2. This is an application for appointment of an arbitrator in terms of Clause
16.0 of the agreement for construction dated February 1, 2018. The
disputes arose out of termination of the agreement and also non-payment
of dues. Several demand notices have been referred to by the petitioner in
support of the contention that the services rendered by the petitioner were
accepted by the respondent, but payments in respect thereof were not
made despite demand notices. The respondent replied to the demand
notice, by a letter dated August 21, 2023, inter alia, relying on the
termination of the contract. It was contended that, upon termination of
the contract, nothing was due and payable. That apart, all the money
claims of the petitioner were allegedly barred by limitation.