Larsen And Toubro Ltd vs Puri Construction Pvt. Ltd on 21 April, 2025

0
46

[ad_1]

Supreme Court of India

Larsen And Toubro Ltd vs Puri Construction Pvt. Ltd on 21 April, 2025

Author: Abhay S. Oka

Bench: Pankaj Mithal, Abhay S Oka

2025 INSC 523

                                                                              Reportable

                                          IN THE SUPREME COURT OF INDIA
                                           CIVIL APPELLATE JURISDICTION

                                      CIVIL APPEAL NOS. 2575-2578 OF 2016

                            Larsen and Toubro Limited                    … Appellant

                                                          versus


                            Puri Construction Pvt. Ltd.                  … Respondents
                            and Others
                                                      with
                                      CIVIL APPEAL NOS. 2580-2581 OF 2016
                                                           and
                                            CIVIL APPEAL NO. 2579 OF 2016


                                                        JUDGMENT

ABHAY S. OKA, J.

FACTUAL ASPECTS

1. These appeals arise out of the judgment and order dated

30th April, 2015, passed by the Division Bench of Delhi High

Court on the appeals preferred under Section 37 of the

Arbitration and Conciliation Act, 1996 (for short, ‘the

Arbitration Act’). The appeals before the Division Bench were

preferred against the judgment dated 26th November, 2008 of
Signature Not Verified

the learned Single Judge in a petition under Section 34 of the
Digitally signed by
ANITA MALHOTRA
Date: 2025.04.21
18:34:47 IST
Reason:

Arbitration Act by which the award of the Arbitral Tribunal

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 1 of 72
was set aside. The Division Bench, by the impugned

judgment, has disagreed with some of the findings recorded

by the learned Single Judge. To that extent, the appeals

preferred by Puri Construction Private Limited and Mohinder

Puri have been allowed. The appeal by Larsen and Toubro

Limited was dismissed. However, the Division Bench

observed that the parties are left to pursue the appropriate

course of actions under law.

2. In these appeals, we are concerned with a company,

Puri Construction Limited and its sister concerns (collectively

referred to as ‘PCL’). We are also concerned with another

company, Larsen and Toubro Limited (hereafter referred to as

‘L&T’). PCL was in possession of lands in the Gurgaon

District, Haryana, as the owner thereof. PCL had obtained

licenses from the Director Town and Country Planning,

Haryana (for short, ‘the DTCP’) to develop the lands for

residential group housing schemes. Earlier, PCL had entered

into a joint venture with ITC Classic Real Estate Finance

Limited (for short, ‘ITCREF’) under the name Florentine

Estates of India Limited for the development of the lands.

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 2 of 72
Ultimately, ITCREF exited from the business. An Exit

Agreement dated 30th July, 1997 was made, which, inter alia,

stipulated that PCL would transfer to ITCREF the built-up

space of 1,95,000 sq. ft. in the project. Thereafter, L&T was

introduced to complete the project.

3. L&T and PCL entered into an agreement for land

development (for short ‘the Development Agreement’) on 19 th

January, 1998, but the date mentioned therein was 10 th

March, 1998. Subsequently, since L&T was of the opinion that

there was a recessionary trend in the real estate market due

to which the project was required to be down-sized, a

supplementary agreement was entered into between L&T and

PCL on 30th December, 1999 (for short ‘the Supplementary

Agreement’). Based on the Supplementary Agreement, a

Tripartite Agreement dated 10th January, 2000 (for short, ‘the

Tripartite Agreement’) was entered into between PCL, L&T

and Lord Krishna Bank (for short ‘the Bank’).

4. Broadly, in the Development Agreement, it was provided
as under:

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 3 of 72

(a) L&T will develop the entire property mentioned in

Schedule ‘A’ of the Agreement, including the part

allocated to PCL, at its own cost;

(b) In phase-I of development, L&T will develop a

portion of Schedule ‘A’ property as described in

Schedule ‘B’. An area of 18.025 acres will be

developed by L&T within 60 months in phase-I. In

phase-II of the development, L&T was to develop

the remaining portion as mutually acceptable to

the parties in view of the prevailing market

conditions;

(c) The ratio of division in the developed property

between PCL and L&T was agreed to be 25% and

75% respectively;

(d) ITCREF was to get an area of 2,20,416 sq. ft. from

the property allocated to PCL;

(e) PCL agreed to pay all External Development

Charges (for short, ‘EDC’) up to the date of the

development agreement. The liability to pay EDC

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 4 of 72
was to be of L&T after receiving No Objection

Certificate (for short ‘NOC’);

(f) L&T was to complete the construction of Phase-I in

60 months, which was subject to extension in view

of prevailing market conditions; and

(g) L&T will not be deemed to be in default if

performance of its obligations under the

development agreement is delayed, inter alia, due

to the prevailing market conditions.

5. The Supplementary Agreement incorporated the
following clauses:

(a) The terms of the Development Agreement will

continue to bind the parties unless otherwise

agreed in the in the Supplementary Agreement,

which shall come into effect after happening of the

following events:

i. L&T taking over or replacing bank guarantees

furnished by PCL to DTCP;

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 5 of 72
ii. The bank paying EDC amounting to Rs. 6

crores to DTCP;

iii. Reimbursement of expenses incurred by PCL

by L&T; and

iv. Compliance with the terms and conditions of

the Tripartite Agreement made by L&T by

paying Rs.5.14 crores to the Lord Krishna

Bank (“the Bank”).

(b) L&T will furnish bank guarantees to DTCP after

approval of the term loan by the bank to PCL;

(c) L&T will pay the EDC of Rs. 6 crores paid by PCL

through the bank and the remaining EDC Charges

within 18 months;

(d) L&T agreed to commence construction work for

3.84 lac sq.ft. of the development, subject to

achieving a confirmed booking/selling target of

75% in phase-I area; and

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 6 of 72

(e) The Agreement would not be construed as a waiver

of any right that has accrued for the extension or

termination under the Development Agreement.

6. In the Tripartite Agreement, it was provided as under:

(a) The Bank will pay a sum of Rs. 6 crores towards

EDC to DTCP on behalf of PCL, which will

constitute a term loan to PCL. The loan will be

secured by 15 acres of land already mortgaged by

PCL to the Bank;

(b) The Bank will issue a bank guarantee of Rs. 4.66

crores to DTCP on behalf of L&T; and

(c) L&T will pay the Bank a sum of Rs. 5.19 crores on

behalf of PCL to discharge the loan availed for

payment of EDC on or before 19th January, 2000.

7. We may note here that there was an arbitration to which

ITCREF and PCL were parties. A consent award was passed

on 13th May, 2000, in favour of ITCREF requiring PCL to allot

1,06,200 sq. ft. to ITCREF.

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 7 of 72

8. PCL by letter dated 18th December, 2000, terminated the

Development Agreement with L&T inter alia, on the grounds

of:

(a) Failure to allocate area to ITCREF;



                     (b) Non-sanctioning        of    funds     towards     the

                            development; and


                     (c)    Non-payment of EDC; and


(d) Other breaches in relation of non-commencement

of work.

9. Delhi High Court referred the dispute between PCL and

L&T to a Sole Arbitrator. Broadly, the following were the

prayers made by PCL before the Arbitral Tribunal:

(a) Direct L&T to satisfy the loan availed from the

Bank and to obtain the release of the title-deeds in

respect of 15 acres of land placed by PCL with the

Bank as security;

(b) Direct L&T to return the title-deeds of the rest of

the lands to PCL;

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 8 of 72

(c) Direct L&T to return the sanctioned development

plans and other documents, including licences,

permits, permissions etc;

(d) Issue a permanent injunction against L&T

restraining it from interfering with any of PCL’s

rights to develop the property; and

(e) For grant of compensation and damages to the

tune of Rs. 300 crores and Rs. 100 crores

respectively.

10. L&T filed a counter-claim before the Arbitral Tribunal,

making the following prayers:

(a) Declare that PCL has no authority to rescind the

contract;

(b) Grant compensation and damages to L&T to the

tune of Rs. 280 crores due to the wrongful

rescission of the agreement by PCL. Rs. 280 crores

were claimed as the reimbursement amount of

profit which L&T would have received by

developing 75% of the area; and

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 9 of 72

(c) Grant reimbursement to L&T of Rs. 8,31,53,968/-

as the amount spent by it towards fulfilling the

obligations under the Development Agreement.

11. The Arbitral Award was made on 28th December, 2002.

The Arbitral Tribunal held that:

(a) L&T jeopardised PCL’s obligations towards

ITCREF;

(b) L&T resiled from and went back upon its original

contractual obligations and tried to effect sales

without sanction under the revised development

plan and without making any provision for the

responsibility towards ITCREF;

(c) L&T had consciously decided to abandon the

Development Agreement and omitted to pay EDC

and also defaulted in the fulfilment of its obligation

to the statutory authorities, ITCREF, as well as the

Bank;

(d) The object of the Supplementary Agreement was

unlawful as it sought to defeat the beneficial

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 10 of 72
interest of ITCREF, which was a signing party to

the Development Agreement; and

(e) The Supplementary Agreement was tainted by

economic coercion, and the signatures of PCL were

obtained by fraud.

12. The operative award is as follows:

“ I. An Award in favour of the Claimants directing the
Respondent to pay Rs. 35 Crores to the Claimants on
account of damages suffered by the Claimants within
four weeks from the date of the award;

II. An Award in favour of the Claimants, directing
the Respondent to settle the claim of Lord Krishna
Bank within 4 weeks of the Award by repayment of
loan of Rs. 6 Crores with such interest that may be
due and payable to Lord Krishna Bank and further
directing the Respondent to secure the release of title
deeds from the said bank and to reimburse the
claimant’s interest charges paid by Puri Construction
Ltd. to Lord Krishna Bank in interregnum; within a
period of four weeks from the date of this award. In
default thereof, the Respondent will pay to the
Claimants a sum of Rs. 75 Crores for loss of saleable
area in respect of 15 acres of land placed in mortgage
with the said bank within a period of four weeks from
the date of this Award.;

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 11 of 72
III. An Award in favour of the claimants directing the
Respondent to return licences permits and
permissions obtained by the Claimants from the
statutory authorities in respect of the lands covered
by the Development Agreement dated 10.3.1998
within 4 weeks of this Award to the Managing
Director of Puri Construction Ltd. and obtain a
certificate of discharge to that effect granted by the
said Puri Construction Ltd. or in lieu thereof the
Respondent will pay to the Claimants a sum of Rs. 5
Crores by way of damages within a period of four
weeks from the date of this Award;

IV. An Award in favour of the Claimants directing
that the Respondent or anybody claiming under the
Respondent is permanently injuncted by restraining
them from interfering in any way or manner with the
rights of the claimants to develop the property
covered under the said Agreement dated 10.3.1998;

V. An Award in favour of the Claimants, directing
the Respondent to indemnify the Claimants in terms
of Clauses 4(b) and 25 of the Development Agreement
dated 10.3.1998 for any action or decree or settlement
to be enforced by ITCREF against the Claimants or in
lieu thereof shall pay to the Claimants a sum of Rs.
50 Crores on such date as such action or decree or
settlement to be enforced by ITCREF against the
Claimants becomes crystallized;

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 12 of 72

VI. An Award in favour of the Claimants, directing
the Respondent to pay cost of the Arbitration
proceedings quantified at Rs. 30 lakhs within a period
of four weeks from the date of the Award;

VII. An Award in favour of the Claimants, directing
the Respondent to pay interest to the Claimants @
12% p.a. on the sums awarded hereinabove
commencing on four weeks from the date of this
Award till actual payment made by the Respondent.”

13. The learned Single Judge in a petition under Section 34

of the Arbitration Act had set aside the Arbitral Award. The

Division Bench by the impugned judgment upheld the

dismissal of L&T’s counter-claim. The Division Bench upheld

the findings of the Arbitral Tribunal that the Supplementary

Agreement was a non-starter as it was vitiated by economic

duress. The Division Bench also upheld the Arbitral

Tribunal’s finding that the Development Agreement was not

novated by the Supplementary Agreement. Division Bench

also upheld the Tribunal’s finding that conditions to be

fulfilled by L&T, subject to which the Supplementary

Agreement was to come into force, were not fulfilled. However,

the Tribunal’s quantification of damages for breach of

contract, amounting to a sum of Rs. 35 crores, and

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 13 of 72
compensation in lieu of securing title deeds with respect to 15

acres of land, amounting to Rs. 75 crores, as well as

compensation for default in returning licences and permits,

amounting to Rs. 5 crores, was set aside. The permanent

injunction granted in favour of PCL, restraining L&T from

interfering with PCL’s development of the Schedule ‘A’

property under the Development Agreement, was upheld.

Even the relief granted of indemnification in favour of PCL for

ITCREF’s claim was set aside without prejudice to the

indemnification for ITCREF’s claim relating to the transfer of

2,20,416 sq. ft of land to the extent envisaged under the

Development Agreement. The Division Bench upheld the

Arbitral Tribunal’s order to the extent that it awarded the cost

of arbitration to PCL. The title deeds deposited with the

Registrar of the High Court were ordered to be released to

PCL. In the light of the above directions and conclusions, the

parties were allowed to pursue their appropriate course of

action. The Division Bench allowed three appeals preferred by

PCL in part and dismissed the appeal preferred by L&T. Both

PCL and L&T, aggrieved by the Division Bench’s decision,

preferred the present Civil Appeals.

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 14 of 72
SUBMISSIONS

14. Very detailed submissions have been made on behalf of

both parties. We are reproducing the gist of the submissions

made by the counsel appearing for the parties.

15. Learned senior counsel appearing on behalf of L&T has

made detailed submissions after inviting our attention to the

findings recorded by the Arbitral Tribunal and by the courts

under Sections 34 and 37 of the Arbitration Act. The learned

senior counsel submitted that though Division Bench of the

High Court has referred to the decision of this court in the

case of Project Director, National Highways No. 45 E and

220, National Highways Authority of India v. M. Hakeem

and Another1, which holds that the court dealing with a

petition under Section 34 cannot modify the award, the

Division Bench purported to modify the award. He submitted

that it is not permissible for the court to uphold a part of the

award and remand the remaining part back to the Tribunal.

He submitted that the decision of the Division Bench is akin

to setting aside the decree for upholding judgment. He

submitted that the reasoning in the award and its operative

1 (2021) 9 SCC 1

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 15 of 72
part are intrinsically linked and the same cannot be severed.

Moreover, this is not a case where there are distinct and

severable claims. He submitted that the effect of the

impugned judgment of the Division Bench is that PCL would

get a chance to improve upon the pleadings by initiating fresh

arbitration before the Tribunal. But, L&T’s doors would be

closed for a fresh adjudication in view of the findings rendered

in the award.

16. According to the learned senior counsel, the Division

Bench has set aside the award directing payment of Rs. 35

crores as damages to PCL. He pointed out that the award

contains a direction to L&T to settle the claim of the Bank by

repayment of the loan of Rs. 6 crores and to secure release of

the title deeds from the Bank; in default, L&T was directed to

pay PCL a sum of Rs. 75 crores. The first part of the relief for

payment of Rs. 6 crores has been upheld by the Division

Bench, but the portion of the award in respect of Rs. 75

crores has been set aside. The award contains a direction

against L&T to return licences, permits and permissions

obtained by PCL from statutory authorities in respect of the

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 16 of 72
lands. On failure to return the documents, L&T was directed

to pay Rs. 5 crores to PCL. However, the Division Bench has

upheld the award directing return of the documents, but has

rejected the award to the extent of payment of Rs. 5 crores.

Moreover, an award-granting injunction against L&T from

interfering in any manner with the rights of PCL to develop

the property has been upheld. The award directed L&T to

indemnify PCL for any action, decree, or settlement to be

enforced by ITCREF or, in lieu thereof, to pay to PCL Rs. 50

crores. The Division Bench has set aside this part of the

award in its entirety. There was an order of costs of

arbitration to the tune of Rs. 30 lakhs in favour of PCL, which

has been confirmed. He submitted that, in fact, no licences,

permits, or permissions obtained from statutory authorities

were in possession of L&T. Moreover, the award in favour of

the Bank is perverse as L&T has sought specific performance

of the contract; there was no need to grant an injunction.

17. Now, coming to the interplay between the Development

Agreement, Supplementary Agreement and the Tripartite

Agreement, he submitted that the rights and obligations of

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 17 of 72
the parties under the said agreements have been decided by

the Arbitral Tribunal without recording reasons. He

submitted that even PCL admitted that the conditions

contained in Sub-clauses (a) to (d) of Clause I of the

Supplementary Agreement were conditions precedent.

However, the Tribunal misread the plain terms of the

Supplementary Agreement contrary to the pleadings and

without assigning any reason, has held that conditions

precedent in Clauses (I), (II) and (III) of the Supplementary

Agreement have not been fulfilled and therefore, the

Supplementary Agreement was a non-starter. He relied upon

the decision of this Court in the case of Dyna Technologies

Private Limited v. Crompton Greaves Limited2.

18. The learned senior counsel further submitted that in

Section 34 proceedings, reasons cannot be supplanted to the

reasons recorded in the award. He invited our attention to

sub-clauses (a) to (d) of Clause I of the Supplementary

Agreement. His submission is that the terms of the

Supplementary Agreement were totally disregarded by the

Tribunal and relied on the original terms of the Development

2 (2019) 20 SCC 1

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 18 of 72
Agreement. He submitted that the award is vitiated due to

lack of reasons. He submitted that the award made was

contrary to the pleadings. The learned senior counsel invited

our attention to the findings of the learned Single Judge in a

petition under Section 34. He submitted that the Division

Bench supplanted its own reasons to uphold the award.

Further, the Division Bench tried to rewrite the contract by

including other clauses as conditions precedent. His

submission is that the Tribunal mixed up various unrelated

issues with issue no. 2 which pertains to economic coercion.

He submitted that the entire focus was on the alleged breach

committed by L&T of the Development Agreement and

abandonment of the site. Unreasoned finding has been given

that the Supplementary Agreement and the Tripartite

Agreement were entered under compulsion. The Tribunal

failed to note that in the Statement of Claim as well as in the

rejoinder filed by PCL, there was assertion regarding the

binding nature of the Supplementary Agreement. One Mr.

Mohinder Puri on behalf of PCL filed an affidavit which was

not only beyond the pleadings, but also contrary to the same

as he, for the first time, alleges exercise of coercion to enter

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 19 of 72
into Supplementary Agreement. Learned counsel relied upon

several documents to show that there was no coercion and

submitted that the Tribunal ignored the documents. He

would, therefore, submit that the award was vitiated in view of

Section 28(1)(a) of the Arbitration Act. He relied upon a

decision of this Court in the case of Associate Builders v.

Delhi Development Authority3. Learned counsel submitted

that the view taken by the Tribunal is not even a plausible

view.

19. Learned senior counsel submitted that a finding was

recorded by the learned Single Judge in the Section 34

petition that the Arbitral Tribunal could not have ignored all

the correspondence and evidence showing why the

Supplementary Agreement was signed. The learned Single

Judge held that the award was self-contradictory and the

findings were mutually destructive inasmuch as while holding

that the Supplementary Agreement was entered into by

compulsion, the Tribunal, thereafter, purported to enforce the

Tripartite Agreement. Learned senior counsel pointed out that

the Division Bench rejected the objection of L&T that the plea

3 (2015) 3 SCC 49

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 20 of 72
of coercion was not taken by holding that the Statement of

Claim is not specific on the point of coercion, but the plea

taken in paragraph 136(5)(a) of the Statement of Claim can be

deemed sufficient. In fact, what is quoted was part of PCL’s

letter dated 18th December, 2000, in response to L&T’s letter

dated 10th July, 2000. It was urged that the above allegation

has nothing to do with economic coercion to compel PCL to

enter into Supplementary Agreement. It is submitted that

Division Bench has supplied reasons to justify the award

which reasons were not there in the award itself. In fact, the

Division Bench went to the extent of converting the plea of

coercion into undue influence even when there was no

pleading to that effect.

20. The Arbitral Tribunal has rendered a contradictory

finding that the Supplementary Agreement was not operative,

but, L&T cannot be relieved of its obligations under the

Tripartite Agreement and thus, is bound to pay the Bank.

Learned counsel reiterated that the Tripartite Agreement

flows from the Supplementary Agreement. He pointed out that

the Arbitral Tribunal held that L&T was bound by the

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 21 of 72
Tripartite Agreement and at the same time observed that the

Supplementary Agreement and the Tripartite Agreement were

signed by PCL under compulsion and in dire need of funding

of EDC payment. He submitted that the learned Single Judge

has rightly held that when the Supplementary Agreement was

a non-starter, as per the Tribunal, no relief could have been

granted under the Tripartite Agreement. Unfortunately, this

argument has not been dealt with by the Division Bench.

21. He invited our attention to Clause 26 of the

Development Agreement which provided that L&T was entitled

to extension of time for completing the construction in case of

adverse market conditions. As per Clause 34, L&T could not

be treated in default of performance of its obligation if it is

delayed or prevented due to adverse market conditions. He

submitted that there were enough documents on record to

show that land prices were falling and prevailing market

conditions did not encourage development of land. He

submitted that though there was a specific pleading to that

effect, the Arbitral Tribunal did not record any finding in the

award with regard to the market conditions and in fact,

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 22 of 72
Clauses 26 and 34 of the Development Agreement have been

completely ignored. However, the learned Single Judge noticed

that there was material on record with respect to the fall in

real estate market and held that Arbitrator could not have

ignored all those correspondences and evidence showing why

the Supplementary Agreement was signed. The Division

Bench recorded the submission that the Tribunal has ignored

Clauses 26 and 34 of the Development Agreement, but, has

not dealt with the submission and tried to supply its own

reasons which were not found in the award. Thus, the

Division Bench acted beyond the scope of Section 37 of the

Arbitration Act.

22. The Arbitral Tribunal committed an error by directing

L&T to make payment to the Bank on the ground that L&T

cannot be relieved of its obligation to the Bank under the

Tripartite Agreement. It is submitted that the Bank was not a

party to the proceedings and therefore, the claim by the Bank

was not before the Arbitral Tribunal. In fact, in the affidavit in

lieu of evidence filed by PCL, it was contended that the Bank

is a third party and any action by the Bank can be tried only

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 23 of 72
by the Debt Recovery Tribunal. Therefore, the submission is

that the award in favour of the Bank is vitiated under Section

28(1)(a)(iv). He submitted that the said argument of L&T was

accepted by the learned Single Judge on the ground that the

Bank was not a party before the Tribunal and the Tripartite

Agreement did not have an arbitration clause. On this aspect,

he pointed out the finding of the Division Bench that the

principal amount of Rs. 6 crores with interest was an amount

payable by L&T to the bank under the Development

Agreement. He submitted that, in fact, the said obligation can

be read only in the Tripartite Agreement.

23. Learned senior counsel submitted that L&T has suffered

a loss of Rs. 5.44 crores towards EDC. Though, the Tribunal

had noted that the EDC payment would normally be

reimbursed, but it failed to offset the same. Learned counsel

pointed out that the sum of Rs. 8.10 crores was deposited

under an interim order dated 24 th January, 2003 passed by

the learned Single Judge in Section 34 petition subject to the

outcome of the proceedings. An application for restitution was

filed by L&T in Section 34 proceedings. By order dated 8 th

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 24 of 72
January, 2011, it was directed to be listed along with the

appeal before the Division Bench. However, the Division

Bench has not dealt with the same. A prayer was made that

L&T may be permitted to file an appropriate application for

restitution before the High Court.

24. The submission of the learned senior counsel is that the

order of the learned Single Judge in the Section 34 petition

deserves to be upheld.

25. The learned senior counsel appearing for PCL pointed

out that basically two issues arise for consideration. The first

is whether there was a breach committed by L&T as held by

the Arbitral Tribunal, and the second question is whether, if

the finding of breach committed by L&T is upheld, the finding

of the Arbitral Tribunal regarding damages can be revived.

26. The learned senior counsel submitted that the scope of

interference in a petition under Section 34 of the Arbitration

Act is now well settled. He relied upon a decision of this Court

in the case of S.V. Samudram v. State of Karnataka and

Another4. If the Arbitral Tribunal’s view is a plausible view, it

4 (2024) 3 SCC 623

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 25 of 72
ought not be interfered with. To arrive at a decision as to

whether a plausible view has been taken, the court would

consider whether the Arbitrator has considered the material

forming part of the record and arrived at a plausible view in

an overall sense and not expect the Arbitrator to deal with the

matter and render a judgment with the detailed reasoning as

is normally found in decisions of the civil courts.

27. Learned senior counsel submitted that to examine the

award in supervisory jurisdiction under Section 34 of the

Arbitration Act, the court must be cautious and should defer

to the view taken by the Arbitral Tribunal even if the

reasoning provided in the award is implied. If the reasons

recorded by the Arbitral Tribunal are intelligible, the award

cannot be set aside just because there were gaps in the

reasoning of conclusions reached by the Arbitral Tribunal.

The submission is that the award of the Arbitral Tribunal in

the present case is intelligible and contains adequate reasons.

He pointed out several findings recorded by the Arbitral

Tribunal with reasons.

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 26 of 72

28. He submitted that L&T’s submission that Clause 26

read with Clause 34 of the Development Agreement permitted

it to seek extension of time is wholly misplaced considering

the fact that L&T abandoned the project because a decision

was taken by L&T to do so. Only in case L&T had paid EDC

and there was no risk of losing the licences, L&T could have

invoked Clauses 26 and 34 of the Development Agreement for

delayed completion of construction. Admittedly, no request

was made by L&T for the grant of extension of time for

completing the construction with the undertaking of making

payment of EDC in terms of Clauses 19 and 25 of the

Development Agreement, which were never modified. Learned

senior counsel submitted that L&T was holding title deeds in

relation to 25 acres of land and did not return the title deeds.

The title deeds in respect of the remaining 15 acres of land

were with the Bank for securing the loan availed for payment

of EDC. The payment of EDC was the liability of L&T as per

the Development Agreement. He also pointed out that L&T did

not lead any of the evidence. The stand of L&T in

considerations of the overall findings of the learned Tribunal

on breach of contract, abandonment etc. is completely out of

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 27 of 72
place and without any basis. In fact, no issues were framed

on the basis of Clauses 26 and 34 of the Development

Agreement.

29. The conditions precedent in the Supplementary

Agreement may be read with their true intent and purport.

Condition precedent no.1 also contains the binding nature of

the Development Agreement, except as agreed otherwise.

Under the Supplementary Agreement, payment of EDC, as

per Clause 19 read with Clause 27 of the Development

Agreement, was continued. The developer was liable to pay

EDC over a period of 18 months in terms of the licence.

Condition precedent no. 1(a) expressly requisited the

‘replacing or taking over’ of the bank guarantee furnished by

PCL. He pointed out the letter dated 15 th March, 2000,

addressed by PCL to the Bank, where the request was made

to continue with the bank guarantee of PCL. However, at the

same time, the request was made to the bank to forthwith

release the margin money of PCL. Learned counsel submitted

that L&T has made a false statement on oath that the bank

guarantee of PCL, with margin money and interest, was

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 28 of 72
released. Altogether, a new case was made out by L&T before

this court, as it was not pleaded before the Tribunal that the

margin money had been refunded and bank guarantees had

been released. In fact, PCL by letter dated 12 th April, 2000

reminded L&T that fresh bank guarantees were to be served

as PCL’s guarantee was not released. According to the specific

pleading of PCL in the Statement of Claims, a condition

precedent for the coming into effect of the said agreement was

replacing and taking over the bank guarantee. In the

Statement of defence-cum-counterclaim of L&T, it was claimed

that L&T had executed a counter bank guarantee. It was

submitted that attributing insufficient reasons in relation to

non-satisfaction of the condition precedent of the

Supplementary Agreement is incorrect. On 07 th October,

1999, L&T had taken a clear stand that the report submitted

by the consultant was not favourable to pursue the project

and hence, they shall not pay EDC. Reliance was placed by

learned counsel on the Statement of Claims of L&T. He invited

our attention to the fact that on 26 th October, 1999, PCL was

again constrained to put L&T on notice that there were

serious defaults of the terms of licences and the Development

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 29 of 72
Agreement. It was submitted that L&T was in possession of

title deeds of area of 25 acres from 15 th and 16th October,

1998. A submission was made that there were sufficient facts

pleaded in the pleadings to show coercion. He submitted that

non-payment of EDC as per Clause 19(b) of the Development

Agreement led to issuance of notice for cancellation of licences

of PCL. In the letter dated 07th October, 1999, L&T had taken

a clear stand that they will not pay EDC. Initially, on 8 th

December, 1998, L&T’s stand was that it was their

responsibility to pay EDC from 01 st July, 1998. Thereafter, a

stand was taken on 02nd April, 1999 that they will pay EDC

only after launch of the project. L&T did not pay Rs. 5 crores

refundable advance to PCL. L&T instructed PCL not to collect

any cheque and on 08th April, 1999, L&T internally instructed

to demobilize resources from the site. The title deeds were in

possession of L&T and the same was pleaded in the

Statement of Claims. Learned counsel submitted that these

all facts constituted coercion. He also pointed out that with

the consent of the parties, the issue was framed on the plea of

coercion being an issue no. 2, and in fact, L&T accepted that

there could be no grievance with the procedure followed by

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 30 of 72
the Arbitral Tribunal in framing issues. In fact, in the final

submission before the Arbitral Tribunal, L&T admitted that

the plea of economic duress was pleaded by PCL by pointing

out that the Supplementary Agreement was signed out of

economic duress and coercion.

30. He submitted that on the question whether the

condition precedent for the Supplementary Agreement was

satisfied, L&T did not lead evidence and evidence of PCL

remained uncontroverted.

31. As regards the contention that the relief granted in the

award was beyond the jurisdiction, learned counsel submitted

that the arbitration clause in the Development Agreement

even covered disputes in connection with the agreement. In

fact, the Supplementary Agreement refers to the fact that

parties to the Development Agreement have agreed to enter

into a tripartite agreement with the Bank. In turn, the

tripartite agreement records that L&T and PCL had entered

into Development Agreement on 10th March 1998. The notice

invoking the arbitration clause refers to the three agreements,

and even in the petition filed under Section 11 of the

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 31 of 72
Arbitration Act, the disputes were set out in relation to the

three agreements. By consent of the parties, vide order dated

14th February, 2001, the disputes in relation to all three

agreements, including the determination of the liability of

ITCREF and the Bank, were referred to the Arbitral Tribunal.

Before the Arbitral Tribunal, L&T took the stand that it was

its liability to ensure payment to the Bank. Also, L&T took a

stand through its counsel that the obligation was cast upon

L&T with respect to the liability of ITCREF. Moreover, L&T did

not take recourse to Section 16 of the Arbitration Act for

challenging the jurisdiction of the Arbitral Tribunal.

32. Learned senior counsel pointed out the issues framed by

the Tribunal concerning damages and compensation. He

submitted that perusal of L&T’s Statement of Defence shows

that the parties were ad idem on the question of valuation at

which sales could be made as L&T had itself based the claim

for damages on such valuation. As regards valuation, the

Tribunal considered the evidence of Shri Mohinder Puri

adduced on behalf of PCL. Therefore, the Tribunal relied upon

agreed valuation based on L&T’s demands in its counter-claim

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 32 of 72
as a reasonable estimate of the loss suffered by PCL. L&T had

pleaded that they were entitled to 75% of the total constructed

area while PCL was entitled to 25%. In fact, the Arbitral

Tribunal used L&T’s computation of loss of profit made by

L&T at Rs. 280 crores as the basis to arrive at PCL’s loss of

profit as Rs. 93 crores. In fact, the estimate of loss caused to

PCL was taken at Rs. 93 crores, which is on the lower side.

After considering the fact that ITCREF had initiated action to

forfeit licenses, the Tribunal reduced the amount awarded as

damages to Rs. 35 crores. Therefore, the findings recorded by

the Tribunal on this behalf are reasonable. Learned counsel

submitted that the Division Bench ought not to have set aside

the Tribunal’s findings on damages awarded to PCL. This was

not a case of no evidence before the Tribunal. The basis of

damages was L&T’s own valuation of the built-up space.

Evidence of Shri Mahendra Puri had gone unchallenged. As

the damages granted to PCL were based on evidence on

record, the said finding should not have been interfered with

in a petition under Section 34 or in an appeal under Section

37 of the Arbitration Act. He submitted that in view of the

decision of this Court in the case of Associate Builders v.

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 33 of 72
Delhi Development Authority3
, incorrect quantification of

damages by the Arbitral Tribunal will not be covered by either

“patent illegality” or “violation of public policy”. Even as

regards the indemnity in favour of ITCREF, the concerned

issue was issue no. 10 before the Tribunal on which detailed

statements were made and findings were recorded by the

Arbitral Tribunal based on the appreciation of the evidence on

record. The finding of the Division Bench that L&T’s

obligation to indemnify was only in terms of the built-up

space is wholly incorrect. Learned senior counsel pointed out

that on one hand, there was non-payment of EDC by L&T, on

the other hand, there were repeated notices sent by DTCP for

cancellation of licences. Moreover, ITCREF had filed a civil

suit in the District Court seeking recovery of rupees 73 crores

plus interest against PCL and also against L&T. In addition to

all this, L&T was holding title deeds of 25 acres of licensed

land of PCL and 15 acres of PCL’s licensed land with the Bank

for which the Bank had invoked securitization laws and also

filed proceedings before the Debt Recovery Tribunal. During

the Arbitral proceedings, L&T always resisted returning the

title deeds in respect of 25 acres of land. Therefore, the

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 34 of 72
argument that the land remained with PCL has no relevance

at all.

33. Lastly, it was submitted that the dispute between the

parties was of the year 2000. The award was made on 28th

December, 2002, after a very detailed hearing before the

Tribunal. Thereafter, the dispute remained sub-judice

continuously before the courts. Therefore, considering the

findings of the Tribunal, as upheld by the Division Bench,

this court will consider exercising extraordinary powers to do

complete justice. Therefore, appeals preferred by L&T may be

dismissed, and PCL may be compensated for the huge legal

expenditure incurred during the last 21 years. It was

submitted that the appeal preferred by PCL be allowed while

upholding the damages and compensation awarded by the

Arbitral Tribunal in terms of the award.

ISSUES FRAMED BY THE ARBITRAL TRIBUNAL

34. The Arbitral Tribunal framed 14 issues which read thus:

Issue No. 1: Whether the Development Agreement dated

10.03.1998 entered into between the Respondent and the

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 35 of 72
Claimants is binding on the parties or the same stand

novated by the Supplementary Agreement dated 30.12.1999?

Issue No. 2: Whether the Supplementary Agreement

dated 30.12.1999 and the Tripartite Agreement dated

10.01.2000 were tainted by coercion and economic duress on

the claimants? If not, whether the claimants and the

Respondent performed respective obligations according to

tenor and terms of the Supplementary Agreement dated

30.12.1999 and the Tripartite Agreement dated 10.01.2000?

Issue No. 3: Whether the Claimants committed breaches

of the fundamental terms of the Development Agreement

dated 10.03.1998 to enable the Respondent to resile from the

agreement of development?

Issue No. 4: Whether the respondent’s Board of directors

in pursuance of reports of Boston Consulting Group (for short

‘BCG’). Richard Ellis and Jones Lang La Salle decide to down-

size/exit the business of real estate development and not to

pay EDC or commence development work?

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 36 of 72
Issue No. 5: Whether there had been non provisions of

security of the development site and unprovoked unilateral

abandonment of the site by L&T. If so whether such actions

had resulted in encroachments causing monetary loss to the

Claimants and in the event of such monetary loss caused to

the Claimants what is the extent of such loss?

Issue No. 6: Whether the Claimants entitled to terminate

the development agreement for the reasons stated in the letter

of termination dated 16.12.2000 or even otherwise?

Issue No. 7: Was the Respondent under any obligation to

commence construction in phase I for development of 3.84

Lac sq. ft. before the Claimants had confirmed

booking/selling targets as per the Supplementary Agreement

dated 30.12.1999?

Issue No. 8: Whether termination of the contract by the

Claimants amounts to wrongful repudiation and entitles

Respondent to rescind the contract and claim damages under

Section 73 and 75 of the Indian Contracts Act?

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 37 of 72
Issue No. 9: Whether the Respondent is entitled to be

relieved of its obligations under the Tripartite Agreement

dated 10.01.2000 and be put in the same position as if such

agreement had not been entered into?

Issue No. 10: Is the Respondent liable to compensate the

Claimants under the agreement of indemnity and if so what

effect?

Issue No. 11: Is the Respondent liable to be compensated

by Claimants by a sum of Rs.8,31,53,968/- including a sum

of Rs.5.19 Crores paid by the LKB as claimed by the

respondent?

Issue No. 12: Is the Respondent entitled to be

compensated by the Claimants a sum of Rs.280 Crores as net

profit being difference in the cost of construction estimated at

Rs.800/- per sq. ft. with the total cost being Rs. 320 Crores as

claimed by the respondent?

Issue No. 13: Are the Claimants entitled to compensation

from the Respondent and damages of a total values of Rs. 300

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 38 of 72
crores and are the Claimants entitled to a further sum of Rs.

100 crores as punitive damages?

Issue No. 14: Whether Mr. Mohinder Puri has the

authority to institute the instant claim petition and to carry

out acts necessary to prosecute the instant claim petition on

behalf of Claimants other than Puri Construction Limited? If

not whether the claim petition for other Claimants is

maintainable?

ARBITRAL TRIBUNAL’S AWARD

35. The Arbitral Tribunal recorded detailed findings. The

findings recorded by the Arbitral Tribunal can be summarised

as under:

Issue No. 1: The conditions precedent in Clauses (I), (II),

and (III) of the Supplementary Agreement were not fulfilled.

Therefore, the Supplementary Agreement was a non-starter,

hence, only the Development Agreement was binding on the

parties which was not novated by the Supplementary

Agreement.

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 39 of 72
Issue No. 2: The Supplementary Agreement and the

Tripartite Agreement were tainted by coercion. These

agreements were executed as PCL was in dire need of money

for making EDC payments. It was the obligation of L&T to

provide funds for payment of EDC and the Tripartite

Agreement was signed since L&T failed to provide the

requisite funds.

Issue No. 3: PCL substantially discharged its obligation

under the Development Agreement. However, by unilaterally

abandoning the project, L&T committed fundamental breach

in its obligation under the Development Agreement.

Issue No. 4: The site inspection conducted by the Arbitral

Tribunal revealed that L&T had not commenced the

development work. L&T did not lead any oral evidence and

failed to produce the relevant documents that were called

upon to be produced by the Tribunal. Thus, L&T took a

conscious decision to abandon the development, not to pay

EDC or fulfil its obligations towards statutory authorities,

ITCREF and the Bank. Therefore, monetary loss was caused

to PCL.

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 40 of 72
Issue No. 5: L&T did not fulfil its obligations under the

development agreement. L&T failed to fund the project. It also

failed to provide sufficient security arrangements at the site,

resulting in encroachment of some sites.

Issue No. 6: PCL was entitled to terminate the

Development Agreement in view of the breaches committed by

L&T as recorded in issue No. 5.

Issue No. 7: Before PCL had confirmed bookings/selling

targets as per the Supplementary Agreement, L&T was not

under an obligation to commence construction in phase 1.

The reason was that the Supplementary Agreement was not

operative and binding, and no responsibility contrary to the

Development Agreement could be fastened on L&T.

Issue No. 8: The termination of the contract by PCL does

not amount to wrongful repudiation, and it does not entitle

L&T to rescind the contract and claim damages under

Sections 73 and 75 of the Contract Act.

Issue No. 9: As the Tripartite Agreement was negated due

to L&T’s default, and since it imposes liability on L&T, it

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 41 of 72
cannot be relieved of its obligation under the Tripartite

Agreement.

Issue No. 10: L&T had complete knowledge of PCL’s

obligation to ITCREF. Under Clause 25 of the Development

Agreement, L&T was responsible for indemnifying PCL against

any loss, liability, cost, or claim that may arise against PCL

due to L&T’s failure to discharge its obligations. The

obligations under Clause 25 shall subsist even after the

termination of the Development Agreement.

Issue No. 11: As L&T had abandoned the project, it cannot

take advantage of its own wrong. Therefore, L&T is not

entitled to compensation from PCL.

Issue No. 12: The claim of Rs. 240 crores made by L&T

was negatived on the ground that L&T itself had abandoned

the project and therefore, it cannot take advantage of its own

wrong.

Issue No. 13: PCL was entitled to compensation from L&T

amounting to Rs. 93 crores in relation to its 25 percent share.

It was based on L&T’s calculation of profit for its 75 percent

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 42 of 72
share. The Tribunal observed that PCL was entitled to

damages of Rs. 35 crores in lieu of L&T’s failure to pay EDC in

a timely manner. However, it was held that PCL was not

entitled to any punitive damages.

Issue No. 14: The authority of Mr. Mohinder Puri to

institute a claim on behalf of PCL was acquiesced by L&T, as

it did not object to the affidavit filed by Mr. Puri. Moreover, Mr.

Puri supplied copies of the board resolutions of the respective

companies granting him power of attorney.

36. We have already reproduced the operative part of the

Award in paragraph 12 above.

FINDINGS RECORDED BY LEARNED SINGLE JUDGE IN
SECTION 34 PETITION

37. Now, coming to the findings recorded in a petition under

Section 34, the findings can be summarised as under:

Issue No. 1: The conditions precedent for the

Supplementary Agreement were satisfied substantially.

Clause (I) was the only condition required to be fulfilled, and

Clauses (II) and (III) were not required to be fulfilled by L&T. It

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 43 of 72
was held that the Arbitral Tribunal gave inconsistent findings

by holding that the Supplementary Agreement was a non-

starter and void. However, the Tripartite Agreement was not

found to be void, though it was entered into as a result of the

Supplementary Agreement.

Issue No. 2: Both the Supplementary Agreement and the

Tripartite Agreement were not tainted by coercion as parties

to it recognized that the market prices had gone down and it

was not advisable to launch the project. In fact, Clause 26 of

the Development Agreement stipulated that construction was

contingent upon prevailing market conditions, and parties

were permitted to rescind the contract in the event of adverse

market conditions.

Issue No. 3: It seems that no submissions were

canvassed in the petition under Section 34.

Issue No. 4: The Tribunal’s conclusion could not be

based solely on the reports of BCG; instead, the inference was

to be drawn by the Tribunal based on the actions.

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 44 of 72
Issue No. 5: The learned Single Judge did not record a

finding on this issue.

Issue No. 6: PCL was not entitled to terminate the

Development Agreement. Although PCL made a commitment

to ITCREF to provide an area of 153,500 sq. ft., it allocated

only 88,320 sq. ft. itself.

Issue Nos. 7 and 8: It appears that no submissions were

made before the learned Single Judge on these issues.

Issue No. 9: The Tribunal exceeded its jurisdiction by

directing L&T to fulfil its obligations towards the Bank. It was

held that the Bank was not a party to the proceedings and the

Tripartite Agreement did not contain any arbitration clause.

Issue Nos. 10, 11 and 12: There were no specific findings

recorded by the learned Single Judge.

Issue No. 13: PCL was not entitled to any compensation from

L&T as it had already paid the price of the land to ITCREF.

Moreover, PCL committed an area to ITCREF, which was more

than its share. PCL’s losses would arise only when ITCREF

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 45 of 72
files a suit for recovering damages for non-fulfilment of the

commitment and failing to hand over the land in due time.

FINDINGS RECORDED BY DIVISION BENCH IN SECTION
37 APPEALS

38. Now, we must consider the findings recorded by the

Division Bench in appeals under Section 37 of the Arbitration

Act.

Issue No. 1: The Division Bench relied upon the conditions

included in Clause II of the Supplementary Agreement. The

Division Bench observed that PCL had spent 17.28 crores

towards EDC out of which payment of Rs. 6 crores was made

by PCL by mortgaging 15 acres of its land. Under Clause II,

L&T was required to make good a plurality of bank guarantees

and assume responsibility for payment of EDC. However,

there was complete failure on the part of L&T to do so.

Issue No. 2: The Division Bench found that the finding of the

Tribunal that the Supplementary Agreement and the

Tripartite Agreement were tainted by coercion was correct. It

was observed that the Arbitral Tribunal rightly found that

economic duress has vitiated the Development Agreement.

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 46 of 72
Issue No. 3: The Division Bench observed that L&T has not

urged any ground with respect to rejection of its counter-claim

before the learned Single Judge.

Issue No. 4: The Division Bench agreed with the finding of

the Tribunal that L&T decided to abandon the project on the

basis of the BCG Report. The Division Bench held that the

award was well supported by evidence. Inspection conducted

by the Arbitral Tribunal showed that L&T had not even

commenced the development work. Though, PCL handed over

the title deeds to L&T on 16 th October, 1998, no progress was

made in construction by L&T. Moreover, L&T delayed the

project and was planning it till 18 th December, 1999. L&T was

fully aware about PCL’s obligation to ITCREF which was

expressly set out in the Development Agreement.

Issue No. 6: There may not be separate findings recorded by

the Division Bench, but the Division Bench, as stated earlier,

agreed that the Tribunal accepted the breaches committed by

L&T.

Issue No. 7: There is no specific finding recorded by the

Division Bench.

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 47 of 72
Issue No. 8 and 9: The Division Bench held that L&T did not

urge any ground with respect to the rejection of its counter-

claim before the learned Single Judge.

Issue No. 10: The Division Bench held that the Tribunal’s

direction to L&T to pay Rs. 50 crores to PCL on crystallization

of ITCREF’s claim deserves to be set aside. The loss suffered

by ITCREF would not be reasonably foreseeable for PCL to be

indemnified against. It was held that L&T’s failure to transfer

the built-up area would have to be accounted for under the

heading damages for the breach of the Development

Agreement by L&T.

Issue Nos. 11 and 12: The Division Bench held that L&T did

not raise any ground with respect to the rejection of its

counter-claim before the learned Single Judge.

Issue No. 13: The Division Bench held that actual loss was

not established by PCL. It was observed that after the

rejection of L&T’s counterclaim, it would be an illegality to rely

on L&T’s calculation of profit. However, the Tribunal’s finding

regarding L&T’s failure to pay EDC timely was affirmed.

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 48 of 72
Issue No. 14: It is evident that the Tribunal’s findings were

not seriously challenged.

39. We now turn to the conclusions recorded in paragraph

119 of the impugned judgment. In substance, the Division

Bench agreed with the findings recorded by the Arbitral

Tribunal that the Supplementary Agreement was a non-

starter, it was vitiated by economic duress, and that the

Development Agreement was not novated by the

Supplementary Agreement. The Division Bench also approved

the finding of the Arbitral Tribunal that L&T committed a

fundamental breach of the Development Agreement. The

Division Bench also upheld the dismissal of L&T’s

counterclaim. Furthermore, the Division Bench concluded

that the permanent injunction granted in favour of PCL was

also justified. However, the quantification of damages and

compensation, as well as indemnification for ITCREF’s claim,

was found to be contrary to the record. The net effect was that

the operative part of the award fixing the monetary liability of

L&T was set aside while leaving open the remedy of PCL for

the quantification of the monetary claim. In view of the

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 49 of 72
confirmation of findings on merits, the award regarding costs

was confirmed. But, in view of the legal position that the

award cannot be varied or modified, the Division Bench did

not restore any part of the arbitral award and held in

paragraph no. 120 that the parties are left to pursue the

appropriate course of action.

CONSIDERATION

40. Firstly, we will deal with the issue of the power of the

Court under Section 34 of partly setting aside the award. This

issue was dealt with by this Court in the case of Project

Director, National Highways No. 45 E and 220, National

Highways Authority of India v. M. Hakeem and Another 1.

This Court, in the said decision, considered its earlier

decision in the case of McDermott International Inc. v Burn

Standard Co. Ltd. & Ors. 5 Ultimately, in paragraph 42, this

Court held thus:

“42. It can therefore be said that this question
has now been settled finally by at least 3
decisions [McDermott International Inc. v. Burn
Standard Co. Ltd.
, (2006) 11 SCC 181] , [Kinnari
Mullick v. Ghanshyam Das Damani
, (2018) 11

5 (2006) 11 SCC 181

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 50 of 72
SCC 328 : (2018) 5 SCC (Civ) 106] , [Dakshin
Haryana Bijli Vitran Nigam Ltd. v. Navigant
Technologies (P) Ltd.
, (2021) 7 SCC 657] of this
Court. Even otherwise, to state that the judicial
trend appears to favour an interpretation that
would read into Section 34 a power to modify,
revise or vary the award would be to ignore the
previous law contained in the 1940 Act; as also
to ignore the fact that the 1996 Act was enacted
based on the Uncitral Model Law on
International Commercial Arbitration, 1985
which, as has been pointed out in Redfern and
Hunter on International Arbitration, makes it clear
that, given the limited judicial interference on
extremely limited grounds not dealing with the
merits of an award, the “limited remedy” under
Section 34 is coterminous with the “limited
right”, namely, either to set aside an award or
remand the matter under the circumstances
mentioned in Section 34 of the Arbitration Act,
1996.”

41. We are conscious of the fact that a larger bench is seized

with the issue of the power of the Court to modify the award

under Section 34. However, we are respectfully bound by the

decision in the case of Project Director, National Highways

No. 45 E and 220, National Highway Authority of India v.

M. Hakeem and Another1. As we have noted, after recording

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 51 of 72
its conclusions in paragraph 119, the Division bench, in the

last paragraph of the impugned Judgment, has not modified

the award.

42. We have perused the three agreements subject matter of

controversy. The Development Agreement is a contract

between PCL and L&T. Clause 4 of the Development

Agreement refers to the obligations of PCL under the

agreement entered into by it on 30 th July, 1997 with ITCREF.

It refers to the fact that PCL had agreed to hand over 1,95,000

sq. ft. of built-up area in the Schedule ‘A’ property, after its

development, comprising high-rise and low-rise buildings,

inclusive of a car park, to ITCREF. It also refers to the fact

that the extent of the built-up area to be allocated to ITCREF

was 2,20,416 sq. ft., which formed part of the allocation made

under the Development Agreement to PCL. The Development

Agreement also provides that PCL had agreed that 15 acres of

land mortgaged to the Bank would be in the remaining

portion of Schedule ‘A’ property and that PCL would get the

mortgage discharged on this 15 acres of land comprised in

Schedule ‘A’ property before commencement of development

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 52 of 72
work in the remaining portion of Schedule ‘A’ property. The

Agreement also provides for the deposit of original documents

in relation to Schedule ‘A’ property (except to the extent of 15

acres of land mortgaged with the Bank). Paragraph 19 records

L&T’s obligation to pay the EDC after receiving the NOC from

the appropriate authority. The Agreement provides that L&T

shall complete the construction of the building on the

Schedule ‘B’ property within 60 months or such mutually

extended period from the date of obtaining sanction for the

building plan, or tax clearance under Section 37-I of the

Income Tax Act, and making the said property available for

development, whichever is later. It has also stipulated that

construction shall be carried out in phases. After completion

of phase of 3,00,000 sq. ft. on Schedule ‘B’ property, L&T, in

consultation with PCL, by mutual consent, shall have the

option and liberty to renew and revise the

specifications/amenities and built-up area of the balance

development and extend the period of completion by a further

period of 12 months, depending upon the prevalent market

conditions.

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 53 of 72

43. Now, we refer to the Supplementary Agreement. In the

recital of the Supplementary Agreement, it is mentioned that

L&T has made only partial compliance with the requirement

under the Development Agreement to pay EDC to DTCP.

Moreover, L&T has failed to furnish a bank guarantee for the

balance payment of EDC. In fact, it records that L&T had

taken a stand that in view of the adverse market conditions,

the project had become unviable and sought further time

from PCL to allow the prevailing real estate market conditions

to improve. Clauses I, II and III of the Supplementary

Agreement read thus:

                      I. “That        the    terms    of   the    Development
                          Agreement          will   continue     to    bind   the

parties hereto, unless otherwise agreed to
in these presents, which shall come into
effect on happening of the following
events :

(a) DEVELOPER replacing or taking over the
Bank Guarantees furnished by the
OWNERS through their Banker to DTCP,
Haryana;

(b) Payment of EDC amounting to Rs. 6
Crore by Lord Krishna Bank to DTCP

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 54 of 72
Haryana, in terms of the Tripartite
Agreement between the parties hereto
with Lord Krishna Bank;

(c) Reimbursement of expenses incurred by
the OWNER as detailed in Annexure I, on
production of proof of payment thereof;

(d) Compliance of the terms and conditions
of the tripartite agreement between the
parties hereto with Lord Krishna Bank,
inter-alia the DEVELOPER paying Rs.

5.19 Crore to Lord Krishna Bank, on
behalf of OWNERS towards discharge of
the loan availed by the OWNERS for
payment of EDC. The said sum of Rs.

5.19 Crore shall be a secured interest free
loan by the DEVELOPER to the OWNERS.

II. The Bank Guarantees would be furnished by
the DEVELOPER to the DTCP after final
approval of term loan by Lord Krishna Bank
to the OWNER and escrow account
arrangement finalisation, either through the
Bankers of the OWNERS or any other Bank
acceptable to DTCP. The said bank
guarantees shall remain valid and in force
upto the date of receipt of completion
Certificate of the I phase of the project.

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 55 of 72
III. The parties hereto agree that the Clause 19
of the Development Agreement shall stand
modified as under:

(a) The EDC Charges of Rs. 1013.14 Lacs
paid so far by the OWNERS shall be
reimbursable only after receipt of the
same from the prospective purchasers of
the apartments in the Project.

(b) The Developer agrees to pay the balance
EDC as under:

i. Rs. 6 Crore through M/s. Lord Krishna
Bank as provided in Clause I(b) supra;

ii. Pay the remaining EDC charges over a
period of 18 months in terms of
licenses.

(c) The EDC paid by the parties shall be
reimbursable to each of the parties from
out of the sale proceeds, as agreed in the
Agreement for Development.”
(emphasis added)

44. We may note here that, as stated in Clause (I) of the

Supplementary Agreement, the terms of the Supplementary

Agreement were to come into effect upon the occurrence of the

events mentioned therein, which included the condition that

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 56 of 72
L&T would replace or take over the bank guarantees

furnished by PCL through their banker to DTCP. Other

condition was of compliance of the terms and conditions of

the Tripartite Agreement which provided for L&T paying sum

of Rs. 5.19 crores to the Bank on behalf of PCL. The Arbitral

Tribunal found that Clauses (I) and (II) were not fully complied

with by L&T. The Tribunal also found that Clause (III) was not

complied with by L&T due to non-payment of EDC charges as

provided therein. On a plain reading of these three clauses,

the learned Single Judge’s finding that Clauses (II) and (III)

were not required to be fulfilled is based on a complete

misreading of Clauses (II) and (III). The Division Bench rightly

agreed with the Tribunal that conditions included in the said

clauses were required to be complied with, but were not

complied with. The Division Bench noted that even the

Supplementary Agreement revealed that the DTCP had issued

a show-cause notice for non-payment of EDC, threatening

cancellation of licenses. Clause (I) of the Supplementary

Agreement makes it very clear that the Supplementary

Agreement shall come into effect only upon the occurrence of

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 57 of 72
the four events specified therein. That is how the

Supplementary Agreement remained a non-starter.

45. We now turn to the Tripartite Agreement, which in turn

refers to the Supplementary Agreement. It is recorded that

PCL and L&T had approached the Bank to avail a term loan of

Rs. 6 crores for payment of EDC charges. Under the said

agreement, the Bank agreed to pay Rs. 6 crores EDC to DTCP

on behalf of PCL. It was agreed that the 15 acres of land

already mortgaged by PCL with the Bank will continue to

serve as a guarantee for the said term loan of Rs. 6 crores.

The Tripartite Agreement provides that the Bank shall

forthwith release, in favour of the PCL, the counter-

guarantees outstanding for the bank guarantees given by the

Bank for a sum of Rs. 466.175 lakhs in favour of DTCP,

Haryana. It was provided in the Tripartite Agreement that

L&T will open an Escrow account with the Bank in New Delhi,

wherein all sale proceeds of the proposed flats will be

deposited. Out of the funds in the escrow account, the Bank

will first appropriate the interest part for the respective period

and out of the balance portion, appropriate 50 per cent

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 58 of 72
towards repayment of the term loan and release the remaining

50 per cent balance to L&T, subject to review on a later date.

It was provided that PCL and L&T have undertaken to launch

the sale of apartments in the Schedule ‘A’ property, covering

an area of 3.84 lakhs sq. ft., by 15th February, 2000. L&T

had also undertaken to complete the said development within

30 months of the commencement of construction. Even all

sale proceeds were to be collected by L&T and deposited with

the Bank in an escrow account. The Tripartite Agreement

provided that L&T shall pay to the Bank a sum of Rs. 5.19

crores on behalf of PCL towards discharge of the loan availed

by PCL for payment of EDC on or before 19 th January, 2000.

Lastly, it was provided that upon full set-off and/or repayment

of the term loan of Rs. 6 crores, including interest thereon,

PCL shall be relieved of its obligation under this Agreement.

46. Looking to the clauses in the Supplementary

Agreement, the finding recorded by the Tribunal that, as the

conditions precedent in the relevant clauses were not

complied with by L&T, the Supplementary Agreement was a

non-starter is undoubtedly a possible finding which could not

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 59 of 72
have been interfered with under Section 34 of the Arbitration

Act. Moreover, it is a finding of fact.

47. Coming to the issue no. 2, it is apparent from the

recitals in the Supplementary Agreement as well as Tripartite

Agreement that as L&T did not discharge its obligation under

the Development Agreement to pay EDC, the Bank was

required to be brought into the picture so that it could

advance a sum of Rs. 6 crores by way of loan for making

payment of the said amount to DTCP. We must mention here

that Clause 19 of the Development Agreement provided that

L&T shall reimburse PCL the EDC amount already paid up to

the date of the Development Agreement by mutually agreed

instalments. The amounts paid by PCL towards EDC up to

the date of execution of the Development Agreement were also

mentioned, as L&T did not pay the amount already paid by

PCL towards EDC. By Clause (III) of the Supplementary

Agreement, Clause 19 was modified. The main reason for the

execution of the Supplementary Agreement and the Tripartite

Agreement was the default on the part of L&T. The Tribunal

looked into various terms and conditions of the Development

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 60 of 72
Agreement and the obligation of L&T to carry out its activities

in a time-bound manner. The Tribunal considered the

pleadings of PCL and the failure of L&T to deny material

paragraphs. The tribunal also referred to a letter dated 7 th

October, 1999, addressed by L&T that its consultant had

reported that it would not be favourable to pursue the project

and therefore requirement of payment of EDC by L&T does not

arise. In fact, L&T relied upon the report of BCG. However, in

respect of order dated 08th November, 2001, L&T did not

produce the relevant documents. The Tribunal has noted that

L&T was aware about PCL’s financial conditions and its

obligations towards ITCREF. The Tribunal also referred to the

fact that on 02nd November, 1999, DTCP issued a show cause

notice proposing cancellation of licenses due to non-payment

of EDC. These facts and the default by L&T left no choice to

PCL but to execute the Supplementary Agreement as well as

the Tripartite Agreement.

48. The Division Bench referred to Section 16(3) of the

Contract Act which provides that where a person who is in a

position to dominate the will of another, enters into a contract

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 61 of 72
with him, and the transaction appears, on the face of it or on

the evidence adduced, to be unconscionable, the burden of

proving that there was no undue influence is on the person in

a position to dominate the will of the other. Illustrations (c)

and (d) of Section 16(3) of the Contract Act were also relied

upon, which deal with cases of economic duress and undue

influence. After examining the evidence, the Division Bench

held that there was no patent illegality in the findings

recorded by the Arbitral Tribunal that the Supplementary

Agreement and the Tripartite Agreement were tainted by

coercion. On consideration of the facts discussed before, such

a view by the Arbitral Tribunal cannot be said to be contrary

to justice and morality. We agree with the view taken by the

Division Bench.

49. Dealing with issue no. 3, the Division Bench referred to

Clause 26 of the Development Agreement and Clause 5 of the

Supplementary Agreement. The Tribunal found that L&T

committed a breach of Clause 19 of the Development

Agreement by not making payment of a single instalment of

EDC. Moreover, interest free deposit of Rs. 5 crores in terms of

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 62 of 72
Clause 12 of the Development Agreement was not paid by L&T

to PCL. The Tribunal found that there was no Development

work carried out and not a single floor of any residential

building was constructed for which development plans were

sanctioned. Therefore, the finding recorded by the Tribunal

that L&T committed fundamental breaches of the agreement

cannot be interfered within the limited jurisdiction under

Section 34 of the Arbitration Act.

50. As regards issue no. 4 and 5, the Division Bench has

considered material on record. The Division Bench recorded

that approval of the competent authority under the Income

Tax Act, 1961 was given on 30th June, 1998 and the building

plans were sanctioned on 30th September, 1998. The title

deeds were handed over by PCL to L&T on 16 th October, 1998.

There are letters on record addressed by PCL complaining to

L&T about failure to make any progress on the site. No EDC

payments were made by L&T. Even planning of the project

was not completed by L&T till December, 1999. That is how

the inspection of the Arbitral Tribunal revealed that L&T did

not commence the development work. From the recital of

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 63 of 72
clauses in the Development Agreement, it is apparent that

L&T was aware of the obligations of PCL towards ITCREF.

Considering the material on record, the Arbitral Tribunal

recorded that there was a conscious decision on the part of

L&T to abandon the development and not to fulfil its

obligations under the contract. Therefore, the Division Bench

accepted the correctness of the finding recorded by the

Tribunal that there was an abandonment of the project on the

part of L&T. The Division Bench rightly declined to find fault

with the findings recorded by the Tribunal on this aspect

based on evidence. Obviously, such conduct on the part of

L&T caused loss to PCL, which ultimately resulted in the

termination of the Development Agreement. The issues based

on the rejection of the counter-claim of L&T have been rightly

addressed by the Division Bench on the ground that there

were no submissions made on the rejection of the counter-

claim before the learned Single Judge in a petition under

Section 34 of the Arbitration Act.

51. The Division Bench dealt with the Tribunal’s direction

to L&T to pay Rs. 50 crores to PCL on crystallization of

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 64 of 72
ITCREF’s claims. The Division Bench held that the type and

kind of losses incurred by ITCREF would not be reasonably

foreseeable for PCL to be indemnified against. Therefore, the

Division Bench rightly observed that while granting a sum of

Rs. 50 crores to PCL, the Tribunal had gone overbroad. The

said finding of the Division Bench cannot be faulted with.

52. As regards the damages of the sum of Rs. 35 crores to

be paid by L&T to PCL on account of breach of the

Development Agreement, the basis taken by the Tribunal was

the figures given by L&T in its counter-claim. Mr. Mohinder

Puri estimated the loss of PCL at Rs. 117 crores. However,

PCL did not prove the said loss, and the Tribunal did not rely

upon any evidence to arrive at a fair assessment of the loss

actually incurred by PCL. The Division Bench held that

instead of basing the findings on the figures set out by L&T in

its counter-claim, the correct approach would have been to

determine the prevailing market rate for sale of built-up area

at the time of the breach and thereupon determine the

proceeds that PCL would have received from the sale of its 25

per cent share under the Development Agreement. Therefore,

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 65 of 72
the award of Rs. 35 crores as damages was fundamentally

contrary to Section 73 of the Contract Act. Such an approach

was completely contrary to substantive law in the form of

Section 73. This finding cannot be disturbed.

53. As regards the direction to pay the amount of Rs. 6

crores with interest, we need not record any finding as the

amount has been paid by L&T. The award in the alternative of

Rs. 75 crores, without proof of the value of land, cannot be

sustained at all. There was no evidence on record to indicate

that the value of the 15-acre area would be Rs. 5 crores per

acre. Similarly, there was no basis for granting Rs. 5 crores to

PCL due to L&T’s failure to return the licenses and other

statutory permits. In these circumstances, we find the view

taken by the Division Bench to be correct.

54. As the termination of the Development Agreement is

upheld, obviously, L&T cannot deal with the property in any

manner and PCL can always deal with the same.

55. In para 119, the Division Bench held thus:

                         “119.      In      the   circumstances,   the   Court
                         concludes as follows:



Civil Appeal Nos. 2575-2578 of 2016, etc.                                        Page 66 of 72
                         a. The finding of the Tribunal that the

Development Agreement was not novated by
the Supplementary Agreement is upheld;

similarly the Tribunal’s findings that the
conditions which were to be fulfilled by L&T
subject to which the said Supplementary
Agreement was to come into force (but were
not fulfilled) are upheld;

b. The finding of the Tribunal that the
Supplementary Agreement was a non-starter
as it was vitiated by economic duress is
upheld. The impugned judgment’s ruling to
the contrary is set aside.


                         c. The finding of the Tribunal that L&T
                         committed            fundamental       breach        of     the
                         Development            Agreement       is   upheld.        The

impugned judgment’s ruling to the contrary is
set aside.

                         d.     The         Tribunal’s    dismissal      of        L&T’s
                         counterclaim is upheld.

e. The Tribunal’s quantification of damages for
breach of contract (35 crores), compensation in
lieu of securing title deeds with respect to 15
acres of land (75 crores) and compensation for
default in returning licences and other permits
is set aside (5 crores). The permanent
injunction granted in favour of PCL restraining
L&T from interfering with PCL’s development

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 67 of 72
of Schedule A property of the Development
Agreement is upheld. The relief granting
indemnification in favour of PCL for ITCREF’s
claims is set aside. It is clarified that this is
without prejudice to the indemnification for
ITCREF’s claims relating to the transfer of
2,20,416 sq. ft. of land to the extent envisaged
under the Development Agreement, The
Tribunal’s order to the extent that it awards
costs of arbitration to PCL is upheld.

f. Title deeds deposited with the Registrar of
this Court pursuant to the directions in FAO
319/2001 are directed to be released to PCL.”

56. The powers of the Appellate Court under Section 37 of

the Arbitration Act are not broader than those of the Court

under Section 34 of the Arbitration Act. Therefore, what

cannot be done in the exercise of the powers under Section 34

cannot be done in an Appeal under Section 37. An Arbitral

Award cannot be modified. Thus, even after recording the

conclusions in paragraph no. 119, the Division Bench has not

modified the Award by partly setting aside the Judgment

under Section 34. In paragraph 121 of the Judgment, the

Division Bench held thus:

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 68 of 72

“121. In light of the above conclusions, parties
are left to pursue the appropriate course of
action under law. This Court notices that since
the dispute has been in subsistence for a
considerable period of time, an attempt may be
made at settling the claims through mediation.
FAO (OS) 21/2009, 22/2009 and 23/2009 are
partly allowed to the above extent; FAO (OS)
194/2009 is dismissed, for the same reason.”

On a conjoint reading of Paragraph 119 and 121, we find that

the remedy of PCL has been kept open to pursue appropriate

course of action under law as there cannot be a remand to the

Arbitral Tribunal for quantification of monetary claim. As the

finding of the Arbitral Tribunal regarding breaches committed

by L&T was affirmed, the Division Bench has rightly

segregated that part of the Award by which, cost of arbitration

was ordered to be paid to PCL by L&T. This part has been

severed from rest of the Award. Therefore, this part of the

Award must be complied with by L&T, if not already done. As

documents of title were deposited with the Registrar, the

direction to hand over the same to PCL cannot be faulted

with. We cannot find any fault with the operative part in

paragraph 120.

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 69 of 72

57. Before we part with Judgment, we must reproduce what

is observed by Division Bench in paragraph no. 120 with

approval:

“120. Before concluding, the court would like to
highlight – more as a post script, the prolix and
near interminable arguments which were
addressed by senior counsel on either side, who
were insistent that the arbitral records, such as
pleadings and documents, had to be examined,
and read out in court. The court unsuccessfully
entreatied them to limit oral arguments; equally
unsuccessful were attempts at ensuring that
written briefs were kept within limits. The
citation of numerous authorities on similar
propositions, and reference to factual material,
reduced an arbitration appeal (against the
decision in Section 34) to the Division Bench into
an appeal on facts, which Section 37 was clearly
not intended to be. One hopes that there is some
clarity within the legal system about the kind of
time limit to arguments in such cases, to ensure
timely disposal of appeals.”

58. We agree with the views expressed by the Division

Bench which we have quoted above. In several appeals arising

out of Sections 34 and 37 proceedings, we have noticed that

there is a tendency on the part of the senior members of the

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 70 of 72
Bar to argue as if these proceedings were regular appeals

under Section 96 of the Code of Civil Procedure, 1908 (for

short ‘CPC’). In this case, while making submissions, the

learned counsel appearing for both the parties have gone into

the minutest factual details. As the Members of the Bar are

aware of the limited jurisdiction of the Courts in proceedings

under Sections 34 and 37 of the Arbitration Act, they must

show restraint. Similarly, we observe a tendency on the part of

the Members of the Bar to rely upon a large number of

decisions, whether relevant or irrelevant, while arguing

Section 34 petitions and Section 37 appeals as well as

appeals arising therefrom. Multiple decisions are cited on the

same proposition of law. This makes hearing time-consuming.

As there are long oral arguments, the Courts permit written

submissions to be filed. That is how very long written

submissions come on record. The Courts have to devote page

after page for dealing with many submissions which ought not

be made considering the limited jurisdiction under Section 34

of the Arbitration Act. This results in very lengthy judgments.

The high monetary stakes involved in the proceedings should

not result in unnecessarily long oral submissions or bulky

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 71 of 72
written submissions. All this results in the criticism about

the arbitrations in India. Therefore, there is a need to impose

time limit on oral submissions in such cases. We cannot

forget that this Court and the High Courts have the appellate

jurisdiction in civil and criminal cases. These Courts should

be in a position to also devote sufficient time to the cases of

the common man. What we have expressed is a matter of

serious concern and introspection for everyone.

59. In view of what we have held earlier, there is no merit in

the appeals and the same are dismissed.

…………………………….J.
(Abhay S Oka)

…………………………….J.
(Pankaj Mithal)

New Delhi;

April 21, 2025.

Civil Appeal Nos. 2575-2578 of 2016, etc. Page 72 of 72

[ad_2]

Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here