Jagdish Chand Gupta vs State Of Himachal Pradesh And Another on 8 August, 2025

0
3

Himachal Pradesh High Court

Jagdish Chand Gupta vs State Of Himachal Pradesh And Another on 8 August, 2025

                                                                    ( 2025:HHC:26993 )




        IN THE HIGH COURT OF HIMACHAL PRADESH SHIMLA

                            Arb. Case no. 429 of 2024
                            Decided on: 08.08.2025
    ____________________________________________________




                                                                            .
    Jagdish Chand Gupta                          ....Petitioner





                            Versus

    State of Himachal Pradesh and another





                                            ...Respondents
    _____________________________________________________
    Coram
    Hon'ble Mr. Justice G.S. Sandhawalia, Chief Justice





    Whether approved for reporting? 1

    For the Petitioner: r                    Mr. Sumeet Raj Sharma, Advocate.

    For the respondents:                     Mr.Arsh Rattan,              Deputy Advocate

                                             General.

    G.S. Sandhawalia, Chief Justice (Oral)

This application has been filed under Section 11 (6)

of the Arbitration and Conciliation Act, 1996 (for short “the Act’)

for appointment of Arbitrator.

2. The agreement as such bearing No.56 was entered

into between the parties for construction of ‘Pre-stressed Box

Cantilever Bridge (71.00 mtrs. Clear span) over Binwa Khad on

Balh Bajuri (Dandhole) to Jamthala Lad Bharol road

inkm.10/495 (Under NABARD RIDF-XV)’.

3. The work was awarded on 21.06.2016 for an

1
Whether reporters of Local Papers may be allowed to see the judgment?

::: Downloaded on – 11/08/2025 21:25:41 :::CIS
-2-

amount of Rs.6,25,00,000/- and had to be completed within two

years. Under Clause 65 of the agreement, all disputes were to

be referred to the sole arbitrator.

.

4. It has been pleaded that the drawings as such were

given and the machinery had been rendered idle due to non-

availability of the approach road. The length of bridge had been

increased from 71.00 mtrs to 95.00 meters and a demand had

been raised for payment of additional length of the bridge

alongwith release of escalation refund of difference between

VAT and GST and also compensation for prolongation and loss

of profitability.

5. Necessary notice dated 21.12.2023 (Annexure P-3)

had been served upon the respondents, which has not been

responded to by the respondents, leading to filing of the

present petition.

6. The stand of the respondents-State as such is to the

extent that the penalty for the delay as imposed was waived off

by the Superintending Engineer, 5th Circle, HPPWD on

10.03.2021. Allegations regarding change of specification and

increase in length of bridge are contested and stated to be not

based on the fact being lump-sum contract. The claim of extra

::: Downloaded on – 11/08/2025 21:25:41 :::CIS
-3-

payment was refuted as such on the ground that the

Department had submitted the drawings of upper part of the

abutment, which is related to bear the cantilever span of the

.

bridge, which transfers the load of the bridge span over to the

abutment.

7. It is also to be noticed that the drawings were

issued part wise to the contractor at different periods of time as

per requirement as per meeting on 02.02.2021.

8. Supplementary affidavit has also been filed by the

State and the stand is the same that the drawings were issued

part wise to the contractor at different periods of time as per

requirement. It has been stated that the reply to notice given by

the petitioner has not been placed on record and a reference

was made to communication dated 04.03.2024 (Annexure R-2)

to point out the defence in sum and substance and also that

the contents of Clause 25 of the contract agreement does not

contain the arbitration clause.

9. A perusal of the agreement would go on to show

that the Clause of arbitration as such is under Clause 65 and

therefore the defence as such of the State is baseless and

once the parties is agreed as per contract to refer the matter to

::: Downloaded on – 11/08/2025 21:25:41 :::CIS
-4-

arbitration, this Court is of the considered opinion that having

agreed as such to the mode of settlement of dispute they are

bound as such by the terms of the contract.

.

10. Keeping in view the above position, I am of the

considered opinion that the matter can only be resolved by

appointment of an Arbitrator. Accordingly, the application is

allowed and Hon’ble Mr. Justice B.S Walia, former Judge

Punjab and Haryana High Court R/o House No.1143, Sector

8C, Chandigarh
r (Telephone No.98140-06691) (email:

[email protected]) is appointed as an Arbitrator to

adjudicate the dispute between the parties, after his disclosure

in writing is obtained in terms of Section 11(8) of the Act and

only after receipt thereof, his appointment, as an Arbitrator,

shall come into force.

11. On his giving consent to arbitrate the dispute

between the parties as an Arbitrator, Hon’ble Mr. Justice B.S

Walia, former Judge, Punjab and Haryana High Court, shall

enter into reference, and shall pass an award in accordance

with law.

12. Copy of this order be furnished to the learned

counsel for the parties and also be furnished to the learned

::: Downloaded on – 11/08/2025 21:25:41 :::CIS
-5-

Arbitrator. The learned Arbitrator so appointed shall be entitled

to fee as per stipulation contained in 4th Schedule appended to

the Arbitration and Conciliation Act, 1996.

.

13. Pending applications, if any, also stand disposed of

accordingly.

( G.S. Sandhawalia )
Chief Justice

8th August, 2025
(priti)

::: Downloaded on – 11/08/2025 21:25:41 :::CIS



Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here