Gallant Equipment Pvt Ltd vs Rashmi Metaliks Ltd on 16 April, 2025

0
23


1. This is an application for interim reliefs, under Section 9 of the

Arbitration and Conciliation Act, 1996.

2. The petitioner and the respondent entered into an agreement

named and styled as “Goods & Service Order”, dated July 5, 2023.

In terms of the said order, core curing oven was to be supplied to

the respondent. The oven was to be manufactured upon approval

of the specifications and drawings by the respondent. The same

was to be delivered within 60 days from the date of receipt of the

confirmed order and advance payment.

2

3. As per the purchase order, the respondent was obliged to pay 50%

advance, against the submission of an advance bank guarantee of

equal value. The said bank guarantee would be valid up to the

delivery of the complete materials at the site of the respondent. It

was further agreed that balance 50% would be paid after

inspection by the engineers of the respondent and prior to

despatch, the petitioner was obliged to submit 20% bank

guarantee which would be valid up to 12 months after the final

installation. The petitioner was required to supply the said goods

within 60 working days after receipt of the confirmed order and

advance payment.