Khark Petrochemical Company vs Hazel Mercantile Ltd on 9 June, 2025

0
49

Bombay High Court

Khark Petrochemical Company vs Hazel Mercantile Ltd on 9 June, 2025

Author: N. J. Jamadar

Bench: N. J. Jamadar

2025:BHC-OS:8433

                                                                                    -IAL-3847-2024-.DOC

                                                                                           Arun Sankpal



                                   IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                        ORDINARY ORIGINAL CIVIL JURISDICTION
                                                 IN ITS COMMERCIAL DIVISION
                                       INTERIM APPLICATION (L) NO. 3847 OF 2024
                                                             IN
                                             COMMERCIAL SUIT NO. 48 OF 2024


                       Khark Petrochemical Company
                       A Company incorporated under the Laws of
                       Islamic Republic of Iran, registration No. 11569,
                       having its office at No. 40, Dejam Jou St.,
                       North Dibaji St., Farmaniyeh Tehran, Iran
                       through its duly constituted Power of Attorney,
                       Mr. Pradeep Singh                                                ..Applicant/
                                                                                            Plaintiff

                              Versus

                       Hazel Mercantile Limited,
                       a company incorporated under the laws of India
                       having its registered office at 181, Ashoka
                       Centre, G.T. Hospital Complex, L.T. Road,
 ARUN                  Mumbai - 400 001.
 RAMCHANDRA
 SANKPAL               Through Its Managing Director,                              ...Respondent/
 Digitally signed by
                       Mr. Nitin Didwania                                             Defendant
 ARUN
 RAMCHANDRA
 SANKPAL
 Date: 2025.06.09
 19:42:13 +0530
                       Mr. Ratan Kumar Singh, Senior Advocate, with Mr. Akshay Gandotra
                             and Ms. Irima Pereira, i/b Vibha Juris Consult Co, for the
                             Applicant.
                       Mr. Prateek Seksaria, Senior Advocate (though VC), with Mr. Vivek
                             Kantawala, Mr. Amey Patil, Mr. Nishant Chotani and Mr. Rohit
                             Agarwal, i/b Mr. Vivek M. Sharma, for the Respondent.

                                                       CORAM:      N. J. JAMADAR, J.
                                 JUDGMENT RESERVED ON :            16th OCTOBER 2024.
                          JUDGMENT PRONOUNCED ON :                 9th JUNE 2025.


                                                            1/64



                        ::: Uploaded on - 09/06/2025                   ::: Downloaded on - 09/06/2025 22:40:32 :::
                                                               -IAL-3847-2024-.DOC

JUDGMENT:

1. This is an Application for grant of interim relief in the Suit

instituted for decree on a foreign award dated 7 th September 2018

passed by the Aribtral Tribunal in Arbitration Case No. 36/P/95/26

under the Rules of Arbitration Center of Iran Chamber (“ACIC”) in Iran,

in favour of the Plaintiff and against the Defendant.

2. The background facts can be summarised as under:

2.1 The Plaintiff is a foreign company incorporated under the

laws of Islamic Republic of Iran. The Plaintiff produces, and deals

in, petrochemical products such as methanol, naphtha, propane

and butane.

2.2 The Defendant is a company incorporated under the

Companies Act 1956. The Defendant is engaged in international

trade and distribution of chemicals and petrochemical products.

2.3 The Plaintiff and Defendant had been engaged in

commercial transactions since the year 2007. The Plaintiff had

been supplying methanol and naphtha to the Defendant as per

mutually agreed terms and conditions. The Defendant through

Mr Abolfazl Maleki, its authorized representative in Iran, used to

place purchase orders upon the Plaintiff for supply of methanol

and naphtha. Thereupon, the Plaintiff issued proforma invoice

along with the terms and conditions of the sale and delivery. The

2/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

Defendant, through its representative in Iran, conveyed its

acceptance of such proforma invoice. Thereafter, the cargo was

shipped as per the instructions of the Defendant. The payment

was to be made within 60 days of the delivery of cargo. The

Defendant had been paying for the goods sold and delivered

through its wholly owned subsidiary Hazel Middle East FZE till,

the year 2014.

2.4 The Plaintiff affirms from 2014 onwards, the Defendant

used Interglobe Trading FZE (“IGT”) and Venture Crosstrade FZE

(“Venture Crosstrade”) for making payments on the Defendant’s

behalf to the Plaintiff’s authorized broker in United Arab Emirates

(“UAE”), Khat Al Abyad, for the cargo delivered by the Plaintiff.

During the period 2015-2016, the Plaintiff claims, 17 cargos were

shipped for the Defendant. As per the business practice, adverted

to the above, the proforma invoices raised by the Plaintiff were

accepted by the Defendant as “buyer” by appending its seal and

signature thereto. Bills of lading were also issued in favour of the

Defendant as consignee.

2.5 The instant Suit pertains to the eight transactions effected

between the August 2015 to January 2016. The Plaintiff claimed,

the Defendant made only part payment with respect to the first

cargo, leaving the balance of amount of AED 80,289,741.53 as

3/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

due and payable in respect of the supplies made by the Plaintiff to

the Defendants under the aforesaid contract. 36 cheques for an

aggregate amount of AED 47,366,126.12 issued by IGT and

Venture Crosstrade, the entities of the Defendant, for and on

behalf of the Defendant, towards the price of the cargo were

dishonored on presentment. A security cheque drawn in the sum

of AED 38,000,000 was also dishonored on presentment.

2.6 The Plaintiff pursued the matter with the Defendant. The

later categorically admitted its default in making the payment. It

was, however, claimed that the cheques could not be cleared on

account of “compliance issue”. On 3 rd January 2016, the

Defendant sought revised proforma invoice in the name of IGT

and Venture Crosstrade. The Plaintiff reluctantly complied with

the said demand and issued revised proforma invoices.

2.7 The Defendant kept on buying time, on one or the other

pretext. Eventually, the Defendant falsely claimed that the

payment was to be made by IGT & Venture Crosstrade; being the

principal of the Defendant.

2.8 As the Defendant continued to make defaults, despite

assurances, the Plaintiff was constrained to invoke Arbitration as

per the Clause (32) of the terms and conditions of the contract. In

accordance with the Rules of ACIC, the Arbitral Tribunal came to

4/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

be constituted. Eventually, the Arbitral Tribunal passed an Award

on 7th September 2018. The Tribunal ordered the Defendant to

pay AED 82,709,509.34 towards the price of the cargo and late

payment charges plus costs of EUR 207,158.82. The Defendant

was also directed to pay the sum of AED 1,100 as compensation

for late payment for each day from the date of the award till

payment of the principal sum of AED 80,299,741.53.

2.9 The Defendant challenged Arbitral Award before the 105 th

Branch of Public Civil Court of Tehran Province and sought its

annulment. The challenge was dismissed by a Judgment dated

15th July 2019. An Appeal was preferred thereagainst before the

33rd Branch of Tehran Province. The matter was remitted to the

Court of first instance. As the Defendant-Appellant failed to

remedy the defects in the Petition, the Court of first instance

again dismissed the Appeal by its judgment dated 13th January

2021.

2.10 The Plaintiff asserts, as the Defendant failed to prefer an

Appeal against the Judgment dated 13 th January 2021, the said

judgment attained finality on 4 th February 2021, as certified by

the ‘Certificate of Finality’ dated 10th January 2024.

2.11 Since Iran is a non-reciprocating foreign territory for the

purpose of enforcement of Award passed in Iran, in India, the

5/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

Plaintiff is constrained to institute the Suit based on the foreign

award for the recovery of the sums, as awarded under the said

Award, as it furnishes a fresh cause of action. All the prerequisites

for a decree on foreign award are fulfilled.

INTERIM APPLICATION:

3. By this Interim Application, the Plaintiff seeks a direction to

the Defendant to secure the amount as awarded under the said foreign

award dated 7th September 2018 by depositing the said amount in this

Court or furnishing an unconditional bank guarantee in the said sum. In

the alternative, the Plaintiff seeks disclosure of assets of the Defendant

and injunction to restrain the Defendant from creating any third party

interest in whatsoever manner, in the movable and immovable property

of the Defendant or otherwise selling, diluting or dealing with the

shares as disclosed by the Defendant in the consolidated financial

statement of Defendant, filed with the Registrar of Companies, during

the pendency of the Suit.

4. The aforesaid reliefs are premised on the fact that the

Plaintiff learnt, in the last week of December 2023 that, a proceeding

being CSA No. C.A. (CAA) 66/MB/2022, has been initiated by the

Defendant along with Shimer Trade Impex Pvt Ltd, another company

before the National Company Law Tribunal (NCLT) Mumbai, Bench-I,

under Section 232 of the Companies Act 2013. The Defendant intends

6/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

to thereby transfer/demerge its business into Shimer Trade Impex Pvt

Ltd. Certain orders have been passed in the said proceeding. The name

of the Plaintiff has not been included in the list of secured and

unsecured creditors furnished by the Defendant. Thus, the Plaintiff

asserts, the said proceeding has been initiated behind the back of the

Plaintiff with an ulterior motive to deprive the Plaintiff of its legally

recoverable dues. The scheme submitted before the NCLT reveals that

the Defendant intends to remove or dispose all its properties with a

view to defraud its creditors including the Plaintiff. It is averred that the

Defendant has defrauded other creditors, like the Plaintiff. Hence, the

Suit seeking urgent interim reliefs without resorting to the pre-

institution mediation under Section 12A of the Commercial Courts Act

2015.

5. Initially a limited Affidavit in Reply was filed on behalf of

the Defendant in opposition to the prayer for ad-interim reliefs. By an

order dated 22nd March 2024, this Court declined to grant any ad-

interim relief and granted liberty to the Defendant to file an Additional

Affidavit in Reply. Thereupon, on 19 th April 2024, an Additional

Affidavit in Reply came to be filed.

RESISTANCE BY THE DEFENDANT:

6. The substance of the resistance put forth by the Defendant

is that the Suit, in the present form, is not at all tenable. Neither a Suit

7/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

can be filed on the strength of the alleged foreign award. Nor the said

foreign award gives a fresh cause of action in favour of the Plaintiff.

Iran is a non-reciprocating country. The foreign award relied upon by

the Plaintiff is not a foreign judgment under Section 2(6) of the Code of

Civil Procedure 1908 (“the Code”). Thus, the provisions of Sections 13

and 14 of the Code are not attracted. The foreign award having been

passed by an Arbitral Tribunal of a non-reciprocating country, it is

incapable of being recognized much less enforced under the provisions

of part II of the Arbitration and Conciliation Act 1996 (“The Act of

1996″). The Plaintiff cannot be permitted to seek enforcement of a

foreign award, indirectly; which the Plaintiff is not entitled to enforce

under the provisions of the Act of 1996. Thus, the suit is misconceived

and untenable in law.

7. Secondly, the Suit is ex-facie barred by the law of

limitation. Though in the Plaint an alternative prayer of a decree on

original cause of action has been made, yet, the Suit primarily rests on

the foreign award dated 7th September 2018. The Suit based on the

original cause of action to recover the price of the goods sold and

delivered in the year 2015-2016 is clearly barred by law of limitation as

the period expired by the year 2018-2019. Even the Suit based on the

alleged foreign award dated 7th September 2018 is also barred by

limitation as the alleged foreign award attained finality on its

8/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

notification under the Rules of ACIC and the award-debtor became

forthwith liable to pay the amount under the said award. Since the suit

has been instituted on 13th January 2024, it is ex-facie barred by

limitation.

8. Thirdly, the Defendant contends, there was no privity of

contract between the Plaintiff and the Defendant. In view of the

sanctions imposed on Iran by USA in the year 2011, the Defendant

contends, the Plaintiff entered into circuitous transactions. The goods

were supplied by the Plaintiff to IGT and Venture Crosstrade, invoices

were raised on those two entities and even those two entities had

drawn cheques towards the price of the goods allegedly sold and

delivered. Upon dishonor of the cheques, the Plaintiff initiated criminal

proceedings against those two entities in the Court at Dubai. Thus, the

Defendant, who operated as an agent of disclosed principal, cannot be

proceeded against as there is no cause of action qua the Defendant. A

reference is made to the previous transactions between the Plaintiff, on

the one part, and IGT and Venture Crosstrade, on the other part, to

buttress the defence that the Plaintiff was fully cognizant of the legal

character of IGT and Venture Crosstrade and has now falsely claimed

that IGT and Venture Crosstrade were introduced by the Defendant only

to facilitate payment of the goods sold and delivered.

9/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

9. The Defendant contends that the foreign award is

otherwise legally infirm and unsustainable. The proceeding before the

Arbitral Tribunal were in complete breach of the fundamental principles

of judicial process and natural justice. The alleged foreign award thus

does not command any binding force. The award has been passed in

utter disregard to the Indian laws and even the principles of natural

justice. Thus, the Suit itself does not deserve to be countenanced.

10. Fourthly, the Suit is barred by the provisions of Section 12A

of the Commercial Courts Act 2015, for not resorting to the mandatory

pre-institution mediation. On the own showing of the Plaintiff, the Suit

did not contemplate any urgent ad-interim or interim relief. The

Plaintiff has made an undisguised attempt to proclaim a false case of

urgency. A facade of urgent interim relief is created with a view to

bypass the mandatory pre-institution mediation under Section 12A of

the Commercial Courts Act 2015. As no case for urgent interim relief

was made out, the Plaint itself is liable to be rejected in view of the bar

contained in Section 12A of the Commercial Courts Act 2015.

11. In any event, the Defendant contends, the prayers in the

instant Application do not deserve any countenance. Since the very

foreign award, which is the basis of the claim of the Plaintiff, is

incapable of being recognized and enforced, the interim relief seeking

direction to deposit or furnish bank guarantee for an unadjudicated sum

10/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

of money and/or unliquidated damages is clearly unsustainable. No

case for grant of reliefs which partake the character of attachment

before judgment is made out.

12. An Affidavit in Rejonder came to be filed controverting the

contentions in the Affidavit in Reply.

SUBMISSIONS:

13. In the wake of the aforesaid pleadings and facts, I have

heard Mr. Ratan Kumar Singh, the learned Senior Advocate for the

Plaintiff-Applicant, and Mr. Prateek Seksaria, the learned Senior

Advocate for the Defendant-Respondent, at some length. The learned

Counsel took the Court through the pleadings and documents on

record, the statutory provisions which, according to them, govern the

arbitral proceeding before the Arbitral Tribunal and the proceedings

thereagainst before the jurisdictional Courts in Iran.

14. Mr. Singh, the learned Senior Advocate for the Plaintiff-

Applicant, submitted that the Defendant having dishonestly defaulted in

payment of the price of the goods sold and delivered, has resorted to all

sorts of defences to further delay and thereby defeat the legitimate

claim of the Plaintiff. Mr. Singh would urge that, there is no denial of

the fact that the Defendant did participate in the arbitral proceedings

before the arbitral tribunal. Neither the factum of the award by the

Arbitral Tribunal based at Iran is in contest. Nor there is much

11/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

controversy over the orders passed by the Courts in Iran in accordance

with the governing Rules. In the backdrop of these rather

uncontroverted facts, the tenability of the Suit, as such, before this

Court, based on the foreign award, can never be contested, urged Mr.

Singh.

15. Mr. Singh would urge that the Suit of the present nature is

maintainable before this Court as the foreign award is enforceable in

India in the same manner and on the same ground as in England under

the common law, i.e., on the grounds of justice, equity and good

conscience. Mr. Singh placed a very strong reliance on the judgment of

the Supreme Court in the case of Badat and Co Bombay Vs East India

Trading Co1 wherein the Supreme Court has enunciated the

circumstances in which a Suit can be filed on the basis of an award

passed by an Arbitral Tribunal the seat of which is in a non-

reciprocating country.

16. Mr. Singh made a strenuous effort to draw home the point

that the law laid down by the Supreme Court in the case of Badat and

Co (Supra) has remained unaffected even after the incorporation of the

Act of 1996. Amplifying the submission, Mr. Singh would contend that

the Part II of the Act of 1996, deals with enforcement of, “certain

foreign awards”. The Act of 1996 thus cannot be said to cover the

foreign awards which have been passed by the Arbitral Tribunal based

1 1963 SCC OnLine SC 9.

12/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

in a non-reciprocating country. Reliance was also placed by Mr. Singh on

the judgment of the Supreme Court in the case of Harendra H. Mehta &

Ors Vs Mukesh H Mehta & Ors2 wherein, according to Mr. Singh, the

law enunciated by the Supreme Court in the case of Badat & Co (Supra)

was reiterated. A judgment of the Delhi High court in the case of Marina

World Shipping Corporation Limited Vs Jindal Exports Private Limited 3

was also pressed into service to buttress the submission that the

enunciation of law in the case of Badat & Co (Supra) still holds good.

17. Therefore, according to Mr. Singh, the principal defence

that the suit, on the basis of a foreign award, is not tenable, is devoid of

any substance. Once this inference is drawn, according to Mr. Singh,

the enquiry in the Suit would be restricted to the question as to whether

the prerequisites for enforcing the foreign award, as enunciated by the

Supreme Court in the case of Badat & Co (Supra), have been fulfilled.

This Court would then be not required to examine the correctness of the

determination by the Arbitral Tribunal, submitted Mr. Singh.

18. Mr. Singh would urge, the defence of bar of limitation is

equally infirm. Taking the Court through the timeline of the proceedings

before the Arbitral Tribunal and the Courts in Iran, Mr. Singh submitted

that the judgment dismissing the Appeal was passed by the Civil Court

at Iran on 13th January 2021, while granting liberty to the Defendant to

2 (1999) 5 SCC 108.

3 2012 SCC OnLine Del 1229.

13/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

prefer an Appeal within a period of 20 days. Consequently, the Award

became final on 4th February 2021. Institution of the Suit on 12th

January 2024 was clearly within the period of limitation.

19. In any event, according to Mr. Singh, the order passed by

the Supreme Court dated 10th January 2022 in Suo Moto Writ Petition

No. 3 of 2020 extending the period between 15 th March 2020 to 28th

February 2022, enures to the benefit of the Plaintiff. If the period of

limitation is reckoned from 1st March 2022, as ordered by the Supreme

Court, the Suit is well within the period of limitation. To this end

reliance was placed on the Supreme Court’s order dated 10 th January

2022 and a decision of a learned Single Judge of this Court in the case

of Novacare Drug Specialities Pvt Ltd Vs State of Goa and Others.4

20. Adverting to the proceedings before the NCLT, for approval

of the scheme under the provisions of Section 232 of the Companies Act

2013 and the orders passed therein, Mr. Singh submitted that the Plaint

does contemplate an urgent interim relief. The de-merger of the

Defendant-company, without showing the Plaintiff as one of its

creditors, despite the Award in question having been passed by the

competent Arbitral Tribunal, would jeopardise the prospect of recovery

of the amount under the said Award, irretrievably. Thus, the challenge

to the tenability of the Suit for not resorting to the mandatory pre-

4 2023 SCC OnLine Bom 1557.

14/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

institution mediation under Section 12A of the Commercial Courts Act

2015, does not merit countenance.

21. Mr. Singh would further urge that the endeavour made on

behalf of the Defendant to question the jurisdiction of the Court, in the

light of the pendency of the proceeding before the NCLT, need not

detain the Court as the reliefs which are sought in the instant Suit and

the Interim Application can never be granted by the NCLT.

Consequently, the bar contained in Section 430 of the Companies Act

2013 is not at all attracted.

22. On the merits of the matter, Mr. Singh would urge, there is

overwhelming material on record which shows that the Defendant and

its authorized representative have categorically acknowledged the

liability. Belatedly a defence was raised that the Defendant was a broker

and the transactions were between the Plaintiff’ and IGT and Venture

Crosstrade. The said defence is ex-facie dishonest and not borne out by

the record. In fact, in a Suit of the present nature, this Court is not

required to delve into the merits of the Arbitral Award. It was reiterated

that the enquiry would be restricted to the satisfaction about the five

principles enunciated in the case of Badat & Co (Supra). Even

otherwise, the correspondence exchanged between the parties squarely

establishes that the Plaintiff had supplied the goods, and after accepting

the proforma invoice and delivery of the goods, the Defendant

15/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

committed default in payment of price thereof. In these circumstances,

the Plaintiff who has a huge claim against the Defendant cannot be left

in the lurch and interest of the Plaintiff deserves to be appropriately

secured, submitted Mr. Singh.

23. Per contra, Mr. Seksaria, the learned Senior Advocate for

the Defendant, mounted a four-pronged attack to the tenability of the

Suit and the reliefs claimed in the instant application. Firstly, it was

submitted that the Suit based on the foreign award is not at all

maintainable. It was urged that the judgment in the case of Badat & Co

(Supra), which constitutes the sheet-anchor of the Plaintiff’s case, has

no application at all to the facts of the case at hand. With the

enactment of the Act of 1996, which consolidated and amended the law

relating to Arbitration in India, including enforcement of Foreign

Arbitral Awards, the remedies must be worked out under the provisions

of the said Act 1996. Since Part II of the said Act 1996 mandates

recognition and enforcement of the Arbitral Award passed by the

Tribunal in a reciprocating territory, the foreign award passed by an

Arbitral Tribunal in a non-reciprocating country, can never be enforced,

lest the foreign award of a non-reciprocating country would stand on a

better footing than that of a reciprocating country which has to pass the

rigours under Part II of the Act of 1996.

16/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

24. Mr. Seksaria would submit that, the Act of 1996 does not

permit recognition and enforcement of a foreign award from a non-

reciprocating country and, thereby, contains a negative import. A very

strong reliance was placed by Mr. Seksaria on the Seven Judge

Constitution Bench judgment in Re: Interplay Between Arbitration

Agreement under the Arbitration And Conciliation Act 1996 and The

Indian Stamp Act 18995 (N.N. Global), to bolster up the aforesaid

submission that there is a negative import in the matter of recognition

and enforcement of a foreign award of non-reciprocating country.

Reliance was also placed on the judgment of the Supreme Court in the

case of Sundaram Finance Ltd Vs NEPC India Ltd 6 as regards the

approach in the matter of interpretation of the provisions contained in

the Act of 1996.

25. Mr. Seksaria would urge that, even otherwise, the

prerequisites for the enforcement of a foreign award in a non-

reciprocating country, as enunciated by the Supreme Court in the case

of Badat & Co (Supra) have not been fulfilled in the facts of the case at

hand. The foreign award, according to Mr. Seksaria, cannot be said to

have attained finality under the laws of Iran. It was controverted that

the judgment dated 15th July 2019 passed by the Tehran Court was

5 2023 INSC 1066
6 1999 (2) SCC 479.

17/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

under the International Commercial Arbitration Act of Iran 1997 (“Iran

Act of 1997″).

26. The bar of limitation was premised in two parts. First, the

Suit based on original cause of action was ex-facie barred by the law of

limitation as the last of the alleged proforma invoices was raised on 1 st

April 2016. Second, as regards the Suit based on the foreign award, Mr.

Seksaria would urge the right to sue accrued to the Plaintiff on the date

of the said Award, i.e., 7th September 2018. The further proceedings

before the Civil Courts at Iran, according to Mr. Seksaria, did not arrest

the period of limitation which began to run from the date of the passing

of the said Award. For this purpose, Mr Seksaria, placed reliance on the

judgment of the Supreme Court in the case of Hindustan Construction

Company Limited And Anr Vs Union of India And Ors.7

27. As a second limb of the submission, Mr. Seksaria would

urge even if the period of limitation is computed from the date of the

dismissal of the Appeal, i.e., 15th July 2019, the Suit instituted in the

month of January 2024 would be ex-facie barred by the law of

limitation. It was urged that under the provisions of Article 137 of the

Limitation Act 1963 the period of limitation for enforcement of a

foreign award is three years from the date of the Award. To draw

support to this submission, Mr. Seksaria banked upon the judgment of

7 (2020) 17 SCC 324.

18/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

the Supreme Court in the case of Government of India Vs Vedanta

Limited (Formerly Cairn India Limited) And Anr.8

28. Thirdly, Mr. Seksaria would urge, with a degree of

vehemence, that the institution of the Suit was clearly in teeth of the

provisions contained in Section 12A of the Commercial Courts Act 2015.

It was submitted that the very fact that the foreign award was passed on

7th September 2018 and the Suit came to be instituted in the month of

January 2024 rules out any element of urgency in the matter. On the

own showing of the Plaintiff, the said foreign award attained finality on

13th January 2021. Yet, the Plaintiff allowed the prescribed period of

limitation to expire and then instituted the Suit.

29. The endeavour of the Plaintiff to press into service the

pendency of the proceeding under Section 232 of the Companies Act

2013, before the NCLT and the orders passed therein, was stated to be

an instance of clever drafting and subterfuge to shore up a false case of

urgency with a view to avoid the mandatory pre-institution mediation.

The entire endeavour of the Plaintiff was to circumvent the peremptory

requirement of Section 12A of the Commercial Courts Act 2015. It was

incumbent upon the Plaintiff to demonstrate promptitude of such

nature that exhausting the remedy of mandatory pre-institution

mediation, without any Court intervention, could lead to into an

irreversible situation as enunciated by Madras High Court in the case of

8 (2020) 10 SCC 1.

19/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

K Varathan Vs Prakash Babu Nakundhi Reddy, 9 submitted Mr. Seksaria.

Consequently, in view of the decision of the Supreme Court in the case

of Patil Automation Private Limited And Ors Vs Rakheja Engineers

Private Limited,10 the Plaint is liable to be rejected by invoking the

provisions contained in Order 7 Rule 11 of the Code.

30. Fourthly, Mr. Seksaria made an endeavour to draw home

the point that the material on record would unmistakably indicate that

the transactions were between IGT and Venture Crosstrade and the role

of the Defendant was that of a broker. Attention of the Court was

invited to the documents which purportedly indicate that the Plaintiff

had raised invoices upon IGT and Venture Crosstrade even in respect of

transactions which do not form part of the subject mater of the Suit and

the Plaintiff had also received payment from IGT and Venture

Crosstrade. The acceptance of the cheques from the above-named

entities and the initiation of action upon dishonor of the cheques were

also pressed into service, to substantiate the aforesaid defence.

31. In substance, Mr. Seksaria would urge that no monies are

payable by the Defendant as claimed by the Plaintiff and, in these

circumstances, on the basis of a legally infirm foreign award passed by

the Aribitral Tribunal in a non-reciprocating country, the reliefs in the

nature of attachment before the judgment cannot be granted. Even

9 C.S. (Comm. Div.) No. 202 of 2022, decided on 13th October 2022.
10 (2022) 10 SCC 1.

20/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

otherwise this Court’s jurisdiction to grant the prayers in the Interim

Application is expressly barred by the provisions contained in Section

430 of the Companies Act 2013, submitted Mr. Seksaria.

CONSIDERATION:

32. To begin with it is necessary to note that the parties are in

unison on the point that the subject Award has been passed by an

Arbitral Tribunal, the seat of which was in a non-reciprocating country.

The parties were, however, at issue over the tenability of the Suit on the

basis of the foreign award passed by a Tribunal situated in a non-

reciprocating country. As this issue goes to the root of the matter, I deem

it appropriate to deal with the same at the threshold.

TENABILITY OF SUIT ON THE BASIS OF AWARD PASSED IN A NON-

RECIPROCATING COUNTRY:

33. Evidently, the edifice of the Suit is sought to be built on the

judgment of the Supreme Court in the case of Badat & Co (Supra).

Since considerable submissions were canvassed on the import of the

judgment of the Supreme Court in the case of Badat & Co (Supra) and

its applicability to the facts of the case, especially in the light of the

enactment of the Act of 1996, it may be apposite to note the factual

backdrop in which the said decision was rendered by the Supreme

Court.

21/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

34. In the case of Badat & Co (Supra) the dispute arose

between Badat and Company, an Indian Firm, and East India Trading

Company, a private limited company incorporated under the laws of the

State of New York in USA, in relation to supply of turmeric by the

Indian Firm to the said foreign company. The parties had agreed to do

business on the terms of the American Spice Trade Association, which

warranted that all questions and controversies and all claims arising

under the contract should be submitted and settled by Arbitration.

35. In the wake of the dispute, the American company invoked

the Arbitration and obtained two ex-parte Awards, followed by the

confirmation judgments passed by the Courts in America. Thereafter,

the American company instituted the Suit based on the Foreign

judgments and, in the alternative, on the two Awards given by the

Tribunal based in New York, before this Court.

36. The tenability of the Suit was questioned by the Indian

Firm, inter alia, on the ground that the Indian Firm was not residing

within the limits of the original jurisdiction of the Bombay High Court

or carrying business therein and thus the High Court had no jurisdiction

to entertain the Suit.

37. In the aforesaid context, the Supreme Court, enunciated

that the Plaintiffs were not entitled to enforce the judgment of the

Supreme Court of the State of New York against the Defendant by a Suit

22/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

instituted on the Original Side of the High Court. The provisions of the

Arbitration (Protocol and Convention) Act 1937 were not attracted as

the United State was not a party to the convention.

38. The Supreme Court, however, went on to examine the

enforceability of the foreign award in India, under common law on the

grounds of justice, equity and good conscience.

39. The Supreme Court, thus, observed, inter alia, as under:

“31. Thus commercial arbitration awards, though
based on a contract to arbitrate are not contracts and
although they are decisions they are not judgments. Even
though that is so, it has been held in several cases in
England that even where an award has not been reduced
to a judgment in a foreign country it can be enforced in
England provided, of course, the award answers mutatis
mutandis the tests for determining the enforceability of
foreign judgments. Thus, the foreign arbitration tribunal
must have acted upon a valid submission within the
limits of jurisdiction conferred by the submission, and the
award must be valid and final.

………

33. It will thus be seen that there is a conflict of
opinion on a number of points concerning the
enforcement of foreign awards or judgments, based upon
foreign awards. However, certain propositions appear to
be clear. One is that where the award is followed by a
judgment in a proceeding which is not merely formal but
which permits of objections being taken to the validity of
the award by the party against whom judgment is sought,

23/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

the judgment will be enforceable in England. Even in that
case
, however, the plaintiff will have the right to sue on
the original cause of action. The second principle is that
even a foreign award will be enforced in England
provided it satisfies mutatis mutandis the tests applicable
for the enforcement of foreign judgments on the ground
that it creates a contractual obligation arising out of
submission to arbitration. On two matters connected with
this there is difference of opinion. One is whether an
award which is followed by a judgment can be enforced
as an award in England or whether the judgment alone
can be enforced. The other is whether an award which it
not enforceable in the country in which it was made
without obtaining an enforcement order or a judgment
can be enforced in England or whether in such a case the
only remedy is to sue on the original cause of action. The
third principle is that a foreign judgment or a foreign
award may be sued upon in England as giving good cause
of action provided certain conditions arc fulfilled one of
which is that it has become final.

… … …

39. Just as a foreign judgment affords a fresh cause
of action upon which a suit can be brought in an English
court, so is the case with regard to a foreign award. Thus,
in Bremer Oeltransport GMBH v. Drewey(2) it was held
that a foreign award furnishes a new cause of action
based on the agreements between the parties to perform
the award. This view has been accepted in Halsbury’s
Laws of England Vol. II, p. 45.

24/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

40. Now, when a plaintiff sues upon a foreign
award what he in fact does is to ask the court to pass a
judgment in his favour for the amount stated in the
award only after proving five facts :

(1) that there was a contract between the parties where
under disputes between them could be referred to
arbitration to a tribunal in a foreign country,;
(2) that the award is in accordance with the terms of the
agreements;

(3) that the award is valid according to the law
governing arbitration proceedings obtaining in the
country where the award was made ;

(4) that it was final according to the law of. that country;
and
(5) that it was a subsisting award at the date of suit.

41. A view has been expressed in some English
cases that an award must also be enforceable in the
country in which is was made before a suit can be
brought, in England on its basis. But upon the view we
are taking it is not necessary to decide this point. Now,
when a suit is brought by a plaintiff on the basis of an
award it is not necessary for him to prove that the
amount claimed was actually payable to him in respect of
the dispute nor it is open to the defendants to challenge
the validity of such an award on grounds like those which
are available in India under Section 30 of the Arbitration
Act. A very limited challenge to the claim based on the
award is permissible to the defendants and that is one of
the reasons why it is important to ascertain whether the
award has in fact attained finality in the country in which
it was made. We will assume that the plaintiffs have

25/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

satisfactorily established the first three of the five
conditions which we have set out above. The question
then is whether the fourth and the fifth conditions have
been satisfied.

………

46. No doubt, an award can furnish a fresh cause
of action. But the award must be final. If the law of the
country in which it was made gives finality to judgment
based upon an award and not to the award itself, the
award can furnish no cause of action for a suit in India.
In these circumstances we hold that though the High
Court of Bombay has jurisdiction to enforce a final award
made in a foreign country in pursuance of a submission
made within the limits of its original jurisdiction, the
awards in question being not final, cannot furnish a valid
cause of action for the suit. Upon this view we allow the
appeal and dismiss the suit with costs throughout The
normal rule as to costs must apply because the choice of
forum made by the plaintiffs was deliberate and with the
knowledge that they were taking a risk in not seeking out
the defendants at the place where they reside or carry on
business.”

40. The Supreme Court has thus held that apart from the

provisions of Arbitration (Protocol and Convention) Act 1937, (which

was then in force) foreign award and foreign judgment based upon

Awards, were enforceable in India on the same grounds and in the same

circumstances on which they were enforceable in England under the

26/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

common law on the grounds of justice, equity and good conscience, if

the necessary conditions were satisfied, namely, the contract between

the parties to refer the dispute to Arbitration to a Tribunal in a foreign

country, the Award is in accordance with the terms of the Agreement,

the Award is valid according to the governing law of the country where

the Award was made, the Award was final according to the law of that

country and the Award subsisted on the date of the institution of the

Suit.

41. The judgment of the Supreme Court in the case of Badat &

Co (Supra) with regard to the enforcement of the foreign award is

based on the applicability of the common law and is de hors the

statutory prescription in the matter of enforcement of foreign award.

The pivotal question which crops up for consideration is whether the

aforesaid law exposited by the Supreme Court in the case of Badat & Co

(Supra) still holds the field, especially after the incorporation of the Act

of 1996?

42. Mr. Singh would urge that the precedential value and

binding efficacy of the judgment in the case of Badat & Co (Supra) is

not diluted by the subsequent legislation. It was urged that the Supreme

Court has in fact followed the judgment in the case of Badat & Co

(Supra) in the case of Harendra H. Mehta (Supra). In Marina World

27/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

Shipping Corporation Limited (Supra) the Delhi High Court has also

followed the judgment in the case of Badat & Co (Supra).

43. A perusal of the judgment in the case of Harendra H. Mehta

(Supra) would indicate that the Supreme Court had, in fact, held that

the judgment in the case of Badat & Co (Supra) was not applicable to

the facts of the case in Harendra H. Mehta (Supra) which was governed

by the provisions contained in Foreign Awards (Regulation and

Enforcement) Act 1961.

44. In the case of Marina World Shipping Corporation Limited

(Supra), the Delhi High Court considered the question whether

execution petition was maintainable in view of the Explanation to

Section 44A of the Code?. Holding that Part II of the Act of 1996 is a

complete Code in itself for the enforcement of a foreign award other

than a situation where a Suit may have been filed for enforcement of

such an Award. where there may be a non-reciprocating country as was

the case in the case of Harendra H. Mehta (Supra), it was observed that

the legal position was not different in Badat & Co (Supra). The Delhi

High Court has in terms referred to the remedy of institution of the Suit

for enforcement of a foreign award passed by the Tribunal in a non-

reciprocating country.

45. In contrast to this, Mr Seksaria would urge that the

enactment of the Act of 1996 which is a consolidating and amending

28/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

law with regard to the domestic and commercial arbitration as well as

enforcement of the foreign award, there is no room for enforcement of a

foreign award passed by the Tribunal in a non-reciprocating country by

institution of a suit. It was urged that any other view would put such

Award in a non-reciprocating country on a better footing than the

Award passed in a reciprocating country which has to pass through the

rigour of recognition and enforcement under Part II of the Act 1996.

46. It was forcefully urged that the Act of 1996 is a self-

contained Code and there is a negative import against the enforcement

of the foreign award which does not fall within the purview of the Act

of 1996. Strong reliance was placed on the judgment of the Constitution

Bench in the case of Re: Interplay Between Arbitration Agreement

(Supra).

47. Before the enactment of the Act of 1996, the law of

Arbitration was contained in the Arbitration Act 1940, the Arbitration

(Protocol and Convention) Act 1937 and Foreign Awards (Recognition

and Enforcement) Act 1961. The United Nations Commission on

International Trade Law (UNCITRAL) adopted the model law in 1985 to

foster the development of a unified legal framework for the fair and

efficient settlement of disputes arising in international commercial

arbitration. All the member States were recommended to give due

29/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

consideration to the model law. The statement of objects and reasons of

the Act of 1996, reads as under:

“2. The United Nations Commission on International
Trade Law (UNCITRAL), adopted in 1985 the Model Law
on International Commercial Arbitration. The General
Assembly of the United Nations has recommeded that all
countries give due consideration to the said Model Law, In
view of the desirability of uniformity of the law of arbitral
procedures and the specific needs of international
commercial arbitration practice. The UNCITRAL also
adopted in 1980 a set of Conciliation Rules. The General
Assembly of the United Nations has recommended the use
of these Rules in cases where the disputes arise in the
context of international commercial relations and the
parties seek amicable settlement of their disputes by
recourse to conciliation. An important feature of the said
UNCITRAL Model Lw and Rules is that they have
harmonised concepts on arbitration and conciliation of
different legal systems of the world and thus contain
provisions which are designed for universal application.

3. Though the said UNCITRAL Model Law and Rules
are intended to deal with international commercial
arbitration and conciliation, they could, with appropriate
modifications, serve a sa model for legislation on domestic
arbitration and conciliation. The present Bill seeks to
consolidate and amend the law relating to domestic
arbitration, international commercial arbitration,
enforcement of foreign arbitral awards and to define the
law relating to conciliation, taking into account the said
UNCITRAL Model Law and Rules.”

30/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

48. Part II of the Act of 1996, with which we are primarily

concerned, deals with the enforcement of certain foreign awards.

Chapter I deals with New York Convention Awards and Chapter II with

Geneva Convention Awards.

49. The definition of “Foreign Awards” in Sections 44 and 53 of

the Act of 1996 designedly restricts the operation of the Chapter I and II

to the Awards in one of such territories as the Central Government,

being satisfied that reciprocal provisions have been made, may, by

notification, declare to be territories to which the respective

Convention applies. In other words, the foreign award referred to in

Section 44 and 53 are the Awards made in pursuance of an agreement

to which the New York Convention or Geneva Convention applies. The

title of Chapter II thus gives an indication that it governs the

enforcement of certain foreign awards, implying thereby that the said

Chapter does not apply to the foreign awards not covered by the

definition of “foreign awards” under Sections 44 and 53 of the said Act.

The Act of 1996, thus, does not make any provision for Awards passed

in Arbitration proceedings which take place in a non-convention

country.

50. It is in the aforesaid context, the submission of Mr. Seksaria

that there is a negative import requires appreciation. There can be no

duality of opinion that the Act of 1996 is a self-contained Code. In the
31/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

case of Furest Day Lawson Ltd Vs Jindal Exports Ltd. 11 the Supreme

Court emphasised that the Act of 1996 is a self-contained Code and

exhaustive and carries with it a negative import. The observations in

paragraph 89, on which a very strong reliance was placed by Mr.

Seksaria, read as under:

“89. It is thus, to be seem that Arbitration Act, 1940,
from its inception and right through to 2004 (in P.S.
Sathappan [(2004) 11 SCC 672)] was held to be a self-
contained code. Now, if the Arbitration Act, 1940 was held
to be a self-contained code, on matters pertaining to
arbitration, the Arbitration and Conciliation Act, 1996,
which consolidates, amends and designs the law relating
to arbitration to bring it, as much as possible, in harmony
with the UNCITRAL Model must be held only to be more
so. Once it is held that the Arbitration Act is a self-
contained code and exhaustive, then it must also be held,
using the lucid expression of Tulzapurkar, J, that it carries
with it ” a negative import that only such acts as are
mentioned in the Act are permissible to be done and acts
or things not mentioned therein are not permissible to be
done.” In other words, a letters patent appeal would be
excluded by the application of one of the general
principles that where the special Act sets out a self-
contained code the applicability of the general law
procedure would be impliedly excluded”

(emphasis supplied)

11 (2011) 8 SCC 333.

32/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

51. After referring to the aforesaid statement of law, the Seven

Judge Bench, enunciated in the case of Re: Interplay Between

Arbitration Agreement (Supra), that it is not permissible to do what is

not mentioned under the Act of 1996. Therefore, provisions of other

statutes cannot interfere with the working of the Arbitration Act, unless

specified otherwise.

52. The observations of the Constitution Bench in paragraph

85 read as under:

“85. The Arbitration Act is a self-contained code iner
alia with respect to matters dealing with appointment of
arbitrators, commencement of arbitration, making of an
award and challenges to the arbitral award, as well as
execution of such awards. When a self-contained code sets
out a procedure, the applicability of a general legal
procedure would be impliedly excluded. Being a self-
contained and exhaustive code on arbitration law, the
Arbitration Act carries the imperative that what is
permissible under the law ought to be performed only in the
matter indicated, and not otherwise. Accordingly, matters
governed by the Arbitration Act such as the arbitration
agreement, appointment of arbitrators and competence of
the arbitral tribunal to rule on its jurisdiction have to be
assessed in the manner specified under the law. The
corollary is that it is not permissible to do what is not
mentioned under the Arbitration Act. Therefore, provisions
of other statutes cannot interfere with the working of the
Arbitration Act, unless specified otherwise.”

(emphasis supplied)

33/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

53. The Arbitration Act is indeed a self-contained Code, inter

alia, with respect to matters covered by the said Act 1996. If the Act of

1996 expressly and specifically excludes the foreign awards made in

non- convention countries, then, can the remedies which were available

in relation to the non conventional awards be said to be barred by the

provisions of the Act of 1996?.

54. I am afraid, the answer cannot be in the affirmative. There

cannot be any manner of doubt that the matters which are governed by

the provisions of the Act 1996 can only be dealt with in the manner

ordained by the said Act. However, where the Act of 1996 expressly

excludes certain categories of foreign awards, from the purview of

enforcement thereunder, the principle of negative import cannot be

applied to such a situation by necessary implication.

55. The prohibition in the matter of the enforcement of the

Awards emanating from non-reciprocating territories ought to find a

mandate in the Act of 1996. Evidently, there is no express prohibition.

In the absence of an express prohibition a matter relating to Arbitration

which is not covered by the Act of 1996 cannot be jettisoned away as

impermissible.

56. A profitable reference, in this context, can be made to a

three Judge Bench Judgment of the Supreme Court in the case of

34/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

Centrotrade Mineral & Metals Vs Hindustan Cooper Ltd, 12 where the

permissibility of two-tier Arbitration, i.e., the adjudication of an Appeal

by another Arbitrator/Tribunal, under the provisions of the Act of 1996,

arose. In the said case, reliance was placed on the aforeextracted

observations in paragraph 89 of the judgment in the Furest Day Lawson

Ltd (Supra), to urge that the Act of 1996 does not permit two tier

Arbitration and, thus, such an Arbitration system was not permissible.

The three Judge Bench observed that, it was unable to fully subscribe to

the aforeextracted broad observations that acts mentioned in the statute

are permissible but acts not mentioned therein are impermissible, and

that the position could be converse. The relevant observations in

paragraph 23 of the judgment of the Centrotrade Mineral (Supra) read

as under:

“23. In any event, we are afraid the passage referred
to by the learned counsel from Fuerst Day Lawson has
been misunderstood and is even otherwise inapposite
since we are not concerned with a statutory appeal but a
non-statutory process agreed upon by parties that has
nothing to do with court procedures. We are also unable
to fully subscribe to the broad observation that acts
mentioned in a statute are permissible but acts not
mentioned therein are impermissible. It could very well
be the converse. In any event, the observations of this
Court were in the context of a statutory appeal not
provided (or provided). In that context, it was observed

12 2017(2) SCC 228.

35/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

that if an appeal is not provided for by a statute, then the
filing of an appeal is not permissible. … … …”

(emphasis supplied)

57. A useful reference can also be made to the Constitution

Bench judgment in the case of Bharat Aluminum Company Vs Kaiser

Aluminum Technical Services Inc.13 In the said case, a submission was

sought to be canvassed that since non- convention awards would not be

governed either by Part I or Part II of the Act of 1996, it would mean

that there is no law governing such Arbitrations. Repelling the

submission, the Constitution Bench, enunciated the law as under:

“169. It was also submitted that Non-Convention
Awards would not be covered either by Part I or Part II.
This would amount to holding that the legislature has left
a lacuna in the Arbitration Act, 1996. This would mean
that there is no law in India governing such arbitrations.

170. We are of the opinion that merely because the
Arbitration Act, 1996 does not cover the non convention
awards would not create a lacuna in the Arbitration Act,
1996
. If there was no lacuna during the period in which
the same law was contained in three different
instruments, i.e. the Arbitration Act, 1996 read with
1961Act, and the Arbitration (Protocol and Convention)
Act, 1937
, it cannot be construed as a lacuna when the
same law is consolidated into one legislation, i.e. the
Arbitration Act, 1996.

13 (2012) 9 SCC 552.

36/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

171. It must further be emphasised that the definition
of “foreign awards” in Sections 44 and 53 of the
Arbitration Act, 1996 intentionally limits it to awards
made in pursuance of an agreement to which the New
York Convention, 1958 or the Geneva Protocol, 1923
applies. It is obvious, therefore, that no remedy was
provided for the enforcement of the ‘non convention
awards’ under the 1961 Act. Therefore, the non
convention award cannot be incorporated into the
Arbitration Act, 1996 by process of interpretation. The
task of removing any perceived lacuna or curing any
defect in the Arbitration Act, 1996 is with the Parliament.
The submission of the learned counsel is, therefore,
rejected. The intention of the legislature is primarily to be
discovered from the language used, which means that the
attention should be paid to what has been said and also to
what has not been said. (See: Gwalior Rayon Silk Mfg
(Wvg.) Co Ltd Vs Custodian of Vested Forests
(1990 Supp
SCC 785 : AIR 1990 SCC 1747). Here the clear intention
of the legislature is not to include the Non-convention
Awards within the Arbitration Act, 1996.”

(emphasis supplied)

58. The aforesaid observations of the Supreme Court, especially

to the effect that, if there was no lacuna during the period in which the

same law was contained in three different enactments, i.e., Arbitration

Act, 1940 read with 1961 Act and the Arbitration (Protocol and

Convention) Act 1937, it cannot be construed as a lacuna when the

same law came to be consolidated into one legislation (The Arbitration

37/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

Act 1996), indicate that despite the enactment of the Arbitration Act

1996, the legal position as regards the enforcement of non-convention

Award remains the same.

59. I, therefore, find substance in the submission of Mr. Singh

that the decision in the case of Badat & Co (Supra) in the matter of

enforcement of non convention Awards still holds the field, and the Suit

of the instant nature is tenable.

WHETHER THE CONDITIONS STIPULATED IN THE CASE OF BADAT &

CO (SUPRA) HAVE BEEN FULFILLED?:

60. Mr. Seksaria submitted that one of the essential conditions

for enforcement of the foreign award emanating from a non-

reciprocating territory has not been fulfilled as the Award in question

cannot be said to have attained finality under the laws of Iran. Laying

emphasis on the observations of the Supreme Court in paragraph 46 of

the Judgment in the case of Badat & Co (Supra), Mr. Seksaria would

urge that the instant suit must meet the same fate as the Suit in Badat &

Co (Supra), since the Award in question has not attained finality.

61. Mr. Seksaria submitted that under Article 6 of the Iran Act

1997, the judicial functions in relation to Article 33 and 35 therein were

entrusted to Tehran Public Court. Under Article 34, an Award can be

deemed to be null and void and unenforceable in the circumstances

38/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

enumerated therein. Under Article 35 of the Iran Act 1997, the Award

Holder was required to file an application to seek recognition and

enforcement of the Award. Since, the Plaintiff had not filed any

application in the Public Court of Tehran for recognition and

enforcement of the Award in question, the Award cannot be said to have

attained finality. It was further urged that had the Plaintiff filed such an

application, the Defendant would have had an opportunity to contend

that there are circumstances which render the Award null and void.

62. Mr. Seksaria would further submit that the the reliance

sought to be placed by the Plaintiff on the decision of Iranian 105 th

Branch of Public Civil Court, dated 15th July 2019, is of no assistance to

the Plaintiff as the said Court had no jurisdiction in the matter of an

international award. Thus, the judgment dated 15 th July 2019 cannot be

treated as a judgment passed under the Iran Act 1997 to urge that the

Award attained finality.

63. In any event, according to Mr. Seksaria, when this Court

has to form an opinion upon a point of foreign law, the provisions

contained in Section 45 of the Indian Evidence Act would be attracted

and, at this stage, there is no material to form an opinion as to the

effects of the laws of Iran.

64. Mr. Ratan Kumar Singh countered the submissions on

behalf of the Defendant. It was urged that the submissions on behalf of

39/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

the Defendant are premised on an incorrect reading of the decision in

the case of Badat & Co (Supra). Under Article 35 of the Iran Act 1997,

the Award Holder was not required to seek recognition before the

Award attained finality. An application was required to be made only for

the enforcement of the international award. There is a difference

between ‘finality’ and ‘enforcement’ of the Award. An Award may be

final and yet unenforceable. This distinction in the concepts of “finality”

and “enforceability” of the Award, was adverted to by the Supreme

Court in paragraph 43 of the decision in the case of Badat & Co (Supra),

urged Mr. Ratan Singh.

65. Secondly Mr. Ratan Singh would submit that in the

proceeding initiated under Article 489 of the Civil Code of Iran, which

was otherwise not applicable to international commercial arbitration

award, the Tehran Public Court considered the challenge both under

Article 489 of the Iranian Civil Procedure Code as well as Articles 33

and 34 of Iran Act 1997. Since the Award can no longer be subjected to

challenge under the mechanism provided by the Iran Act 1997, Mr.

Ratan Singh would urge, the challenge to the tenability of the Suit on

the ground that the Award has not attained finality is completely

misconceived.

66. The aspect of the finality of the Award is of critical salience

on two counts. First, finality to the foreign award under the laws of

40/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

non- convention country, where it was passed, is a pre-condition for a

Suit based on the foreign award, as enunciated in Badat & Co (Supra).

In fact, in the said case, the Supreme Court on facts held that, under the

governing provisions of the New York State, the Defendant was entitled

to apply for vacating the Award on certain grounds and thus imperil the

finality accorded to the Award by his contract. Therefore, it cannot be

said that the Award has attained finality till the entire procedure was

gone through and, thus, the Award in question, not being final, could

not furnish a valid cause of action for the Suit.

67. Secondly, the issue of finality assumes significance in the

context of the bar of limitation for the Suit based on the foreign award.

It is the stand of the Plaintiff that the award attained finality after 20

days of the disposal of the Appeal by an order dated 13th January 2021.

68. The parties are not at issue over the character of the Award

qua Iran. It was an international award for Iran as well, though the seat

of Arbitration was in Tehran. Under the Article of 1(b) of the Iran Act

1997, an Arbitration is international if at the time of conclusion of the

Arbitration Agreement, one of the parties to the Agreement, is not a

national of Iran under Iranian law. Article 2 of the Iran Act 1997

provides that Arbitration of disputes in international commercial

relations shall be conducted in accordance with the provisions of the

said Act. Article 6, which deals with the supervisory authority of the

41/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

Courts, provides that performance of functions specified in certain

Articles including Articles 33 and 35 are entrusted to the Public Court in

the provincial capital where the place of Arbitration is located and

where, and for as long as, the place of Arbitration has not been

designated, such functions will be performed by Tehran Public Court.

Article 36(1) excludes Arbitration of international commercial disputes

under the said Act, 1997 from the Arbitration Rules contained in the

Civil Procedure Code and other laws and regulations.

69. Chapter 7 of the Iran Act 1997 governs the recourse against

the Awards. Under Article 33(1) an Arbitral Award may be set aside by

the Court specified in Article 6 upon the application of a party when the

circumstances stipulated in Clauses (a) to (i) exists. Article 34 provides

for nullity of Award. It reads as under:

Article 34. Nullity of award
An arbitral award shall be deemed null and void and
unenforceable where:

(1) the principal subject-matter of the dispute is not capable
of settlement by arbitration under Iranian law;
(2) the terms of the award would be contrary to the public
policy or good morals of the State, or to the mandatory
provisions of this Act;

(3) the arbitral award made in respect of immovable property
located in Iran is in conflict with the mandatory laws of the
Islamic Republic of Iran or with the contents of valid official
documents, unless the “arbitrator” has been authorized to act
as amiable compositeur regarding the latter issue.”

42/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

70. Enforcement of the Award is regulated by Article 35. It

reads as under:

Article 35. Enforcement
(1) Except for instances specified in Articles 33 and 34 of
this Act, arbitral awards made in accordance with the
provisions of this Act shall be recognized as binding and
enforceable after notification thereof and, upon application
in writing to the court specified in Article 6, enforcement
procedures in connection with court judgments shall be put
into effect.

(2) Where a party requests the court specified in Article 6 of
this Act to set aside an arbitral award, while the other party
requests for its recognition or enforcement, the court may,
on the application of the party requesting recognition or
enforcement of the award, order the other party to provide
appropriate security.”

71. From the perusal of the judgment of 105 th Branch of Public

Civil Court dated 15th July 2019 (Exhibit “JJ”), it prima facie appears

that the Award was challenged by invoking the provisions contained in

Article 489 of the Civil Procedure Code under which an Arbitral Award

shall be null and void and unenforceable if the circumstances stipulated

in Clauses (1) to (7), therein, exist. As noted above, the International

Arbitration is excluded from the Arbitration Rules contained in the

Iranian Civil Procedure Code.

43/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

72. Mr. Ratan Singh would urge that, nonetheless, the Public

Civil Court which decided the said proceeding, was the competent Court

under the Article 6 of the Iran Act 1997 and has, in fact, decided the

matter on merits, including the grounds which were available for

setting aside an Arbitral Award under Article 33 of the Iran Act 1997.

73. The aforesaid submission, in my considered view, requires

consideration, upon forming a correct opinion as to the foreign law. The

merits of the decision of the Public Civil Court at Tehran dated 15 th July

2019 are not as significant as the question of jurisdiction. Prima facie, a

proceeding invoking Article 489 of the Iranian Civil Procedure Code was

not tenable. In such circumstances, can element of finality be attached

to the award, in the context of the said decision dated 15 th July 2019

and the subsequent remand of the matter by the Court of Appeal of

Tehran province, by order dated 11 th August 2020 (Exhibit “KK”) and

the eventual decision dated 13th January 2021 by the Public Civil Court

(Exhibit “LL”), dismissing the Appeal, appears debatable.

74. It would be contextually relevant to note that Article 33(3)

of the Iran Act 1997, reads as under:

Article 33. Application for setting aside an arbitral
award
(1) … … …

(2) … … …

(3) The application for setting aside the award
under the provisions of paragraph (1) of this Article shall

44/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

be submitted to the court specified in Article 6 within
three months of notification of the award, including
correction or interpretation of the award, or an
additional award, otherwise the application shall be
inadmissible.”

75. An application for setting aside the Award is required to be

made to the Court specified in Article 6, and within three months from

the notification of the Award. Lest the Application shall be inadmissible.

Could it be urged that after three months of the notification of the

Award, the right of the party to seek setting aside of the award stood

foreclosed and the award attained finality?.

76. Article 34, on the other hand, declares the circumstances in

which an Arbitral Award shall be deemed to be null and void and

unenforceable. At what stage and before which forum, the nullity of the

Award can be agitated, is again a matter which prima facie does not

seem to be free from doubt.

77. As noted above, Article 35 provides that except for

instances specified in Article 33 (setting aside of the Award) and 34

(Nullity of award), Arbitral Awards made in accordance with the

provisions of this Act shall be recognized as binding and enforceable

after notification thereof.

78. The submission of Mr. Ratan Singh that the Plaintiff was

not required to file an application for enforcement for the finality of the

45/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

award, may carry some substance. However, in the case at hand, the

Plaintiff does not claim that the award became final and binding on the

date it was made, but seeks to postpone the date of finality to the award

to the order dated 13th January 2021 passed by the Public Civil Court,

Tehran (Exhibit “LL”).

79. In this view of the matter, in my view, prima facie, it is

debatable whether the award attained finality and, if so, the date on

which the award attained finality, and the determination may require

evidence to be adduced in the matter of interpretation of the foreign

law

BAR OF LIMITATION:

80. The aforesaid, prima facie, finding as regards the finality of

the award also bears upon the aspect of limitation. It may be apposite to

note that, apart from the award in question, the Plaintiff rests his claim

on the original cause of action, albeit, in the alternative. However,

during the course of the submissions, it was urged on behalf of the

Plaintiff that the Suit is, in fact, primarily filed on the foreign award

dated 7th September 2018 having attained finality on 4 th February 2021.

The aforesaid being the nature of the suit claim, it may be necessary to

note the averments in the Plaint as regards the point of limitation.

81. In paragraph 94 of the Plaint, the Plaintiff has averred that

if the Plaintiff is not found entitled to a decree on the basis of the

46/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

foreign award then the Plaintiff is entitled to recovery of the amount on

the basis of the original cause of action. In paragraph 95 of the Plaint,

the Plaintiff claims that the cause of action in respect of each of the

cargos arose after the expiry of the period of 60 days from the date of

issue of Bill of Lading in respect to each cargo and the assurances made

by the Defendant to pay the outstanding amount, the last of which was

on 26th April 2016. In the second part, the Plaintiff claims cause of

action arose on the date of award, i.e., 8 th September 2018 followed by

the judgments of the Court of the first instance on 15 th July 2019, the

Appeal Bench judgment dated 11th August 2020 and again the judgment

of Court of first instance dated 13 th January 2021 and, lastly, on the

expiry of 20 days period thereof, i.e., 4 th February 2021. Lastly, the Suit

is stated to be governed by Article 113 of the Limitation Act (paragraph

98).

82. Evidently, the institution of the suit on 12 th January 2024,

on the basis of the original cause of action constituted by the sale and

delivery of the goods, the last of which was on 1 st April 2016, appears

prima facie, beyond three years from the date of the accrual of the

cause of action. Though an endeavour was made on behalf of the

Plaintiff that there is an acknowledgment of the debt in the form of the

e-mails referred to in paragraph 95 of the Plaint, and, therefore, a fresh

cause of action accrues, yet, the Plaintiff does not seem to have made

47/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

the requisite pleadings in the Plaint to base the suit on the alleged

acknowledgment of debt. In any event, the last of the e-mails referred

to in paragraph 95 of the Plaint was on 26th April 2016.

83. On the aspect of the bar of limitation, in the context of the

Suit based on the foreign award, before adverting to delve into the issue

of finality to the award, the law which governs the period of limitation

for a suit of the present nature, deserves to be ascertained.

84. Mr. Seksaria, placed a very strong reliance on the judgment

of the Supreme Court in the case of Vedanta Limited (Supra) to urge

that the suit ought to have been instituted within a period of three years

from the date of the award. In the case of Vedanta Limited (Supra), the

Supreme Court, inter alia, considered the question of limitation for

filing the enforcement/execution petition for enforcement of foreign

award in India. In that context, the Supreme Court held that the issue of

limitation for enforcement of foreign award being procedural in nature,

is subject to the lex fori, i.e., the law of the forum that the foreign

award was sought to be enforced, namely, the Limitation Act 1963. The

said Act of 1963 does not contain any specific provision for enforcement

of a foreign award. An application for execution of a foreign decree

would be an application not covered under any other Article of

Limitation Act, and, would, thus be governed by Article 137 of the

Limitation Act. Article 136 of the Limitation Act (which provides 12

48/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

years period of limitation for execution of the decree) wound not be

applicable for the enforcement/execution of the foreign award, since it

is not a decree of Civil Court in India. Thus, the period of limitation for

filing a Petition for enforcement of a foreign award under Sections 47

and 49 of the Act 1996 wold be governed by Article 137 of the

Limitation Act 1963, which prescribes a period of three years from the

date when the right to apply accrues.

85. Undoubtedly, the aforesaid enunciation of law was in the

context of the enforcement of a foreign award emanating from a

reciprocating territory and enforceable under Part II of the Act of 1996.

In the instant case, since the Award emanates from a non-reciprocating

territory, the suit has been instituted on the basis of a foreign award.

However, that would not make much qualitative difference in the

matter of the application of law of limitation, i.e. the Limitation Act

1963. A suit for which no period of limitation is prescribed, would be

governed by the residuary Article 113, which provides that a suit for

which no limitation is provided elsewhere in the Schedule, the period of

limitation would be three years and the time begins to run when the

right to sue accrues.

86. Thus, the question as to when the right to sue accrued to

the Plaintiff comes to fore. The Plaintiff asserts the right to sue accrued

when the award, which was passed on 7 th September 2018, attained

49/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

finality on 4th February 2021, i.e., 20 days after the dismissal of the

Appeal by the Court of first instance on 13 th January 2021. This claim of

the Plaintiff, in turn, raises the issue of the date of finality of the award

dated 7th September 2022.

87. I have already adverted to the provisions contained in Iran

Act 1997. A party is entitled to seek setting aside of the award under

Article 33 of the Iran Act 1997 on the grounds set out therein, within a

period of three months from the date of the notification of the award,

before the Court designated under Article 6 therein. This Court is

persuaded to take a prima facie view that if the proceeding for setting

aside the award were not initiated within the said period of there

months, the award would attain finality. This view is in accord with the

submissions forcefully canvassed on behalf of the Plaintiff that there is a

distinction between “finality” and “enforceability” of the award, as

indicated in paragraph 43 of the judgment in the case of Badat & Co

(Supra). Consistent with this view, if the Plaintiff was not required to

file an application for enforcement of the award under Article 35 of the

Iran Act 1997, which was again the stand of the Plaintiff, the award

would have attained finality after the expiry of the period of three

months from the date of the award with no proceeding having been

filed by the Defendant for setting aside the award under the provisions

of Iran Act 1997.

50/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

88. The Plaintiff, however, seeks to defer the finality to the

award dated 7th September 2018, on the basis of the proceeding which

was initiated by the Defendant, under the Iranian Code of Civil

Procedure. Whether such a proceeding before the forum which

apparently lacked jurisdiction, by an adversary, would extend the period

of limitation or defer the finality otherwise attached to the award dated

7th September 2018, prima facie, appears contentious.

89. From the perusal of the provisions contained in the Iranian

Act 1997 which governs an international arbitration, prima facie, it

appears difficult to draw an inference that the finality to the award in

question could have been deferred on the strength of a proceeding,

which appeared to be not properly constituted, and abortive.

90. In the aforesaid view of the matter, I find substance in the

submission of Mr. Seksaria that even if the benefit of the order dated

10th January 2022 passed by the Supreme Court, in Suo Moto Writ

Petition No. 3 of 2020 is extended, it appears to be seriously debatable,

whether the suit was filed within the period of limitation.

91. I am conscious that the question of limitation is more often

than not a mixed question of fact and law, and cannot be legitimately

decided on the basis of bare averments, and submissions. However, in

the case at hand, since the entire case of the Plaintiff rests on the date

of postponement of finality to the award, dated 7 th September 2018,

51/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

which appears rather tenuous, such tentative finding as regards the bar

of limitation is required to be recorded.

CONSEQUENCES OF NON-INVOCATION OF MEDIATION UNDER

SECTION 12A OF THE COMMERCIAL COURTS ACT:

92. The prayer in the Interim Application were principally

rested on the assertion that the proceeding before the NCLT, Mumbai,

being CSA No. C.A. (CAA) 66/MB/2022 under the provisions of Section

232 of the Companies Act 2013, manifest the clear intent of the

Defendant to defraud the Plaintiff as the Plaintiff has not been shown as

the creditor, despite the award. Reference is made to various orders

passed by the NCLT; the last one dated 12 th November 2023, whereby

the Applicant-Defendant herein was allowed to convene and hold

meeting at any date not later than 31 st March 2024, convenient to the

secured creditors. The pendency of the said proceeding before the NCLT

and the possibility of the orders being passed therein, to the prejudice

of the Plaintiff, was pressed as justification for the non-invocation of

mediation under Section 12A of the Commercial Courts Act.

93. Mr. Sekseria would urge that the aforesaid justification is plainly

untenable. Inviting attention of the Court to the orders passed by the

NCLT right from 14th October 2022, Mr. Seksaria would urge that the

Plaintiff had full knowledge about the said proceeding long back and,

yet, the suit came to be instituted without resorting to the mandatory

52/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

pre-institution mediation. Mr. Seksaria laid particular stress on the fact

that the aspect of urgency is required to be considered in the light of

award which came to be passed on 7 th September 2018 and the Suit

itself being ex-facie barred by law of limitation.

94. Mr. Ratan Singh joined the issue by strenuously urging that

this ground also underscores the dishonest intent of the Defendant. An

endeavour was made to demonstrate that the Plaintiff did make

attempts to amicably settle the disputes at both, pre and post award

stage. Attention of the Court was invited to the Minutes of the Meeting

chaired by the Joint Secretary FT(SA) Department of Commerce on 17 th

July 2017 to resolve the issue of pending payment by the Defendant to

Iranian companies. A Defendant who dishonestly evades the liability

cannot be permitted to score a march by taking a technical defence,

urged Mr. Singh.

95. Even otherwise, Mr. Singh would urge, the Plaintiff has

satisfactorily made out the case of urgency if considered in the light of

the limited enquiry warranted at the nascent stage. Reliance was placed

by Mr. Ratan Singh on the judgment of the Supreme Court in the case of

Yamini Manohar Vs T.K.D. Keerthi 14 wherein it was enunciated that

non-grant of relief at ad-interim stage will not justify dismissal of the

Suit under Order VII Rule 11.

14 (2024) 5 SCC 815.

53/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

96. Section 12A of the Commercial Courts Act 2015 bars the

very institution of the Suit without exhausting remedy of pre-institution

mediation, if the Suit does not contemplate any urgent interim relief. In

the case of Patil Automation Private Limited (Supra), the Supreme

Court, has emphasized the mandatory character of the pre-institution

mediation, in the context of legislative object behind the introduction of

the pre-insitution mediation. The object unerringly points to at least

partly foisting compulsory mediation on the Plaintiff in a Suit which

does not contemplate an urgent interim relief.

97. In the case of Kaulchand H. Jogani Vs Shree Vardhan

Investment15 this Court had an occasion to consider the nature and

import of the provisions contained in Section 12A of the Commercial

Courts Act. In paragraphs 28 to 31 this Court observed as under:

“28. In the case of Patil Automation (supra) the Supreme
Court has emphasized the legislative object behind
introduction of preinstitution mediation as a mandatory
measure. Evidently, the outlet for not resorting to pre-
institution mediation is provided by the text of Section
12A itself namely a suit contemplating an urgent interim
relief. In my view, if the said outlet is construed too
loosely in the sense that mere filing of an application for
interim relief, howsoever unjustified and unwarranted it
may be, would take the suit out of the purview of Section
12A, it may run counter to the legislative object. The
interdict contained in Section 12A can be easily

15 2022 SCC OnLine Bom 4752
54/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

circumvented by filing an application for interim relief
without their being any reason or basis therefor. Such an
interpretation may not advance the legislative object.

29. The Parliament, it seems, has designedly used the
expression, “a suit, which does contemplate any urgent
interim relief ….”. This phrase cannot be interchangeably
used with the expression, “where the plaintiff seeks an
urgent interim relief…” The test would be whether the
suit does contemplate an urgent interim relief.

30. In a given case, the Court may be justified in
embarking upon an inquiry as to whether there is an
element of justifiability in the claim for urgent interim
relief or such a prayer is a mere subterfuge to overcome
the bar under Section 12A. At the same time, the scope of
such an inquiry would be extremely narrow. Such an
inquiry cannot partake the character of determination of
the prayer for interim relief on merits. It cannot be urged
that if the Court is disinclined to grant interim relief then
the justifiability of the institution of the suit, without pre-
institution mediation, can itself be questioned. Therefore,
the Court may be called upon to stear clear of two
extremes.

31. In my considered view, the proper course would be
to asses whether there are elements which prima facie
indicate that the suit may contemplate an urgent interim
relief irrespective of the fact as to whether the plaintiff
eventually succeeds in getting the interim relief. In a
worst case scenario, where an application for interim
relief is presented without there being any justification
whatsoever for the same, to simply overcome the bar

55/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

under Section 12A, the Court may be justified in
recording a finding that the suit in effect does not
contemplate any urgent interim relief and then the
institution of the suit would be in teeth of Section 12A
notwithstanding a formal application.”

98. In the Yamini Manohar (Supra), the Supreme Court

referred to the aforeextracted observations in paragraph 31, and a

judgment of the Delhi High Court in the case of Chandra Kishore

Chaurasia Vs R.A. Perfumery Works (P) Ltd16 and thereafter enunciated

the law as under:

“10. We are of the opinion that when a plaint is filed
under the CC Act, with a prayer for an urgent interim
relief, the commercial court should examine the nature
and the subject matter of the suit, the cause of action,
and the prayer for interim relief. The prayer for urgent
interim relief should not be a disguise or mask to
wriggle out of and get over Section 12A of the CC Act.
The facts and circumstances of the case have to be
considered holistically from the standpoint of the
plaintiff. Non-grant of interim relief at the ad-interim
stage, when the plaint is taken up for
registration/admission and examination, will not justify
dismissal of the commercial suit under Order VII, Rule
11 of the Code; at times, interim relief is granted after
issuance of notice. Nor can the suit be dismissed under
Order VII, Rule 11 of the Code, because the interim
relief, post the arguments, is denied on merits and on
examination of the three principles, namely, (i) prima

16 2022 SCC OnLine Del 3529.

56/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

facie case, (ii) irreparable harm and injury, and (iii)
balance of convenience. The fact that the court issued
notice and/or granted interim stay may indicate that the
court is inclined to entertain the plaint.

11. Having stated so, it is difficult to agree with the
proposition that the plaintiff has the absolute choice and
right to paralyze Section 12A of the CC Act by making a
prayer for urgent interim relief. Camouflage and guise to
bypass the statutory mandate of pre-litigation mediation
should be checked when deception and falsity is
apparent or established. The proposition that the
commercial courts do have a role, albeit a limited one,
should be accepted, otherwise it would be up to the
plaintiff alone to decide whether to resort to the
procedure under Section 12A of the CC Act. An ‘absolute
and unfettered right’ approach is not justified if the pre-
institution mediation under Section12A of the CC Act is
mandatory, as held by this Court in Patil Automation
Privated Limited
(Supra)

12. The words ‘contemplate any urgent interim relief’
in Section 12A (1) of the CC Act, with reference to the
suit, should be read as conferring power on the court to
be satisfied. They suggest that the suit must
“contemplate”, which means the plaint, documents and
facts should show and indicate the need for an urgent
interim relief. This is the precise and limited exercise
that the commercial courts will undertake, the contours
of which have been explained in the earlier
paragraph(s). This will be sufficient to keep in check and

57/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

ensure that the legislative object/intent behind the
enactment of Section 12A of the CC Act is not defeated.

(emphasis supplied)

99. The Commercial Courts are enjoined to examine the matter

as to whether the suit does contemplate any urgent interim relief and

the Plaintiff does not have absolute and unfettered right in determining

as to whether he should not resort to pre-institution mediation. The

Supreme Court has postulated that the prayer for urgent interim relief

should not be a disguise or mask to wriggle out of and get over Section

12A of the Commercial Courts Act. The expression, “contemplate any

urgent interim relief” suggests that the suit must “contemplate”, which

means the Plaint, documents and facts should show and indicate the

necessity of an urgent interim relief.

100. On the aforesaid anvil, a primary enquiry on the basis of

the averments in the Plaint, documents annexed thereto and the

attendant facts of the case, prima facie, indicates that the Suit does

contemplate an urgent interim relief. The fact that this Court had

declined to grant ad-interim relief, or for that matter, this Court may not

eventually grant the interim relief, does not bear upon the tenability of

the Suit sans pre-institution mediation.

101. As noted above, the driving force for the institution of the

Suit and the prayers for urgent interim reliefs, as claimed by the

58/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

Plaintiff, was the apprehension of orders being passed by the NCLT in

the “scheme” proceeding. It can be urged that since the award was

passed on 7th September 2018 and even the said award has attained

finality almost prior to three years, there was no question of grant of

urgent interim relief. However, the matter cannot be approached from

this perspective only. The copies of the order passed by NCLT (annexed

at Exhibit “A” to “F” to the Interim Application) do indicate that the

amalgamation proceeding has been pending before the NCLT since the

year 2022. NCLT had ordered issuance of notice to various persons and

authorities. The Defendant was directed to hold the meetings of the

secured creditors in the matter of the approval of the scheme. Time was

sought by the Defendant to hold such meetings. By an order dated 22 nd

November 2023, extension was granted till 31 st March 2024. It was the

apprehension of the Plaintiff that once the creditors’ meeting is held and

the creditors convey their acceptance, the scheme could be approved by

the NCLT and thereupon the possibility of the recovery of the award

amount would be affected. The fact that the Plaintiff was not shown as

one of the creditors, despite holding an award against the Defendant,

was the principal grievance.

102. Evidently, on the date of the institution of the Suit, above-

numbered proceeding was sub-judice before the NCLT and the meeting

of the creditors of the Defendant was yet to be held. In a case of this

59/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

nature, where the Plaintiff apprehended that the recovery of award

amount would be jeopardised, on account of the orders passed in the

scheme proceeding, which was, in fact, sub-judice on the date of the

institution of the Suit, it cannot be said that the suit did not

contemplate an urgent interim relief. What consequences follow the

approval of the scheme, need not be delved into in judging the urgency

of the matter. In the circumstances of the case, the pendency of such

proceeding and likelihood of it being approved, in my view, furnished

an adequate justification for claiming urgency. Though the delay on the

part of the Plaintiff in approaching the Court from the date of the award

and even the date the award attained finality, may bear upon the

entitlement of the Plaintiff for interim relief. However, the urgency is

required to be judged, in the light of the circumstances as obtained on

the date of the institution of the Suit.

103. Thus, I am impelled to hold that the Suit did contemplate

an urgent interim relief.

LIABILITY OF THE DEFENDANT: WHETHER A VERY STRONG

PRIMA FACIE CASE HAS BEEN MADE OUT:

104. The substance of the defence of the Defendant was that it

had acted as a broker of the named principal, i.e., IGT and Venture

Crosstrade. Reliance was placed on the Exclusive Brokerage Agreement

with Venture Crosstrade (Exhibit “EE”), dated 27th March 2012, and IGT,

60/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

dated 31st May 2012 (Exhibit “FF”). Since, on the own showing of the

Plaintiff, in respect of the subject transactions proforma invoices were

issued in the name of IGT and Venture Crosstrade, 36 cheques were

delivered by those entities and upon dishonor of those cheques, the

Plaintiff lodged criminal proceedings against those entities, it was

submitted that the transaction was between the IGT and Venture

Crosstrade. Reliance was placed on the Affidavit filed on behalf of the

IGT and Venture Crosstrade in a suit instituted by the Defendant against

those entities before this Court.

105. On behalf of the Plaintiff, it was urged that the said Suit is

collusive one. IGT and Venture Crosstrade are the entities owned and

controlled by the Defendant. Rajesh Harlalka, who is the director of the

Defendant, is the Managing Director of Venture Crosstrade.

106. Banking upon the purchase orders and the correspondence

exchanged between the parties, the Plaintiff asserts the real transaction

was between the Plaintiff and the Defendant and the later subsequently

dishonestly introduced IGT and Venture Crosstrade with a design to

dupe the Plaintiff.

107. Mr. Ratan Singh submitted that the Arbitral Tribunal has

considered the aforesaid specific defence of the Defendant and rejected

the same by ascribing justifiable reasons. Therefore, this Court need not

delve into the said aspect of the matter.

61/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

108. At this juncture, it is imperative to note the trade licences

of IGT and Venture Crosstrade indicate that they were incorporated as

the free zone commercial entities engaged in general trading. Mr. Karan

Singh Karki was shown the owner of IGT and Mr. Rajesh Harlalka the

owner of the Venture Crosstrade. Secondly, there are Exclusive

Brokerage Agreements in which the Defendant is shown as the broker

and IGT and Venture Crosstrade as the principal.

109. The question as to whether there are circumstances which

would warrant lifting of the corporate veil, for the reason that Mr.

Rajesh Harlalka, who is the director of the Defendant is also the

Managing Director of Venture Crosstrade, is a matter for adjudication.

Had it been a case where the Plaintiff had not issued the invoices in

respect of the subject transaction in favour of IGT and Venture

Crosstrade, different considerations would have come into play. Not

only the Plaintiff issued the proforma invoices in the name of IGT and

Venture Crosstrade but also accepted cheques from those entities

towards the price of the goods and, upon dishonor of the cheques, even

prosecuted IGT and Venture Crosstrade before the jurisdictional

Commercial Courts.

110. All these factors cannot be brushed aside as inconsequential

and immaterial.

62/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

111. If considered in the light of the aforesaid nature of the

claim of the Plaintiff and the action taken by the Plaintiff to enforce the

liability against IGT and Venture Crosstrade, it cannot be said that a

very strong prima facie case is made by Plaintiff so as to grant the

interim relief of the nature claimed by the Plaintiff. The suit is

essentially for the enforcement of a money claim. In the face of the

aforesaid material, especially in the light of the nature of the award, the

suit for the enforcement of which, prima facie, will have to encounter

the challenge on the count of the finality thereto and the bar of

limitation, and the fact that the Plaintiff had dealt with IGT and Venture

Crosstrade as independent entities and even took steps to enforce

liabilities against those entities, the test of strong prima facie case and

the reasonable chance of the decree being eventually passed in favour

of the Plaintiff cannot be said to have fulfilled.

112. Therefore, I am inclined to hold that the Plaintiff failed to

establish a very strong prima facie, case for the grant of interim reliefs

which are essentially in the nature of attachment before judgment. In

the circumstances of the case having regard to the impediments which

the Plaintiff will have to surmount, the balance of convenience tilts in

favour of the Defendant. An interim relief of the nature sought by the

Plaintiff may cause irreparable loss to the Defendant.

63/64

::: Uploaded on – 09/06/2025 ::: Downloaded on – 09/06/2025 22:40:32 :::

-IAL-3847-2024-.DOC

113. Resultantly, the Application deserves to be rejected. Hence

the following order.

:ORDER:

       (i)     Application stands rejected.

       (ii)     Costs in cause.

                                              [N. J. JAMADAR, J.]




                                    64/64



 ::: Uploaded on - 09/06/2025                   ::: Downloaded on - 09/06/2025 22:40:32 :::
 

[ad_1]

Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here