Bombay High Court
Exquisite Buildcon Projects Pvt. Ltd vs The State Of Maharashtra, Dept. Of … on 12 February, 2025
Author: G. S. Kulkarni
Bench: G. S. Kulkarni
2025:BHC-AS:11122-DB Equisite Buildcon Projects Pvt Ltd vs The Sttae of Maharashtra & Ors 401-wp-10129-2024.doc Shephali IN THE HIGH COURT OF JUDICATURE AT BOMBAY CIVIL APPELLATE JURISDICTION WRIT PETITION NO. 10129 OF 2024 Exquisite Buildcon Projects Pvt Ltd, A private limited company incorporated under the Companies Act,1956 through it's Authorised Signatory & C.E.O. of the Company, Mr Rajesh Alias Raajesh Sheth having its Registered Office at 506, Mastermind-1, Royal Palms, Aarrey Mmilk Colony, Goregaon (E). Mumbai 400 065 And also only Communication address at 504, Marble Park View Building, Opp Pawan Hans Airport, Near Ishwalal Park, Baptista Road, Vile Parle West, ...Petitioner SHEPHALI Mumbai 400 056 India (Ori. Claimant) SANJAY MORMARE Digitally signed ~ versus ~ by SHEPHALI SANJAY MORMARE Date: 2025.03.10 15:45:43 +0530 1. The State of Maharashtra, Department of Revenue and Forest, Floor No 7-MA.A., Madam Cama Road, Hutatma Rajguru Chowk, Mantralaya (Extension), Mumbai 400 032. through its Principal Secretary, Email: [email protected] 2. Office of the Inspector General of Registration and Controller of Stamps, Ground Floor, Opposite Vidhan Bhavan (Coucil Hall), New Administrative Building, Pune 411 001, Page 1 of 4 12 February 2025 ::: Uploaded on - 10/03/2025 ::: Downloaded on - 14/03/2025 21:22:27 ::: Equisite Buildcon Projects Pvt Ltd vs The Sttae of Maharashtra & Ors 401-wp-10129-2024.doc Maharashtra, India. 3. Office of the Collector of Stamps, Andheri, 1st Floor, MMRDA Building, Bandra Kurla Complex, Bandra (East), Mumbai - 400 051 Email: ...Respondents [email protected] (Ori. Respondents) A PPEARANCES FOR THE PETITIONER Mr Rahul Motkari, with Manasi Pawar. FOR THE RESPONDENT Ms P.J. Gavhane, AGP. STATE CORAM : G. S. KULKARNI & ADVAIT M. SETHNA, JJ. DATE : 12 FEBRUARY 2025 Oral Judgment (Per Advait M Sethna, J.): 1. This petition is filed under Article 226 of the Constitution of India praying for the only substantive relief, which reads thus: "(a) This Hon'ble Court be pleased to issue a writ of mandamus or any other writ in the like nature thereby directing and ordering the Respondent No. 2 to adjudicate and decide the Petitioner's Application dated 11.01.2024 (Exhibit 'K') at the earliest and within a time bound period." 2. Rule. Respondents waive service. Rule made returnable forthwith. With the consent of the parties, heard finally. Page 2 of 4 12 February 2025 ::: Uploaded on - 10/03/2025 ::: Downloaded on - 14/03/2025 21:22:27 ::: Equisite Buildcon Projects Pvt Ltd vs The Sttae of Maharashtra & Ors 401-wp-10129-2024.doc 3. Mr. Rahul Motkari, learned counsel for the petitioner would submit that the grievance of the petitioner is restricted to directing the respondents to initiate and complete the process of pending adjudication and decision on the petitioner's application dated 11 January 2024 filed with respondent no. 2 under the Amnesty Scheme 2023 floated under the Maharashtra Stamp Act, 1958. The said application is for the respondents to consider and adjudicate the requisite stamp duty payable under the MoU/Assignment Agreement dated 20 July 2016, which is the subject matter of pending arbitration proceedings before the learned Sole Arbitrator. 4. Ms. Gavhane, learned AGP for the State would oppose the petition. However, there is no written opposition/reply to the said petition. 5. We have heard the learned counsel for the parties and, with their assistance, perused the record. We find that it is undisputed that the application of the petitioner dated 11 January 2024 is pending with respondent no. 2. Therefore, such application ought to be decided in accordance with law. 6. In our view, the following order would meet the ends of justice: ORDER
(a) Respondent no. 2 is directed to decide the application
of the petitioner dated 11 January 2024 after hearing
Page 3 of 4
12 February 2025
::: Uploaded on – 10/03/2025 ::: Downloaded on – 14/03/2025 21:22:27 :::
Equisite Buildcon Projects Pvt Ltd vs The Sttae of Maharashtra & Ors
401-wp-10129-2024.doc
the parties and pass a reasoned order in accordance with
law, within a period of four weeks from the date of this
order is made available to the said respondent.
(b) All contentions of the parties are expressly kept open.
(c) The petition is disposed of in the above terms. No order
as to costs.
(ADVAIT M. SETHNA, J) (G. S. KULKARNI, J)
Page 4 of 4
12 February 2025
::: Uploaded on – 10/03/2025 ::: Downloaded on – 14/03/2025 21:22:27 :::