A copy of the order dated January 15, 2025, along with a forwarding

letter of the learned Advocate dated January 16, 2025 was served in

the office of the award debtor. Despite such service, none appears on

behalf of the award debtor.

2. The award debtor was directed to file affidavit of assets and also a

senior officer of the award debtor was directed to be available for

examination on the returnable date. As the award remained

unchallenged, it is incumbent upon the award debtor to pay off the

awarded amount in this execution proceeding. The sum awarded

(principal and interest) as of now, comes to more than Rs.10 lakhs.