Central Warehousing Corporation vs Mohammed Azmath on 4 January, 2025

0
64

Bangalore District Court

Central Warehousing Corporation vs Mohammed Azmath on 4 January, 2025

   KABC170026022023                           Digitally signed by
                                 SUDINDRA SUDINDRA NATH S
                                 NATH S   Date: 2025.01.06
                                          15:46:48 +0530




IN THE COURT OF LXXXIII ADDL. CITY CIVIL & SESSIONS JUDGE,
           COMMERCIAL COURT, BENGALURU (CCH-84)

            Present: Sri S. Sudindranath, LL.M., M.B.L.,
                        LXXXIII ADDL. CITY CIVIL & SESSIONS JUDGE
                                   BENGALURU.

                           COM.A.P.No.166/2023

                 Dated on this 4th day of January 2025

   Plaintiff/s               Central Warehousing Corporation,
                             (Government of India Undertaking)
                             Regional Office,
                             No.9, Pallavi Complex,
                             Mission Road,
                             Bangalore - 560027.
                             Represented by
                             Regional Manager.

                             (By Sri.M.Aswathanarayana Reddy,
                              G.L.Ravi, Advocates)
                             // versus //
   Defendant/s        1.     Sri.Mohammed Azmath,
                             Proprietor,
                             M/s.Zag Transport,
                             Opp. PWD Quarters,
                             House No.1-892,
                             Old Jewargi road,
                             Gulbarga - 585102.

                      2.     The Arbitral Tribunal of
                             Pradeep Kumar Gupta,
                             Sole Arbitrator,
                             Former Special Director General,
                             CPWD, T-17,
                             Green Park Extension,
                             New Delhi -16.
                                    2
                            CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023




                          (D1 By Sri.Sundar Raj,
                           Shakthi Prakash.D.T., Pavan Kumar,
                          Aleemuddin Siddiqui, Advocates)



    Date of Institution of suit        :         26/08/2017
    Nature of the suit                 :    Arbitration Suit under
                                               Arbitration Act
    Date of commencement of            :
    recording of the evidence                          --
    Date  on     which   the           :         04/01/2025
    Judgment was pronounced.
                                       :   Year/s   Month/s Day/s
    Total duration
                                            07         04           09


                          JUDGMENT

This is a petition under Section 34 of the Arbitration

and Conciliation Act filed by the claimant before the

Arbitral Tribunal challenging the Arbitral Award passed

by Respondent No. 2 herein, dated 31-5-2017, in case

No. ARB-PKG-914, partly allowing the claim of the

claimant / petitioner herein & awarding Rs. 4,54,508 out

of the total claim of Rs. 20,61,294 and also allowing the

counterclaims raised by the Respondent before the

Arbitral Tribunal, namely Respondent No. 1 herein.
3

CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

2. On issuance of notice of present petition, the

Respondent No. 1 has entered appearance through

counsel and filed detailed objections to the present

petition. Notice to Respondent No. 2, who is the learned

arbitrator, is dispensed with.

3. It is to be noted that during the pendency of the

present petition, Respondent No. 1 had filed I.A. No. 2

under Order VII Rule 10 CPC, contending that the

present petition has to be filed before the Gulbarga court

and the courts at Bangalore do not have jurisdiction to

entertain the present petition. Said application has been

rejected by my learned predecessor vide order dated 18-

04-2023.

4. Initially, the present petition was filed before the

Additional City Civil Court, Bangalore, and was

numbered as A.S. 100 of 2017. Thereafter, considering

that the case involves a commercial dispute of value
4
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

which is more than the specified value, the present case

was transferred to this Commercial Court and

renumbered as above Commercial AP 166 of 2023.

5. The arbitration records have been secured and are

available in the file.

6. At the time of arguments, both sides have filed

written arguments and I have perused the same. I have

also perused the records of the case.

7. The only point that arises for my consideration is :-

Whether the impugned arbitral award

dated 31-5-2017 passed by Respondent No.

2 herein in case No. ARB/PKG/914,

dismissing certain claims of the petitioner

herein and allowing the counterclaims of

Respondent No. 1 herein calls for

interference in the present petition?
5

CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

8. My answer to the above point is as per finding for

the following :-

REASONS.

9. In the course of this judgment, for the sake of

convenience, the parties are referred as per their rank

before the Arbitral Tribunal i.e. the Petitioner herein is

referred to as the Claimant and Respondent No. 1 herein

is referred to as the Respondent.

10. The facts in brief are that, the claimant is a

corporation established under the Warehousing

Corporation Act, 1962. The claimant floated a tender for

appointment of a handling and transport contractor [H&T

contractor] at Gulbarga, and the respondent, who was

the existing contractor for the earlier period, submitted

his bid. The bid of the respondent was accepted vide

office letter dated 29.09.2010, which culminated in a

formal agreement between the parties dated 15.11.2010.

The respondent was appointed as Handling and
6
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

Transport Contractor (H&T Contractor) for a period of two

years from 18.10.2010 to 17.10.2012.

11. Disputes arose between the parties under the said

agreement, since it is the grievance of the claimant that

the respondent contractor was not deploying sufficient

labor for timely clearance of rakes. This resulted in show

cause notice being issued to the contractor by the

claimant. Due to delay in clearance of the rakes, the

railways was charging substantial demurrage charges,

which were paid by the claimant and adjusted from the

payments due to the contractor / Respondent. On

18.08.2012, the last rake was handled by the contractor

respondent, and thereafter the contractor made himself

unavailable for performing his part of the work under the

contract. In spite of several communications to the

contractor requesting him to resume the work, the

contractor did not respond. Ultimately, the claimant

issued a letter dated 8-10-2012 terminating the contract
7
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

with effect from 8-10-2012 and brought to the notice of

the contractor that the handling and transport work for

the remaining term of the contract, that is, up to 17-10-

2012, would be carried out through a new contractor at

the risk and cost of the respondent.

12. The contract between the parties contained

arbitration clause for the settlement of any dispute

between the parties by arbitration by a sole arbitrator to

be appointed by the MD of the claimant. In view of

disputes having arisen between the parties, initially one

Mr. S.P. Singha was appointed as sole arbitrator, and on

his death, Respondent No. 2 was appointed as the

arbitrator by the MD of the claimant.

13. The claimant filed a statement of claim reiterating

the above facts and raised the following claims. Claim

No. 1 was towards the demurrage charges deducted by

Food Corporation of India and towards payment for
8
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

casual labor. The total amount of such demurrage

charges and amount recoverable towards non-supply of

casual labor was claimed as Rs. 21,37,393. After

adjusting the amount recovered from the bills, as well as

the pending bills of the contractor and the security

deposit viz. Rs. 12,30,264, the net amount claimed under

Claim No. 1 was Rs. 9,07,129.

14. Under Claim No. 2, the claimant sought a sum of

Rs. 6,77,067 towards risk and cost amount for the period

from 8-10-2012 to 17-10-2012, i.e. from the date of

termination of the contract of the respondent till the

completion of the contract period, when the handling and

transport work, was carried out through a new

contractor.

15. Claim No. 3 was for recovery of a sum of Rs.

4,77,098 on the ground that the claimant received a

notice from the recovery officer, office of the Employees’
9
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

Provident Fund Organization, Regional Office, Gulbarga,

demanding payment of penal damages and interest of the

said sum of Rs. 4,77,098. Since the claimant, as the

principal employer, apprehending that the liability may

crystallize, the claimant paid the above amount to the

recovery officer of the Employees’ Provident Fund

Organization. However, since this amount was essentially

payable by the contractor, the claimant sought recovery

of the said amount.

16. Accordingly, the statement of claim was filed

claiming a total sum of Rs. 20,61,294 along with interest.

17. To the said statement of claim, the respondent filed

a detailed statement of defense denying the claims of the

claimant and also raised counterclaims. It was contended

that the deduction of demurrage charges by the Food

Corporation of India was illegal, and therefore there was

no question of the respondent paying the said amounts
10
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

to the claimant. In respect of Claim No. 2, for recovery of

risk and cost amount for 10 days from 8-10-2012 to 17-

10-2012 is concerned, it was contended that there is no

basis for the calculation of the amount of Rs. 6,77,067 as

claimed, and therefore the claimant is not entitled to the

same. Insofar as Claim No. 3 for recovery of PF amount is

concerned, it was contended that the respondent has

already paid the due amount towards PF, and there was

an error in the statement, for which the respondent had

requested the Commissioner of Regional Office Provident

Fund, Gulbarga, to provide records because on some

occasions the claimant was directly depositing the PF

amount, and on other occasions the respondent was

paying the same. Therefore, in fact, no amount was due

and payable to the PF Department, and the claimant was

not justified in paying the said sum to the PF

Department, and therefore the claimant is not entitled to

recovery of the same.

11

CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

18. Apart from denying the claims, the respondent

also raised various counterclaims. Firstly, a sum of Rs.

30,000 [sic: Rs. 30 Lakhs] was claimed towards pending

bills. Apart from this, it was contended that the

demurrage had been illegally adjusted out of the

payments to the contractor and therefore sought recovery

of Rs. 9,43,680, which was unlawfully adjusted towards

the demurrages from the amount payable towards the

bills of the contractor respondent. Apart from this,

another counterclaim raised was for recovery of the

security deposit amounts of Rs. 6,25,000 and Rs. 54,800.

Thereby, counter-claim was raised for recovery of a total

sum of Rs. 46,33,480 towards counterclaims.

19. To the said counterclaims, the claimant filed an

objection statement and rejoinder denying all the

counterclaims. The respondent filed a subsequent

pleading styled as a “counter to the rejoinder”, in which

the respondent amplified its counterclaims, by claiming
12
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

sum of Rs. 88,68,451/= towards Difference amount

payable for diverted route of 21 kilometers from 16-8-

2010 to 22-10-2012. This claim was raised on the ground

that during the contract period, as per the orders of the

Deputy Commissioner, Gulbarga, there was a change of

route, as a result of which the respondent had to carry

the goods for an additional distance of 21 kilometers,

which was not covered in the contract. Hence, the

respondent claimed an additional amount of Rs.

88,68,451.

20. Apart from this, another counterclaim raised was

for a sum of Rs. 19,90,034 towards the breakdown of the

weighbridge of the claimant from 14-1-2011 to 22-10-

2012, as a result of which 10% of the weighment had to

be weighed at a distant weighbridge. Hence, for carrying

the goods for the additional distance for weighing 10% of

the goods, this counterclaim was raised.
13

CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

21. Thereby, in this subsequent pleading, the

respondent raised a counterclaim for a total sum of

Rs. 1,36,91,965.

22. Before the learned arbitrator, the parties adduced

both oral and documentary evidence. After hearing both

sides, the learned arbitrator passed the impugned award,

whereby, as against the total claim of the claimant of Rs.

20,61,294, the learned arbitrator partly allowed the

claims of the claimant only to the extent of Rs. 4,54,508

and awarded interest thereon of Rs. 2,30,981.

23. Insofar as the counterclaims are concerned, the

learned arbitrator awarded a sum of Rs. 1,36,71,467 and

also awarded interest of Rs. 69,50,707. Thereby, by the

operative portion of the award, the learned arbitrator

held that the total amount, including interest, payable to

the respondent under the counterclaims is Rs.

2,06,22,174, whereas the amount payable to the
14
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

claimant is Rs. 4,54,508 plus interest amount of Rs.

2,30,981, that is Rs. 6,85,489, and held that if the said

amounts are not cleared within 3 months, the said

amounts will carry interest.

24. Aggrieved by the said arbitral award, insofar as it

rejects some of the claims of the claimant and awards the

counterclaims of Respondent, the Petitioner / claimant is

before this court challenging the said award under

Section 34 of the Arbitration and Conciliation Act.

25. In the petition, as well as the written arguments

filed by the learned counsel for the petitioner, it is

contended that the arbitral award suffers from an error

apparent on the face of the record and patent illegality.

Further, it is contended that the learned arbitrator has

passed the award ignoring relevant provisions of the

contract between the parties, thereby going beyond the

terms of the contract, which is impermissible.
15

CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

26. Two technical contentions raised are that the award

is passed without framing issues and that the contract

does not provide for the raising of counterclaims by

Respondent No. 1. Therefore, the counterclaims have

been illegally raised and could not have been considered

by the learned arbitrator on merits.

27. Apart from this, all other contentions raised by the

claimant pertain to the findings of the learned arbitrator

in respect of the claims and counterclaims, contending

that they are perverse and suffer from illegality appearing

on the face of the award. On these grounds, the

petitioner seeks to set aside the arbitral award.

28. Per contra, in the objections to the present petition

filed by Respondent No. 1 and the written arguments

filed by the learned counsel for Respondent No. 1, the

findings of the award are supported. It is contended that
16
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

the petitioner has not made out grounds to set aside the

arbitral award under Section 34 of the Act.

29. Having considered the rival contentions, at the

outset, let me deal with the two technical contentions

raised by the petitioner that the award is vitiated since

issues were not framed and that the learned arbitrator

could not have considered the counterclaims on their

merits because there is no clause in the contract

permitting the raising of counterclaims.

30. Insofar as the contention that the award is vitiated

as it was passed without framing issues or formulating

points for consideration is concerned, it is to be noted

that there is an order of the Learned Arbitrator [earlier

Arbitrator : Mr. S.P. Singha] dated 24-04-2014, which

is as follows:

“The revised statement of claims after
correction was submitted on 18th November
2013 by the Regional Manager, Presenting
Officer CWC of the Regional Office, Bangalore.

17

CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

The Respondent, M/s. Zak Transport, has not
filed the defense statement till today.
However, the Respondent has been allowed
time to submit the defense statement and the
counterclaim by 30th November 2014 as
requested in its application.
I have decided to hear both the parties at
Bangalore at 10.30 hours on 26.05.2014 in
the Regional Office, Central Warehousing
Corporation at No. 9, Mission Road,
Bangalore, 560027.

I have also decided that each claim and
counterclaim will be an issue for
adjudication. However, parties are at
liberty to propose any new issues for
consideration.

During the hearing, the rules of procedure
under Section 19 of the Arbitration and
Conciliation Act 1996, venue of the arbitration
proceedings, Section 20 of the Act, language
during the arbitral proceedings, Section 22 of
the Act, and procedure of hearings and
written proceedings, Section 24 of the Act will
be decided after hearing both the parties on
this date.”

(Emphasis Supplied)

31. Therefore, it is clear that in the course of the

arbitral proceedings, there is an order of the learned

arbitrator, viz. the earlier arbitrator Mr. Singha, holding

that each claim and counterclaim will be an issue for

adjudication, but giving liberty to both sides to propose
18
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

any new issues. The claimant, in the course of the

arbitral proceedings, did not raise any grievance with

respect to the said order of the learned arbitrator, nor did

the claimant propose any new issues viz. other than each

claim and counterclaim being considered a distinct issue

for adjudication. It is to be noted that, having not

proposed any new issues and having allowed the arbitral

proceedings to culminate in the passing of the award

without raising any objections at the relevant point of

time or calling upon the Learned Arbitrator to frame

issues, it does not now lie in the mouth of the claimant to

attack the arbitral award on the ground that it is passed

without formally framing issues.

32. On the perusal of the arbitral award, it is noted that

the Learned Arbitrator has considered each head of claim

and counterclaim separately, assigning separate reasons

for the same, and therefore no prejudice is caused to

either side by non-framing of the issues. As rightly noted
19
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

by the Learned Arbitrator in the order dated 24-04-2014,

each claim and counterclaim shall form a distinct issue

to be adjudicated separately, and that is how the learned

arbitrator has proceeded in the impugned award, and

therefore no prejudice has been caused to the claimant

by non-framing of issues since each head of claim and

counterclaim is considered separately and adjudicated

separately. Therefore, this is not a ground for setting

aside of the arbitral award.

33. Even otherwise, it is to be noted that under Section

19 of the Arbitration and Conciliation Act, the arbitral

tribunal is not bound by the procedures enjoined by CPC,

and therefore it is not mandatory for the arbitral tribunal

to frame issues as mandated by Order 14 of the CPC.

Further, under Section 19 [3] of the Act, the arbitral

tribunal, subject to any agreement between the parties

regarding procedure, is free to conduct the proceedings in

the manner it considers appropriate. Therefore, as long
20
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

as the Learned Arbitrator has followed the principles of

natural justice and no prejudice has been caused to

either side, it was not mandatory for the Learned

Arbitrator to frame issues separately.

34. In this regard, reference may be made to the

following rulings, wherein it is held that it is not

mandatory for the Learned Arbitrator to frame issues;

The Citizens Co-operative Bank Ltd. V
Krishan Lal Choudhary and others 2018
SCC OnLine J&K 747

11. It was next contended that the
direction for framing issues while
conducting Arbitration proceedings was
also not necessary. What is stated by the
learned counsel for the appellant may be
correct. While the Arbitrator may be at liberty
to adopt its own procedure for conducting the
Arbitration proceedings in accordance with
the broader parameter laid down in the 1989
Act and the rules frame thereunder, yet in the
absence of any prohibition expressly
prescribed in the Act and the rules, it would
be open to the Arbitrator to even frame issues
for purposes of crystallizing the dispute
pending before the Arbitrator. We, therefore,
modify the judgment and order impugned
to the extent that while it may not be
necessary for the Arbitrator to
21
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

necessarily frame issues for adjudication
of the dispute, yet the Arbitrator may be
at liberty to frame issues, if he deems it
necessary.

(Emphasis Supplied)

Narayandas Chatrabhuj Mawani v.

Hiralal Haribhai Thakkar, 1992 SCC
OnLine Bom 353 : (1993) 1 Bom CR
168 at page 172

12. No legal proposition has been stated by
the arbitrator in the said Award which is the
basis thereof and is erroneous. The Court has
no jurisdiction to investigate into the merits of
the case and to examine the documentary
and oral evidence for the purpose of find out
whether or not the arbitrator had committed
an error of law or fact. Since all questions of
law as well as fact were referred to
arbitration the decisions of the arbitrator
thereon is final, conclusive and binding on the
parties thereto. It was not obligatory for
the arbitrator to frame issues as is done
in trial of a suit. Nor the arbitrator was
required to record separate findings on
each of the contentions raised by the
petitioner before him. In law, the arbirator
was entitled to make a lump sum award and
the lump sum award made by him suffers
from no infirmity. Since the arbitrator has
awarded certain amount without indicating
why he has done what he has done, it can
not be said that be did not decide all matters
in dispute referred to him. There is nothing to
show that the arbitrator did not consider or
decide all the disputes raised to him or that
there is failure on his part in exercising
22
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

jurisdiction vested in him. The claim of the
respondents against the petitioner as on the
date of the said suit was not barred by
limitation. The arbitrator has not
misconducted himself. In the absence of any
reasons for making the Award, it is not open
to the Court to interfere with the Award. There
is no error of law apparent on the face of the
said award.

(Emphasis Supplied)

35. In the light of the above law and for the reasons

discussed supra, I reject the first technical contention

raised in the present petition to set aside the award on

the ground that the Learned Arbitrator did not frame

issues.

36. Now turning to the second technical contention,

that there is no clause in the contract entitling the

respondent to raise the counterclaim, and therefore the

counterclaim could not have been considered by the

learned arbitral tribunal on its merits, it is to be noted

that the arbitration clause is contained in the terms of

the tender, which is incorporated as part of the contract
23
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

between the parties. Clause XIX of the Tender

Documents provides for arbitration and provides that all

disputes arising out of the agreement shall be referred to

the sole arbitration of any person appointed by the

Managing Director of Central Warehousing Corporation,

New Delhi.

37. Ultimately, at the end of Clause XIX, it is provided

as follows: “Subject as aforesaid, the Arbitration and

Conciliation Act 1996 shall apply to the arbitration

proceedings under this clause.”

38. It is to be noted that in Clause XIX, there is no

specific prohibition against the respondent from raising a

counterclaim. Therefore, the general provisions of

Arbitration and Conciliation Act are applicable insofar as

raising the counterclaims are concerned, and since under

the Arbitration and Conciliation Act it is perfectly open to

the respondent in the arbitral proceedings to raise a
24
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

counterclaim, it follows that even in the present case

there was no prohibition on the respondent from raising

the counterclaim, and therefore it is not possible to set

aside the award on the ground that the arbitral tribunal

was barred from considering the counterclaims of the

respondent on merit. Therefore, the second technical

contention raised in the present petition also fails.

39. Now, let me consider each head of the claim and

counterclaim to determine whether the finding of the

arbitral tribunal on any of the claims and

counterclaims is patently illegal appearing on the

face of the award and hence liable to be set aside

under Section 34 of the Act.

40. Claim No. 1 raised by the petitioner / claimant is

for recovery of the demurrage charges and charges for

casual labour. It is to be noted that after deducting the

sums payable to the respondent under unpaid bills and
25
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

security deposit amount, the net amount claimed under

this head is Rs. 9,07,129. However, it is noted at page 8

of the Arbitral Award that, the claimant withdrew the

claim towards non-supply of causal labour and therefore,

it was only the claim for demurrage charges which had to

be considered by the arbitral tribunal.

41. The reasoning of the arbitral tribunal with regard to

this claim is found at pages 7 to 10 of the arbitral award.

Firstly, the Learned Arbitrator has noted that in reply to

the order dated 30-6-2014 of the previous arbitrator, the

claimant stated that they have withdrawn their claim on

account of non-supply of casual labour. Therefore, the

Learned Arbitrator has proceeded to consider Claim No. 1

only in respect of recovery of the demurrage charges

deducted by Food Corporation of India.

42. In this regard, the Learned Arbitrator has noted that

the respondent / contractor had quoted the rates about
26
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

seven months prior to the commencement of the contract

period. Only after the contractor quoted the rates in the

tender on 25th May 2010, the DRM Solapur increased

the demurrage charges to Rs. 600 per wagon per hour.

On this basis, the learned arbitrator has concluded that

it was not possible for the respondent contractor to have

anticipated such an abnormal and “illegal” increase in

the demurrage charges from Rs. 100 to Rs. 600 per

wagon per hour at the time of quoting the rates.

43. Then the learned arbitrator refers to the ruling of

the Hon’ble Bombay High Court in Maharashtra State

Electricity Distribution v DSL Enterprises : 2009 (4) Bom

CR 843, wherein it is held that where there is a breach of

a basic / main term of the contract, which is so primary

that upon such a breach the other reciprocal promises

cannot be performed by the other party, it constitutes a

fundamental breach of the contract.

27

CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

44. Then the learned arbitrator observes that in the

instant case, at the time of quoting rates for the tender,

no prudent person could imagine that there would be

such an abnormal increase in demurrage charges of

500%. Apart from this, the Learned Arbitrator observes

that there was a change in rake composition, which was

increased from 42 wagons to 58 wagons, but there was

no corresponding change in the free period allowed for

handling of such rakes. Apart from this, the Learned

Arbitrator relies upon a news report published in The

Hindu newspaper, Gulbarga edition, dated 28-7-2012, to

note that there are no basic facilities for handling goods

at Gulbarga railway station.

45. Then the learned arbitrator has noted that even

when the learned arbitrator personally visited the

Gulbarga railway station on 6-4-2016, the situation had

not improved, and the situation at Gulbarga railway

station is not much different from those in other railway
28
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

stations where the railways have been restrained from

enforcing the policy of round-the-clock working due to a

lack of infrastructure facilities.

46. Ultimately, the Learned Arbitrator has concluded as

follows: “From the various correspondence exchanged by

the parties in CD1, it is clear that there were other reasons

like no specific timing of placing rakes due to the round-

the-clock system, non-availability of infrastructure facilities

for accommodating jumbo rakes, claimant’s inability to

depute any staff to the railway goods shed for overnight

supervision and watch, etc. Obviously, all these factors

are basic factors for the respondent and are beyond his

control, and the respondent cannot be held responsible for

such lack of infrastructural facilities and consequent

breaches on these accounts committed and attributable to

the claimants. I, therefore, award a nil amount against

Claim No. 1 to the claimants.”

29

CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

47. Therefore, on reading the above reasons assigned by

the learned arbitrator, it is clear that there was no

dispute raised before the learned arbitrator that, in fact,

the demurrage charges were deducted by Food

Corporation of India due to delay in handling of the rakes

by the respondent contractor. However, the finding of the

learned arbitrator is that there was an abnormal rise in

demurrage charges from Rs. 100 to Rs. 600 per wagon

per hour, which could not have been anticipated by the

contractor, and the delay in handling the rakes is not

attributable to the contractor since there was a lack of

infrastructure facilities, etc.

48. On this ground, the Learned Arbitrator holds that

the contractor is not liable to indemnify the claimant for

the demurrage charges, which have been admittedly

deducted by FCI against the claimant. The Learned

Arbitrator has also noted that the increase in demurrage

charges and lack of infrastructure facilities constitute a
30
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

fundamental breach of the contract, and the contractor

respondent could not be expected to work at the rates

mentioned in the tender when there was such a

fundamental change in the prevailing conditions, which

resulted in a fundamental breach of the contract.

49. In respect of his findings on Claim No. 1, where

the learned arbitrator has committed a cardinal error

is in failing to appreciate that if indeed there was a

fundamental breach of the contract due to the change in

prevailing conditions, such as the increase in demurrage

charges from Rs. 100 to Rs. 600, increase in the

composition of the rakes from 42 wagons to 58 wagons

without a corresponding increase in the free period for

handling the rakes, and lack of infrastructure facilities

for handling the rakes around the clock (24 hours a day),

then it was for the contractor to terminate the contract

on the ground that, in view of the fundamental breach of
31
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

the contract, the contractor cannot be expected to work

at the rates quoted in the tender.

50. However, admittedly, the contractor has at no point

of time terminated the contract on this ground. Instead,

the contractor has continued to take benefit under the

contract by raising bills. This being the case, after the

contract was terminated by the claimant due to the

contractor not being available at the spot, the contractor

cannot turn around at this stage and claim that the

contractor could not do the work at the rates quoted in

the tender for the above reasons. Having taken advantage

of the contract all along, when the dispute arises between

the parties, the contractor cannot contend that there was

a fundamental breach of the contract by the claimant

due to a change in the prevailing conditions, such as an

increase in demurrage charges, etc. If really there was a

fundamental breach of contract, the option was available

to the contractor to terminate the contract.
32

CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

51. In this regard, reference may be made to the law

laid down by Hon’ble Apex Court in the case of

Maharashtra State Electricity Distribution Co. Ltd.

v. Datar Switchgear Ltd., (2018) 3 SCC 133 : (2018) 2

SCC (Civ) 65 : 2018 SCC OnLine SC 20 at page 176,

as follows;

67. In the aforesaid backdrop, we agree with
the approach of the High Court in spelling
out the proposition of law that once it is
established that the party was justified in
terminating the contract on account of
fundamental breach thereof, then the said
innocent party is entitled to claim damages for
the entire contract i.e. for the part which is
performed and also for the part of the contract
which it was prevented from performing.

(Emphasis Supplied)

52. In the light of the above law, it follows that in the

event of a fundamental breach of contract, it is open to

the affected party to terminate the contract. But without

terminating the contract, the respondent cannot raise the
33
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

ground of increasing demurrage charges, change in

composition of the rake, etc., as a ground for not doing

the work under the contract effectively and efficiently.

Ultimately, it is to be noted that it is the responsibility of

the handling and transport contractor, to handle the

rakes within the free period. If the rakes are not disposed

of within the free period, then it attracts the demurrage

charges. When admittedly demurrage charges have been

deducted against the claimant, then since the demurrage

charges have been raised due to failure of the contractor

to handle the rakes within the free period given by

railways, certainly it is the liability of the contractor to

indemnify the claimant to the extent of demurrage

charges admittedly deducted, and the contractor cannot

raise justifications such as an increase in demurrage

charges, change in composition of the rakes, etc., as a

ground for denying the said liability. In this regard,

reference may be made to the terms of the tender, which

form part of the contract between the parties. As per
34
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

clause XII of the terms of the tender between the parties,

it is laid down as follows:

Liability of contractors for losses etc.
suffered by the corporation.

(a) The contractor shall be liable for all
costs, damages, demurrage, wharfages,
forfeiture of wagon registration fee,
charges, and expenses suffered or incurred
by the corporation due to the contractor’s
negligence and unworkmanlike
performance of any services under this
contract or breach of any terms thereof or
their failure to carry out the work with a
view to avoid incurrence of damages, etc.,
and for all damages or losses occasioned
to the corporation due to any act, whether
negligent or otherwise, of the contractors,
themselves or their employees. The
decision of the regional manager regarding
such failure of the contractor and their
liability for the losses etc. suffered by the
corporation shall be final and binding on
the contractor.

(b) The corporation shall be at liberty to
reimburse themselves for any damages,
losses, charges, costs, or expenses
suffered or incurred by them due to the
contractor’s negligence and unworkmanlike
performance of service under the contract
or breach of any terms thereof. The total
sum claimed shall be deducted from any
sum then due or which at any time
hereafter may become due to the contractor
under this or any other contract with the
35
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

corporation. In the event of the sum which
may be due from the corporation as
aforesaid being insufficient, the balance of
the total sum claimed and recoverable from
the contractors as aforesaid shall be
deducted from the security deposit
furnished by the contractors as specified in
paragraph XI. Should this sum also be not
sufficient to cover the full amount claimed
by the corporation, the contractor shall pay
to the corporation on demand the
remaining balance of the aforesaid sum
claimed.”

(Emphasis Supplied)

53. Therefore, from the above terms of the contract

between the parties, it is clear that for any demurrage

charges incurred due to the contractor’s negligence and

unworkmanlike performance of the services, it is the

contractor / respondent who is liable to face such

demurrage charges.

54. In the case on hand, the respondent contractor has

quoted rates for handling the rakes within the free period

allotted by the railways. The scope of work of the

contractor respondent under the contract is that the
36
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

contractor has to handle and transport the rakes from

the railway platform to the godowns within the free

period allotted by railways. For this purpose, the

contractor has to depute sufficient manpower and labor

at the spot. The justification raised by the respondent

contractor for not clearing the rakes from the railway

platform within the free period is threefold. Firstly, it is

contended that earlier there were specific working hours,

and subsequently, the clearing had to be done round the

clock for all 24 hours. Secondly, the abnormal increase in

the demurrage charges from Rs. 100 to Rs. 600 per

wagon per hour. Thirdly, the lack of infrastructure

facilities. Fourthly, the change in composition of the rake

from 42 to 56 wagons per rake.

55. Insofar as the lack of infrastructure facilities is

concerned, the same cannot be a ground for the

respondent to justify non-handling of the rake within the

free period provided by railways because under the
37
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

contract, as per page 3 of the tender documents, it is

specifically provided as follows:

“The tenderers must get themselves fully
acquainted with the size and location of
the godowns vis a vis loading and
unloading points before submission of
tenders, and rates quoted by them for
loading into and unloading from trucks and
wagons shall be deemed to have been done
after such acquaintance. Once a tender is
submitted by a tenderer, he shall be
deemed to have fully acquainted himself
with the size and location of the godowns
vis a vis loading and unloading points,
and shall not be entitled to any compensation
arising out of any discrepancy in the size and
location of the group of godowns found later
on, or on the ground that the workers
employed by him are demanding higher rates
of wages, if the load involved in certain
operations is more, or the bags to be handled
are heavier.”

(Emphasis Supplied)

56. Therefore, the contractor was expected to acquaint

himself fully and thoroughly with the infrastructure or

the lack of infrastructure before submitting the tender. In

fact, from the records, it is forthcoming that the

respondent was the handling and transport contractor
38
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

even for the earlier period, and therefore it is clear that,

being fully aware of the infrastructure facilities available,

the contractor submitted the bid, and therefore the

contractor cannot now turn around and claim lack of

infrastructure as one of the reasons for not clearing the

rakes within the free period allotted by railways.

57. Insofar as the change of timings to 24 hours a day,

the increase in demurrage charges from Rs. 100 to Rs.

600, and the change in composition of the rake from 42

wagons to 56 wagons without a corresponding increase

in the free period is concerned, it is to be noted that if

these factors were responsible for the delay in handling

and transporting the rake from the railway platform, and

if as a result of these changes, there was a fundamental

breach of the contract as held by the Learned Arbitrator,

it was open to the contractor to terminate the contract on

this ground, claiming fundamental breach of the contract

due to the above changes. However, instead of doing so,
39
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

the contractor has continued with the contract,

continued to raise bills, and received the charges under

the contract from the claimant, which is evident from the

fact that the learned arbitrator himself holds that no

amount is due under counterclaim No. 1 towards

pending bills.

58. In this regard, the learned arbitrator at page 16 of

the award, while dealing with counterclaim No. 1, holds

as follows:

“Claimants gave clarifications to order dated
22-08-2016, vide their letter No. H-700(18)/
GLB-II/ ARBN/ 2016/4831, dated 14-09-
2016, (CD-10), enclosing therewith Annexure
1 to Annexure 6. Respondents were therefore
directed to examine Annexure 6 and intimate
specifically the bills which are not paid by the
claimant so far, if any. In the absence of any
satisfactory reply by the respondent, written
or otherwise, I assume that all bills have
been settled as explained by claimants,
and I give nil award against
counterclaim No. 1 to the respondents.”

(Emphasis Supplied)
40
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

59. Therefore, the specific finding of the Learned

Arbitrator is that there are no pending bill amounts

payable by the claimant to the respondent. This means

that till the contract was terminated by claimant with

effect from 8-10-2012, the respondent continued to raise

bills and receive the bill amounts without any demur or

objection. Having taken advantage of the contract all

along, at this stage, the respondent cannot turn

around and contend that there was a fundamental

breach of the contract due to an increase in

demurrage charges and a change in composition of

the rakes or change in working hours.

60. Ultimately, it is to be noted that the very purpose of

appointment of H&T contractor, (handling and transport

contractor), is to clear the rakes from the railway

platform. Therefore, if there is any delay in clearing the

rakes, resulting in the levying of demurrage charges, then

it is certainly the liability of the contractor to indemnify
41
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

the claimant for such demurrage charges. Therefore, by

holding the contrary, the learned arbitrator has

committed an illegality which is writ large on the face of

the arbitral award itself because as per the tender clause

XII (extracted supra), it is the liability of the contractor to

pay for any demurrage charges resulting from the

contractor’s negligence or unworkmanlike performance.

The very fact that there was delay in handling and

transporting the rakes within the free period points to

negligence on the part of the contractor and the

contractor cannot take shelter in specious grounds such

as change in timings and change in composition of the

rakes when the contractor has not raised grievances in

this regard and has not terminated the contract on these

grounds but continued to take benefit under the contract

till the contract was terminated by the claimant with

effect from 8-10-2012. For all these reasons, I hold

that the arbitral award insofar as rejecting claim No.

1 for demurrage charges calls for interference under
42
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

section 34 of the Act on the ground that it is

contrary to the terms of the contract between the

parties, namely clause XII extracted supra and suffers

from patent illegality appearing on the face of the

award since the liability of the contractor is denied

on the ground of fundamental breach of the contract

due to increase in demurrage charges etc., but at no

point of time did the contractor himself terminate

the contract on such grounds. Accordingly, the above

finding suffers from patent illegality appearing on the

face of the award and hence the award insofar as

claim No. 1 is liable to be set aside under section 34

[2A] of the Act.

61. Claim No. 2, raised by the claimant, is for risk and

cost amount for the period from 8-10-2012, that is, the

effective date of termination of the contract, till 17-10-

2012, the date on which the contract period would have

actually come to an end. It is to be noted that the basis of
43
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

this claim is that since the contractor did not appear at

the work site for carrying out the contract work, the

claimant was constrained to terminate the contract with

effect from 8-10-2012 and from said date till the end of

the contract period, that is up to 17-10-2012, for a period

of about 10 days, the work was done at the risk of the

contractor through a new contractor, namely Sunny

Transport Company, and for the difference in rates

between the rates quoted by the respondent and the

rates of the new contractor, this claim is raised, which is

quantified at Rs. 6,77,067 as per the statement of claim

and which is modified to Rs. 8,95,900 in the course of

the inquiry.

62. In this regard, the learned arbitrator at pages 10 to

12 of the award has noted that the claimant has

produced two bills, one for handling of wheat and one for

handling of rice by the new contractor. Whereas the bill

for handling of rice is for the work done on 13-10-2012 &
44
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

14-10-2012, which is within the contract period, the bill

for wheat is for the period from 8-10-2012 to 31-10-

2012, which is beyond the contract period. The learned

arbitrator has observed that rate-wise work slips for

wheat have not been produced and therefore it cannot be

established that the entire work dealt with under the bill

was done during the contract period. Therefore, in so far

as the charges towards handling of wheat are concerned,

the learned arbitrator has presumed that the work was

done uniformly and awarded a proportionate amount of

the said bill, that is, the bill is for 8-10-2012 to 31-10-

2012, and proportionate amount only for 8-10-2012 to

17-10-2012 is awarded in respect of wheat. On this

basis, the learned arbitrator has awarded a sum of Rs.

1,58,927/= towards wheat and allowed the entire bill

towards rice i.e. Rs. 2,95,581/= and thereby awarded

total sum of Rs. 4,54,508 towards claim No. 2.
45

CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

63. When the claimant failed to produce the date-wise

work slip for wheat to show what was the quantity of

wheat handled between 8-10-2012 to 17-10-2012, no

fault can be found with the learned arbitrator in refusing

to award the entire bill amount for handling of wheat,

since the bill was dated from 8-10-2012 to 31-10-2012,

which is well beyond the contract period which ended on

17-10-2012. Therefore, the contention of the claimant

that the entire claimed amount of Rs. 8,85,900 ought to

have been awarded is unacceptable. In any event, this

court in a section 34 petition cannot enter into the realm

of appreciation of evidence and therefore, viewed from

any angle, the finding of the learned arbitrator partly

awarding claim No. 2 does not call for interference in

the present petition.

64. Claim No. 3 raised by the claimant was for recovery

of Rs. 4,77,098 towards EPFO payment made by the

claimant on behalf of the respondent, to the PF
46
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

department. The learned arbitrator has essentially taken

note of two facts to reject this claim. Firstly, the learned

arbitrator has noted that the sum of Rs. 4,77,098 directly

paid by the claimant to the department is in respect of PF

claims for the period from October 2007 onwards,

whereas the contract period in the instant case is from

18-10-2010 to 17-10-2012. Therefore, the learned

arbitrator firstly holds that the claim for recovery of Rs.

4,77,098 which is paid by the claimant on behalf of the

respondent to the PF department is in respect of a period

which is earlier to the contract between the parties and

therefore the learned arbitrator does not have the

jurisdiction to entertain this claim since it does not relate

to the contract period. Secondly, the learned arbitrator

has noted that from various correspondence between the

parties, it is forthcoming that the entire PF amount had

already been either deducted from the various bills of the

contractor or directly paid by the contractor, and

therefore, when there was such a serious dispute
47
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

regarding the liability in respect of the PF amount, the

claimant could not have directly paid the demanded

amount to the department and expect the respondent to

indemnify the claimant to the extent of the paid amount.

In this regard, the learned arbitrator has appreciated the

material on record and noted that a letter of the claimant

dated 24-3-2011 states that 10% payment is being

withheld from the bill for default in EPFO recoveries.

There is another letter written by the respondent dated 7-

3-2011 wherein the respondent requested the claimant to

obtain a DD for Rs. 3,68,998 on account of PF dues up to

28-2-2011. There is another letter from the respondent

requesting for deduction of EPFO arrears of Rs. 1,50,000

from the bills. Apart from this, there is a claimant’s

letter dated 7-5-2012 remitting Rs. 6,60,691, out of the

demand of Rs. 11,60,691. The balance of Rs. 5 lakhs had

already been paid by way of deduction from the bills.

Therefore, on the basis of the appreciation of

evidence, the learned arbitrator has observed that
48
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

there was in fact no liability of the respondent

towards arrears of PF and therefore the claimant

cannot recover the said sum of Rs. 4,77,098, which

was unjustifiably paid by the claimant to the PF

department. These findings of the learned arbitrator are

in consonance with the material on record and therefore

do not call for interference in the section 34 petition.

Accordingly, I hold that the finding of the learned

arbitrator rejecting claim No. 3 does not call for

interference in the present petition.

65. Claim No. 4 of the claimant considered in the

award at page 14-15 is for approving the recovery of Rs.

12,30,264 made from bills and security deposit amount

towards the demurrage charges. However, no such claim

is raised in the statement of claim. This claim is rejected

by the learned arbitrator on the short ground that while

dealing with claim No. 1, the claim for demurrage

charges has been rejected and therefore it follows that it
49
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

is not possible for the claimant to adjust the bill amount

and the security deposit amount towards demurrage

charges. In this regard, I have already held supra that

the finding of the learned arbitrator rejecting claim No. 1

suffers from patent illegality appearing on the face of the

records. Once the conclusion is reached that the

claimant is entitled to the demurrage charges as claimed,

it follows that, since under the terms of the tender, the

claimant is entitled to set off any amount of the

respondent lying with the claimant against dues payable,

it follows that, the claimant was entitled to adjust the

demurrage charges from the bill amount and also from

the security deposit charges. Therefore, the finding of the

learned arbitrator rejecting claim No. 4 is liable to be set

aside, for the same reasons as applicable to claim No. 1.

66. Insofar as claim No. 5 is concerned towards

interest, the learned arbitrator awarded a uniform rate of

interest to both the parties at rate of 11% p.a. both on
50
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

the amounts awarded to the claimant and the

counterclaim amounts awarded to the respondent and

therefore since uniform rates of interest have been

awarded to both sides, the claimant can have no

grievance with regard to the findings of the learned

arbitrator on claim No. 5.

67. Now turning to the counterclaims, Counterclaim

No. 1 for pending bill amount of Rs. 30 lakhs has been

rejected by the learned arbitrator, which has not been

challenged by the respondent. Therefore, in this petition

filed by the claimant, there is no need to consider the

correctness of the findings on counterclaim No. 1.

68. Counterclaim No. 2 is for recovery of Rs.

58,76,523, which has been adjusted towards demurrage

charges. This counterclaim has been awarded on the

short ground that while dealing with claim No. 1, it has

been held that the claim for demurrage charges is illegal
51
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

and not payable by the respondent. For the same reasons

as applicable to claim No. 1, wherein I have already held

that the contractor is liable to pay the demurrage

charges, it follows that the allowing of this counterclaim

for recovery of the amount adjusted from the bills

towards demurrage charges calls for interference. Hence,

for the same reasons as applicable to claim No. 1, I

hold that the finding of the learned arbitrator on

counterclaim No. 2 is liable to be set aside.

69. Insofar as counterclaim Nos. 3 and 4 are concerned,

they are for recovery of security deposit amounts. These

counterclaims have been awarded by the learned

arbitrator on the short ground that the levying of

demurrage charges is illegal and therefore, the security

deposit amounts could not have been adjusted towards

demurrage charges. For the reasons already noted supra

while dealing with claim No. 1 and 4, I have held that

this finding of the learned arbitrator is patently illegal
52
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

and calls for interference in the present petition. Hence,

it follows that since the Respondent was liable to pay the

demurrage charges and the security deposit amounts

have been adjusted towards the demurrage charges,

there is no question of the respondent seeking to recover

the security deposit amount. Hence, for the same

reasons as applicable to claim No. 1, the finding of

the learned arbitrator on counterclaims Nos. 3 and 4

is liable to be set aside.

70. Counterclaim No. 5: This counterclaim is raised by

the respondent for recovery of a sum of Rs. 88,68,451

due to additional expenditure incurred since there was

an increase in distance to be traversed between the

Gulbarga railway goods shed and CWC warehouse. It is

an admitted fact between the parties that originally the

distance between the above two points was only 4 km. In

August 2010, a decision was taken by the district

authorities to impose restrictions on the movement of
53
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

heavy vehicles, which resulted in an increase in the

distance to be traversed between the railway goods shed

and CWC warehouse. According to the respondent, the

distance increased to 21 kilometers, whereas the learned

arbitrator has accepted the contention of the claimant

that the actual distance traversed increased to only 16

kilometers. The respondent is claiming an additional

amount since the respondent had to transport the goods

over a longer distance due to the restrictions on the

movement of heavy vehicles imposed by district

authorities.

71. The learned arbitrator, with regard to this

counterclaim, firstly takes note of the fact that although

the restriction on the movement of heavy vehicles was

brought into force in August 2010, which is much earlier

to the commencement of the contract period on 18-10-

2010, the rates were quoted by the contractor much

earlier, in March 2010 itself. And at the time of quoting
54
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

the rates, the contractor could not have anticipated that

there would be restrictions imposed by district

authorities resulting in increasing the distance between

the railway goods shed and CWC warehouse from 4 km

to 16 km. The learned arbitrator further takes note that

as per Annexure R44 dated 2 November 2010, the

contractor had claimed extra payment for the additional

distance. The learned arbitrator has rejected the

contention that the lead of 16 kilometers is within the

specified limit of 17 kilometers as per the tender

documents by referring to rulings of the Hon’ble Apex

Court and Hon’ble Bombay High Court holding that

revised rates can be provided even where the contract

does not provide for the same, and the concept of

fundamental breach of contract. Ultimately, the learned

arbitrator has awarded an additional amount of Rs.

58,37,790 towards the 12 kilometers additional distance

over which goods had to be transported by the

respondent.

55

CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

72. In this regard, at the outset, it has to be noted that

even as per the finding of the learned arbitrator, as a

result of traffic restrictions imposed by district

authorities, the distance to be traversed increased to 16

km. This specific finding is recorded at page 22 of the

Arbitral Award wherein the learned arbitrator has

observed as follows:

“The additional distance required to be

traversed by the respondent is 12 kilometers,

(actual distance traversed 16 kilometers

minus original distance 4 kilometers.)”

(Emphasis Supplied)

73. Therefore, the learned arbitrator has recorded a

factual finding that even after the increase in the

distance, the total distance to be traversed was only 16

kilometers and not 21 kilometers as contended by the

respondent.

56

CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

74. In the background of this specific factual finding

recorded by the learned arbitrator, it is now necessary to

look into the tender document under the head of general

information, wherein in the contract between the parties,

it is laid down as follows:

“General information
A. Place of operation:

The works in and around Gulbarga-II in these
presents shall mean and include the area
within the radius of 17 km from the
railway station of Gulbarga-II/ Municipal
Corporation, and CWC warehouse comprises
following groups of godowns.”

75. Therefore, as per the tender document, the lead of

17 kilometers is factored into the contract between the

parties, and on that basis, the contractor has submitted

the rates. When, even as per the finding of the learned

arbitrator, the increase in distance is only 16 kilometers,

the increased distance to be traversed is only 16 km,

which is well within the 17 km radius / lead, prescribed

by the tender document. The learned arbitrator could
57
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

not have applied equity to grant an additional rate for

the additional distance of 12 km to be traversed by

the respondent.

76. In this regard, the law is well settled that the

learned arbitrator, being a creature of the contract, has

to decide the dispute strictly in terms of the contract and

cannot apply general principles of justice and equity to

grant relief to the party. In this regard, reference may be

made to the following rulings;

Food Corpn. of India v. Chandu
Construction
, (2007) 4 SCC 697 : 2007
SCC OnLine SC 496 at page 702

11. It is trite to say that the arbitrator
being a creature of the agreement between
the parties, he has to operate within the
four corners of the agreement and if he
ignores the specific terms of the contract,
it would be a question of jurisdictional
error on the face of the award, falling
within the ambit of legal misconduct
which could be corrected by the court. We
may, however, hasten to add that if the
arbitrator commits an error in the construction
of contract, that is an error within his
jurisdiction. But, if he wanders outside the
58
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

contract and deals with matters not allotted to
him, he commits a jurisdictional error
(see Associated Engg. Co. v. Govt. of
A.P.
[(1991) 4 SCC 93] and Rajasthan State
Mines & Minerals Ltd. v. Eastern Engg
.

Enterprises [(1999) 9 SCC 283] ).

Board of Control for Cricket in India v
Deccan Chronicle Holdings Ltd.
2021 SCC
OnLine Bom 834 : (2021) 4 Bom CR 481 :

(2021) 3 Arb LR 125

233. Given the wording of the Arbitration Act, a
longer examination of the antecedents of these
concepts is unnecessary. The statute itself is
clear and unambiguous; and in Associate
Builders, the Supreme Court in paragraph 42.3
extracted Section 28 and said that a
contravention of it is a sub-head of patent
illegality. Ssangyong Engineering does not
change this position. Given this now-settled
position in law, it is unnecessary to examine
the additional authorities on which Mr. Mehta
relies, all to the same effect. They also say this
: commercial arbitrators are not entitled
to settle a dispute by applying what they
conceive is ‘fair and reasonable,’ absent
specific authorization in an arbitration
agreement. Section 28(3) also mandates
the arbitral tribunal to take into account
the terms of the contract while making
and deciding the award. Section 28 is
applicable to all stages of proceedings before
the arbitral tribunal and not merely to the
making of the award. Under Section 28(2), the
Arbitral Tribunal is required to decide ex aequo
et bono or as amiable compositeur only if the
59
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

parties expressly authorize it to do so. The
Arbitrator is bound to implement the
contractual clauses and cannot go
contrary to them. He cannot decide based
on his notions of equity and fairness,
unless the contract permits it.

(Emphasis Supplied)

77. Therefore, the finding of the learned arbitrator on

counterclaim No. 5 is liable to be set aside is that even as

per the factual finding recorded by the learned arbitrator,

as a result of the traffic restrictions on the movement of

heavy vehicles, the distance between the railway goods

shed and CWC warehouse increased to 16 km, which is

within the 17 km radius prescribed by the tender

document. Therefore, going by the terms of the contract

between the parties, the learned arbitrator could not have

awarded any extra amount by considering equity, by

holding that the respondent is to be compensated for

damages suffered due to the increase in the lead distance

when such lead distance was already factored into the

contract, which provided for a lead distance of 17
60
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

kilometers, whereas on facts, the actual lead distance

traversed by the respondent was only 16 km.

78. To get over this term of the contract, the learned

arbitrator has relied upon two rulings. Firstly, reliance is

placed upon the ruling of the Hon’ble Apex Court in the

case of Rashtriya Chemicals and Fertilizers v Chowgule

Brothers, where the proposition of law laid down is that

the original understanding of the parties at the time of

making the offer and its acceptance is important. Relying

upon this ruling, the learned arbitrator observes that at

the time of submission of the rates by the contractor, the

distance was only 4 km, and no normal person could

anticipate that there would be an increase in the

distance. The learned arbitrator has also referred to the

ruling of Bombay High Court in Maharashtra State

Electricity Distribution v. DSL Enterprises and held that

the imposition of traffic restrictions, which increased the
61
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

distance from 4 kilometers to 16 kilometers, constitutes a

fundamental breach of the contract.

79. However, as in the case of finding in respect of

demurrage charges, the learned arbitrator has committed

an error in failing to appreciate that, if there was a

fundamental breach of the contract due to an increase in

the distance to be traversed by the respondent, then it

was for the respondent to terminate the contract on that

ground. Further it is to be noted that, admittedly as on

the date of commencement of the contract period, the

traffic restrictions were already in force, and therefore,

the traffic restrictions were not a development

subsequent to the commencement of the contract period.

This is because traffic restrictions were brought into force

in August 2010, whereas the contract period commenced

from 18-10-2010.

62

CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

80. Therefore, if there was really a fundamental breach

of the contract as held by the learned arbitrator by

imposition of traffic restrictions, then, at inception of the

contract itself, the contractor ought to have raised

grievance or, and in case the grievance were not met,

ought to have terminated the contract on the ground of

fundamental breach of the contract, on the ground that

the conditions on which the rates were submitted no

longer prevail. Having not done so and having taken

advantage of the contract, by raising bills and receiving

amounts under the contract, after the contract is

terminated by the claimant, the respondent cannot turn

around and raise a claim for payment higher than that

prescribed under the contract on the ground that he had

to traverse longer lead distance. Therefore, the finding of

the learned arbitrator awarding sum of Rs. 58,37,790

towards larger distance to be traversed by respondent is

liable to be set aside on two grounds. Firstly, the

increased lead even after imposition of travel restrictions
63
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

was within the lead of 17 kilometers prescribed by the

tender document. Secondly, the travel restrictions were

in force as on the date of commencement of the contract

and without any demur in respect of increase in distance,

the respondent entered upon the contract and has taken

advantage of payments under the contract and therefore

after the contract is terminated, the respondent cannot

turn around and claim higher prices due to increase in

distance. For these reasons, the finding of the learned

arbitrator partly allowing counterclaim No. 5 suffers

from patent illegality appearing on the face of the

award and therefore liable to be set aside.

81. Counterclaim No. 6 : Under this counterclaim, the

respondent is seeking ₹19,90,034 due to breakdown of

weighbridge of the claimant. In this regard, the case of

the respondent is that the weighbridge at CWC

warehouse No. 2 was not functioning since November

2011. Therefore, the claimant orally directed respondents
64
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

to weigh at least 10% of the goods at CWC Warehouse

No. 1, which resulted in an additional distance of 22 km.

And therefore, for such additional distance of 22 km in

respect of 10% of the weightment, this counterclaim is

raised.

82. With regard to this counterclaim, the learned

arbitrator has held that the fact of breakdown of the

weighbridge is not disputed. The learned arbitrator has

noted that the claimant, being a government of India

undertaking, ought to be a model employer and the

claimant should have appointed a committee for

verification of the distance. The learned arbitrator further

notes that, generally during the period of the contract,

the contractor is advised to concentrate and continue

with the work with an assurance that payment for the

same would be finalized and made soon and the

contractor also accepts the same in good faith. Therefore,

the learned arbitrator has noted that inaction on the part
65
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

of the claimant initially in getting the committee

appointed and later on putting the onus on the

respondent themselves cannot be accepted. Thereby,

ultimately, the learned arbitrator has held that the

respondent is to be compensated for damages for the

additional distance traversed and under this head

awarded sum of Rs. 12,77,354.

83. In reaching this finding, the learned arbitrator has

failed to take note of Clause XV of the Tender dealing

with remuneration, which is as follows.

“Remuneration:

A. The contractor shall be paid the remuneration
in respect of services described in Para XIX
and performed by them at the contract rate.
B. If the contractor is required to perform any
service in addition to those specifically
provided for in the contract and the annexed
schedule, the contractor’s remuneration for
the same will be paid at the rates as
negotiated and fixed by mutual agreement.
C. The contractor will have the right to
represent in writing to the regional
manager that a particular service which they
are being called upon to perform is not
covered by any of the services specifically
provided for in the contract or, as the case
66
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

may be, is not auxiliary or incidental to such
services. Provided that such
representation in writing must be made
within 15 days after the date of actual
performance of such services. If no such
representation in writing is received
within the said time, the contractor’s
right in this regard will be deemed to
have been waived.

D. The question whether a particular service is or
is not covered by any of the services
specifically described and provided for in the
contract, or is not auxiliary or incidental to
any of such services shall be decided by the
regional manager, whose decision shall be
final and binding on the contractor.”

(Emphasis Supplied)

84. Therefore, on plain reading of above clause XV of

the tender / contract between the parties, it is clear that

as per sub-clause A, the contractor is only entitled to

remuneration at the contract rate. In case any additional

service is provided, then the contractor’s remuneration

shall be as negotiated and fixed by mutual agreement. In

the case on hand, admittedly there was no such mutual

agreement to pay extra remuneration for additional

distance. In such a case, if according to the contractor,
67
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

the contractor performed any additional services over and

above that prescribed by the contract, then the

contractor had the right to give a representation to the

regional manager within 15 days from the date of

performance of such additional services. And if no such

representation was given within 15 days, then it is

deemed that the contractor has waived his right to

additional remuneration for additional services. In the

case on hand, the only representation given by the

contractor seeking extra payment for extra distance

traversed due to breakdown of the weighing machine

is the representation dated 25 November 2011 which

is marked as annexure R45. However, this

representation is given to the manager of the CWC

Unit 2 and not to the regional manager as mandated

by Clause XV [C] of the contract. As already noted

supra, as per clause XV of the contract, the contractor is

only entitled to remuneration at the contract rate. Any

additional remuneration should either be fixed by mutual
68
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

consent under clause B or a demand for such additional

remuneration should be made within 15 days to the

regional manager and in case no such demand is made to

the regional manager, it is deemed that the contractor

has waived his right to claim additional remuneration for

additional work. Admittedly, in this case, the only

representation given seeking additional remuneration for

additional distance due to breakdown of the weighing

machine is annexure R45, but the said representation is

not given to the regional manager. Therefore, there is

non-compliance with Clause XV sub-clause C and

therefore it follows that the contractor is deemed to have

waived his right to seek additional remuneration for the

additional work. Without appreciating this vital clause of

the contract between the parties, the learned arbitrator

has made general observations that generally during the

contract period the contractor is advised to concentrate

and continue the work with assurance that payment for

the same would be finalized and the contractor also
69
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

accepts the same in good faith. However, in the case on

hand there was absolutely no material on record before

the learned arbitrator to reach such a conclusion that

such an assurance was made for extra payment by the

claimant to the respondent. As already held supra, the

learned arbitrator, being the creature of the contract, has

to decide the dispute strictly in terms of the contract.

When there was a breach of clause XV [C] by the

respondent in failing to give a representation to the

regional manager within 15 days of the additional work,

then it is deemed that the contractor has waived his right

to claim additional remuneration for the additional work.

The learned arbitrator was bound by the said term of the

contract between the parties and therefore could not

have awarded extra remuneration under counterclaim

No. 6. Therefore, the said finding of the learned

arbitrator partly allowing counterclaim No. 6 is

against the specific terms of the contract and
70
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

therefore suffers from illegality appearing on the face

of the record and is therefore liable to be set aside.

85. Insofar as counterclaim No. 7 is concerned, it is in

respect of interest, but since for the above reasons I have

set aside the award, insofar as awarding the

counterclaims, the question of granting interest on the

counterclaims does not arise.

86. Before parting, reference may be made to the

rulings relied upon by Learned Counsel for Respondent

No. 1. Firstly, reliance is placed upon the judgment of the

Hon’ble Apex Court in Mahakali Sujatha v. Future

Generali India Life Insurance Co. Ltd., (2024) 8 SCC

712. Specifically, reliance is placed upon paragraph 41

and 42 of this judgment. In said paragraph 41 and 42 of

the judgment, discussion is made in respect of the

burden of proof. The said ruling is inapplicable to the

facts of the present case because in a Section 34 petition,
71
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

the court cannot enter into the realm of appreciation of

evidence, and therefore, the question of appreciating

burden of proof and the onus of proof does not really

arise in the present petition. In fact, the arbitral award

has been set aside on the ground that the relevant terms

of the contract have been ignored by the learned

arbitrator and on the ground that there is illegality writ

large on the face of the award insofar as denial of the

demurrage charges to the claimant. Therefore, viewed

from any angle, this ruling is not helpful to Respondent

No. 1.

87. Secondly, reliance is placed upon the ruling of the

Hon’ble Apex Court in Kailash Nath Associates v. DDA,

(2015) 4 SCC 136. Specifically, reliance is placed upon

paragraphs 33 to 40 and 43 of this judgment. In this

judgment, the findings are summarized at paragraph 43.

This ruling essentially deals with compensation payable

towards breach of contract and provides that where a
72
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

contract names a specified amount as liquidated

damages or as penalty, the party complaining of breach

is only entitled to reasonable compensation not exceeding

the amount so stated. This ruling has no application to

the facts of the present case because the respondent has

failed to prove that there was any breach of contract and

this is not a case where the contract between the parties

specified any amount payable as either liquidated

damages or as penalty.

88. Having recorded the above findings, it is to be

noted that, the law as it presently stands is that the

court in the Section 34 petition cannot modify the award,

but the court can either set aside the award in whole or

in part.

89. In this regard, in the case of J.G. Engineers (P) Ltd.

v. Union of India, (2011) 5 SCC 758 : (2011) 3 SCC
73
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

(Civ) 128 : 2011 SCC OnLine SC 704 at page 775,

Hon’ble Apex Court held as follows;

25. It is now well settled that if an award deals
with and decides several claims separately
and distinctly, even if the court finds that
the award in regard to some items is bad,
the court will segregate the award on items
which did not suffer from any infirmity and
uphold the award to that extent. As the
award on Items 2, 4, 6, 7, 8 and 9 was upheld by
the civil court and as the High Court in appeal did
not find any infirmity in regard to the award on
those claims, the judgment of the High Court
setting aside the award in regard to Claims 2, 4,
6, 7, 8 and 9 of the appellant, cannot be
sustained. The judgment to that extent is liable to
be set aside and the award has to be upheld in
regard to Claims 2, 4, 6, 7, 8 and 9.

(Emphasis Supplied)

90. Therefore, in the light of the above law, it is clear

that where the award deals with various aspects which

are severable and the Court finds that it is only part of

the award which is liable to be set aside, then only such

portion of the award has to be set aside. That this

position of law has not undergone any change is evident
74
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

from observation made in latest ruling of Hon’ble Apex

Court in the case of Larsen Air Conditioning and

Refrigration Company v. Union of India and Others

2023 SCC OnLine SC 982, as follows;

13. In the present case, given that the
arbitration commenced in 1997, i.e., after the
Act of 1996 came into force on 22.08.1996, the
arbitrator, and the award passed by them,
would be subject to this statute. Under the
enactment, i.e. Section 31(7), the statutory rate
of interest itself is contemplated at 18% per
annum. Of course, this is in the event the
award does not contain any direction towards
the rate of interest. Therefore, there is little to
no reason, for the High Court to have interfered
with the arbitrator’s finding on interest accrued
and payable. Unlike in the case of the old Act,
the court is powerless to modify the award and
can only set aside partially, or wholly, an
award on a finding that the conditions spelt
out under Section 34 of the 1996 Act have
been established. The scope of interference by
the court, is well defined and delineated [refer
to Associate Builders v. Delhi Development
Authority11
, Ssangyong Engineering
Construction Co. Ltd v. National Highways
Authority of India (NHAI
)12 and Delhi Airport
Metro Express Pvt. Ltd. v. Delhi Metro Rail
Corporation Ltd.13
].

(Emphasis Supplied)
75
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

91. Therefore, it is clear that, award can be set aside

“partially or wholly” and only because portion of award

which is severable from rest of the award is tainted, there

is no need to set aside the award as a whole.

92. Be it noted that, in Gayatri Balasamy v. M/S ISG

Novasoft Technologies Limited in Special Leave to

Appeal (C) Nos.15336-15337/2021 in orders dated 20-

02-2024, the question which has been referred to the

larger bench is whether, under Section 34 of the Act,

court has the power to modify the award and it has not

been doubted that, the Court has the power to partially

set aside the award and it is not necessary to set aside

the award as a whole.

93. In view of my above findings, answering the point

for consideration accordingly, I proceed to pass the

following :-

76

CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

ORDER

The Petition under Section 34 of the

Arbitration and Conciliation Act is allowed,

in part.

Consequently, the Impugned Arbitral

Award passed by the Learned Sole Arbitrator

[Respondent No. 2 herein] dated 31-5-2017,

in case No. ARB/PKG/914 is partly set

aside in respect of the following findings

and claims / counterclaims;

i) The award insofar as rejecting claim

No. 1 for demurrage charges is hereby

set aside. However, since this court

cannot modify the award in a Section

34 petition, it follows that having set

aside the award rejecting the

demurrage charges, this court cannot
77
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

award any amount under claim No. 1,

but it is left open to the claimant to

initiate fresh arbitration insofar as

claim No. 1 is concerned.

ii) The award rejecting claim No. 4 is set

aside. However, this claim is only for

approving recovery of Rs. 12,30,264/=

made from bills and security deposit

amount and since, the corresponding

counterclaim No. 1 for recovery of

balance bill amount has been rejected

by Learned Arbitrator himself and

corresponding counterclaim No. 3 and

4 for recovery of security deposit

amounts, are being rejected vide

present judgment, the question of

initiating fresh arbitration for this

claim No. 4 does not arise.

78

CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

iii) The award in respect of awarding

Counterclaim No. 2 to 6 is set aside.

The award in respect of partly allowing

Claim No. 2 & rejecting Claim No. 3 and

Counterclaim No. 1 is confirmed and so also

the rate of interest awarded in respect of

the claim No. 2 [under claim No. 5] is

confirmed. Since all the counterclaims have

been set aside, the rate of interest on

counterclaim amounts [awarded under

counterclaim No. 7] does not survive.

In view of confirmation of award in

respect of Claim No. 2, the claimant is

entitled to recover the sum of Rs. 4,54,508

as awarded under claim No. 2, along with

interest at 11% per annum, which is

quantified at Rs. 2,30,981 in the award and
79
CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

accordingly, the award holding that the

Petitioner / claimant is entitled to recover

the sum of Rs. 6,85,489 from the

respondent is confirmed.

That portion of the award allowing the

counterclaims and holding that the

respondent No. 1 is entitled to recover the

sum of Rs. 2,06,22,174 from the

Petitioner / claimant is hereby set aside.

Considering the facts and

circumstances of the case and the fact that,

some claims / counterclaims have been set

aside and some have been confirmed, both

sides to bear their respective costs.

Ordered accordingly.

80

CT 1390_Com.A.P.166-2023_Judgment.doc
KABC170026022023

Office to issue soft copy of this

judgment to both sides by email if

furnished.

[Dictated using Dragon Professional Speech Recognition
Software Version 15.3, transcript revised, corrected,
signed and then pronounced by me in open court on this
the 04th day of January, 2025]

(Sri. S. Sudindranath)
LXXXIII ADDL.CITY CIVIL AND SESSIONS JUDGE,
COMMERCIAL COURT; BANGALORE.



Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here