[ad_1]
Bombay High Court
Flagship Infrastructure Ltd. Through … vs The Competent Authority Dist. Dy. Reg. … on 15 April, 2025
Author: Amit Borkar
Bench: Amit Borkar
2025:BHC-AS:17010
                                                                                   3-wp151-19-F.doc
                    Amk
                            IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                    CIVIL APPELLATE JURISDICTION
                                     WRIT PETITION NO. 151 OF 2019
                                                 WITH
                                 INTERIM APPLICATION NO. 18160 OF 2022
                                                 WITH
                                 INTERIM APPLICATION NO. 19665 OF 2022
                    1. Flagship Infrastructure Ltd.
                       (Initially known as Flagship Infrastructure Pvt.
                       Ltd.) Behind Cognizant, Rajiv Gandhi
                       InfoTech Park Phase No.1, Hinjewadi, Tal:-
                       Mulshi District:- Pune By and through its
                       present director/authorized Signatory:- Ms.
                       Meghali Katdare
                    2. Flagship Infrastructure Ltd.
                       (Initially known as Flagship Infrastructure Pvt.
                       Ltd.) By and through its director/authorized
                       Singnatory:- Ms. Meghali Katdare
                       Blue Ridge, Behind Cognizant, Rajiv Gandhi
                       InfoTech Park, Phase No.1, Hinjwadi, Tal:-
                       Mulshi District:- Pune
                                                                             ...Petitioner
                                        V/s.
                    1. The Competent Authority
                       District Deputy Registrar of the Co-operative
                       Societies, Pune (Rural) Pune.
                    2. Blue Ridge Unit "A" (Tower No.1 to 8) CHS
                       Ltd. S. No. 119/125/154 to 160/160/2 to
                       171/17 Plot No.1, Behind Cognizant, Rajiv
                       Gandhi InfoTech Park Phase No.1, Hinjwadi,
                       Tal:- Mulshi District:- Pune
                       By and through Shri. Vaibhavraj Kumthekar
                       Shri. Samir Gokhale                        ...Respondents
                                                  ..........
                                                     1
                ::: Uploaded on - 15/04/2025                ::: Downloaded on - 15/04/2025 22:21:06 :::
                                                                     3-wp151-19-F.doc
 Mr. Prasad Dani, Senior Advocate i/b. Mr. Sarthak S. Diwan for the
 Petitioners.
 Ms. M. P. Thakur, AGP for Respondent No.1-State.
 Mr. Anil Anturkar, Senior Advocate i/b. Sugandh Deshmukh for
 Respondent No.2 in Writ Petition and and for the Applicants in all
 Interim Applications.
                                   ..........
                           CORAM             : AMIT BORKAR, J.
                           RESERVED ON       : APRIL 4, 2025
                           PRONOUNCED ON     : APRIL 15, 2025
 JUDGMENT
1. This petition raises a narrow, but important question of law:
whether a notification issued under Section 20(4) of the
Maharashtra Regional and Town Planning Act, 1966 (MRTP Act),
granting a developer ten years’ time for completing a development
project, can override the statutory obligation cast upon the
developer under the Maharashtra Ownership Flats (Regulation of
the Promotion of Construction, Sale, Management and Transfer)
Act, 1963 (MOFA) and Rule 9 of the MOFA Rules, 1964, to execute
a conveyance of title in favor of a cooperative housing society
within four months of its formation. This Court is thus called upon
to examine the scheme and purpose of the two statutes and decide
which must prevail in the event of an apparent conflict.
 2.      The present petition has been instituted by the petitioners,
 who are developers, questioning the legality and validity of the
 judgment and order dated 27th November 2018 passed by the
 District Deputy Registrar, Co-operative Societies, Pune (Rural). By
                                         2
::: Uploaded on – 15/04/2025                 ::: Downloaded on – 15/04/2025 22:21:06 :::
                                                                      3-wp151-19-F.doc
 the said order, rendered in Application No. DC 16/2018-19, a
 certificate of deemed conveyance has also been issued in favor of
 respondent No.2 – the Housing Society. The certificate pertains to
 land admeasuring 442.25 square feet, together with the
 constructed area of 85,926.373 square meters, and includes an
 undivided share and interest in the common areas and common
 facilities to the extent of the said area. The land in question forms
 part of Survey Nos. 119 (Part) to 125 + 154 (Part) to 160/2 to
 171 + 173, situate behind Cognizant, Rajiv Gandhi InfoTech Park,
 Hinjewadi, Pune.
 3.      The petitioners, feeling aggrieved by the said order and
 certificate of deemed conveyance, have approached this Court
 invoking its writ jurisdiction.
 4.      The facts necessary for deciding the present petition, briefly
 stated, are as under: The petitioners are the original developers
 and owners of the property in question. They had undertaken the
 development of a township project known as Blue Ridge, after
 securing requisite permissions under the provisions of the
 Maharashtra Regional and Town Planning Act, 1966. The
 construction was to be carried out in a phased manner as per the
 sanctioned plans.             The dispute giving rise to the present
 proceedings is confined only to Towers 1 to 8 within the said
 township project. Respondent No.2-Society was registered on 12th
 September 2011. According to respondent No.2, the Society
 comprises eight buildings consisting of 811 flats, 12 shops, and
 common amenities, spread over the land forming part of the Blue
 Ridge Township. It is the grievance of respondent No.2 that despite
                                        3
::: Uploaded on – 15/04/2025                  ::: Downloaded on – 15/04/2025 22:21:06 :::
                                                                  3-wp151-19-F.doc
 repeated requests, the petitioners failed to convey the land and
 constructed premises to the Society, as required by law.
 5.      Faced with such inaction, respondent No.2 preferred an
 application for deemed conveyance before the District Deputy
 Registrar under the provisions of Section 11(3) of MOFA. The
 application was duly accompanied by necessary documents and
 records. On receipt of notice from the authority, the petitioners
 appeared and contested the application. By way of written
 submissions and oral arguments, the petitioners contended that
 the application was not maintainable in law. It was urged that no
 cause of action had arisen, inasmuch as the petitioners had not
 committed any breach of statutory duty. It was further submitted
 that the description of the subject matter of the application was
 incorrect, inasmuch as the entire master layout of the township
 could not be the subject matter of a deemed conveyance
 application restricted only to Towers 1 to 8. The petitioners also
 contended that the right of respondent No.2, if at all, could only
 extend to the land directly beneath the eight buildings in question,
 and not to the entire larger parcel of land forming the township.
 6.      Both parties submitted written arguments before the
 authority. After affording full opportunity of hearing to the
 petitioners and the society, the District Deputy Registrar, by the
 impugned order dated 26th November 2018, allowed the
 application of respondent No.2 and issued a certificate of deemed
 conveyance. Aggrieved thereby, the petitioners have preferred the
 present writ petition.
                                  4
::: Uploaded on – 15/04/2025              ::: Downloaded on – 15/04/2025 22:21:06 :::
3-wp151-19-F.doc
 7.      This Court, by an order dated 14th January 2019, issued
 Rule and granted interim relief in terms of prayer clause (c) of the
 petition, thereby staying the operation of the certificate of deemed
 conveyance pending the hearing and final disposal of the petition.
 The petition has now been placed for final hearing.
 8.      Mr. Dani, learned Senior Advocate appearing on behalf of the
 petitioners, invited the attention of this Court to various provisions
 of the Maharashtra Regional and Town Planning Act, 1966 (“MRTP
 Act”), including Sections 2(13D), 2(27), 14(l), 17, 18(3), and
 44(2), to contend that the State Government had sanctioned the
 township project by issuing a notification under Section 20(4) of
 the said Act. According to the learned Senior Advocate, such
 integrated township, being specially sanctioned, occupies a higher
 pedestal and would prevail over the other general provisions of the
 MRTP Act. In the event of a conflict between regional plans,
 development plans, or subordinate rules and regulations, it is the
 integrated township, sanctioned under the special provisions, that
 must prevail. He submitted that the township project in question,
 being a special township permitted under Section 18(3) of the
 MRTP Act, is entitled to benefits and concessions such as
 exemption from individual Non-Agricultural (NA) permissions,
 concession in stamp duty, and the grant of floating Floor Space
 Index (FSI). The floating FSI, it was pointed out, could be utilized
 anywhere within the township area, irrespective of the location of
 the particular plot. The completion certificate for individual
 buildings, he submitted, could be granted only after the
 completion of the entire township as per the conditions stipulated
                                   5
::: Uploaded on – 15/04/2025               ::: Downloaded on – 15/04/2025 22:21:06 :::
                                                                  3-wp151-19-F.doc
in the notification issued under Section 20(4) of the MRTP Act.
 9.      Mr. Dani further drew the attention of the Court to the
 agreements executed with the flat purchasers under Section 4 of
 the Maharashtra Ownership Flats Act (“MOFA”). He submitted that
 at the time of purchase of the flats, the flat purchasers were made
 fully aware of the nature and character of the integrated township
 project. It was specifically disclosed to them that the developers
 retained the right to utilize the floating FSI anywhere within the
 township area, even after the completion of individual buildings.
 Thus, it was contended that the flat purchasers, having entered
 into agreements with full knowledge and consent regarding the
 development rights reserved by the petitioners, cannot now seek to
 defeat those rights by seeking conveyance of the larger parcel of
 land. Learned Senior Advocate next submitted that respondent
 No.2-Society had filed the application for deemed conveyance on
 18th July 2018 under Section 11 of MOFA, by which time the Real
 Estate (Regulation and Development) Act, 2016 (“RERA”) had
 already come into force. He pointed out that the Maharashtra Real
 Estate Regulatory Authority (Form of Annual Statement of
 Accounts and Annual Report) Rules, 2017, had also been notified
 on 20th April 2017.
 10.     According to him, under the scheme of RERA and the said
 Rules, in the case of a layout project, the conveyance is limited to
 the structure of the building and not of the entire underlying land.
 The conveyance of the land comprising the entire layout would be
 permissible only after the last building in the layout has received
 an occupation certificate. He contended that in case of any
                                  6
::: Uploaded on – 15/04/2025              ::: Downloaded on – 15/04/2025 22:21:06 :::
                                                                               3-wp151-19-F.doc
 inconsistency between MOFA and RERA, the provisions of RERA,
 being a later Central legislation, would prevail. In support of his
 submissions, reliance was placed on the judgment of the Hon’ble
 Supreme Court in Dr. Abraham Patani & Anr. v. State of
 Maharashtra & Ors., (2023) 11 SCC 79.
 11.     Mr. Dani also referred to the Maharashtra Housing
 (Regulation and Development) Act, 2012, which came into force
 on 8th July 2014. He submitted that Section 19 of the said Act,
 which provided for conveyance of title, recognized the right of the
 developer to utilize the increased FSI within a layout even after the
 completion          of        individual     buildings,    provided         the      entire
 development of the layout was not complete. He contended that
 this recognition of the right to utilize increased FSI survives, and
 that the competent authority ought to have borne in mind these
 legislative provisions while deciding the application for deemed
 conveyance.
 12.     Learned Senior Advocate then submitted that although the
 competent authority recorded a finding in the impugned order that
 it had no jurisdiction to adjudicate upon rights relating to
 increased FSI and related matters, in the operative portion of the
 order, the authority proceeded to grant benefits relating to
 increased FSI to respondent No.2-Society. He contended that the
 operative        part         of   the     order   was    self-contradictory            and
 unsustainable in law.
 13.     Dealing with the objection raised on behalf of respondent
 No.2 that the applicability of RERA and the Maharashtra Housing
                                               7
::: Uploaded on – 15/04/2025                           ::: Downloaded on – 15/04/2025 22:21:06 :::
                                                                  3-wp151-19-F.doc
 Act, 2012 had not been specifically pleaded in the reply before the
 competent authority, Mr. Dani submitted that the petition contains
 various grounds which substantively raise these points. He
 contended that it was open to the petitioners to raise legal issues
 during the course of hearing, and the objection to such
 submissions being advanced at the stage of final arguments ought
 not to be entertained. He thus submitted that the impugned order
 deserves to be quashed and set aside.
 14.     Per contra, Mr. Anturkar, learned Senior Advocate appearing
 on behalf of respondent No.2-Society, supported the impugned
 order. He contended that the points relating to the applicability of
 the Maharashtra Housing (Regulation and Development) Act, 2012
 had not been raised in the reply before the competent authority,
 and therefore, it was not permissible for the petitioners to raise
 such points for the first time during oral submissions before this
 Court. According to him, procedural fairness demands that points
 not raised before the lower authority cannot be entertained at a
 belated stage. He further submitted that the Maharashtra Housing
 Act, 2012, had already been repealed by the RERA Act with effect
 from 1st May 2016. The agreements for sale in the present case
 had been executed in the year 2008, and therefore, the provisions
 of the 2012 Act were not applicable. Dealing with the petitioners’
 reliance on RERA, Mr. Anturkar submitted that the argument based
 on Rule 9 of the Maharashtra Rules framed under RERA was
 misconceived. Rule 9 applies only to agreements executed under
 Section 17 of RERA. In the present case, the agreements were
 executed prior to the coming into force of RERA and are governed
                                   8
::: Uploaded on – 15/04/2025              ::: Downloaded on – 15/04/2025 22:21:06 :::
                                                                  3-wp151-19-F.doc
 by MOFA. Thus, Rule 9 of the RERA Rules has no application. He
 submitted that under Section 11 of MOFA, the competent authority
 is empowered to grant deemed conveyance in respect of the
 superstructure as well as the land underneath and appurtenant
 thereto. According to him, a clear distinction must be drawn
 between the land immediately underneath the building and other
 lands forming part of common amenities, open spaces, or lands
 reserved for FSI utilization.
 15.     In the present case, he pointed out, the entire constructed
 area measures approximately 85,926.373 square meters, and the
 land admeasures 44,282.52 square meters. The FSI has already
 been fully utilized. Therefore, the competent authority was correct
 in granting deemed conveyance in respect of the constructed area,
 as no unused FSI remained available for future exploitation by the
 developer. Accordingly, he submitted that the impugned order is in
 accordance with law and does not warrant interference.
 16.     In light of the submissions advanced on behalf of the
 petitioner, it becomes necessary to examine the statutory scheme
 of both the MRTP Act and the MOFA. The Maharashtra Ownership
 Flats Act, 1963 (known as MOFA) is a law made for protecting
 ordinary people who buy flats. It was passed by the State
 Government because, at that time, many promoters were taking
 advantage of home buyers. People would spend their entire life’s
 savings to buy a flat, but even after paying the full price, they
 would not get a clear legal title to the property. Promoters would
 sometimes hand over the keys and let the buyers live in the flat,
 but would not transfer the legal ownership. They would continue
                                   9
::: Uploaded on – 15/04/2025              ::: Downloaded on – 15/04/2025 22:21:06 :::
                                                                   3-wp151-19-F.doc
 to control the land and the building. MOFA was made to stop this
 kind of wrongdoing. The law puts several duties on the developer,
 who is called the “promoter” in the Act, to protect the interests of
 flat purchasers. One very important duty is given in Section 11 of
 MOFA. This section says that after selling the flats, the promoter
 must transfer the ownership rights that is, the title to the land and
 the building to the body formed by the flat purchasers. This body
 could be a cooperative housing society, a company, or any other
 organization made by the flat owners.
 17.     The law does not leave the timeline for this transfer open-
 ended. Rule 9 of the Maharashtra Ownership Flats Rules, 1964
 clearly says that if the sale agreement does not mention the time
 for handing over ownership, the promoter must transfer the
 property within four months from the date the society or other
 organization of flat buyers gets registered. In plain words, once the
 flat owners form a cooperative society, the promoter has no choice
 he must transfer the property to the society within four months.
 This is a strict requirement. It is not just a guideline or suggestion.
 It is a must.
 18.     The reason behind this strict rule is simple, a person who has
 paid the full amount and completed all formalities should not be
 left at the mercy of the promoter. The buyers should get clear
 ownership rights quickly, without unnecessary delay. Otherwise,
 the promoter would continue to have control over the property
 and the buyers would remain insecure. MOFA has been recognized
 by the Supreme Court, as a special law made for consumer
 protection. Once the flats are sold, the promoter must take all
                                    10
::: Uploaded on – 15/04/2025               ::: Downloaded on – 15/04/2025 22:21:06 :::
                                                                   3-wp151-19-F.doc
 steps necessary to complete his legal title and must then transfer
 that title to the buyers’ society. After this transfer, the promoter’s
 rights are only limited to those flats which are still unsold. Even for
 those unsold flats, the promoter becomes just another member of
 the society, like any other flat owner.
 19.     The duty of the promoter to transfer ownership is not just a
 private promise. It is a legal obligation under the Act. The
 lawmakers were very clear that after selling the flats and forming a
 society, the promoter must lose all power and control over the
 property. The flat purchasers must become full and final owners. If
 a promoter tries to hold on to control by delaying transfer or
 giving excuses like pending development he is going against the
 very purpose for which MOFA was made.
 20.     To further strengthen the rights of flat owners, the
 Government brought an amendment in 2008. This amendment
 added a new idea called “deemed conveyance”. Under Section
 11(3) to 11(5) of MOFA, if the promoter does not transfer
 ownership within the prescribed time, the flat purchasers’ society
 can apply to a competent authority, usually the District Deputy
 Registrar. The authority will check the documents and hear both
 sides. If the society’s claim is correct, the authority can pass an
 order and directly execute the conveyance deed, giving ownership
 to the society, even without the promoter’s cooperation. This
 system shows that transferring ownership is not optional. It is a
 must. The rights of flat buyers would mean nothing if promoters
 could keep delaying conveyance by taking shelter under other laws
 like the MRTP Act. The Legislature wanted to give flat buyers a
                                   11
::: Uploaded on – 15/04/2025               ::: Downloaded on – 15/04/2025 22:21:06 :::
                                                                  3-wp151-19-F.doc
 clear and absolute right to become legal owners of their flats and
 the land attached to them, free from any delay, conditions, or
 commercial tactics of the promoter.
 21.     The Maharashtra Regional and Town Planning Act, 1966
 (commonly called the MRTP Act) is a law made to ensure that the
 growth of cities and towns happens in an organized and planned
 manner. Before this law came into force, cities were growing in an
 unplanned way, and there was a need for a proper system to
 manage land use and development. The main purpose of the
 MRTP Act is to make sure that the use of land happens in a
 systematic way. It does this by creating regional plans and
 development plans which set out how different areas can be used
 for homes, shops, industries, gardens, schools, and so on. The law
 also controls who can build what and where, so that public
 facilities like roads, parks, and drainage are properly planned. In
 plain words, this law looks at the “big picture” of how cities should
 grow, so that there is order and not chaos. The MRTP Act is about
 city planning and development control. It is not about the private
 dealings between a promoter and a flat buyer. One important part
 of the MRTP Act is Section 20(4). This section says that if the
 Government wants to change or modify a regional plan, it can do
 so by issuing a notification in the Government Gazette after
 following certain steps like inviting objections and suggestions.
 Through this notification, the Government can allow special rules
 for particular projects.
 22.     At this stage, it is very important to understand that MRTP
 Act and MOFA are two different laws made for two very different
                                  12
::: Uploaded on – 15/04/2025              ::: Downloaded on – 15/04/2025 22:21:06 :::
                                                                    3-wp151-19-F.doc
 purposes. MRTP Act deals with how land is used, how cities are
 developed, and how big projects should be planned and carried
 out from the State’s and public’s point of view. It looks at the larger
 interest where roads, parks, hospitals, and schools should come,
 and how construction should happen according to development
 plans.      MOFA, on the other hand, is about the rights of flat
 purchasers. It focuses on making sure that promoters deal fairly
 with people who buy flats that they give all necessary information,
 that the building is constructed as promised, and that the
 ownership of the flat (and land) is properly and timely transferred
 to the buyers’ society. Thus, while the MRTP Act speaks about
 planning of the city, the MOFA speaks about protecting the home
 buyers. This difference is very important. Even if the promoter has
 permission under the MRTP Act to take ten years to complete the
 entire township, that does not mean he can hold on to the
 ownership of flats or land for so many years and refuse to transfer
 ownership to the flat buyers who have already paid the full
 amount and moved into their homes.
 23.     It is a well-settled rule in law known as generalia specialibus
 non derogant. It simply means that when two laws apply, and one
 law is general and the other law is special, the special law will
 override the general law, especially when the special law is made
 to protect a particular class of people. Here, even though MOFA
 was made in 1963 and MRTP Act in 1966, the MOFA Act has been
 amended many times (like in 1983, 1986, 2008, and so on) to
 strengthen the rights of flat purchasers. It continues to be a law
 that deals specially with promoter-buyer relations. The MRTP Act,
                                    13
::: Uploaded on – 15/04/2025                ::: Downloaded on – 15/04/2025 22:21:06 :::
                                                                 3-wp151-19-F.doc
 though also amended, has remained focused on town planning,
 and it does not deal with sale of flats or the obligations of
 promoters towards flat buyers. Thus, there is no real conflict
 between MRTP and MOFA. Even if the promoter has town
 planning permissions and an extended timeline under MRTP Act,
 when it comes to giving ownership to flat buyers who have already
 bought and occupied their flats, MOFA must prevail. The promoter
 cannot delay the conveyance by citing permissions or concessions
 under MRTP Act. The promoter’s town planning rights under
 MRTP Act and his legal duty under MOFA are two different things.
 The town planning permission does not take away the flat
 purchasers’ right to become owners under MOFA.
 24.     Having considered the arguments of both sides, this Court
 finds as follows: The two laws, MOFA and the MRTP Act, deal with
 different subjects. Both can work together without clashing with
 each other. When we read these two laws in a way that makes
 them both meaningful, it becomes clear that when it comes to
 issues between a promoter and flat buyers, MOFA must prevail.
 There is nothing in the MRTP Act, or even in the Section 20(4)
 notification the promoter is relying on, that says MOFA will not
 apply. The MRTP notification only gives the promoter more time of
 ten years to finish the township’s construction and development
 work. It does not say anywhere that the promoter is allowed to
 hold on to the ownership of flats already sold and occupied. Thus,
 it is very much possible for the promoter to comply with MOFA by
 handing over ownership of the already completed and occupied
 buildings to the flat owners’ society, and at the same time,
                                 14
::: Uploaded on – 15/04/2025             ::: Downloaded on – 15/04/2025 22:21:06 :::
                                                                   3-wp151-19-F.doc
 continue to enjoy the other development benefits under MRTP for
 the unfinished parts.
 25.     It is well settled if a law requires to do something in a
 particular way, one has to do it exactly that way and not in any
 other manner. MOFA rules state that the conveyance must be done
 within four months from the date of registration of the society.
 That is the only method and timeline allowed. The promoter
 cannot use an excuse of a government notification that talks about
 project completion to delay handing over ownership. If the law
 wanted promoters to delay conveyance till township completion, it
 would have clearly said so. But neither MOFA nor the MRTP Act
 say that. Therefore, both laws must be followed in their own areas
 and when it comes to promoter-flat buyer relations, MOFA is
 supreme.
 26.     In the case of Lok Housing & Construction Ltd. v. Lok Everest
 Co-op. Housing Society, 2025 SCC Online Bombay 711 , a promoter
 made a similar excuse. He contended that conveyance should
 happen only after the whole layout was complete, and pointed to a
 agreement clause deferring conveyance. This Court rejected that
 argument and clearly held that Rule 9 of MOFA fixes a strict four-
 month time limit. Any part of the contract that tries to go against
 this rule is void. In that case, the Court noted that even after 30
 years, the promoter had not given conveyance. Such delay was
 called “completely against the purpose of MOFA” and very unfair to
 flat owners. The Court held that no clause in the agreement can
 defeat a promoter’s legal duty under MOFA. If an agreement
 between buyer and promoter cannot postpone conveyance, then
                                   15
::: Uploaded on – 15/04/2025               ::: Downloaded on – 15/04/2025 22:21:06 :::
                                                                     3-wp151-19-F.doc
 surely a general government notification under MRTP, which does
 not even talk about flat buyers’ rights, cannot be used to avoid the
 conveyance obligation. The Lok Housing judgment also held that
 Section 11 of MOFA is a very important safeguard. It is meant to
 end the promoter’s control once the flats are sold. Allowing a
 promoter to keep ownership for ten years or more would defeat
 the very purpose for which MOFA was made.
 27.     The Supreme Court also gave a strong message in
 Nahalchand Laloochand Pvt. Ltd. v. Panchali Co-op. Housing
 Society (2010) 9 SCC 536. In that case, while dealing with the
 issue of parking spaces, the Court explained the larger scheme of
 MOFA. It said the promoter has the right to sell only flats and not
 the common areas, land, parking spaces, or other facilities. All
 those must be transferred to the society. The Supreme Court said
 very clearly that any arrangement made by the promoter with
 buyers that goes against MOFA is not valid. By the same reasoning,
 if a promoter tries to hide behind an MRTP permission to avoid
 handing over title, that too is not valid. The law (MOFA) must be
 followed as it is.
 28.     It is therefore clear that MOFA’s provisions for protecting flat
 owners, especially timely transfer of ownership, must be strictly
 followed. Promoters cannot escape their duties under MOFA by
 pointing to other permissions, administrative timelines, or private
 agreements. Following the MOFA timeline is very important. If
 conveyance is delayed for ten years (or even longer if the township
 gets delayed), the society formed by the flat owners faces legal
 problems such as society’s name does not get recorded as owner in
                                    16
::: Uploaded on – 15/04/2025                 ::: Downloaded on – 15/04/2025 22:21:06 :::
                                                                      3-wp151-19-F.doc
 government records like property cards and revenue entries.
 Without ownership, the society cannot take loans for major repairs
 or redevelopment. Banks and financial institutions usually refuse
 loans if ownership is unclear. If the promoter becomes bankrupt or
 gets into legal trouble, creditors can try to claim the land because
 it is still in the promoter’s name. The promoter can misuse the
 delay to use extra FSI or development rights without the society’s
 knowledge or permission, affecting the rights of existing flat
 owners. This is why MOFA insists that the “entire land and
 building” must be transferred to the society once flats are sold. The
 promoter should retain only the unsold flats and nothing else.
 Timely conveyance gives full transparency, makes flat owners true
 legal owners, and protects their investment. It also empowers the
 society to manage the property, enforce their rights, and even
 compel the promoter to complete pending amenities if needed.
 Thus, this Court cannot support any interpretation that would
 leave flat owners vulnerable and the promoter in control even after
 flats are sold and occupied.
29. For all these reasons, this Court holds that:
(i) A notification under section 20(4) of the MRTP Act,
1966, cannot override or postpone the legal duty of
conveyance under MOFA.
(ii) MOFA, being a special law made to protect flat buyers,
will prevail over the general provisions of the MRTP Act.
(iii) The ten-year period given to the Petitioner (promoter)
under Section 20(4) of the MRTP Act is only for completing17
::: Uploaded on – 15/04/2025 ::: Downloaded on – 15/04/2025 22:21:06 :::
3-wp151-19-F.docconstruction. It does not affect the promoter’s duty to
transfer ownership to flat buyers within four months of
forming the society.
(iv) By the time the flat owners’ society was formed, the
Petitioner had already sold flats and handed over possession.
         Therefore, the obligation under MOFA became applicable,
         and the Petitioner had to transfer the title.
 30.     In light of the legal discussion and the parameters laid down
 hereinabove, it becomes necessary to scrutinize the facts of the
 present case in the context of the settled legal position. After
 carefully perusing the documents placed on record and giving
 anxious consideration to the rival submissions advanced by the
 learned Senior Advocates appearing for the parties, certain
 material aspects emerge which are undisputed and stand
 established.
 31.     Firstly, it is an admitted position that the agreements for sale
 between the petitioners, who are the promoters, and the individual
 flat purchasers were executed in the year 2008, much prior to the
 coming into force of the Real Estate (Regulation and Development)
 Act, 2016. Secondly, it is not disputed that respondent No.2, the
 cooperative housing society comprising the flat purchasers of
 Towers 1 to 8, came to be registered under the provisions of the
 Maharashtra Cooperative Societies Act, 1960 on 12th September
 2011. Thirdly, it is also admitted that the possession of the flats in
 Towers 1 to 8 was handed over to the flat purchasers, and that the
 flat purchasers have been in occupation thereof since the
                                     18
::: Uploaded on – 15/04/2025                 ::: Downloaded on – 15/04/2025 22:21:06 :::
                                                                   3-wp151-19-F.doc
 completion of construction of the said towers. Fourthly, it is not in
 dispute that despite the registration of the society on 12th
 September 2011, and despite the passage of considerable time
 thereafter, the petitioners did not execute the conveyance of title in
 favour of respondent No.2-society as required under Section 11 of
 MOFA read with Rule 9 of the MOFA Rules. These factual aspects,
 emerging from the record and admitted on both sides, form the
 basis for determination of the controversy in the present case.
 32.     The promoter tried to justify the delay in giving ownership to
 the society by pointing to two clauses (Clauses 6.3.1 and 6.3.2) in
 the sale agreements. According to the promoter, these clauses
 allowed them to delay conveyance for ten years after completion
 of Towers 1 to 8, or until the entire township project is completed,
 whichever happens earlier. In my opinion, this argument cannot be
 accepted. Because there is a clear rule under Rule 9 of the MOFA
 Rules, which lays down a strict time limit for the promoter to give
 ownership to the society. Rule 9 says that unless both sides
 specifically agree to a different period, the promoter must execute
 the conveyance within four months from the date of registration of
 the society.
 33.     The purpose of Rule 9 must be seen in the light of MOFA’s
 overall goal which is to protect flat purchasers and ensure they get
 clear ownership without unnecessary delay. Rule 9 is not just a
 formality. It is a real protection created by law against endless
 delays by promoters. The four-month period is written into law to
 make sure that flat buyers are not left in uncertainty about who
 owns the land and the building where they live. A promoter cannot
                                    19
::: Uploaded on – 15/04/2025               ::: Downloaded on – 15/04/2025 22:21:06 :::
                                                                   3-wp151-19-F.doc
 escape this responsibility by simply pointing to private agreement
 clauses, especially if those clauses depend on uncertain future
 events like full township completion, which flat buyers themselves
 have no control over.
 34.     The use of the word “period” in Rule 9 of MOFA Rules is very
 important. In common understanding, a “period” means a fixed,
 definite block of time, like four months, six months, etc. It does not
 mean some vague or uncertain future event. This meaning fits the
 general rule in law: unless the context requires otherwise, words in
 a law must be given their natural, everyday meaning. Here, the
 word “period” is clear and plainit points to a definite timeline. The
 promoter’s argument that the conveyance can be delayed until ten
 years after completion of Towers 1 to 8, or till the entire township
 is done would destroy this certainty. It would replace a clear
 deadline with an uncertain, shifting future event. That is not
 allowed. Courts are not allowed to change or rewrite clear laws
 under the excuse of interpretation. If courts start allowing such
 changes, it would defeat the whole purpose for which MOFA was
 made to protect flat buyers. If the promoter’s argument is
 accepted, it would allow promoters to hold on to ownership
 forever, just by pointing to some incomplete work in the township.
 This would bring back the very problems MOFA wanted to prevent.
 Thus, the word “period” in Rule 9 must be understood as a
 definite, fixed time and not an open-ended condition. Any clause
 in a sale agreement (like Clauses 6.3.1 and 6.3.2) that tries to
 override this rule is void (meaning invalid) because it goes against
 the law.
                                   20
::: Uploaded on – 15/04/2025               ::: Downloaded on – 15/04/2025 22:21:06 :::
3-wp151-19-F.doc
 35.     Based on the above discussion, I am firmly of the opinion
 that an agreement clause (like Clauses 6.3.1 and 6.3.2) that says
 the promoter can delay conveyance until the full project is
 complete goes against Rule 9 of MOFA. Especially when most of
 the flat purchasers have already taken possession, have formed a
 registered society, and have fulfilled their obligations, the
 promoter cannot hide behind private clauses to delay conveyance.
 If I accept the promoter’s argument, it would make the protection
 given to flat purchasers under MOFA meaningless, and would give
 complete, unregulated power to the promoter. That is not what the
 law allows. Therefore, the promoter was under a legal duty to
 execute the conveyance deed within four months from the date the
 society was registered (i.e., within four months from 12th
 September 2011). The promoter failed to do so. Thus, the
 application filed by respondent No.2-society under Section 11 of
 MOFA was legally correct.
 36.     The next contention of petitioners is based on Rule 9 of the
 Maharashtra RERA Rules which talks about how and when a
 promoter must transfer ownership (i.e., execute a conveyance)
 under Section 17 of the RERA Act. In plain words, Rule 9 says that
 if the project is a layout (meaning a bigger project with multiple
 buildings or wings), the promoter must first complete the entire
 layout and only then execute the conveyance of the common areas,
 land, and building. If it is just one building, the promoter must
 execute conveyance after the occupancy certificate for that
 building is obtained.
                                   21
::: Uploaded on – 15/04/2025              ::: Downloaded on – 15/04/2025 22:21:06 :::
3-wp151-19-F.doc
 37.     The promoter (petitioner) is trying to use this Rule to argue
 that only the building structure has to be conveyed not the land
 beneath it. The promoter can wait until the occupancy certificate
 for the last building in the layout is obtained. In my opinion, this
 argument made by the promoter cannot be accepted for multiple
 reasons. First, if we read Section 17 and Rule 9(2) together, it
 becomes obvious that when the law says “in the absence of local
 law,” it is referring to cases where no state-specific law exists. In
 Maharashtra, there is already a local law the Maharashtra
 Ownership Flats Act, 1963 (MOFA). MOFA was already in place
 long before RERA came into existence. It has its own complete
 rules about when and how the promoter has to give conveyance to
 flat buyers. Thus, the phrase “local law” under Section 17 should
 be interpreted to mean MOFA in Maharashtra. In fact, the
 lawmakers who made RERA were very much aware that laws like
 MOFA already existed in different states. That is why, in Section
 17, they clearly said that RERA timelines will apply only if no local
 law exists. So, the complete code of MOFA particularly Sections 10
 and 11, and Rule 9 of the MOFA Rules still applies fully in
 Maharashtra. MOFA already provides a clear timeline to promoters
 for transferring ownership. Therefore, the promoter cannot rely on
 Rule 9 of RERA to delay conveyance where MOFA already applies.
 In the present case the flat buyers’ society was formed way back in
 2011. The agreements between promoter and flat buyers were
 signed under MOFA, much before the RERA Act and RERA Rules
 even came into force. Thus, the promoter cannot now fall back on
 RERA or its Rules to escape the duty he had under MOFA.
                                   22
::: Uploaded on – 15/04/2025               ::: Downloaded on – 15/04/2025 22:21:06 :::
3-wp151-19-F.doc
 38.     Moreover, on a careful reading of Section 17 of the RERA
 Act, it becomes clear that this section puts a responsibility on the
 promoter (promoter) to do two main things: First, to execute a
 registered conveyance deed that means to officially transfer
 ownership of the flat and a share in the common areas to the
 buyers’ association (society). Second, to hand over possession of
 the flats, buildings, or plots, along with the documents of title and
 common areas, to the society within a specific time. This must be
 done according to the sanctioned plan and the deadlines set by the
 local laws. Now, the important point is this the proviso (the
 condition) in Section 17 says that only if there is no local law
 available, the promoter must carry out the conveyance within
 three months from the date of getting the occupancy certificate.
 39.     Similarly, sub-section (2) of Section 17 says that the
 promoter must hand over necessary documents and plans, and
 again, this is to be done as per local laws. If there is no local law,
 then he must do it within 30 days after getting the completion
 certificate. Thus, the structure of Section 17 itself shows that local
 law comes first, and the timeline under RERA applies only if no
 local law exists. In Maharashtra, Rule 9(2) of the Maharashtra
 RERA Rules has been made to support Section 17 of the Act. Rule
 9(2) also talks about the promoter’s obligation to convey title
 under Section 17.
 40.     Second, Section 17 of RERA itself talks about handing over
 not just the flat or building structure, but also the undivided share
 in the land and common areas. It does not say anywhere that only
 the building structure must be conveyed. Thus, the promoter’s
                                   23
::: Uploaded on – 15/04/2025               ::: Downloaded on – 15/04/2025 22:21:06 :::
                                                                   3-wp151-19-F.doc
 argument that only the building and not the land should be
 transferred has no basis in the law. Third, if the promoter’s
 interpretation is accepted that he can wait until the whole
 township is completed then flat owners will be left without
 ownership rights for an indefinite number of years. This would
 completely defeat the very purpose of MOFA, which was made to
 protect flat purchasers and to stop promoters from holding onto
 ownership unnecessarily. The law expects that once people have
 paid for their flats and taken possession, they should become legal
 owners without having to wait endlessly.
 41.     Thus, in plain words the promoter cannot delay conveyance
 by depending on RERA Rules because MOFA already applies. The
 promoter cannot claim that only the building needs to be conveyed
 and not the land. The promoter must convey both the flat, the
 share in the land, and the common areas to the society. Rule 9 of
 RERA does not change the promoter’s legal duty which had
 already arisen under MOFA. Hence, the petitioner’s argument
 based on Rule 9 of RERA Rules is rejected.
 42.     In the present case, a few important facts cannot be disputed
 that the agreements for sale were signed under Section 4 of MOFA.
 The agreements were signed before RERA came into force. The
 society (respondent No.2) was registered on 12th September 2011.
 The four-month period under Rule 9 of MOFA Rules for handing
 over ownership ended in 2011 itself. By the end of four months
 from the date of registration, the flat buyers’ society had already
 earned the right to demand conveyance from the promoter under
 MOFA. This right, once earned under MOFA, cannot be taken away
                                   24
::: Uploaded on – 15/04/2025               ::: Downloaded on – 15/04/2025 22:21:06 :::
                                                                   3-wp151-19-F.doc
 by trying to apply the timelines of another law (RERA) that came
 into force later. If the promoter’s argument is accepted that RERA
 timelines should now apply it would defeat the whole purpose of
 MOFA, which is a consumer-friendly law specially made to protect
 flat buyers. It would mean giving more time to promoters to delay
 conveyance, which is exactly what MOFA was made to prevent.
 43.     Thus, when it comes to providing the timeline for executing
 conveyance there is no conflict between MOFA and RERA. MOFA
 continues to apply, especially for agreements signed before RERA
 came into force. The language of Section 17 of RERA supports
 MOFA’s application where a local law like MOFA already exists.
 Therefore, in my opinion, the promoter’s argument cannot be
 accepted.
 44.     The next submission advanced on behalf of the petitioner
 pertains to the findings recorded by the Competent Authority in
 the impugned order. It was submitted that although the Competent
 Authority recorded a categorical finding that it did not possess
 jurisdiction to adjudicate upon the rights relating to increased
 Floor Space Index (FSI), nonetheless, in the operative part of the
 order, the Competent Authority proceeded to confer benefits
 arising from the alleged increased FSI in favour of respondent
 No.2-society.
 45.     Having given careful consideration to the said submission, in
 my opinion, the grievance raised by the petitioner merits
 acceptance. Once the Competent Authority, upon due examination,
 concluded that it lacked jurisdiction to adjudicate upon disputes or
                                   25
::: Uploaded on – 15/04/2025               ::: Downloaded on – 15/04/2025 22:21:06 :::
                                                                   3-wp151-19-F.doc
 rights pertaining to the increased FSI particularly in the light of
 notification under section 20(4) of MRTP Act, it was not open for
 the Competent Authority to thereafter, in the operative portion of
 the order, grant any relief to respondent No.2-society in relation to
 such increased FSI. It is well-settled that a statutory authority must
 act strictly within the bounds of its jurisdiction. If the Competent
 Authority in the peculiar facts of this case held that it had no
 power to decide upon rights concerning additional FSI, any
 directions issued in that regard in the operative part of the order
 would clearly be beyond the scope of its authority and would be
 legally unsustainable.
 46.     In my considered opinion, therefore, to the extent that the
 impugned order purports to confer or deal with rights arising from
 the alleged increased FSI, the same cannot be sustained. The
 proper remedy available to respondent No.2-society, in such
 circumstances, would be to approach the competent civil court by
 instituting appropriate proceedings seeking adjudication of its
 rights, if any, in relation to increased FSI and any related
 entitlements. Accordingly, this Court deems it appropriate to clarify
 that the rights, if any, of respondent No.2-society concerning the
 increased FSI and other related issues are kept expressly open to
 be agitated and adjudicated before a competent civil court in
 properly instituted proceedings, in accordance with law.
 47.     With respect to the petitioners’ contention that, in view of
 the promulgation of the MHRDA Act, the provisions of the MOFA
 Act have been rendered inoperative by implied repeal, this Court
 has already considered such arguments in Dosti Corporation,
                                   26
::: Uploaded on – 15/04/2025               ::: Downloaded on – 15/04/2025 22:21:06 :::
                                                                              3-wp151-19-F.doc
 Mumbai v. Sea Flama Cooperative Housing Society Limited & Ors.
 (2016 (5) Mh.L.J. 102). In that decision, this Court authoritatively
 held that an implied repeal of an earlier law may be inferred only
 where a subsequent statute is expressly empowered to override the
 earlier statute and is so fundamentally inconsistent with the earlier
 statute that both cannot coexist harmoniously. It was further held
 that unless there is a direct inconsistency, both statutes are to be
 construed as operating together in their respective spheres.
 Accordingly, the right to obtain a conveyance deed under the
 MOFA Act is not a mere procedural right or a right to sue, but a
 statutorily vested substantive right conferred upon societies.
 Moreover, no notification in respect of Section 56 of the MHRDA
 Act has been issued by the State Government, and therefore, the
 operative provisions of the MOFA Act, including Section 11, remain
 in force and are capable of being enforced. In view of the said
 judicial pronouncement, the contention raised by the respondents
 that the petitioner is precluded from claiming relief under the
 MOFA Act on account of its repeal is devoid of merit and stands
 rejected.
 48.     Furthermore, it is necessary to add that the object and
 purpose of the MOFA Act are distinct from those of the MHRDA
 Act. While the MOFA Act primarily governs the rights and
 obligations of promoters and flat purchasers, ensuring statutory
 protection        to     purchasers   in        relation   to     conveyance           and
 management of properties, the MHRDA Act is regulatory in nature
 and establishes authorities for regulation and promotion of the real
 estate sector. The two enactments operate in different fields, and
                                            27
::: Uploaded on – 15/04/2025                          ::: Downloaded on – 15/04/2025 22:21:06 :::
                                                                   3-wp151-19-F.doc
 unless there is an express repeal or an irreconcilable conflict, the
 rights under the MOFA Act cannot be abrogated by implication.
 Consequently, the petitioner-society’s application for deemed
 conveyance continues to be maintainable under Section 11 of the
 MOFA Act.
 49.     The consistent judicial refrain, as articulated in Shimmering
 Heights CHSL & Ors. v. State of Maharashtra (Writ Petition
 No. 3129 of 2016, decided on 6th April 2016), Zainul Abedin
 Yusufali Massawala & Ors. v. Competent Authority (reported in
 (2016) SCC OnLine Bom. 6028), P.R. Enterprises & Ors. v. the
 Competent Authority (Writ Petition No. 11251 of 2016, decided on
 27th November 2018), and Mehboob Ali Humza & Ors. v. District
 Sub-Registrar (3), Mumbai & Ors. (Writ Petition No. 3129 of 2016,
 decided on 24th June 2016), is that writ proceedings under
 Article 226 of the Constitution of India are inherently ill-suited for
 resolving disputes involving competing claims to title, ownership,
 or proprietary development rights. The jurisdiction of the
 Competent Authority under Section 11 of the MOFA Act is
 narrowly circumscribed to operationalizing and effectuating the
 statutory and contractual duty to execute conveyance in favor of
 flat purchasers or their legal entity in accordance with the
 sanctioned plan and the terms recorded in the registered
 agreements.
 50.     The Competent Authority is not empowered to adjudicate
 intricate questions of title, ownership disputes, or competing
 development rights that require examination of complex evidence
 or third-party rights. These disputes necessarily fall within the
                                   28
::: Uploaded on – 15/04/2025               ::: Downloaded on – 15/04/2025 22:21:06 :::
                                                                       3-wp151-19-F.doc
 exclusive domain of the civil courts, where full-fledged trial,
 examination, and cross-examination of evidence can take place.
 Therefore, any grievance raised by the petioners alleging that the
 Respondent-society’s claim exceeds its lawful entitlement must be
 agitated by way of a substantive civil suit. The existence of such
 competing claims does not, by itself, oust the society’s right to seek
 deemed conveyance under Section 11 of the MOFA Act before the
 Competent Authority.
 51.     In view of the foregoing discussion and upon a careful
 consideration of the factual matrix and the applicable legal
 principles, I pass following order:
(i) The Writ Petition is partly allowed in the aforesaid
terms.
(ii) The order dated 27th November 2018 passed by the
Competent Authority granting deemed conveyance in favour
of respondent No.2-society is upheld, except to the limited
extent that the conferment of benefits relating to increased
FSI is set aside.
(iii) The rights of respondent No.2-society in relation to
increased FSI and related entitlements are kept expressly
open to be adjudicated by the competent civil court in
properly instituted proceedings.
(iv) The petitioners retain the liberty to agitate their
substantive civil rights before the civil court in a civil suit.
(v) Rule is made absolute in the aforesaid terms.
                                       29
::: Uploaded on – 15/04/2025                   ::: Downloaded on – 15/04/2025 22:21:06 :::
3-wp151-19-F.doc
(v) There shall be no order as to costs.
(vi) All pending applications, if any, stand disposed of.
(AMIT BORKAR, J.)
                                       30
::: Uploaded on – 15/04/2025                   ::: Downloaded on – 15/04/2025 22:21:06 :::
 
[ad_2]
Source link 
