OS:91
of one parcel of 20 TMT quantity of Naphtha (LAN) +/- 10%, every

month during May 17 to April 2018. The petitioner accepted and an

agreement was entered into on May 25, 2017.

b. Clause 5 of the agreement provided that the price of Naphtha

would be based on the formula FOB + Market Premium + $5). As per

the said clause, average of Naphtha MOPAG (average of platts quotes)

for all the quotes during the loading month, would be considered as

FOB for any parcel loaded in a month. The market premium would be

calculated on the average of Argus Premium and Platts Premium for the

period taken for FOB. The exchange rate would be the average available

RBI reference rate of US Dollar to Indian Rupee conversion, starting

from the pricing date of the first FOB quote, till the last date of FOB

quote considered for pricing.

c. The provisional price as per the above formula would be arrived at

after taking the average of five quotes prior to the Bill of Lading (B/L)

date. Excise invoice would be generated on the basis of the provisional

price. The agreement further provided that in case the final billing rate

arrived at as per the agreed formula was higher than the rate already

billed, a supplementary invoice having the excess element would be

issued by BPCL to HPL. In case the final bill arrived at as per the

formula was less than the bill already raised, a credit note would be

issued by BPCL to HPL. As per clause 6 of the agreement, the vessel

engaged for transfer of the cargo from the load Port (Kochi) to the
5
2025:CHC-OS:91
discharge Port (Haldia), was to be appointed by HPL only upon

executing a Charter Agreement with the vessel’s owner. All the charges,

expenses, losses, damages and claim of any manner with regard to the

vessel, were to be borne by HPL.

d. On the basis of the said agreement, HPL placed an order for the

month of July, 2017 for supply of 41.8 KT of Naphtha. Accordingly, a

vessel named MT Sanmar Sonnet was chartered by HPL, to carry the

cargo from Kochi Port to the plant at Haldia. The loading was scheduled

during the laycan period of July 27 – July 28, 2017.

e. The vessel reported on July 28, 2017 at 5:30 P.M. at Kochi Port for

loading of the product. The vessel could not be berthed on its arrival.

The loading of Naphtha could be started on July 29, 2017 at 11:18

A.M. The loading of the entire 41.8 kg Naphtha was completed on

August 1, 2017 at 11:36 A.M.. According to BPCL, the time taken was

the standard loading time for loading 41.8 kg of Naphtha in a vessel.

f. On completion of the loading, two B/Ls one for the quantity of

Naphtha loaded in the month of July and other for the quantity of

Naphtha loaded in the month of August, were raised by BPCL.

g. HPL raised objections to the splitting up of the B/L. HPL insisted

on one single B/L to be dated as August, 1, 2017. Mr. Suchandan

Chatterjee, DGM Commodity Business Team of HPL, by an e-mail had

observed that as loading was a continuous process under the SOF, two

different dates were not proper. The same would create problems in the
6
2025:CHC-OS:91
system of HPL and there would be a mismatch. BPCL was requested to

change the date of the B/Ls to the loading completion date of August 1,

2017 and to send the revised B/L to HPL, to enable synchronization of

the B/L and the invoice.

h. By e-mail dated August 4, 2017, Mr. Raman Shahi, Area Manager

Industrial, Kolkata (BPCL), put Mr. Suchandan Chatterjee on notice

that, as the loading of the vessel Sanmar Sonnet was completed on

August 1, 2017, invoicing had been done on the same date. It was

specified in the e-mail that final pricing would be arrived at once BPCL

got all the quotes for the month of August, 2017. The factum of

provisional pricing of the cargo loaded on Sanmar Sonnet was informed

to HPL. HPL disagreed with the provisional pricing, and communicated

its own calculation. By an e-mail dated August 10, 2017, an Officer of

BPCL explained the provisional pricing calculations that had been

provided on the basis of “Around B/L” quotes and not prior quotes. It

was explained that final pricing would be arrived at upon taking into

consideration all the quotes published in the loading month i.e. August,

2017 and the difference in price / calculations, would be settled

through debit or credit notes. Thereafter, BPCL requested payment as

per the calculations attached to the e-mail dated August 10, 2017. On

the basis of provisional pricing, the claimant raised an invoice for Rs.

1,435,191,955.00.

7

2025:CHC-OS:91
i. Although, at HPL’s request, BPCL prepared a single B/L dated

August 1, 2017 i.e. on the date when the loading was completed, but

HPL did not pay the final price. The single B/L was handed over to HPL

on August 14, 2017. The final invoice was based on the average quotes

for the month of August (treating August 2017 as the loading month).

HPL made payment on August 18, 2017, on the basis of the two B/Ls.

Objections were raised by BPCL by e-mail dated August 30, 2017, to

which HPL replied on September 4, 2017, inter alia, contending that

the issue was not with regard to a single or a split up B/L, but the

enhanced price claimed by BPCL was in deviation to the agreed terms.

BPCL contended that the provisional invoice dated August 1, 2017,

amounting to Rs.143,51,91,955/- was based on the provisional pricing

formula laid down in the agreement for sale and supply of 41.84 kg of

Naphtha. Platt’s quotes dated July 28, July 31, August 1, 2 and 3 of

2017, were taken into consideration in arriving at the net average price

of Naphtha per metric-ton i.e. Rs. 29,067.19/-. The provisional invoice

was raised on the basis of such rates. HPL made payment of Rs.

133,29,18,214.93/- on August 18, 2017. As per the agreed terms, the

final price was payable to BPCL on the basis of average quotes for the

loading month. The final B/L issued by the master of the vessel was

dated August 1, 2017. The agreement provided that the provisional bill

would be adjusted either by debit or credit notes. The final bill was

calculated and one debit note dated August 31, 2017, for the
8
2025:CHC-OS:91
differential amount of Rs. 66,94,251/- was sent to HPL. HPL made

further payment of Rs.1,07,40,802.96/-. Rs. 98,227,188.11/- was due

and payable as the principal due, according to BPCL.

j. BPCL had placed the product safely on board and thereby handed

over possession of the goods on August 1, 2017. The delivery was

complete on August 1, 2017. As the pricing was on FOB basis, the sale

got completed once the entire product was free on board. As per clause

8 of the agreement, title of the goods passed from BPCL to HPL at the

disconnection of the last permanent flange. In the present case, loading

started on July 29, 2017 and the flange was disconnected on August 1,

2017. Final pricing of average quote of August 2017, was taken into

consideration by BPCL for claiming the differential amount and

generation of the debit note. The debit note was issued in connection

with the final pricing for the goods delivered and sold. BPCL, by an

Advocate’s letter dated November 27, 2017, informed HPL that an

amount of Rs, 98,227,188.11/- was due and payable upon the final bill

having been raised. The method of calculation as to how BPCL had

arrived at the figure of Rs. 98,227,188.11/-, was also provided in the

letter. HPL denied such liability to pay and emphasized that the

payment had already been made and nothing was due and payable.

According to HPL, whether payment was made as per the single B/L or

Split B/Ls was a non-issue. BPCL contended that, the provisional

invoice considering the date of the Bill of Lading (B/L) as August 1,
9
2025:CHC-OS:91
2017 was not objected to by HPL. Upon becoming aware of the upward

trend in the price of Naphtha in the month of August, 2017 and its

impact on the final price of Naphtha loaded on August 1, 2017, HPL

changed its mind. According to BPCL, the entire loading of Naphtha

was a single transaction and the agreement did not provide for splitting

up of invoices. It was BPCL’s case that as the entire transaction was

one and continuous, the loading month should be considered as one,

i.e. the month when the loading was completed. Accordingly, a claim

was made for a sum of Rs. 10,69,81,787.05/- in respect of the balance

price of Naphtha sold and supplied, along with interest.

6. The calculation of the claim was as follows :-

“A. Principal

Invoice No. Date Invoice Amount Amount Received
Provisional – 01.08.17 1,435,191,955.00 1,332,918,214.93
4550013114
Debit Memo No 31.08.17 6,694,251.00 10,740,802.96
9646950000
Total 1,441,886,206.00 1,343,659,017.89
Balance 98,227,188.11
Principal Amt

B. Interest

Principal Amount 98,227,188.11
Interest @SBI Base Rate (9% till 30 th Sept 2017) + 10%
1%
Days (16 – 30 Sept) 15
Total interest for Sept 2017 403673/-

              Interest @ SBI Base Rate (8.95% from Oct 1st to         9.95%
                               Dec 2017) +1%
                     Days (1st Oct to 31st Dec 2017) 92.
                   Total Interest for 1st Oct 17 to Dec 17          2463484.05
              Interest @ SBI Base Rate (8.65% from Oct 1st to         9.65%
                               Dec 2017) + 1%
                   Days (1st Jan 18 to 31st March 18) 90
                    Total interest from Jan 18 to Mar 18            2337268.84
                                         10
                                                                                     2025:CHC-OS:91
             Interest @ SBI Base Rate (8.70% from 1st April to             9.70%
                                 Aug 17) +1%
                       Days (1st April 18 to 14 Aug 18)
                Total interest amount for April 18 to 14th 18           3550172.78
                          Total (Principal + Interest)                10,69,81,787.05



7. The statement of claim was filed before the learned Arbitral Tribunal with

the above claim and the following prayers were made:-

a) An Award that the Claimant is entitled to receive an amount
of Rs 10,69,81,787.05 from the Respondent as the balance
consideration money as pleaded in paragraph 17.

b) Interest on award @ 18% per annum until realization.

              c)    Costs.
              d)    Such other or further other order or orders."

8. HPL filed a counter-statement and also made a counter-claim as

hereunder :-

              "Particulars                                           Amounts (INR)
               Claim on account of risk purchase                 :   11,38,35,602
               Demurrage claim                                   :   46,50,000
               Dead freight claim                                :   6,40,000
               Excess payment refund claim                       :   2,27,72,651
               Principal amount claimed                          :   14,18,98,253
               Interest at the rate of 12% per annum on
               the Principal amount                        : 98,38,208

                                             Total Claim         :15,17,36,461"

9. BPCL filed its rejoinder to the counter statement of facts and the counter-

claim filed by HPL. BPCL did not adduce any oral evidence. It was agreed

in the fourth sitting dated November 1, 2018, that no oral evidence would

be adduced by either of the parties. However, HPL decided to adduce oral

evidence and produced two witnesses. Arguments commenced from

December 14, 2019. Forty sittings were held and the tribunal made and
11
2025:CHC-OS:91
published its final award on December 30, 2021. The award was as

follows :-

“The Award :

9. In the result –

a) The claim and the counter claim put forth by the claimant BPCL and the
respondent HPL respectively, can not be allowed, accordingly, both the
claim of BPCL and counter claim of HPL, arising out of the pricing
dispute is dismissed.

b) The respondent’s counter claim for dead freight is allowed to the extent
ie: USD 9985.94 @ the conversion rate as on 05 01 2018.

c) HPL shall also be entitled to interest on the said amount in (b) above after

7 days from 05 01 2018 as specified in paragraph 6.16 and 6.17
hereinbefore till the date of the Award.

d) The respondent’s counter claim for demurrage is allowed to the extent as
specified in paragraph 7.22 hereinbefore (INR 21,61,476.55 and INR
5,79,338.00);

e) HPL shall be entitled to interest on the above amounts at (d) ie: (i) on INR
21,61,476.55 for MT Jag Prerana after 15 days from the date of the
respective original debit note raised after 10.05.2018 (paragraph 7.7
hereinbefore) and (ii) on INR 5,79,338.00 for MT Sanmar Sonnet after 15
days from the date of the respective original debit note raised after
25.04.2019 (paragraph 7.9 hereinbefore), over the respective transactions
at the same rate of interest as provided in C1.5, till the date of award.

f) The respondent’s counter claim for risk purchase is allowed to the extent
as specified in paragraph 8.29 and 8,30 hereinbefore at INR
11,38,35,602.00;

g) The respondent shall be entitled to interest on the above amounts at (f),
as provided in C1.5, for the period from 15 days after the date of debit
note raised by HPL after 26.04.2018 (the payment date to Saudi Aramco).

h) In the facts and circumstances of the case, no cost is awarded against
any of the parties;

i) The Award shall carry interest @7% per annum simple till realization.”
12

2025:CHC-OS:91

10. Mr. Tilak Bose, learned Senior Advocate appearing for BPCL submitted

that the dispute had arisen on account of non-payment of the differential

price of goods supplied by BPCL. HPL did not ever raise any claim by way

of refund or under any other head. As a counter-blast to the claim made

by BPCL, the counter-claim had been filed. Mr. Bose contended that even

though the scope of interference by a court under section 34 of the A & C

Act, 1996 was limited, but the law had permitted the Courts to interfere

when an award was either unreasoned or based on extraneous

consideration, or when the terms and conditions of the contract were

ignored or misinterpreted. According to Mr. Bose, the final price was

payable on average quotes for the loading month. The price of cargo was

to be calculated on FOB basis i.e. free on board. The delivery of the goods

was completed as soon as the dispatch of the vessel was complete on

August 1, 2017. The title passed when the flange was disconnected. B/L

was issued by the Master of the vessel on August 1, 2017. Even if loading

commenced on July 29, 2017, the date of completion of loading would be

considered to be the loading month. The B/L for August 1, 2017 was

issued at the request of HPL. HPL also understood the loading month to

be August, 2017, even though the loading began on July 29, 2017. It was

HPL’s own understanding that loading was a continuous process and a

single B/L for the month of August, 2017 should be initiated. The manner

of payment made by HPL was wrongly sustained by the learned Arbitral
13
2025:CHC-OS:91
Tribunal. HPL made payments of the provisional invoice on the quantities

mentioned in the split B/L dated July 29, 2017 and August 1, 2017. In

the split B/L dated July 31, 2017, average price for July 2017 had been

taken and in the B/L of August 1, 2017, average price of August 2017

had been taken. At the request of HPL, a single B/L dated August 1, 2017

was prepared. E-mails were exchanged between the parties. The Arbitral

Tribunal did not appreciate that, as one final B/L was raised at the

request of HPL, as a natural corollary to such request, only a single

invoice should be prepared on the basis of the average quotes of August

2017. Such was the term in the agreement, which was ignored by the

tribunal. The learned Arbitral Tribunal did not appreciate that the

provisional invoice was replaced by the final invoice dated August 1,

2017. The tribunal failed to determine the actual meaning of the

expression ‘loading month’. The calculation of the final invoice was to be

made on the basis of the price for the loading month in terms of the

contract. The award was based on misinterpretation of the clauses of the

contract. The tribunal gave its own interpretation to the terms and

conditions of the agreement entered into between the parties. The

tribunal had re-written the agreement. The award was liable to be set

aside on the ground of perversity and patent illegality.

11. Mr. Bose relied on clause 5 of the agreement in order to support his

contention that the price of Naphtha was agreed to be calculated on the

basis of the quotes for the loading month and the provisional pricing
14
2025:CHC-OS:91
would not be final and binding. The contract had made a special provision

for raising a final bill and a supplementary invoice. The final billing rate

would be in terms of the average quotes of the loading month. In this

case, the loading month would be August, 2017, as the loading was

completed on that date. Disconnection of the hose took place on August

1, 2017. Parties also understood August 2017 as the loading month,

which the tribunal failed to appreciate. Clause 5 of the agreement was

relied upon. The relevant portion reads as follows:-

“5. PRICE:

Naphtha supplies will be made on the pricing based on formulae
(FOB+ Market Premium + $5), wherein FOB and Premium shall be
worked as below:-

FOB: Average of Naphtha MOPAG (Average of Platts quotes) for all-
the-quotes during the loading month (M) will be considered as FOB
for any parcel loaded in a month (M).”

12. Clause 7c was relied upon to explain the commencement and conclusion

of laytime. It was urged that clause 7c provided that laytime would cease

upon disconnection of the hose. Clause 7c reads as follows :-

“7c. Lay time shall commence 6 hours after NOR (Notice of Readiness)
and shall cease upon hose disconnection.”

13. Clause 8 of the agreement was relied upon to urge that disconnection of

the last permanent flange indicated that the entirety of the cargo had

been loaded in the vessel tank. As the supply was on FOB basis, it meant

that the supply was completed and the obligation of BPCL was fulfilled
15
2025:CHC-OS:91
upon the entire cargo being loaded on the vessel on August 1, 2017.

Clause 8 reads as follows :-

“8. Delivery & Risk of Property :

Title and risk of loss of the cargo (including but not limited to
contamination, evaporation, etc.) shall pass from the BPCL (seller) to
HPL (buyer) at the disconnection of the last permanent flange at loading
terminal.”

14. Mr. Bose urged that the definition of FOB in the Agreement, was ‘parcel

loaded in a month’. It was treated as a unit. The expression ‘parcel loaded

in a month’ should be read in conjunction with the recital of the

agreement. The same reads as follows:-

“Whereas HPL had requested BPCL to supply one parcel of 20 TMT
quantity of Naphtha every month”.

15. The same meaning was attached to the parcel size of 20,000 MT as would

appear in clause 7b of the agreement. Even if the loading of cargo

commenced in a particular month and spilled over to the next month, by

virtue of clause 8 of the agreement, the title did not pass from BPCL to

HPL until disconnection of the last permanent flange. The title passed on

August 1, 2017 and the parcel loaded in a month should be the month of

disconnection of the hose. Clause 7 b reads as follows :-

“7b Total Allowed lay time at load port shall be Thirty Six (36) hours for a
parcel size of 20,000 MT. Total allowed lay time shall be increased or
decreased on prorate basis (SHINC) with actual loading quantity.”

16. It was urged that the interpretation given by the tribunal, to the

expression ‘parcel’, as a unit of the cargo supplied, to be taken separately
16
2025:CHC-OS:91
for the month of July and August, was absurd and would defeat a

common sense approach to commercial transactions arising out of FOB

contracts. A common man, with a reasonable amount of prudence, would

find the reasons assigned by the tribunal and the interpretation of the

tribunal, to be shocking. The GST return was calculated by BPCL on the

basis of the final pricing and was paid. Once BPCL had altered its

position by making such payment on the basis of the final pricing, which

was within the knowledge of HPL, HPL was estopped from disputing the

final invoice. Reliance was placed on the various communications

between the parties in support of the contention that HPL had agreed to

make payments as per the final B/L dated August 1, 2017, on the basis

of the invoices and the supplementary bill raised. Several

documents/letters dated 4.8.2017, 5.8.2017, 10.8.2017, 11.8.2017,

12.8.2017, 14.8.2017, 22.8.2017, 30.8.2017, 4.9.2017 and 5.9.2017 were

ignored by the tribunal. The request for a single B/L was to enable HPL to

synchronize the B/L with the invoice. HPL had requested for a revised

B/L and stated that non-receipt of documents would delay BPCL’s

payment. The single B/L dated August 1, 2017, was for the entire

quantity supplied and prepared at the repeated request of HPL. HPL had

asked its agents to facilitate release of a single B/L, to be prepared afresh,

for the entire quantity dated August 1, 2017 and to replace the split B/Ls

issued earlier. The shipping agent of HPL collected B/L from BPCL’s office

as per instruction of HPL. BPCL wrote to HPL, inter alia, stating that the
17
2025:CHC-OS:91
final pricing has been fixed on the quotes for the month of August 2017.

BPCL wrote to HPL, stating that the transaction involved GST

implications. In spite of providing all the requested relevants documents

within August 14, 2017, HPL had made payments on the basis of two

split bills without considering that the payment of the GST component

was made as per the final bill and the debit note should be honoured.

Reference was made to the decision of Delhi Metro Rail Corporation

Limited vs Delhi Airport Metro Express Private Limited reported in

(2024) 6 SCC 357, in support of the contention that the award should be

set aside on the ground of non-consideration of vital evidence and specific

terms of the agreement.

17. Mr. Bose contended that the claim for differential pricing and the prayer

for payment of the deficit amount which was raised in the final invoice,

should have been directed by the learned tribunal. The documents relied

upon would show that the parties had agreed that in spite of provisional

pricing on the basis of five average quotes for the loading month, a final

pricing would be made and a final invoice would be raised. The parties

were conscious that there would be a differential amount i.e. payment

either in excess of or lesser than the provisional pricing which was to be

adjusted by debit or credit notes. Such agreement was on the

understanding of the fact that quotes could vary from month to month

and the pricing was to be made on the average quotes of the loading

month, i.e., the month when the hose was disconnected. The learned
18
2025:CHC-OS:91
tribunal had rewritten the terms of the agreement by interpreting ‘parcel’

as a single and separate unit for July and August.

18. Mr. Bose then proceeded to address on the illegality and perversity in

allowing the counter claims for demurrage, dead freight and risk

purchase. With regard to the counter-claim for demurrage, Mr. Bose

contended that the vessel used for transfer of the cargo from the load port

at Kochi to the discharge port at Haldia, was to be provided by HPL. A

charter party agreement was to be executed with the vessel owner.

Reference was made to clause 6 of the agreement. It was submitted that

as per clause 7, delay in loading would be to the account of BPCL. All

subsequent demurrage charges were to be borne by HPL. Clauses 7a and

7c of the agreement were placed.-

“7a Demurrage (if any) at load port will be on BPCL account.
7c Lay time shall commence 6 hours after NOR (Notice of Readiness) and
shall cease upon hose disconnection.”

19. Clause 7g provided that HPL would provide the vessel owner’s demurrage

claim and debit note, to prove the final demurrage applicable for the load

port. The same was to be provided within 90 days from completion of

discharge of cargo. Clause 7g reads as follows :-

“7g Buyer shall provide vessel owner’s demurrage claim, relevant portion
of charter party mentioning demurrage PDPR (Per Day Prorate), and debit
note from HPL regarding the final demurrage applicable for load port
within 90 days of completion of discharge of the cargo. Seller will respond
to the claim by acceptance or counter within 15 days of claim failing
which the Buyer’s claim shall be deemed to have been accepted by Seller
19
2025:CHC-OS:91
and buyer shall raise debit note accordingly. Seller shall settle the claim
within 15 days from date of debit note.”

20. HPL had raised a demurrage claim in respect of three vessels, namely,

M.T. Jag Prerana (B/L dated 03.06.2017), M.T. Sanmar Sonnet (B/L dated

31.7.2017 and August 1, 2017) and M.T. Sanmar Sonnet (B/L dated

30.9.2017). In respect of M.T. Sanmar Sonnet (B/L dated 31.7.2017 and

1.8.2017), claim for demurrage was disallowed. For M.T. Jag Prerana and

M.T. Sanmar Sonnet the counter-claims for demurrage were allowed. Mr.

Bose submitted that the basis of the calculation was incorrect as the split

B/Ls were replaced by the final B/L dated August 1, 2017. The tribunal

wrongly held that losses were suffered at the load port, although there

was no evidence before the learned tribunal. The two invoices raised by

the shipping company did not specify that the demurrage was on account

of the losses suffered at the load port. The finding of the learned tribunal

that the demurrage was suffered “admittedly” at the load port was

perverse and based on no evidence. The agreement provided that

demurrage would be paid by BPCL only if there was delay in loading.

Subsequent demurrage charges would be payable by the buyer. Mr. Bose

submitted that the required documents as per clause 7(g) were not

submitted. Moreover, the claim for demurrage was made much beyond

the period of 90 days. Reliance was placed on the decision of Ssanyong

Engineering and Construction Company Limited vs. National

Highways Authority of India (NHAI) reported in (2019) 15 SCC 131, on
20
2025:CHC-OS:91
the proposition that findings based on no evidence would render the

award unsustainable on the ground of patent illegality.

21. With regard to the claim for dead freight, Mr. Bose relied on clause 3 of

the agreement and further submitted that dead freight could be allowed if

the loss was suffered when the quantity loaded was below the quantity/

volume, nominated by the buyer. The calculation of dead freight would be

the difference between actual per Metric Ton freight incurred and the

freight cost in case the buyer’s nominated quantity had been loaded.

Clause 3 reads as follows :-

“3. DEAD FREIGHT CLAUSE :

Dead freight loss due to quantity loaded blow the cargo volume
nominated by the Buyer shall be on Seller’s account. It shall be
calculated based on the difference between the actual per MT freight
incurred and the freight cost in case the buyer’s nominated quantity had
been loaded. [(Total freight/loaded Qty) (Total freight/Buyer’s nominated
Qty)] * Loaded Qty.

In case of dead freight loss, if any, HPL shall send a debit note to BPCL,
payment of which to be done by BPCL through electronic Transfer within
7 days from the date of issuing of Debit Note. Conversion rate would be
as per RBI reference for the pricing period of cargo.”

22. There was no evidence which would indicate that loss was sustained by

the buyer on account of less cargo being loaded for the relevant month i.e.

December 2017. The award itself recorded that the vessel owner had

raised a an invoice for a lumpsum freight charge of $ 67.60 as per the e-

mail dated December 13, 2017. BPCL had loaded 19971.88 MT. On the

basis of such difference, dead freight for 453.12 MT had been calculated.
21

2025:CHC-OS:91
Such calculation was not permissible because it was a lumpsum freight,

and the actual per MT freight could never be worked out. In the case in

hand, the actual per MT freight would be the same as freight cost and

therefore there would to be no difference. Unless loss was proved, dead

freight was not payable. Section 73 and 74 of the Indian Contract Act

was relied upon to show that payment for damages could be awarded only

if loss had been sustained. Reliance was placed on the decision of the

Hon’ble Apex Court in Kailash Nath Associate vs. Deuli Development

Authority reported in (2015) 4 SCC 130.

23. The next submission of Mr. Bose was on the illegality in allowing the

counter-claim under the head, risk purchase. According to Mr. Bose, the

tribunal had misconstrued the contractual provisions. No man, with

reasonable prudence, would have allowed such counter-claim. The claim

was de hors the provisions of the contract. Allowing such claim was in

effect, re-writing the contractual provisions. The tribunal acted in excess

of jurisdiction and went beyond the scope of the dispute. Judicial

interference under section 34 of the A & C Act was permissible in this

case. The tribunal failed to consider the meaning of ‘Laycan’ which was

March 4/5 of 2018. The first date was the earliest when the ship was to

be made available. The second date was the date of cancellation, i.e. the

date on which the person entrusted with the loading could cancel the

agreed ‘laycan’. Reliance was placed on the definition of Laycan, Laytime

and Notice of Readiness, by referring to the Dictionary of Shipping Terms
22
2025:CHC-OS:91
(4th Edition) by Peter Brodie, LLP Publication. It was submitted that, if the

ship did not arrive, the seller could cancel the laycan. Here, before the

ship was brought by the buyer, the cargo offered was cancelled. Clause 19

of the agreement provided that only when the seller failed to comply with

the terms and conditions mentioned under clause 6, relating to cargo

laycan nomination, the buyer, in addition to taking other legal steps,

would be entitled to make risk purchase at the seller’s cost. There was no

failure on the part of the seller to comply with the terms and conditions

mentioned in clause 6. Clause 6 had no manner of application in the facts

of the case. The incidence of breach contemplated under the agreement

did not arise. No vessel had been nominated and no Charter Party

Agreement had been executed by HPL at the relevant point. Although, the

goods were offered by the seller for the laycan period, HPL decided to

reject such goods and refused to enter into a Charter Party Agreement. No

vessel was brought to the load port to enable the seller to load the cargo.

Several correspondences were relied upon in support of such contentions.

24. Clause 6 reads as follows:-

“6. CARGO/LAYCAN NOMINATION:

The vessel engaged for the transfer of the cargo from load port (Kochi) to
the discharge port (Haldia) shall be appointed by HPL only, who shall
appoint the said vessel by executing the charter agreement with the
vessel owner. All the charges, fee, expense, loss, damage, claim of any
manner whatsoever with regard to the said vessel shall be borne by HPL.”

25. The tribunal totally ignored such facts. Clause 6 of the agreement

contemplated a situation where the buyer was agreeable to purchase
23
2025:CHC-OS:91
goods to be supplied by the seller and the vessel was arranged. In the

instant case, although, the goods were offered by BPCL for the period 3rd

to 5th March, 2018, HPL, in its wisdom, decided to reject such goods and

refused to enter into a Charter Party Agreement for arrangement of the

vessel. No vessel had been brought to the load port to enable the seller to

load the cargo. Mr. Bose relied on the e-mails dated 3.2.2018, 5.2.2018 (4

in number), 6.2. 2018 (2 in number), 12.2.2018, 16.2.2018, 20.2.2018 (3

in number), 21.2.2018, 23.2.2018 (3 in number), 24.2.2018, 26.2.2018 (3

in number), 8.3.2018, 15.3.2018, 20.03.2018 and 04.4.2018. Mr. Bose

submitted that the alleged purchase of the cargo under the risk purchase

clause, was made by HPL in the month of April 2018 i.e. much later than

the laycan period. Damages on account of risk purchase could not be

permitted if there was no spot purchase during the same laycan period.

Moreover, no notice had ever been issued by HPL to the petitioner,

regarding invocation of the risk purchase clause on account of the failure

of the petitioner to keep its commitment of loading the goods during the

laycan period. HPL’s document with regard to the risk purchase was

fabricated. There was no evidence of risk purchase during the relevant

laycan period. The contract contemplated supply of Naphtha by BPCL up

to 20 TMT +- 10%. BPCL fulfilled the supply within the stipulated period,

i.e., 219 TMT Naphtha by December 2017. Thereafter, by reason of

overhauling of its tanks, supply was disrupted. This aspect had not been

looked into by the learned tribunal. BPCL could not supply cargo in
24
2025:CHC-OS:91
January, February, March and April 2018. On account of such non-

supply of cargo between January and April, there was no complaint from

HPL. Clause 2 of the agreement provided that HPL undertook to purchase

a minimum quantity of 20 TMT of Naphtha +/- 10% at buyer’s option,

every month, during the validity period of the agreement. This could not

be treated as a firm commitment on the part of BPCL to supply as per

such clause. The failure could not be regarded as a breach. HPL, by its

conduct had waived any objection to the non-supply of the cargo between

January to April 2018, when the overhauling work was going on. Mr.

Bose further submitted that the goods were offered to HPL, but HPL

refused on the ground that the specifications of the goods i.e.,

composition of the various elements of Naphtha, as provided in the

agreement, had not been met. According to Mr. Bose, one or two

deviations may have occurred, but majority of the parameters had been

satisfied. Even the cargo which was offered by the petitioner and rejected

by the buyer on February 26, 2018, had met with the contractual

specifications. The rejection of the goods by HPL, was contrary to the

terms and conditions of the contract. The petitioner offered goods which

fulfilled the guaranteed specifications as per annexure 1 of the contract.

Such fact was completely ignored by the tribunal and the tribunal relied

on random isolated parameters, which were not the guaranteed

specifications. The rejection of the goods by the buyer, was a breach of

the agreement by the buyer, but the learned tribunal ignored such
25
2025:CHC-OS:91
breach. Award of damages on account of risk purchase of Naptha from

Saudi Aaramco, sometime in 2018, was not covered by the agreement.

The quality of the goods purchased from Saudi Aaramco also was not as

per the agreed specification. The tribunal did not consider whether the

goods purchased from Saudi Aaramco met the guaranteed specifications.

Damages on account of risk purchase could be allowed only if similar

goods were purchased by HPL during the relevant laycan nomination, on

account of the seller not being able to load the goods during the laycan

nomination. In the present case, the scenario was completely different. It

did not call for award of damages. Such award of damages suffered from

perversity. A further vital issue was ignored by the tribunal, inasmuch as,

the time to supply the goods under the agreement was extended and by

July, 2018, BPCL had supplied an aggregate quantity of 50.613 TMT of

Naphtha. The e-mails exchanged between the parties formed vital

evidence in this regard, which the learned tribunal had chosen to ignore.

26. Mr. Sabyasachi Chowdhury, learned Senior Advocate appearing for HPL

submitted that the views taken by the learned tribunal were possible

views and not open to challenge before this court. The tribunal had

interpreted the terms and conditions of the contract, the clauses thereof

and held that some of the counter-claims of HPL were justified. The

tribunal supplied the reasons. The first claim of HPL for refund on

account of differential pricing was rejected on the ground that HPL had

paid the money as raised by the provisional invoice. Calculation of the
26
2025:CHC-OS:91
price for the month of July, 2017 and August, 2017 were made separately

in the invoice. The parties understood that the pricing would be

considered as per the respective loading months. Thus, it was the finding

of the tribunal that the ‘parcel of goods’ in this case would be the unit

loaded in each month i.e. July and August. Mr. Chowdhury submitted

that the learned tribunal, thus, rejected the claim of HPL. The contract

provided that the payment would be made as per the quotes for the

month of July, 2017. The tribunal proceeded on the conduct of the

parties. The laycan period as per clause 6 was narrowed down to July 27,

2017 and July 28, 2017. Mr. Chowdhury submitted that HPL chose not to

challenge such finding as the tribunal’s interpretation of the clauses were

based on how the parties understood and treated the terms and

conditions with regard to pricing. The tribunal was the master of facts

and of the quality of evidence. The conclusion of the learned tribunal on

this score should not be interfered with, even if an alternative view on the

interpretation of clause 5 of the said agreement was possible. The formula

arrived at by the tribunal was on the interpretation of the expression

‘loading month’ which was taken subsequently as July, 2017 and August,

2017, and as such, the quantum of goods loaded in July and August were

treated to be separate parcels. It was contended that passing of the title of

the goods would not affect the price of the same or vice versa. The

intention of the parties to the contract was the key to determine what

actually transpired between them. The interpretation given by BPCL that
27
2025:CHC-OS:91
the title would pass only on August 1, 2017, upon disconnection of the

last permanent flange at the loading terminal and the final price should

be based on the average quotes of August 2017, would permit BPCL to

take advantage of its own delay in loading the vessel. Admittedly, the

vessel could not berth on July 28, 2017, due to congestion in the load

port and the vessel berthed on July 29, 2017 at 9 hours, when the

loading commenced. The price at which the goods were to be sold was to

be determined solely on the basis of the contract between the buyer and

the seller of such goods. The passing of the title of the goods would not

affect the price of the same. Clause 5 clearly provided the manner in

which the price of the goods would be ascertained. Thus, the date on

which the title had passed from BPCL to HPL was not relevant in the

instant case.

27. It was submitted that HPL had claimed demurrage on three counts. First

in respect of M.T. Jag Prerana (B/L dated 3.6.2017), second in respect of

M.T. Sanmar Sonnet (B/L dated 31.7.2017 and 1.8.2017) and the third in

respect of M.T. Sanmar Sonnet (B/L dated 30.9.2017). HPL had urged that

the demurrage claimed was on pre-estimate of the loss expected to be

suffered by HPL on account of failure by the seller and the claim of HPL

was not restricted to the actual loss suffered by them. The learned

tribunal did not accept such contention, but followed the principle that

one could be indemnified to the extent one had been damnified. The

tribunal only allowed the counter-claim of HPL on account of the
28
2025:CHC-OS:91
demurrage to the extent of the amount which was paid to the vessel

owner by HPL. BPCL had admitted that demurrage was payable to HPL.

Such admission was available from the e-mail dated September, 16,

2018. HPL had provided calculations for the demurrage hours. The

submission of BPCL that the delay was on account of the force majeure

event, was held to be contrary to the force majeure clause under clause

17 of the agreement. Similarly, while awarding the counter-claim of HPL

on account of dead freight, the learned tribunal followed the same

principle. By the e-mail dated January 22, 2018, BPCL had admitted the

claim of HPL on account of the dead freight. Once BPCL sought waiver of

dead freight, the liability to pay the same was admitted. The formula in

clause 3 of the agreement had been duly applied in consonance with the

calculations of proportionate dead freight. With regard to the claim on

account of the risk purchase, Mr. Chowdhury submitted that from the

contemporaneous correspondence, it would be evident that clause 19 of

the agreement had been breached by BPCL. The e-mail dated February 3,

2018, would clearly indicate that Naphtha was not available as BPCL had

already exported the same. Therefore, HPL requested for a confirmation of

availability of Naphtha for the month of March 2018. By an e-mail dated

February 5, 2017, HPL recorded BPCL’s confirmation of availability of 20

KT of cargo. By a subsequent email of February 5, 2018, BPCL confirmed

that they would provide 30 KT Naphtha during March 4 and 5 2018.

BPCL requested for acceptance of the cargo by HPL. By an e-mail dated
29
2025:CHC-OS:91
February 6, 2018, HPL confirmed lifting of 30 KMT Naphtha during 4th

and 5th March, 2018. By an e-mail dated February 12, 2018, HPL

requested BPCL for availability of cargo for the month of April, 2018.

BPCL responded to the e-mail on February 15, 2018, to the effect that

BPCL would be in a position to offer 35 KT Naphtha in the month of April,

2018. By the said e-mails, BPCL confirmed that since the parties would

be completing the MoU, the cargo for April 2018 would be dispatched

under the new MoU terms only. In respect of the cargo scheduled for 4th

and 5th March, 2018, BPCL shared quality parameters by their e-mail

dated February 16, 2018. By an e-mail dated February 16, 2018, HPL

informed BPCL that the specifications shared by BPCL, differed from

contractual specifications. However, as a special case and without

creating a precedence, HPL was agreeable to accept the cargo by deviating

from the contractual specifications. By an e-mail dated February 20,

2018, the quality parameters of certified batches were shared by BPCL

with HPL. It would be evident from a subsequent e-mail of HPL dated

February 20, 2018, that the parameters of the cargo shared by BPCL on

February 20, 2018 was of further inferior quality. By the said e-mail, it

was clearly communicated by HPL to BPCL that, further deterioration of

the quality would cause immense inconvenience to HPL and HPL would

have to take up the matter with their plant. From the e-mail dated

February 21, 2018, sent by BPCL, it would be evident that there was an

admission with regard to the inferior quality of Naphtha. Similarly, the e-
30

2025:CHC-OS:91
mail sent by BPCL on February 23, 2018, requesting HPL to accept such

inferior quality of cargo, itself, would prove that the quality of cargo

proposed to be supplied by BPCL or as was available with BPCL, was of

low quality. That itself was a breach. HPL had expressed displeasure

when BPCL had deviated from the accepted specifications. By an e-mail

dated February 26, 2018, BPCL shared the test result of the product

planned for loading on 4th and 5th March, 2018. HPL rejected the cargo

saying that the same did not even meet the parameters which were

accepted by it, upon deviating from the original parameters. By an e-mail

dated March 8, 2018, HPL requested BPCL to advise on the next laycan

for supply of cargo as per the contractual specifications. BPCL however

did not respond to the said e-mail. By letters dated March 17th and 18th

2018, HPL informed BPCL that it had no other way of procuring Naphtha

and was compelled to opt for risk purchase, to ensure fleet security. BPCL

had failed to supply the agreed quantity of Naphtha upon meeting the

contractual specifications. Several opportunities were given to BPCL to

meet the quality of Naphtha and share the test results of the same to

enable HPL to ascertain whether the quality of Naphtha that was

proposed to be loaded, at least met some of the specifications. The

respondent had rejected the cargo as the test results were much below

the standard quality and the deviation was not accepted. Continuous

supply of Naphtha was mandatory and there was no other option, but to

go for risk purchase. The contention of Mr. Bose that only when the vessel
31
2025:CHC-OS:91
was sent by HPL, clause 6 could be invoked, was not acceptable. The

parties were negotiating on the quality of Naphtha to be supplied. The

supply in July 2018 was independent and was not an extension of the

agreement. BPCL offered to supply 35 KT of Naphtha with the laycan of

19-20th July. By email dated June 21, 2018, upon ascertaining the

quality parameters, HPL confirmed the deal on independent terms and

conditions, which inter alia, included pricing period and loading month

average. BPCL admitted that the subject agreement was valid only upto

April 30, 2018.

28. The question of the respondent entering into a Charter Party Agreement

and sending a vessel for loading did not arise. The respondent was

already aware that the quality of goods proposed to be loaded was not up

to the mark. There was no reason why the respondent would be under an

obligation to accept low quality goods when the parameters had been

specifically stated in the annexure to the contract. There was a default on

the part of BPCL to supply the required quantity of Naphtha with the

required specifications, and as such, the risk was justified. The date of

the risk purchase was not relevant. A comparative analysis of the

parameters of the goods purchased from Saudi Aaramco with what was

proposed to be supplied by BPCL, would show that the quality offered by

Saudi Aaramco was comparatively closer to the agreed specifications.

According to Mr. Chowdhury, the scope of interference of a Court under

section 34 of the A & C Act is extremely limited and he submitted that the
32
2025:CHC-OS:91
application should be dismissed. Reliance was placed on the decision of

OPG Power Generation Private Limited vs. Enexio Power Cooling

Solutions India Private Limited and Another reported in 2024 SCC

OnLine SC 2600.

29. Considered the submissions of the respective parties. Recourse against an

arbitral award is provided under chapter VII of the A & C Act, Section 34

deals with an application for setting aside an award. The same is quoted

below:-

“34. Application for setting aside arbitral award.–(1) Recourse to a Court
against an arbitral award may be made only by an application for setting
aside such award in accordance with sub-section (2) and sub-section (3).
(2) An arbitral award may be set aside by the Court only if–

(a) the party making the application [establishes on the basis of the
record of the arbitral tribunal that]–

(i) a party was under some incapacity, or

(ii) the arbitration agreement is not valid under the law to which the
parties have subjected it or, failing any indication thereon, under the law
for the time being in force; or

(iii) the party making the application was not given proper notice of the
appointment of an arbitrator or of the arbitral proceedings or was
otherwise unable to present his case; or

(iv) the arbitral award deals with a dispute not contemplated by or not
falling within the terms of the submission to arbitration, or it contains
decisions on matters beyond the scope of the submission to arbitration:

Provided that, if the decisions on matters submitted to arbitration can be
separated from those not so submitted, only that part of the arbitral
award which contains decisions on matters not submitted to arbitration
may be set aside; or

(v) the composition of the arbitral tribunal or the arbitral procedure was
not in accordance with the agreement of the parties, unless such
33
2025:CHC-OS:91
agreement was in conflict with a provision of this Part from which the
parties cannot derogate, or, failing such agreement, was not in
accordance with this Part; or

(b) the Court finds that–

(i) the subject-matter of the dispute is not capable of settlement by
arbitration under the law for the time being in force, or

(ii) the arbitral award is in conflict with the public policy of India.

[Explanation 1.–For the avoidance of any doubt, it is clarified that an
award is in conflict with the public policy of India, only if,– (i) the
making of the award was induced or affected by fraud or corruption or
was in violation of section 75 or section 81; or (ii) it is in contravention
with the fundamental policy of Indian law; or (iii) it is in conflict with the
most basic notions of morality or justice.

Explanation 2.–For the avoidance of doubt, the test as to whether there
is a contravention with the fundamental policy of Indian law shall not
entail a review on the merits of the dispute.]
[(2A) An arbitral award arising out of arbitrations other than
international commercial arbitrations, may also be set aside by the
Court, if the Court finds that the award is vitiated by patent illegality
appearing on the face of the award: Provided that an award shall not be
set aside merely on the ground of an erroneous application of the law or
by re appreciation of evidence.]
(3) An application for setting aside may not be made after three months
have elapsed from the date on which the party making that application
had received the arbitral award or, if a request had been made under
section 33, from the date on which that request had been disposed of by
the arbitral tribunal: Provided that if the Court is satisfied that the
applicant was prevented by sufficient cause from making the application
within the said period of three months it may entertain the application
within a further period of thirty days, but not thereafter.
(4) On receipt of an application under sub-section (1), the Court may,
where it is appropriate and it is so requested by a party, adjourn the
proceedings for a period of time determined by it in order to give the
arbitral tribunal an opportunity to resume the arbitral proceedings or to
34
2025:CHC-OS:91
take such other action as in the opinion of arbitral tribunal will eliminate
the grounds for setting aside the arbitral award.

[(5) An application under this section shall be filed by a party only after
issuing a prior notice to the other party and such application shall be
accompanied by an affidavit by the applicant endorsing compliance with
the said requirement. (6) An application under this section shall be
disposed of expeditiously, and in any event, within a period of one year
from the date on which the notice referred to in sub-section (5) is served
upon the other party.]”

30. The award has been challenged on the grounds of non-consideration of

material evidence, non-supply of reasons, conclusions based on surmise

and conjecture, the tribunal rewriting the terms and condition of the

contract etc. According to BPCL, the tribunal had given its own

interpretation of the relevant clauses of the contract, while refusing the

prayer for payment of the differential price as per the final invoice. The

expression ‘parcel’ was misconstrued. The interpretation given by the

tribunal was incomprehensible and shocking to the conscience of a

reasonable man. The tribunal had made out a third case. Further

contention was that the counter claims of the respondent, apart from the

prayer for refund, were wrongly awarded, without taking into account the

relevant clauses of the contract. The clauses of the agreement had to be

strictly construed. The tribunal gave a liberal and equitable meaning to

the clauses relating to demurrage, dead freight and risk purchase.

31. The issues to be decided in this application are whether the arbitral

award is in conflict with the public policy of India or/and is vitiated by
35
2025:CHC-OS:91
patent illegality apparent on the face of the award. Section 34(2)(v)(b)(ii)

provides that, when a court finds that the arbitral award is in conflict

with the public policy of India, it may set aside the award. Explanation -I

thereto provides that an award will be in conflict with the public policy of

India only if it is in contravention with the fundamental policy of Indian

law or it is in conflict with the most basic notions of morality or justice.

The first ground under Explanation – I is not relevant as it is nobody’s

case that the making of the award was affected by fraud or corruption or

was in violation of Section 75 or 81. Explanation -2 clarifies that the test

as to whether there is a contravention with the fundamental policy of

Indian law shall not entail a review on the merits of the dispute.

Explanation 2A provides that an arbitral award arising out of the

arbitrations other than International Commercial Arbitrations may be set

aside by Court if the Court finds the award is vitiated by patent illegality

appearing on the face of the award. . Thus, the award in the instant case

has to be scrutinized within the limitation of the law which permits

setting aside of an award i.e. whether the award is either in contravention

of the fundamental policy of Indian law or is in conflict with the most

basic notions of morality or justice or is patently illegal.

32. In this case, the Arbitral Tribunal considered the background of the

dispute which led to the reference. The tribunal dealt with the claim and

thereafter the counter-claims, in a phased manner.

36

2025:CHC-OS:91

33. First, the tribunal dealt with the claim and counter claim relating to the

differential pricing (pricing dispute) for sale and supply of Naphtha during

the loading i.e., July 29, 2017 and August 1, 2017. In order to appreciate

the claim based on the final invoice and counter-claim for refund of

excess payment in respect of the said loading period, the tribunal referred

to clauses 5, 6, 7 and 8 of the contract, which were also relied upon by

Mr. Bose in support of the claim for the differential pricing as per the final

invoice.

34. The learned tribunal applied the above clause to the balance claim of the

petitioner and the counter claim for refund, i.e., the pricing dispute

between the parties. It was observed that the supply was for the month of

July, 2017. The laycan was narrowed down to July 27, 2017 and July 28,

2017. Such laycan period was accepted by both the parties. The notice of

readiness was issued on 28th July, 2017 at 17:30 hrs. Accordingly, the lay

time commenced from 23:30 hrs. of July 28, 2017 as per clause 7(c). Due

to congestion at the port, berthing was delayed and the vessel berthed at

9:00 hrs. on July 29, 2017. The loading commenced at 11:18 hrs. on July

29, 2017. The contractual lay time of 72 hrs. ended at 23:30 hrs. of July

31, 2017. According to BPCL, the laycan actually ended by 02:45 hrs. on

August 1, 2017. The loading was completed at 11:36 hrs. of August 1,

2017. The hose was disconnected at 12:20 hrs. of August 1, 2017. The

tribunal recorded that delay in loading the cargo was an admitted

position. Berthing of the vessel was delayed due to congestion in the load
37
2025:CHC-OS:91
Port and because high capacity pumps were not available to load the

cargo. Such observations of the learned tribunal were based on a

communication dated August 31, 2017 from an officer of BPCL to an

officer of HPL. Paragraph 2 of the said e-mail is significant. The said

paragraph is quoted below:-

” 2. The loading started at 1118 Hrs on 29th Jul’17 and completed at
1136 Hrs on 1st Aug’ 17. This is within the standard loading time of 72
Hrs that requires to load 40KT in a vessel. However, the loading took this
much time due to non-availability of high capacity pump on account of
technical issues.”

35. In the above background, the claim was considered. BPCL raised two bills

of lading (B/L), one for 33968.155 MT, being quantity loaded in the

month of July, 2017 and the other for 7875.049 MT which was the

quantity loaded on August 1, 2017. A provisional invoice for the total

cargo loaded was raised on the split B/L. HPL requested for one B/L and

BPCL replaced the two B/Ls. HPL disputed the provisional bills on the

ground that the average of prior 5 days quotes had not been properly

taken. However, HPL made its own calculation and made its payment.

Subsequently, BPCL raised a debit note for the final bill for 41483.204

MT, i.e., the total quantity loaded in July and August taken together, on

the basis of the average quotes during the month of August 2017. HPL

disputed the same on the ground that the pricing should be on the

average quotes during the month of July, 2017 i.e. the originally agreed

laycan period. However, HPL paid on the basis of its own calculation
38
2025:CHC-OS:91
based on the July 2017 quotes, for 33968.155 MT and August 2017

quotes, for 7875.049 MT. The manner of payment/calculation by HPL was

available in annexure R1 to the annexures of the counter statement.

36. BPCL’s claim for the difference in price paid by HPL and the price quoted

on the basis of average quotes during the month of August, 2017 together

with interest, were rejected by the learned tribunal. The submissions of

learned counsel for BPCL, the documents available before the tribunal

and the tribunal’s understanding and construction of the provisions of

the agreement and how the parties understood the contract, were taken

into account. It was held that the meaning and import of the expression

“loading month” in clause 5 of the agreement was unambiguous. FOB

was explained in Clause 5. The average of Naphtha for all the quotes

during the loading month was to be considered as FOB for any parcel

loaded in a month. According to the learned tribunal “any parcel loaded in

a month” was to be given its plain, simple and ordinary meaning. The

phrase should not be rendered either redundant or otiose. It should be

construed harmoniously with the other provisions. The tribunal held that

there was no special context to hold the loading month to be August,

2017. Rather, the loading month should be partly July 2017 and partly

August 2017, as per the quantum loaded in each of those months. The

expression “any” before the word “parcel” and the article “a” before the

word “month” was significant and indicative. The expressions “any” and

“parcel”, would mean that each cluster of cargo or unit of cargo loaded in
39
2025:CHC-OS:91
the particular month would be treated as a separate parcel or unit and a

part of the whole of the cargo loaded in the months of July and August.

The expression should be read as “any parcel in a month” meaning

thereby the parcel of Naphtha loaded in July would be treated as one unit

and the parcel of Naphtha loaded in August would be treated as a

separate unit and the prices should be calculated on the prior five quotes

of July, for the parcel of goods of cargo loaded in the month of July and

similarly on the prior five quotes of August, for the quantity of cargo

loaded in August 2017. The definition of the expression “parcel” was

adopted from the shorter Oxford English Dictionary, which meant a part

of anything, considered separately as a unit, a similar portion or particle,

a component, part of something, something included in a whole. In this

context clause 5 is quoted below:-

“5. PRICE:

Naphtha supplies will be made on the pricing based on formulae (FOB+
Market Premium + $5), wherein FOB and Premium shall be worked as
below:

 FOB: Average of Naphtha MOPAG (Average of Platts quotes) for all-
the-quotes during the loading month (M) will be considered as
FOB for any parcel loaded in a month (M)”

37. According to the tribunal, the expression “parcel” had been used in the

contract to signify a quantity. Clause 7(b) was referred to. The same is

quoted below:-

“7(b) Total Allowed lay time at load port shall be Thirty Six (36)
hours for a parcel size of 20,000 MT. Total allowed lay time shall be
40
2025:CHC-OS:91
increased or decreased on prorate basis (SHINC) with actual
loading quantity.”

38. It was held that the parcel could be any quantity qualified by size or

qualified by the time of loading i.e. any parcel loaded in a month.

According to the learned tribunal, the communication between the parties

clearly indicated that HPL was agreeable to the price based on the average

quotes for the month of July, in respect of the parcel loaded in the month

of July and on the average quotes for the month of August, 2017 for the

parcel loaded in the month of August, 2017. In fact, HPL made payment

against the provisional invoice. BPCL insisted on average quotes for the

month of August, 2017. The contention of HPL was that the loading

month should be construed on the basis of the laycan month i.e. July.

The tribunal rejected the claims of both parties for the simple reason that,

the meaning of “loading month” and “loading laycan” were different as

would appear from clause 6b. Clause 6b is quoted below:-

“6b By the 1st of M-1(where M = loading Month) buyer shall nominate the
5 days loading Laycan within the 15 day laycan as agreed above which
seller to confirm within 2 days of receipt of HPL’s proposed laycan. In
case seller is unable to accept the 5 day loading laycan as proposed by
HPL, within 2 days of receipt of HPL’s proposed laycan. Seller may
propose alternate laycan with a maximum deviation of +/- 2 days from
the Buyer’s proposed laycan.”

39. Laycan was the period within which the vessel had to report. The

reporting of the vessel depended on the terms of the charter party

contract between HPL and the vessel owner. BPCL was not a party to the
41
2025:CHC-OS:91
same. What was agreed between BPCL and HPL were the days of the

laycan in the loading month. Those two days of the laycan were the period

within which the vessel had to report and notify its readiness. Therefore,

according to the tribunal, the loading month should be given the meaning

as it appeared from clause 5 i.e., for any parcel loaded in a month. There

was neither inconsistency nor ambiguity in the expression “loading

month” in clauses 5 and 6, as per the understanding of the learned

tribunal. The said expression had nothing to do with the laycan period.

Therefore, according to the learned tribunal, the average quotes of any

parcel loaded in a particular month would be the price of the cargo for

that month. Therefore, the quantity loaded within July 31, 2017 would be

a separate and distinct parcel from the quantity of cargo loaded on

August 1, 2017. The arguments of BPCL and HPL were turned down. The

tribunal was of the opinion that, disconnection of the last permanent

flange was relevant for passing of title and risk, which had nothing to do

with the pricing.

40. Section 9 of the Sale of Goods Act, 1930 was considered. It was held that

the price had been fixed in terms of clause 5 and had to be determined on

the basis of the said clause, namely, FOB for any parcel loaded in a

month. Section 9 of the Act of 1930 provided that the price in a contract

of sale could be fixed by the contract or may be left to be fixed in a

manner which would be agreed to or determined in the course of dealings

between the parties. In the present case, the price had been fixed in terms
42
2025:CHC-OS:91
of clause 5 and it had been determined on the basis of the said clause.

HPL’s contentions with reference to the clause to show that laycan had

been fixed earlier, and pertained to the month of July, were not

considered relevant for the purpose of deciding whether the counter-claim

of HPL under the head ‘differential pricing’ should be allowed or not.

According to the tribunal, price was to be determined on the

interpretation of clause 5, which was independent of other clauses. Clause

6 was a guideline for laycan, narrowed down to loading laycan, whereas,

clause 7 dealt with demurrage and clause 8 dealt with passing of title and

risk. Each of those clauses were held to be independent of each other

and according to the tribunal, the clauses did not suffer from any

ambiguity. The tribunal found that it was not necessary to look for any

other clause to interpret the meaning of the expression “loading month”.

The meaning of the expression “loading month”, was absolutely clear and

unambiguous under clause 5. The decisions cited by the parties were also

considered. It was found that there was no repugnancy in the expression

“loading month” used in clause 5, with the other clauses, when the

subject or context was pricing. The tribunal, while negating BPCL’S claim

held that, how both the parties understood the contract was reflected by

their conduct, inasmuch as, BPCL issued two separate B/Ls for two

parcels, followed by the provisional bill, thereby, pricing the two parcels

separately. HPL made the payment based on average quotes of July 2017

for the parcel loaded in July and average quotes of August 2017 for the
43
2025:CHC-OS:91
parcel loaded in August. As a result, the claim of BPCL for further

amount as per the single B/L and the HPL’s claim for refund of excess

payment made for the quotes of August, were both rejected. Findings of

the learned tribunal are based on the tribunal’s understanding and

construction of the contract and the way the parties understood clause 5.

The Tribunal is the master of facts. The construction of the contract must

be left to the tribunal. The scope of interference of the Court under

section 34 of the A & C Act is limited. The Court cannot re-appreciate the

evidence. The view of the tribunal is a possible view. The tribunal’s

interpretation of the clauses, as have been discussed hereinabove, do not

appear to be either patently illegal or bereft of reasons. According to the

tribunal, when the parties by their conduct had displayed that they had

treated each of the parcels of cargo loaded in July and August separately,

and calculation was made in the provisional invoice on the average quotes

of July and August separately, payments were also made as per the

calculation of HPL on the average quotes of July and August separately,

they could not turn around and claim something which was contrary to

what they had accepted by their conduct. Although, it has been urged

before this court that the GST payment was based on the calculation in

the final invoice, the petitioner had altered its position by making such

payment, and thus the respondent was estopped from challenging the

validity of the differential price claimed on the basis of the final invoice,

such case has not been made out in the statement of claim and there are
44
2025:CHC-OS:91
no pleadings to that effect. Thus, this Court does not find any reason to

interfere with the decision of the learned tribunal on the first issue.

41. Reference is made to the decision of Bharat Aluminium Co. v. Kaiser

Aluminium Technical Services Inc., reported in (2016) 4 SCC 126 , the

Hon’ble Apex Court held as follows:-

“10. In the matter of interpretation, the court has to make different
approaches depending upon the instrument falling for interpretation.
Legislative drafting is made by experts and is subjected to scrutiny at
different stages before it takes final shape of an Act, Rule or Regulation.
There is another category of drafting by lawmen or document writers who
are professionally qualified and experienced in the field like drafting
deeds, treaties, settlements in court, etc. And then there is the third
category of documents made by laymen who have no knowledge of law or
expertise in the field. The legal quality or perfection of the document is
comparatively low in the third category, high in second and higher in
first. No doubt, in the process of interpretation in the first category, the
courts do make an attempt to gather the purpose of the legislation, its
context and text. In the second category also, the text as well as the
purpose is certainly important, and in the third category of documents
like wills, it is simply intention alone of the executor that is relevant. In
the case before us, being a contract executed between the two parties,
the court cannot adopt an approach for interpreting a statute. The terms
of the contract will have to be understood in the way the parties wanted
and intended them to be. In that context, particularly in agreements of
arbitration, where party autonomy is the grund norm, how the parties
worked out the agreement, is one of the indicators to decipher the
intention, apart from the plain or grammatical meaning of the
expressions and the use of the expressions at the proper places in the
agreement.”

45

2025:CHC-OS:91

42. In the matter of M/s Hindustan Construction Company Limited vs M/s

National Highways Authority of India, reported in 2023 INSC 768, the

Hon’ble Apex Court held as follows:-

“23. For a long time, it is the settled jurisprudence of the courts in the
country that awards which contain reasons, especially when they
interpret contractual terms, ought not to be interfered with, lightly. The
proposition was placed in State of UP v Allied Constructions17: “[..] It
was within his jurisdiction to interpret Clause 47 of the Agreement
having regard to the fact-situation obtaining therein. It is submitted that
an award made by an arbitrator may be wrong either on law or on fact
and error of law on the face of it could not nullify an award. The award is
a speaking one.
The arbitrator has assigned sufficient and cogent
reasons in support thereof Interpretation of a contract, it is trite, is a
matter for arbitrator to determine (see M/s. Sudarsan Trading Co. v. The
Government of Kerala
, AIR (1989) SC 890). Section 30 of the Arbitration
Act, 1940 providing for setting aside an award is restrictive in its
operation. Unless one or the other condition contained in Section 30 is
satisfied, an award cannot be set aside. The arbitrator is a Judge chosen
by the parties and his decision is final. The Court is precluded from
reappraising the evidence. Even in a case where the award contains
reasons, the. interference therewith would still be not available within the
jurisdiction of the Court unless, of course, the reasons are totally
perverse or the judgment is based on a wrong proposition of law”

24. This enunciation has been endorsed in several cases (Ref McDermott
International Inc. v. Burn Standard Co. Ltd18
).
In MSK Projects (I) (JV)
Ltd v State of Rajasthan19
it was held that an error in interpretation of a
contract by an arbitrator is “an error within his jurisdiction”.
The
position was spelt out even more clearly in Associate Builders (supra),
where the court said that: “[..] if an arbitrator construes a term of the
contract in a reasonable manner, it will not mean that the award can be
set aside on this ground. Construction of the terms of a contract is
primarily for an arbitrator to decide unless the arbitrator construes the
46
2025:CHC-OS:91
contract in such a way that it could be said to be something that no fair
minded or reasonable person could do.”

43. In the matter of McDermott International Inc. v. Burn Standard Co.

Ltd., reported in (2006) 11 SCC 181, the Hon’ble Apex Court held as follows:-

“112. It is trite that the terms of the contract can be express or implied.
The conduct of the parties would also be a relevant factor in the matter
of construction of a contract. The construction of the contract
agreement is within the jurisdiction of the arbitrators having regard to
the wide nature, scope and ambit of the arbitration agreement and they
cannot be said to have misdirected themselves in passing the award by
taking into consideration the conduct of the parties. It is also trite that
correspondences exchanged by the parties are required to be taken into
consideration for the purpose of construction of a contract.
Interpretation of a contract is a matter for the arbitrator to determine,
even if it gives rise to determination of a question of law. (See Pure
Helium India (P) Ltd. v. ONGC [(2003) 8 SCC 593] and D.D.
Sharma v. Union of India [(2004) 5 SCC 325] .)

113. Once, thus, it is held that the arbitrator had the jurisdiction, no
further question shall be raised and the court will not exercise its
jurisdiction unless it is found that there exists any bar on the face of
the award.”

44. In the matter of Pure Helium India (P) Ltd. v. Oil & Natural Gas

Commission, reported in (2003) 8 SCC 593, the Hon’ble Apex Court held as

follows:-

“29. In State of U.P. v. Allied Constructions [(2003) 7 SCC 396 : (2003) 6
Scale 265] this Court held: (SCC p. 398, para 4)
“Interpretation of a contract, it is trite, is a matter for the arbitrator to
determine (see Sudarsan Trading Co. v. Govt. of Kerala [(1989) 2 SCC 38
47
2025:CHC-OS:91
: AIR 1989 SC 890] ). Section 30 of the Arbitration Act, 1940 providing
for setting aside an award is restrictive in its operation. Unless one or
the other condition contained in Section 30 is satisfied, an award
cannot be set aside. The arbitrator is a judge chosen by the parties and
his decision is final. The court is precluded from reappraising the
evidence. Even in a case where the award contains reasons, the
interference therewith would still be not available within the jurisdiction
of the court unless, of course, the reasons are totally perverse or the
judgment is based on a wrong proposition of law. An error apparent on
the face of the records would not imply closer scrutiny of the merits of
documents and materials on record. Once it is found that the view of
the arbitrator is a plausible one, the court will refrain itself from
interfering.”

45. The next issue decided was the counter-claim under the head dead

freight. The learned tribunal considered clauses 2 and 3 of the agreement. The

clauses are quoted below:-

“2. QUANTITY :

BPCI, shall-supply from Kochi refinery and HPL undertakes to
purchase a minimum quantity of 20 TMT of Naphtha +/- 10% at
Buyer’s option every month during the validity period of the
agreement.

In case of an additional requirement of Naphtha quantity in any
month, the same will be decided on mutual consent of BPCL and HPL.
Loading of such quantity shall be governed by all the terms of this
agreement.

3. DEAD FREIGHT CLAUSE:

Dead freight loss due to quantity loaded below the cargo volume
nominated by the Buyer shall be on Seller’s account. It shall be
calculated based on the difference between the actual per MT freight
incurred and the freight cost in case the buyer’s nominated quantity
48
2025:CHC-OS:91
had been loaded. (Total freight/loaded qty) – (Total freight/Buyer’s
nominated Qty * Loaded Qty
In case of dead freight loss, if any, HPL shall send a debit note to
BPCL, payment of which to be done by BPCL through Electronic
Transfer within 7 days from the date of issuing of Debit Note.
Conversion rate would be as per RBI reference for the pricing period of
cargo.”

46. Clause 2 provided that BPCL would supply from Kochi refinery and HPL

undertook to purchase minimum quantity of 20 TMT of Naphtha +/-10%, at

the buyers option, every month, during the validity period of the agreement. In

case of additional requirement of Naphtha in any month, the same would be

decided on mutual consent of BPCL and HPL. The loading of such quantity

would be governed by all the terms and conditions of the agreement. The dead

freight clause provided that loss suffered due to quantity of cargo loaded below

the agreed volume nominated by the buyer, would be on the seller’s account. It

would be calculated based on the difference of rate between the actual per

metric ton freight incurred and the freight cost in case the buyer’s nominated

quantity had been loaded i.e. [(total freight / loaded quantity), (the total

freight/buyer’s nominated quantity x loaded quantity)]. In case of dead freight

loss, if any, HPL would issue a debit note to BPCL and payment would be done

by BPCL by electronic transfer within 7 days from the date of issuance of the

debit note. Conversion rate would be as per RBI’s reference for the pricing

period of cargo. The tribunal came to the finding that the loss was suffered by

the seller due to loading of lesser quantity of cargo than what was nominated

by the buyer and should be borne by the seller. In the present case, the claim
49
2025:CHC-OS:91
for dead freight was not in dispute. The claim for dead freight was in respect of

the voyage of M.T. Jag Padma (B/L dated December 03.12.2017). HPL was

bound to purchase a minimum quantity of 20 TMT of Naphtha +/- 10% every

month during the validity period of the agreement. In case of M.T. Jag Padma,

HPL sent an e-mail to BPCL on October 28, 2017 stating that it had planned

for 20 TMT +/- 10% of Naphtha during end of November, 2017. Another e-mail

was sent on December 2, 2017 to the vessel owner initially declaring the final

loadable quantity of subject vessel as 20350 MT, stating that the owner would

try to load close to 20500 MT on best endeavour. Accordingly, HPL declared a

loadable quantity of 20350 MT. Question No. 338, which was put to RW1, was

referred to in this context by the learned tribunal. The evidence referred to by

the tribunal indicated that at 13:03 hrs. on December 2, 2017, the Master of

vessel M.T Jag Padma sent an e-mail stating “message well received. As

instructed, Vessel will load to 7.60M FW Draft,. arrival Haldia … Vessel makes

loadable for 7.60M FW draft – 20425 MT”. The said e-mail was part of the

annexureS to the counter-statement. Question nos. 341 to 346 and 350 of the

Cross-examination of RW1 were referred to. It was found that the vessel owner

raised an invoice for lump sum freight charges for the above quantity,

amounting to $477067.50. Reference was made to the Affidavit of Evidence of

RW2. BPCL loaded 19971.88 MT. According to the tribunal, dead freight was

charged for the less amount loaded i.e., 453.12 MT. The short loading was

found to be lower than the margin of +/- 10% of 20 KT. HPL raised a claim for
50
2025:CHC-OS:91
dead freight by an e-mail dated January 5, 2018 and in reply BPCL did not

contradict any of the facts relating to the claim. BPCL stated as follows :-

“At various times BPCL has accommodated the last moment request
(towards loading completion) for increasing the quantity nominated
earlier. This has been done in the spirit of reducing your dead freight, as
we were having product with us and there was scope of further loading in
your vessel. Keeping the same spirit in mind, we would request you to
kindly not consider the difference in quantity of the subject cargo, which
is well within the range of 20KT +- 10% for dead freight claims.”

47. The above facts were available from the documents at pages 144-145 of

the annexures to the counter statement. The contention of HPL was that the

quantity nominated by HPL by an e-mail dated October 28, 2017, through the

Master of vessel, was 20425 MT. The same was well within the extra 2 KT of

Naphtha. HPL had the option to nominate such amount as per clause 2 of the

agreement. BPCL admitted the loading of 19971.88 MT of Naphtha. Thus, the

tribunal held that HPL was entitled to dead freight.

48. The question which the tribunal decided under the said head was

whether having regard to the provision of the contract, dead freight would be

payable and the learned tribunal came to the finding that despite the margin of

+/- 10% specified in clause 2, nothing had been mentioned about the range of

+/- 10% in clause 3. It only indicated that dead freight loss due to quantity

loaded below the agreed volume nominated by the buyer, would be on the

seller’s account. Therefore, as per the understanding of the learned tribunal,

BPCL having loaded lesser quantity of cargo than what was nominated by the

buyer, was liable to pay the dead freight. The tribunal observed that the
51
2025:CHC-OS:91
contract must be construed strictly. The reference to the margin of 10% +/- in

clause 2, was conspicuously absent in clause 3. The tribunal opined that the

omission seemed to be deliberate. Both the parties were prudent commercial

entities, having in-depth experience in trade and commerce with intelligent

advice available to them. The tribunal held that it was not required to supply

the omission in the language used in the contract in such context. The terms

in clause 2 and 3 were the real reflection of the intention of the parties. Thus,

BPCL’s contention that the quantity supplied was within the margin of +/-10%

was not accepted by the tribunal, upon interpretation of clause 3. Clause 2

prescribed the accountability of BPCL to supply the quantity nominated by

buyer, at the option of the buyer. The buyer had the option to nominate any

quantity equal to 10% +/- of 20TMT. The seller was obligated to supply the

quantity nominated by the buyer. Thus, according to the tribunal, Clause 3

made BPCL liable for dead freight loss, on account of loading of less quantity of

cargo. The margin of +/- 10% of 20 TMT, could not be taken advantage of by

BPCL, when the quantity mentioned was at the option of HPL. This was the

finding of the learned tribunal and this Court does not find either any illegality

or unreasonableness in such finding. The findings are based on the

interpretation of the clauses, evidence of RW1 and RW2, the communication

between the parties and the communication of the vessel owner. The learned

tribunal came to a finding that the ultimate effect of the two clauses i.e. clause

2 and 3, were not in dispute. The intention of the parties were clear and would

manifest from the reply dated January 8, 2018, when BPCL requested HPL to
52
2025:CHC-OS:91
waive the claim. There was nothing on record to show that BPCL had ever

disputed the claim or dealt with the same except in the e-mail dated January 8,

2018. BPCL’s supply of 19971.88 MT against HPL’s nomination of 20425 MT,

was not in dispute and the dead freight claim was equivalent to 6.4 lakhs.

HPL’s calculation based on the formula at clause 3, was not accepted.

According to the learned tribunal, HPL could not claim anything more than

USD 9985.94 with interest. The findings are at paragraph 6.17 of the award.

“In the counter claim raised, HPL gave its calculation based on the
formula provided in Cl.3 of the agreement. It pointed out as below: Vessel
freight as per B/L USD 454350/19971.88 MT = USD 22.74/MT. Vessel
freight as per HPL nominated quantity USD 454350/20245MT = USD
22.24.

Dead freight : USD (22.74-22.24) x 19971.88 MT= USD 10079.56. But we
find that the figures USD 22.74-22.24 calculates to USD 0.5.
and loaded cargo 19971.88 x USD 0.5 works out to USD 9985.94.
Therefore HPL cannot claim anything more than USD 9985.94 ie: for INR
equivalent at the conversion rate as on 05 01 2018.”

49. The next head of the counter claim was for demurrage. The same was

claimed on three counts. First claim was in respect of MT Jag Prerana (B/L

dated 03.06.2017), second was in respect of M.T. Sanmar Sonnet (B/L dated

31.07.2017 and 01.08.2017) and the third was in respect of M.T. Sanmar

Sonnet (B/L dated 30.09.2017). The learned tribunal relied on the submissions

of the parties and deemed it fit to look into the documents in support of the

demurrage claim of HPL. The tribunal’s finding was based upon consideration

of respective documents relating to NOR and the Statement of Fact submitted

by the vessel owner. The Statement of Fact and NOR were not in dispute. The
53
2025:CHC-OS:91
tribunal found that details relating to NOR, commencement of loading,

completion of loading , disconnection of the flange, berthing and release of

moorings were all available. All those documents were certified by the vessel

owner.

50. In respect of M.T. Jag Prerana (B/L dated 03.06.2017), the tribunal held

that although the demurrage hours at the load port were shown to have been

for 57.9 hrs. and the PDPR at 666.667, BPCL admitted 54.4 hrs. of demurrage.

HPL claimed demurrage on the basis of 58.22 hrs. From the different

correspondences exchanged, it was found that the vessel owner filed a claim

against HPL for 49.41 hrs. Such claim was available from the affidavit of

evidence of RW2. It was found that the vessel owner had reduced its claim

further to a total $33580.65 by an e-mail dated April 16, 2018, after deducting

TDS, which came to Rs. 21,61,476.55/. The evidence of RW2 was relied upon.

Such amount was found payable by BPCL.

51. In respect of M.T. Sanmar Sonnet (B/L dated 31.07.2017), it was found

by the learned tribunal that free lay time, demurrage rate, the events relating

to NOR commencement of lay time, cessation on free lay time and

disconnection of hose, were all admitted. BPCL admitted demurrage hours of 5

hrs. 17 minutes amounting to $4290, whereas HPL claimed $7732.29. It was

found that the vessel owner did not claim any demurrage taking into account

the lay time at the load port and discharge port. Thus, nothing was found

payable in respect of the said B/L.
54
2025:CHC-OS:91

52. In respect of M.T. Sanmar Sonnet B/L dated 30.09.2017, the learned

tribunal found that free lay time, demurrage rate, notice of reduction,

commencement of lay time, cessation of free lay time and the hose

disconnection, were all admitted. The demurrage hour at the load port was

21.30 hours and the demurrage rate was $ 812.5, which amounted to $

17468.75. The vessel owner filed a claim against HPL by an e-mail dated

November 9, 2017, for a total of 10 hrs. 37 minutes and claimed $ 8626.04.

The evidence of RW2 and annexure C of BPCL’s annexure to the rejoinder to

such claim were considered. Exhibit R11 i.e. the e-mail of BPCL dated

September 16, 2018, was duly considered. The e-mail stated as follows :-

“Due to sunken boat in the channel, CPT did not grant the Pilot for
berthing / sailing for all tankers during this period … Thus claim falls
under force majeure clause and hence there is Nil demurrage.”

53. The arguments of the learned counsel for BPCL were considered. BPCL

argued that the force majeure clause should be invoked in this case. Due to

unexpected circumstances, the delay had occurred. The learned tribunal

considered the document and came to the finding that BPCL had requested

HPL to waive the demurrage claim. Therefore, BPCL could not dispute liability

for demurrage by applying the force majeure clause. Clause 17 of the

agreement was considered. The same is quoted below :-

“17. FORCE MAJEURE CLAUSE:

If either of the parties to the contract is impended in abiding by the
contract terms by any circumstances of Force Majeure as hereunder
defined then the party who is impeded shall within seven days give notice
in writing to the other party together with evidence relied upon for the
55
2025:CHC-OS:91
same and will agree postponement of the date of completion as may be in
all circumstances be considered reasonable.

For the purpose of this contract, Force Majeure shall mean and be
limited to the following:


         a)                 Any war, invasion, act of foreign enemies, rebellion or
         Hostilities
         b)                 Any riot or civil commotion
         c)                 Any Acts of God such as severe earthquake, typhoon

or Cyclone, flood, tempest, epidemic or other natural physical disasters

d) Any accident, fire or explosion

e) Strikes and lock outs beyond 14 consecutive calendar
days and beyond the reasonable control of the parties affected.

Should one or both the parties be prevented from fulfilling their
contractual obligations during the period of Force Majeure lasting
continuously for a period of one month, both the parties should consult
with each other regarding future implementations of this contract. Both
the parties shall cooperate fully to decide upon alternatives for meeting
commitments / course of action. Both the parties should consult with
each other regarding future commitments/course of action.”

54. The tribunal held that neither had BPCL given the 7 days’ notice in

writing to HPL nor was there any evidence to show that an agreement for

postponement of the date of completion of the loading, had been arrived at. It

was found that the force majeure clause did not include prohibition of berthing

and sailing imposed by CPT. In the absence of a notice invoking the force

majeure clause and in the absence of evidence of an agreement to postpone the

date of loading, the clause was not attracted. Such finding of the learned

tribunal should not be interfered with. The findings are based on facts and
56
2025:CHC-OS:91
interpretation of the contract. The evidence discloses a request by BPCL to HPL

to withdraw the claim for demurrage. Clause 7 of the agreement was also

considered. The same is quoted below :-

“7. DEMURRAGE AND LAYTIME :

a. Demurrage (if any) at load port will be on BPCL account.
b. Total Allowed lay time at load port shall be Thirty Six (36) hours for a
parcel size of 20,000 MT. Total allowed lay time shall be increased or
decreased on prorata basis (SHINC) with actual loading quantity.
c. Lay time shall commence 6 hours after NOR (Notice of readiness) and
shall cease upon hose disconnection.

d. Any delays and time loss due load port limitation shall be on sellers
account.

e. In the eventuality of bad weather half time to count as used lay time on
time on demurrage.

f. Demurrage Rate shall be as per charter party. Any demurrage charge
incurred due to the delay in loading of the cargo at load port (Kochi) shall be
borne by the seller whereas any demurrage charge incurred subsequently
shall be borne by the buyer.

g. Buyer shall provide vessel owner’s demurrage claim, PDPR (Per Day
Prorata), and debit note from HPL, regarding the final demurrage applicable
for load port within 90 days of completion of discharge of the cargo. Seller
will respond to the claim by acceptance or counter within 15 days of claim
failing which the Buyer’s claim shall be deemed to have been accepted by
Seller and buyer shall raise debit note accordingly. Seller shall settle the
claim within 15 days from date of debit note.”

55. Thus, in respect of Sanmar Sonnet (B/L 30.09.2017) HPL had paid Rs.

5,79,338.00/- against the vessel owner’s claim. Therefore, the tribunal held

that, HPL was entitled to what was paid and nothing more. The tribunal

rejected the submission of the learned counsel for BPCL that, the claim for
57
2025:CHC-OS:91
demurrage was in the nature of indemnity and subject to proof. The tribunal

was of the view that as per the contractual terms, demurrage was payable

under the circumstances prescribed under clause 7.

56. The last counter-claim was for risk purchase. Such claim was made on

the basis of clause 19 of the Agreement, which was the performance clause.

The clause is quoted below :-

“19. PERFORMANCE CLAUSE :

I. Subject to the clause 16 of the present agreement, in case the seller
fails to comply with the terms and conditions as mentioned under Clause
6 – Cargo/Laycan nomination, the Buyer shall in addition to any legal
remedies, be entitled to exercise the following option:

 Risk purchase at seller’s cost: To purchase from any other source
similar material. The price for such purchase shall be deemed
conclusively the best price, which the Buyer could obtain. To the price,
Buyer may add cost of procurement, if any, to arrive at the Procurement
price. If such price is higher than the price fixed for the lot as per the
contract terms, then seller has to compensate the Buyer for the loss
suffered. The compensation amount will be calculated as follows :

Compensation amount = (Procurement Price obtained from the market –
Contract Price considering last day of the laycan being the deemed B/L
date) x Buyer’s Nominated Qty
II. Subject to the clause 16 of the present agreement in the event the
Seller fails to load to vessel within 2 days from the last date of the agreed
lay/can, the buyer in addition any other legal and commercial remedies
be entitled to exercise the following option:

 Risk purchase at the seller’s cost as defined.

 Claim and recover Freight and Demurrage from the Seller in full,
Freight and Demurrage calculation shall be as per Charter Party terms.
 HPL shall issue a debit note for the compensation amount, if any,
under the present clause to BPCL, payment of which to be done by BPCL
through Electronic Transfer within 15 days from the date of Debit Note.

58

2025:CHC-OS:91
Conversion rate would be as per RBI reference for the pricing period of
cargo.

**** **** ****
III. Subject to the clause 16 of the present agreement, in the event the
Buyer fails to uplift the nominated quantity or uplifts cargo which is less
than the nominated quantity, the seller in addition to any other legal and
commercial remedies be entitled to exercise the following options:

a. Risk sale at buyer’s cost: To sell to any other potential buyer. The price
for such sale shall be deemed conclusively the best price, which the seller
could obtain. To the price, Seller may add transaction cost, if any, to
arrive at the selling price. If such price is lesser than the price fixed for
the lot as per the contract terms, then Buyer has to compensate the
Seller for the loss suffered. The compensation amount will be calculated
as follows:

Compensation amount = (Selling Price obtained from the market –
Contract Price considering last day of the laycan being the deemed B/L
date) x Min contractual quantity or Balance contractual cargo quantity
not uplifted in MT, as agreed between the Buyer and the Seller.

BPCL shall issue a debit note for the compensation amount, if any, under
the present clause to HPL, payment of which to be done by HPL through
Electronic Transfer within 15 days from the date of issuing of Debit Note.
Conversion rate would be as per RBI reference for the pricing period of
cargo.

Without prejudice to the terms and conditions hereof defining ground for
claim of Force Majeure, it is further agreed that the Buyer or Seller shall
not be liable for any loss, claims or demands, of any nature whatsoever
or be deemed in breach of the Agreement, because of any delay or failure
in observing or performing any of the conditions or provisions of the
Agreement, if such delay or failure is caused by or arises out of any
action or order direct or indirect of the Government of India or any
agency thereof”

57. The dispute arose in respect of February / March consignment. BPCL

was unable to supply the specified quality of Naphtha. BPCL informed HPL that
59
2025:CHC-OS:91
by mid-February, BPCL was going for export and therefore, no Naphtha was

available even for a lesser quantity than HPL’s requirement of 30 KT of cargo by

February 10, 2018 and close to 40 KT by February 15, 2018. The subsequent

facts were gathered by the tribunal from the e-mails exchanged between the

parties. Those were dealt with at paragraph 8.3 of the award. The analysis of

the above e-mails indicated that BPCL was unable to supply the cargo even

during the extended period as it could not meet the parameters with regard to

the quality of the components of Naphtha. The relevant period was the laycan

period between March 4 and 5, 2018. BPCL had informed HPL about the test

results of the 22 KT of Naphtha to be loaded in HPL’s vessel, having laycan

between 4 and 5 March, 2018. The report was considered by HPL and HPL

informed BPCL that the offered cargo was not as per the specifications and

could not be accepted. HPL expressed disappointment due to failure of BPCL to

supply cargo as per the contractual specifications at the last moment, which

had jeopardized HPL’s procurement planning and operation. HPL requested

BPCL to advise on the next laycan to supply cargo which would meet the

contractual quality. Although, after much persuasion, HPL had taken approval

from their plant to deviate from the specification, HPL did not expect BPCL to

ship out the cargo without considering the requirement of a term customer.

BPCL did not advise on the next laycan as requested by HPL. Upon receiving no

offer from BPCL, HPL sent an e-mail to International Naphtha Suppliers,

enquiring about the possibility of spot supply of 25 KT +/- 10% of Naphtha to

be loaded in the first fortnight of April 2018. No reply was received to the said
60
2025:CHC-OS:91
e-mail. Question Nos. 160 and 281, which were put to RW1 were referred to.

On March 15, 2018, trade confirmation was received from Saudi Aramco,

confirming the agreement entered into between Saudi Aramco and HPL. The

affidavit of evidence of RW2 was relied upon. The agreement was entered into

on March 14, 2018 for spot supply of 55 KT +/- 10% of Naphtha with laycan of

March 27, 2018. HPL informed BPCL by a letter dated March 17, 2018 that

since December, 2017, on account of BPCL’s inability to supply the volume of

Naphtha required by the agreement, HPL’s supply chain had been severely

affected. Even deviated quality of Naphtha, as per the specifications offered on

February 16, 2018, for the supply in March 2018, could not be provided by

BPCL. Therefore, HPL was compelled to opt for risk purchase to ensure feed

security to HPL’s plant and requested for feedback for the next cargo

availability for April 2018. BPCL did not reply. On April 4, 2018, invoice was

raised by Saudi Aramco, for supply of 58 KT of Naphtha amounting to

$33807431.56. The findings of the learned tribunal are based on the e-mails

exchanged between the parties, duly supported by evidence of RW1 and RW2

and the exhibits. The learned tribunal came to the following conclusions :-

“8.8. The exchange of emails, as referred to above between the parties,
are all admitted and are part of the documents disclosed before the
tribunal. The next result of the above facts as available from the
correspondences discussed above appears to be as follows :-

a) That the shipment for February was due, but could not be supplied by
BPCL on account of its export commitments and the February 4-5 laycan
was shifted to March 4-5 laycan.

61

2025:CHC-OS:91

b) HPL requested for 30KT for 4-5 March laycan and BPCL was agreeable
to confirm 35KT in that laycan.

c) HPL requested for further 30/40KT for the April 2018 laycan, but
BPCL informed that this April requirement of HPL would be in excess of
the quantity agreed to be supplied under the present agreement and that
such supply should be considered in terms of a new MoU.

d) By 16 02 2018 BPCL intimated quality parameters which were not in
line with the contractual parameters and requested for HPL’s
acceptability.

e) HPL agreed to accept that deviated specification / quality without
precedence and requested for confirmation of firm quality specification
for future shipments.

f) Subsequently, by series of communications test results of the cargo to
be shipped for 4-5 March laycan were shared by BPCL admitting that
there was further deviation of the specification shared on 26 02 2018 and
requested for acceptability of HPL. BPCL also pointed out that it
understood the operational difficulties due to such changes and assured
that such deviation would not occur in future.

g) There was admission of deviation of specification by BPCL. Both the
parties admitted that there was deviation from the specified quality.

h) Ultimately, HPL could not accede to BPCL’s request for acceptance of
further deviated quality offered on 26 02 2018. HPL also complained that
HPL did not expect BPCL to ship out that 16 02 2018 quality cargo
without any consideration of the requirement of a term customer.

i) Admittedly, February laycan shipment was postponed to 4-5 March
and then it had offered deviated quality on 16 02 2018 and then on 26
02 2018 offered further deviated quality of specification (than that of the
quality shared on 16 02 2018) about six days-before the 4-5 March 2018
laycan.

j) Admittedly, very less time was left for HPL for procurement planning for
its requirement in order to run its plant compelling HPL to decline the
62
2025:CHC-OS:91
offer on the ground that the further deviated quality was unacceptable
for its plant.

k) In such circumstances, the option remained with HPL was to go for
risk purchase. This risk purchase materialised on 14 03 2018.

l) It also appears from the correspondences that the April laycan also did
not materialize.

m) According to BPCL, the April shipment required by HPL was outside
the quantity agreed in the agreement. BPCL informed that adjusting the
February supply due on 4-5 March since not materialized from the April,
supply of 20KT would be due to HPL under the current agreement.

n) HPL’s request for next laycan for April 2018 by mail dated 26 02 2018
and 08 03 2018 were not responded to by BPCL.

o) It is also an admitted position that there were some more supplies in
July, 2018. However, BPCL insisted that these supplies should be in
terms of new MoU on the ground that the current agreement expired by
efflux of time with the expiry of April 2018.

p) In the circumstances, HPL, floated a global tender for purchasing the
specified quality of Naphtha. However, no response was received by HPL.
Ultimately HPL had to spot purchase from Saudi Aaramco 58KT of
Naphtha. This also did not match accurately with the specifications
agreed in the agreement. However, Mr. Choudhury contends that it was
similar to the specifications agreed in the agreement and better in quality
than that was offered last by BPCL for 4-5 March laycan. Whereas Mr.
Mitra contends that the quality of the offer made by BPCL was better
than that was purchased by HPL from Saudi Aaramco.

q) On this ground Mr. Mitra argues the point of mitigation with the
additional ground of non-purchase from Indian market resulting into
higher price of the cargo added with higher freight charges and customs
duties claimed by the respondent.”

63

2025:CHC-OS:91

58. The contentions of the learned counsel for BPCL that the full quantity

under the said agreement was supplied by BPCL within the extended period,

i.e., July 2018, in terms of the contract, was not accepted. It was held that

such supply was independent of the subject agreement. The tribunal observed

that clause 19 of the Agreement provided for risk purchase under three

situations. First, was the seller’s failure to comply with the terms and

conditions mentioned under clause 6 relating to cargo laycan nomination.

Second situation was the seller’s failure to load the vessel within 2 days from

the last date of agreed laycan and the third situation was the buyer’s failure to

uplift the nominated quantity. In the present case, the second situation was

found to be applicable i.e. the seller failed to load the vessel within 2 days from

the last date of the agreed laycan. In the present case, the laycan was fixed

between March 4 to 5, 2018. BPCL was not in a position to supply the required

specification. It requested HPL to accept further deviated quality of Naptha,

much inferior to the quality disclosed on February 16, 2018. The tribunal held

that, BPCL was not in a position to load the agreed quality of cargo. HPL could

not be forced to accept the inferior quality. Therefore, according to the learned

tribunal, the second situation was attracted i.e. failure to load the vessel within

two days from the last date of laycan. Consequence of the failure of the seller

under situations 1 and 2 was risk purchase. Risk purchase was held to be the

result of default. The relevant paragraphs of the award are quoted below:-

“8.11. The consequences of seller’s failure under situations 1 and Il is the
risk purchase. The risk purchase provisions are common in both
situations 1 and II. It deals with a particular instance of default in either
64
2025:CHC-OS:91
of the situations. It is confined to seller’s failure to fix laycan in the first
case and seller’s failure to load the vessel within two days from the last
laycan date fixed in the second case. It is not dependent on the supply of
the total quantity agreed viz. 240KT +/- 10% under the agreement. It is
dependent on the quantity agreed for the laycan fixed and its default.
Under the terms of the contract Cl. 1 mentions the total supply as 240KT
+/- 10%. This amount is to be supplied in terms of Cl.2 being 20KT +/-
10% at buyer’s option every month. In this case buyer had opted for
40KT for February and March 2018 since February 2018 cargo could not
be supplied by BPCL on account of its own export commitment. BPCL
agreed to supply on 4-5 March, 2018 laycan 30/35KT. Therefore,
subsequent delivery is immaterial. Section 19(II) sprang to action as
soon there was sellers failure to load within two days of the last laycan
date (05.03.2018). Therefore, whether the subsequent delivery was under

the same contract or not, is not necessary to be gone into.
8.12. The risk purchase in CI.9 (Il) is not confined only on the seller’s
failure to load on arrival of the vessel. This clause is to be construed to
mean and include seller’s failuba to load the vessel even when the seller
is not in a position to load on the laycan for arrival of the vessel with the
specified cargo agreed between the parties. The failure includes
incapacity to load or inability to load on the laycan date. In other words,
it is dependent on the readiness to load. The vessel will reach the load
port only if the seller informs the buyer that the seller is capable/ready to
load on the laycan date. Therefore, Mr. Mitra’s argument that risk
purchase under situation II is attracted only when vessel reaches the
load port, cannot be accepted. Such an interpretation would fall foul of
prudent and good industrial practice and would be contrary to due
diligence on the part of the seller. Acceptance of such an interpretation
would render the risk purchase clause redundant in the given
circumstances, such as have happened in this case. Inasmuch as in
such a case in order to avail risk purchase the buyer would have to send
the vessel knowing fully well that the seller is unable and not in a
position to supply/load the agreed quality, incurring cost of charter
party.

65

2025:CHC-OS:91
8.13. Mr. Mitra argues that the price of Saudi Aaramco Naphtha was
higher. Whether the price was higher or lower is immaterial in view of
Cl.19. Inasmuch as risk purchase entitles HPL to purchase from other
source similar material and it provides that the price of such risk
purchase shall be deemed conclusively the best price, which the buyer
could obtain.

8.14. Endeavour has been made by Mr. Mitra to argue that the Naphtha
purchased from Saudi Aaramco was inferior in quality. The burden of
proving BPCL’s assertion that the quality of Saudi Aramco cargo inferior
to that of BPCL’s last offered cargo was on BPCL. But BPCL has not given
any evidence on this fact. BPCL has not examined any witness on its
behalf to assert this fact. We have seen that BPCL had admitted that the
quality offered on 16 02 2018 was interior than the agreed quality and
this quality further deviated in its last otter and requested for HPL’s
acceptability. The fact remains that the incidence of Risk-purchase
having occurred, Cl. 19-has been attracted. We, therefore, are bound to
follow the conditions provided in Cl.19. We can neither red something
(which is not there) in the Cluse, nor we can add or introduce something
into the Clause. In these circumstances we are to fall back on the
materials on record for deciding this question in terms of Clause 19. A
comparative table has been given both by Mr. Mitra and Mr. Choudhury
and it appears that there were certain parameters, which were better,
and the parameters of some were inferior. But the fact remains that
BPCL requested for acceptability of HPL of a deviated quality after its
inability to supply the agreed quality on account of its export
commitment. Even then, the quality deteriorated further from the quality
offered on 16 02 2018. HPL had agreed to accept the deteriorated quality
shared on 16 02 2018, after persuading its Plant, without creating
precedence. But BPCL shipped out that quality without reserving the
same for its term customer. But HPL could not persuade its plant to
accept the further deteriorated quality shared on 26 02 2018. It is HPL,
who would understand its necessity/operation security of the plant
situation. It cannot injure itself and take any risk to create disturbance
in the plant operation and/or jeopardizing its plant by accepting deviated
66
2025:CHC-OS:91
quality only to mitigate the sufferance of BPCL. We have also noted that
BPCL had admitted that it understood the operational difficulties that
might arise due to such changes and assured that this would not occur
in future (pg. 91 & 92 RD).

8.15. Mr. Mitra also compares the parameters of the Saudi Aaramco
material and the deteriorated material offered by BPCL last and also
referred to various questions.

8.16. A comparative study of the specifications offered by BPCL and
Saudi Aramco shows that Saudi Aramco had lower Sulphur content and
hat parameter of IBP was not available in the test data of Saudi Aramco.

Whereas Saudi Aramco Naphtha was within the acceptable contractual
parameters unlike Naphtha offered by BPCL. Reid Vapour Pressure being
another important parameter was 6.1 psia for Saudi Aaramco and 12.5
psia for that offered by BPCL when the maximum limit was 12 psia.
Similarly, in case of Olefin the maximum permissible Vol% being 1.0 in
the agreement, was 0.8 Vol% in the Naphtha offered by BPCL whereas it
was only 0.03 Vol% in case of Saudi Aaramco Naphtha. That apart, BPCL
under the agreement was bound to supply the guaranteed specifications
and not similar material. Whereas third party procurement can be of
similar material.

8.17. Cl.19 refers to similar material. It does not say identical material.
BPCL, having created the problem, cannot force upon HPL to accept
further deteriorated material as similar material.
8.18. Mr Mitra’s argument on this point cannot be sustained for
the reasons enumerated as hereafter. BPCL committed first breach by
informing HPL that due to its export commitment BPCL would not be
able to supply any quantity of agreed quality even in smaller size for
HPL”s February 2018 requirement (R-6 pg 104 RD). This was condoned
by HPL. HPL’s request for laycan was fixed on 4-5 March 2018. On 16 02
2018 BPCL committed second breach by offering deviated quality (inferior
than the agreed quality, R-6 pg 97 8: 96 RD) for 4-5 March 2018 laycan.
This was also condoned by HPL by agreeing to accept the deviated quality
without creating any precedent. Not being able to deliver this cargo
offered on 16 02 2018, BPCL then committed third breach on 26 02 2018
67
2025:CHC-OS:91
by offering further deviated quality (even inferior to that offered on 16 02
2018, R-6 pg 85-88 86 & 186-192). HPL attempted to condone this
breach also by requesting its plant to acknowledge acceptability, which
was declined by HPL’s plant on the ground of plant safety (R-6, pg 85
RD). This consideration was highly technical. HPL was not expected to
take the risk of injuring itself jeopardizing its plant by accepting further
deviated quality. These defaults adversely affected HPL’s procurement
planning for feeding the plant. At this juncture, only 6 days were left for
the 4-5 March laycan. After having committed breach thrice, BPCL
cannot force its further deviated quality offered on 26 02 2018 upon HPL
on the ground that that such deviated quality similar to the agreed
quality. The moment the third breach was committed by BPCL, the
incidence of risk purchase sprang into action in terms of Cl. 19 of the
agreement. Now it is no more open to BPCL to question HPL’s risk
purchase on the ground that the BPCL’s 26 02 2018 quality was similar
to or more similar than Saudi Aramco quality and argue that HPL’s risk
purchase was not justified and that this risk purchase fell foul of the
principles of mitigation and as such HPL’s risk purchase can not be
allowed. This argument seems to be an attempt to put the clock back,
inasmuch as once the incidence of risk purchase having occurred, CL.19
was activated and sprang into action by reason of clear and
unambiguous terms of the agreement.

8.19. Mr. Mitra argues vehemently on the HPL’s failure to mitigate the
loss by not purchasing the same from Indian market incurring higher
freight and subjecting the cargo to customs duty. He submits that HPL
did not endeavour to reduce the cost and mitigate the damages. He relies
on AIR 1962 SC 366 [Muralidhar Chiranjilal vs. Harish Chandra
Das).The principles enunciated therein are settled principles of law. HPL
had the responsibility to mitigate the loss. At the same time, it is also
settled principle of law that in order to save the defaulting seller from
further damage, the buyer cannot injure itself and take the risk of
jeopardizing its plant operation. Such plant operation, in this case, is
68
2025:CHC-OS:91
technical in nature and plant operators of HPL were the best judges to
decide whether such risk was worth taking.

8.20. Mr. Mitra also argues that no notice for risk purchase was given to
the claimant. This argument is also untenable. Cl. 19, nowhere in its four
corners, speaks for any notice to be given to the claimant before the risk
purchase. However, a notice dated 17 03 2018 was given by HPL to BPCL
at pgs. 106-107 of RD forwarded by a mail dated 20 03 2018 at 11:04 am
at pg. 105 of RD.

8.23. So far as market enquiry in the Indian market is concerned, a
general mail was issued by HPL inviting supply of the specified quality of
Naphtha, but no reply was received. We must also appreciate the time in
between was very short and HPL’s plant would have been in jeopardy due
to collapse of procurement planning. There is no doubt that the situation
was emergent. It has come on evidence that HPL had enquired, but did
not enquire from ONGC, Hindustan Petroleum Corporation Ltd. (HPCL)
and Indian Oil Corporation Ltd. (IOCL). Mr. Mitra, in his argument, has
made a mountain out of this failure to enquire from ONGC, HPCL and
IOCL. This has been replied to by Mr. Choudhury that HPL already had
term agreement with IOCL and HPCL and that whatever quantities were
available for spot supply, did not meet HPL’s quality specification.

8.24. Enquiries were made with respect to spot supply availability in
March 2018 with foreign (Q.92, 183-184 of RW-l’s deposition) and
domestic suppliers (Q.125-127 of RW-1’s deposition] as well as floating
an email enquiry to potential spot suppliers generally (Ext. C-14, initially
marked as C-ID-1 during Q.160 of RW-1’s deposition). HPL did not
enquire about possibility of spot suppliers from Hindustan Petroleum
|Q.124 & 224 of RW-1’s deposition] and IOCL [Q.124, 239-241 of RW-l’s
deposition] because it already had term agreements with those
companies to purchase all the Naphtha meeting its required
specifications and whatever quantities they had with them for spot
supplies, did not meet HPL’s quality specifications. HPL did not enquire
about the possibility of spot supply from ONGC [Q.123 & 126 of RW-1’s
deposition] owing to the fact that ONGC supplies all the Naphtha meeting
69
2025:CHC-OS:91
HPL’s specifications to its own petrochemical company, OPAL. As a
result, after all enquiries, Saudi Aaramco matched as the only supplier
with spot supplies then available meeting HPL’s immediate requirement.
According to Mr. Choudhury, HPL had acted reasonably in the given
circumstances and duly satisfied the test of reasonability as recognized
by the Hon’ble Supreme Court in M. Lachhia Setti & Sons Ltd. & Ors. vs.
Coffee Board
| AIR 1981 SC 162 paragraphs 12-14).

***

8.27. In respect of mitigation, Mr. Choudhury argues that HPL was under

no obligation to injure itself, its character, its business or its property to
reduce the damages payable by BPCL, the wrong doer. “The question
what is reasonable for a plaintiff to do in mitigation of his damages is not
a question of law, but one of facts in the circumstances of each particular
case, the burden of proof being upon the defendant.” Halsbury’s Laws of
England V.10 para 143 pg.113 quoted in Muna Sona Sundaram Chettier
vs. Sona Theeanna Chockalingam Chettiar
[AIR 1938 Madras 672].
The
same principle was also enunciated in Prafulla Ranjan Sarkar (supra)
and M. Lachhia Setti (supra). At the same time, HPL was not obliged to
accept inferior quality Naphtha from BPCL, which was rejected by its
plant, merely because the same would have reduced the damages
payable by BPCL. Such contention would amount to feeding the breach.
HPL commenced its search for that similar material only after validly
rejecting the cargo offered by BPCL.
The decision in M/s. Muralidhar
Chiranjilal (supra) [paragraphs 4, 12 and13] is distinguishable, as in this
case the contract had become impossible of performance and the BPCL
had to prove the market rate for had similar goods, which the BPCL failed
to supply. provided the procurement cost of similar material which is
deemed conclusively the best price.

8.29 HPL claimed that the procurement price for 58326.86 KT of cargo
value adding the cost of freight, customs duty etc. converted into INR
comes to INR 249,28, 18,209.00 (R-8, page 109 RD). The details of cargo
value, freight invoice, cargo handling charges, on board charges, marine
insurance charges, custom duty etc and the payments made therefor are
70
2025:CHC-OS:91
on record (Ext-R-8 pages 109 to 126). The procurement price for 30 KT
prorata works out to INR 128,21,63,077.00 (paragraph 28 CS). The
contract price for
30 KT cargo as per formula works out to INR 116,83,27,675.00
(paragraph 38 read with Annexure D at page 38, Affidavit Evidence of
RW-1 and para 26, CS). Thus applying the formula provided in Cl, 19,
the difference works out to INR 11,38,35,602.00.

8.30. In the circumstances as discussed above, we hold that HPL was
justified in resorting to CI.19 (I) for risk purchase in the given
circumstances for BPCL’s inability or incapacity to supply even the
inferior quality material offered on 16 02 2018, which HPL did not expect
BPCL to ship out without any consideration of the requirement of a term
customer, and then offering further inferior quality material after having
failed to supply February commitment owing to BPCL’s export
commitment compelling HPL to resort to risk purchase within a very
short span of time. Therefore, HPL is entitled to recover the difference
between the agreed price and the risk purchase price in terms of the
formula provided in C1.19 (t) applicable to C1.19 (II) adding to the
purchase price being deemed conclusively the best price the cost of
procurement together with freight, customs duty etc. proportionate to
30KT out of 58KT spot purchase pro rata on all these counts. HPL shall
also be entitled to interest at the rate as agreed in Cl. 5 from 15 days
after the raising of the debit note by HPL after 26.04.2018 (the date of
payment to Saudi Aramco) till the date of Award.”

59. Such findings of the learned tribunal are also based on the materials on

record and the understanding of the clauses of the contract. The explanation of

BPCL in not being able to supply either the quality of Naphtha that was

originally agreed or the quality with deviations which was later agreed, were

considered and rejected with reasons. BPCL asked HPL to agree to accept a

further low quality of Naphtha which was found to be contrary to the agreed
71
2025:CHC-OS:91
terms and the nomination of the buyer. Thus, it was held that as the seller

could not ensure supply of the quality of Naphtha that was nominated, the risk

purchase clause would be applicable, irrespective of whether a higher price was

paid to Saudi Aramco and in spite of there being other sellers of Naphtha in the

country or even if the quality supplied by Saudi Aramco was worse than the

quality offered by BPCL. Whether the vessel was actually berthed or not, could

not be relevant in view of the unreadiness to supply. With regard to the

quantity of Naptha supplied later, it was found that the same was not

connected with the cargo involved in the risk purchase.

60. The issues have been discussed in details, as above. Some important

judicial authorities are discussed to test whether the award is liable to be set

aside upon application of the ratios laid down.

61. The Hon’ble Apex court in OPG Power Generation Private Limited vs

Enexio Power Cooling Solutions India Private Limited and Anr. reported in

2024 SCC Online SC 2600, upon discussing the decisions rendered earlier on

such issue held that, an award could not be said to be against public policy of

India if there was a mere infraction of the municipal laws of India. For an

award to be in contravention with the public policy of India, there must be

infraction of the fundamental policy of Indian law including a law meant to

serve public interest or public good. Such situation has not arisen in the

instant case.

62. In Oil and Natural Gas Corporation LTD. (ONGC) v. Saw Pipes Ltd.

reported in (2003) 5 SCC 705 it was held that when an award was patently in
72
2025:CHC-OS:91
violation of statutory provisions, the same would be contrary to public interest.

Such an award was likely to adversely affect the administration of justice. An

award could be set aside on the ground of patent illegality, if it was so unfair

and unreasonable that it shocked the conscience of the court. Such award

would be adjudged as opposed to public policy. As discussed earlier, this court

does not find that the award shocks its conscience.

63. In Associate Builders vs Delhi Development Authority reported in

(2015) 3 SCC 49, the Hon’ble Apex court held that the principle of audi

alteram partem was undoubtedly a fundamental juristic principle in Indian law.

It was held that disregarding orders of superior courts or the binding effect of

the judgment of a superior court, would also be regarded as being contrary to

the fundamental policy of Indian law. It was further elaborated that when a

finding was based on no evidence or an arbitral Tribunal took into account

something irrelevant to decide the issues or ignored vital evidence while

arriving at its decision, such decision would necessarily be perverse. To this, a

caveat was added by observing that when a court applied the public policy test

to an arbitral award, it should not act as a court of appeal and consequently

errors of fact could not be corrected. Similarly, a possible view of the

arbitrators on facts also could not be corrected as the arbitral tribunal was the

master of the quality and quantity of evidence and the facts. The quality of the

evidence, that is, the evidence was up to the expectation of a judicially

trained mind, would not per se render an award vulnerable. Thus, if the

arbitral Tribunal’s approach was neither arbitrary nor capricious, the tribunal
73
2025:CHC-OS:91
would have the last word on facts and evidence. The court finds that the

approach of the learned tribunal was reasonable and not arbitrary.

64. The Hon’ble Apex court in Ssanyong Engineering and Construction

Company Limited vs National Highway Authority of India reported in

(2019) 15 SCC 131, held that the award would be vulnerable if patent illegality

appeared on the face of the award and such illegality went to the root of the

matter. If an arbitral tribunal wandered beyond the contract and dealt with

matters not referred, would also be a jurisdictional error and the award could

be set aside on the ground of patent illegality. This is not such a case.

65. In view of the discussions which have been made in the foregoing

paragraphs with regard to the manner in which the arbitral tribunal had dealt

with the claim of the petitioner and the counterclaim of the respondents, this

court does not find that justice has been denied, inasmuch as, the award so

passed has neither shocked the conscience of the court nor is the award

patently illegal.

66. In paragraph 59 of OPG (supra), the Hon’ble Apex Court discussed

morality. Morality was also held to be akin to shocking the conscience of the

court. In paragraph 60, patent illegality was discussed and it was held that if

an award patently violated statutory provisions, it would be against public

interest and thus the award could be set aside on the ground of patent

illegality.

67. Perversity as a ground of challenge was discussed in paragraphs 63 to

67. It was held that the decision of the tribunal should be so irrational that no
74
2025:CHC-OS:91
reasonable man could have arrived at such a finding. Paragraph 63 to 67 are

quoted below:-

“63. Perversity as a ground for setting aside an arbitral award was
recognized in Western Geco (supra). Therein it was observed that an
arbitral decision must not be perverse or so irrational that no reasonable
person would have arrived at the same. It was observed that if an award
is perverse, it would be against the public policy of India.

64. In Associate Builders (supra) certain tests were laid down to
determine whether a decision of an arbitral tribunal could be considered
perverse. In this context, it was observed that where: (i) a finding is based
on no evidence; or (ii) an arbitral tribunal takes into account something
irrelevant to the decision which it arrives at; or (iii) ignores vital evidence
in arriving at its decision, such decision would necessarily be perverse.
However, by way of a note of caution, it was observed that when a court
applies these tests it does not act as a court of appeal and, consequently,
errors of fact cannot be corrected. Though, a possible view by the
arbitrator on facts has necessarily to pass muster as the arbitrator is the
ultimate master of the quantity and quality of evidence to be relied upon.
It was also observed that an award based on little evidence or on
evidence which does not measure up in quality to a trained legal mind
would not be held to be invalid on that score.

65. In Ssangyong (supra), which dealt with the legal position post 2015
amendment in Section 34 of the 1996 Act, it was observed that a decision
which is perverse, while no longer being a ground for challenge under
“public policy of India”, would certainly amount to a patent illegality
appearing on the face of the award. It was pointed out that an award
based on no evidence, or which ignores vital evidence, would be perverse
and thus patently illegal. It was also observed that a finding based on
documents taken behind the back of the parties by the arbitrator would
also qualify as a decision based on no evidence in as much as such
decision is not based on evidence led by the parties, and therefore, would
also have to be characterized as perverse,
75
2025:CHC-OS:91

66. The tests laid down in Associate Builders (supra) to determine
perversity were followed in Ssyanyong (supra) and later approved by a
three-Judge Bench of this Court in Patel Engineering Limited v. North
Eastern Electric Power Corporation Limited
.

67. In a recent three-Judge Bench decision of this Court in DMRC
Ltd. v. Delhi Airport Metro Express (P) Ltd. [DMRC Ltd. v. Delhi Airport
Metro Express (P) Ltd., (2024) 6 SCC 357 : (2024) 3 SCC (Civ) 112 : 2024
INSC 292] , the ground of patent illegality/perversity was delineated in
the following terms : (SCC p. 376, para 39)

“40. In essence, the ground of patent illegality is available for setting
aside a domestic award, if the decision of the arbitrator is found to be
perverse, or so irrational that no reasonable person would have arrived at
it; or the construction of the contract is such that no fair or reasonable
person would take; or, that the view of the arbitrator is not even a
possible view. A finding based on no evidence at all or an award which
ignores vital evidence in arriving at its decision would be perverse and
liable to be set aside under the head of “patent illegality”. An award
without reasons would suffer from patent illegality. The arbitrator
commits a patent illegality by deciding a matter not within its jurisdiction
or violating a fundamental principle of natural justice.”

68. Scope for interference with an arbitral award was discussed in paragraph

68 and 69 which are quoted below:-

“Scope of interference with an arbitral award

68. The aforesaid judicial precedents make it clear that while exercising
power under Section 34 of the 1996 Act the Court does not sit in appeal
over the arbitral award. Interference with an arbitral award is only on
limited grounds as set out in Section 34 of the 1996 Act. A possible view
by the arbitrator on facts is to be respected as the arbitrator is the
ultimate master of the quantity and quality of evidence to be relied upon.

76

2025:CHC-OS:91
It is only when an arbitral award could be categorised as perverse, that
on an error of fact an arbitral award may be set aside. Further, a mere
erroneous application of the law or wrong appreciation of evidence by
itself is not a ground to set aside an award as is clear from the provisions
of sub-section (2-A) of Section 34 of the 1996 Act.

This extract is taken from OPG Power Generation (P) Ltd. v. Enexio Power
Cooling Solutions (India) (P) Ltd.
, (2025) 2 SCC 417 : 2024 SCC OnLine
SC 2600 at page 473

69.In Dyna Technologies [Dyna Technologies (P) Ltd. v. Crompton
Greaves Ltd.
, (2019) 20 SCC 1, paras 27-43] , a three-Judge Bench of
this Court held that courts need to be cognizant of the fact that arbitral
awards are not to be interfered with in a casual and cavalier manner,
unless the court concludes that the perversity of the award goes to the
root of the matter and there is no possibility of an alternative
interpretation that may sustain the arbitral award. It was observed that
jurisdiction under Section 34 cannot be equated with the normal
appellate jurisdiction. Rather, the approach ought to be to respect the
finality of the arbitral award as well as party’s autonomy to get their
dispute adjudicated by an alternative forum as provided under the law.”

69. In Paragraph 71.1 of OPG (supra), it was held that, in order to avoid

being vulnerable to challenge, the tribunal’s reasons must deal with all the

issues that were put to it. It should set out the finding of facts and its reasons

so as to enable the parties to understand them and state how particular points

were decided. The tribunal was required to set out not only its views, but also

make it clear that it had considered the alternative version and had rejected

such version. The said paragraph is quoted below :-

“71.1 As to the form of a reasoned award, in Russell on Arbitration (24th
Edition, Page 304) it is stated thus :

77

2025:CHC-OS:91
“6.032. No particular form is required for a reasoned award although ‘the
giving of clearly expressed reasons responsive to the issues as they were
debated before the arbitrators reduces the scope for the making of
unmeritorious challenges’. When giving a reasoned award the tribunal
need only set out what, on its view of the evidence, did or did not happen
and explain succinctly why, in the light of what happened, the tribunal
has reached its decision, and state what that decision is. In order to
avoid being vulnerable to challenge, the tribunal’s reasons must deal
with all the issues that were put to it. It should set out its findings of fact
and its reasoning particular points were decisive. It should also indicate
the tribunal’s findings and reasoning on issues argued before it but not
considered position with respect to appeal on all the issues before the
tribunal. When dealing with controversial matters, it is helpfulfor the
tribunal to set out not only its view of what occurred, but also to make it
clear that it has considered any alternative version and has rejected it.

Even if several reasons lead to the same result, the tribunal should still
set them out. That said, so long as the relevant issues are addressed
there is no need to deal with every possible argument or to explain why
the tribunal attached more weight to some evidence than to other
evidence. The tribunal is not expected to recite at great length
communications exchanged or submissions made by parties. Nor is it
required to set out each step by which it reached its conclusion or to deal
with each and every point made by the parties. It is sufficient that the
tribunal should explain what its findings are and the evidential route by
which it reached its conclusions.”

70. The award, which has been scrutinized in detail, indicates that the

contentions of the petitioner were taken into consideration and applied in the

context of the terms and conditions of the contract. As long as the relevant

issues have been addressed, the award is sustainable on the ground of

adequacy of reasons. It is sufficient if the tribunal explains what the findings
78
2025:CHC-OS:91
are and the evidence on the basis of which the conclusions have been arrived

at. An award will pass the test of being a reasoned award, if it reads properly,

is intelligible and adequate.

71. Paragraph 72 of OPG (Supra) laid down that, if the conclusion of the

arbitrator was based on a possible view of the matter, the court should not

interfere. It was further held that an arbitral tribunal had the jurisdiction to

interpret a contract, having regard to the terms and conditions of the contract,

conduct of the parties, correspondences exchanged, circumstances of the case

and pleadings. The relevant paragraph is quoted below:-

“72. An Arbitral Tribunal must decide in accordance with the terms of
the contract. In a case where an Arbitral Tribunal passes an award
against the terms of the contract, the award would be patently illegal.
However, an Arbitral Tribunal has jurisdiction to interpret a contract
having regard to terms and conditions of the contract, conduct of the
parties including correspondences exchanged, circumstances of the case
and pleadings of the parties. If the conclusion of the arbitrator is based
on a possible view of the matter, the Court should not intefere [ See
: SAIL v. Gupta Brother Steel Tubes Ltd., (2009) 10 SCC 63 : (2009) 4
SCC (Civ) 16; Pure Helium India (P) Ltd. v. ONGC, (2003) 8 SCC
593; McDermott International Inc. v. Burn Standard Co. Ltd., (2006) 11
SCC 181; MMTC Ltd. v. Vedanta Ltd., (2019) 4 SCC 163 : (2019) 2 SCC
(Civ) 293] . But where, on a full reading of the contract, the view of the
Arbitral Tribunal on the terms of a contract is not a possible view, the
award would be considered perverse and as such amenable to
interference.”

72. The submissions of Mr. Bose with regard to the illegality in the award do

not pass the tests which have been laid down in the above judicial authorities.
79

2025:CHC-OS:91

73. In Dyna Technologies Private Limited vs. Crompton Greaves Limited

reported in (2019) 20 SCC 1, a Three-Judge Bench of the Hon’ble Apex Court

held that the jurisdiction under section 34 of the said Act could not be equated

with the normal appellate jurisdiction. Rather, the approach would be to

respect the finality of the arbitral award as well as the party’s autonomy to get

the dispute resolved by an alternative forum as provided in law. In the said

decision, the Hon’ble Apex Court also held that the award was amenable to

challenge if no reasons were recorded or the reasons recorded were

unintelligible, improper and revealed a flaw in the decision making process.

The scope of interference of the courts on the interpretation or the construction

of the contract by the tribunal was also discussed in the said decision and it

was held that the Courts should not interfere when the view of the arbitral

tribunal on the terms of the contract was a possible view. It was further

observed that the arbitral Tribunal had the jurisdiction to interpret a contract

having regard to the terms and conditions of the contract, conduct of the

parties, the correspondences exchanged, circumstances of the case and

pleadings.

74. The reference to British Shipping Laws, definition of laytime, laycan, and

shipment period in FOB sales, and the authority cited by Mr. Bose, are not

relevant in the present context. The difficulties which arose in practice, when

parties to a FOB contract used the words laytime or laycan, to indicate the date

of shipment, were deliberated upon. In the case in hand, although the

expressions laycan and laytime were used in the contract, the counter claims
80
2025:CHC-OS:91
were allowed, on the interpretation of the clauses of the contract. The definition

of laycan in the context of risk purchase to contend that, as the vessel had

never arrived, BPCL could cancel, was found irrelevant in view of clause 19.

The learned Tribunal clearly held that, the circumstances to allow the counter

claim under the head risk purchase in terms of clause 19 of the contract,

existed. The seller was not in a position to supply the quality of goods either

within the dates which were settled or thereafter and could not even advise as

to when the cargo would be available. Under such circumstances, the Tribunal

found from the evidence that, HPL had no other alternative, but to approach

Saudi Aramco for spot purchase.

75. McDermott International Inc. v. Burn Standard Co. Ltd. reported in

(2006) 11 SCC 181, does not support the case of the petitioner.

76. PSA SICAL Terminals (P) Limited vs Board of Trustees of V.O.

Chidambar Port Trust Tuticorin reported in 2021 SCC Online SC 508 is

also a decision on the tribunal’s authority to interpret a contract and the

correspondence exchanged by the parties. The subject award, as already

discussed above, has taken into consideration the contractual terms and the

correspondence exchanged between the parties. Oral and documentary

evidence have been considered. Weighing of evidence by this court cannot be

permitted. The tribunal is the best judge in respect of both quality and quantity

of evidence.

77. In Steel Authority of India Limited versus M/s TLT Engineering

India Private Limited and Anr., the Hon’ble Court held that, a court
81
2025:CHC-OS:91
exercising jurisdiction under Section 34, of the said Act, could not undertake

an adjudication, so as to supply reasons in support of an award or supplement

the reasons of the arbitral tribunal. In this case, the court is not required to

justify the findings arrived at by giving additional reasons and further

interpretations.

78. The decisions Rajinder Kumar Kindra vs Delhi Administration

through Secretary (Labour) & Ors. reported in (1984) 4 SCC 635 and K.P.

Poulose vs State of Kerala reported in (1975) 2 SCC 235 have no relevance.

79. The award is based on reasons, appreciation of evidence, both oral and

documentary and interpretation of the contract. The award refers to the

answers to the relevant questions put to RW1 and RW2. The award deals with

the correspondence between the parties. Each issue was dealt with separately

and decided. The findings are intelligible, adequately reasoned and sound.

80. Under such circumstances, this application is dismissed. GA COM 2 of

2024 is accordingly disposed of. The award is upheld.

Later

81. Learned Advocate for the petitioner prays for stay of the award. The

prayer for stay is refused.

Urgent Photostat certified copies of this judgment, if applied for, be

supplied to the parties upon fulfillment of requisite formalities.

(Shampa Sarkar, J.)



Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here