M/S Kshitij Infraventures Pvt Limited vs The State Of Telangana on 29 April, 2025

0
14

Telangana High Court

M/S Kshitij Infraventures Pvt Limited vs The State Of Telangana on 29 April, 2025

Author: Nagesh Bheemapaka

Bench: Nagesh Bheemapaka

       HON'BLE SRI JUSTICE NAGESH BHEEMAPAKA

                WRIT PETITION No. 6754 OF 2024

O R D E R:

Heard Sri N. Sreedhar Reddy, learned counsel for

petitioner and learned Government Pleader for Labour on behalf

of respondents.

2. This Writ Petition is filed challenging the

proceedings in Crl.M.P.No. 1722 of 2023 on the file of Court of

Hon’ble XII Additional Metropolitan Magistrate, Hyderabad,

initiated by the 2nd respondent under Section 33-C (1) of

Industrial Disputes Act, 1947 and consequently to quash the

same by declaring them to be illegal, arbitrary and without

jurisdiction.

3. It is the case of petitioner that it came into

existence by virtue of the orders passed by this Court dated

01-09-2015 in Company Petition Nos. 175 to 178 of 2015,

whereby a Scheme of Arrangement of Demerger was sanctioned.

Under this Scheme, M/s Maheshwari Megaventures Limited was

the demerged company and M/s Kshitij Infraventures Private

Limited was the resultant entity. It is further stated that

M/s Maheshwari Megaventures Limited itself came into
2

existence by virtue of the Orders of Amalgamation passed by

this Court dated 22-03-2005 in Company Petition Nos. 201, 202

and 203 of 2004 concerning the amalgamation of M/s Ashish

Developers and Builders and M/s RKM Builders Private Limited.

It is stated that M/s Diwan Bahadur Ramgopal Mills (referred to

as ‘DBR Mills’) commenced its operations in 1920 at Tank Bund

Area in Hyderabad after entering into a lease deed with

landowners, namely Chenai family. The land in question

eventually devolved upon Mrs. Khorshed Shapoorchenai, vendor

of petitioner, pursuant to a Compromise Decree dated

20-10-1967 in Civil Suit No. 38 of 1967 instituted by Mrs. Freny

Rashid Chenai, mother-in-law of Mrs. Khorshed Shapoorchenai,

on the file of the Chief Judge, City Civil Court, Hyderabad.

It is further stated that subsequently, the mill

became financially unsustainable, was declared a sick unit

under Section 15(1) of the Sick Industrial Companies (Special

Provisions) Act, 1985, and failed to remit lease rentals to the

landowner, Mrs. Khorshed Shapoorchenai. This led to initiation

of eviction proceedings for recovery of possession and damages.

Eventually, the dispute culminated in a compromise, wherein

petitioner came to be impleaded as Plaintiff No.2 in O.S.No. 69
3

of 2003, filed for eviction and damages, and facilitated a

settlement between the original landowner and tenant DBR

Mills. Under the terms of compromise, Mrs. Khorshed

Shapoorchenai agreed to retain Acs.6.00 and relinquished her

rights over Acs.16.00 in favour of the tenant, M/s DBR Mills, in

order to amicably resolve the dispute.

It is averred that M/s DBR Mills, in turn, executed a

Development Agreement with petitioner for the development of

Acs.16.00 of the land. Further, petitioner’s predecessor,

M/s Ashish Developers and Builders, entered into an Agreement

of Sale dated 03-12-1998 with Mrs. Khorshed Shapoorchenai

for purchase of the entire extent of Acs.22.5 by paying full sale

consideration. It was based on this Agreement petitioner was

impleaded as Plaintiff No.2 in O.S.No. 69 of 2003. Petitioner

asserts that, while functioning as M/s Maheshwari

Megaventures Limited, it entered into a Development Agreement

dated 15-03-1999 with M/s DBR Mills Ltd. for development of

the land admeasuring Acs.16.00 on which mill was situated. In

consideration thereof, petitioner undertook the responsibility to

settle the monetary claims payable to workers of DBR Mills.

However, the said compromise entered into among petitioner,
4

DBR Mills and landowner Mrs. Khorshed Shapoorchenai could

not be effectuated and stood frustrated due to the conduct of

DBR Mills, rendering it null and void and incapable of being

enforced. Consequently, DBR Mills continued as a tenant at

sufferance, and the ownership of the entire leasehold property

reverted to Mrs. Khorshed Shapoorchenai.

It is also mentioned that, out of the total land

admeasuring Acs.22.00, registered conveyance deeds were

executed by Mrs. Khorshed Shapoorchenai in favour of

petitioner in respect of Acs.6.00 under Document Nos. 1349 of

2009 and 1350 of 2009, executed on 27-10-2006 and

28-10-2006 respectively. During the subsistence of the said

compromise and under the understanding among the parties,

petitioner, acting as developer of Acs.16.00 for which DBR Mills

held leasehold rights, entered into an arrangement for payment

of dues to the mill’s workmen.

It is stated that on 07-03-2017, six Workers’ Unions of

M/s DBR Mills entered into an agreement with petitioner

company, under which they undertook to pay Rs.7,00,000/-

(Rupees Seven Lakhs only) to each workman as full and final

settlement of all arrears of salary, back wages, and other dues.
5

This agreement was recorded as a Memorandum of Settlement

under Section 12(3) of the Industrial Disputes Act, 1947, and

Rule 60 of the Telangana State Industrial Disputes Rules, 1958,

and was arrived at in the presence of the Conciliation Officer.

It is stated though the said agreement was entered

into, the same cannot be construed as a valid and binding

settlement under Section 12(3) of the 1947 Act, in strict legal

terms. Petitioner contends that it is merely a Development

Agreement Holder and not the employer of the said workmen,

and hence, not amenable to proceedings under the Industrial

Disputes Act in such capacity. It is stated that prolonged

disputes were pending before various Courts involving petitioner

and management of M/s DBR Mills. It is further stated that

there was no authentication or finalization of list of workers who

were employed at the time when DBR Mills ceased operations,

and due to this reason, petitioner was unable to effect any

payments under the agreement dated 07-03-2017.

Meanwhile, some workers purportedly filed Applications before

the 2nd respondent, who, without verifying the maintainability of

the claims under the Act, issued Certificate of Recovery and

forwarded the same to the Hon’ble Court of XII Additional
6

Metropolitan Magistrate, Hyderabad, in Crl.M.P.No. 1722 of

2023, seeking to recover a sum of Rs.30,38,00,000/- from

petitioner.

4. Learned counsel for petitioner submits that a

settlement under Section 12(3) of the 1947 Act, can only be

executed between an employer and its employees/workmen in

the course of an industrial dispute and not with a third party,

such as petitioner, who is merely a Development Agreement

Holder. Therefore, it is submitted that the 2nd respondent acted

without jurisdiction in issuing Certificate of Recovery and

referring the matter under Section 33-C(1) of the Act.

It is also argued that, assuming without admitting, even if any

terms of the Agreement dated 07-03-2017 were violated, the

only remedy available to the affected parties would be to

approach the competent Civil Court for appropriate relief, and

not to invoke the coercive mechanism available under the

Industrial Disputes Act. Learned counsel draws attention of this

Court to Section 33-C(1) and contends that the said provision

does not empower the 2nd respondent to issue Recovery

Certificate against a third party who is not an employer, and

especially in the absence of a valid employer-employee
7

relationship under the Act. Section 33-C(1) of the Industrial

Disputes Act, 1947 reads as under::

” Where any money is due to a workman from an
employer under a settlement or an Award or under the provisions of
Chapter V-A, the workman himself or any other person authorized by
him in writing in this behalf or in the case of the death of the workman,
his assignee or heirs may, without prejudice to any other mode of
recovery, make an application to the appropriate Government for the
recovery of the money due to him and if the appropriate Government is
satisfied that any money is so due, it shall issue a Certificate for that
amount to the Chief Judicial Magistrate or the Chief Metropolitan
Magistrate having jurisdiction and the Chief Judicial Magistrate or the
Chief Metropolitan Magistrate, as the case may be, shall proceed to
realize the money as if it were a fine imposed by such Magistrate.

Provided that every such application shall be made within
one year from the date on which money became due to the workman
from the employer.

Provided further that any such application may be
entertained after the expiry of the said period of one year if the
appropriate Government is satisfied that the applicant had sufficient
cause for not making the application within the said period”.

Learned counsel submits that a plain reading of the

relevant provision reveals that jurisdiction of the Chief Judicial

Magistrate or the Chief Metropolitan Magistrate, as the case

may be, to recover money under the Act is circumscribed by the

existence of a due amount payable to the workman by the

employer under either a settlement or an award or under the
8

provisions of Chapter V-A of the said Act. It was contended that,

in the present case, petitioner is not the employer within the

meaning of the Act. The settlement in question is alleged to have

been entered into between the workmen unions and petitioner.

However, it is submitted that it is a development agreement

holder and does not fall within the definition of ’employer’ as per

the Act. It was further contended that Application filed by the

workmen or their representatives was made after a lapse of

more than three years from the date of the alleged settlement.

Therefore, it was urged that proceedings in Crl.M.P. No. 1722 of

2023, initiated before the Court of the Hon’ble XII Additional

Metropolitan Magistrate, Hyderabad, should have been rejected

at the threshold on the ground of limitation. It was further

contended that the Magistrate entertained the Application and

took cognizance of the matter without proper application of

mind and mechanically, issued notice to petitioner based on the

reference made by the 2nd respondent.

Learned counsel further submitted that definition of

‘industrial dispute’ under Section 2(k) and ‘settlement’ under

Section 2(p) of the 1947 Act are applicable only in cases

involving employer and employees or between employer and
9

workmen or even between workmen and workmen inter se. It

was asserted that a third party like petitioner, who is merely a

development agreement holder with no control or nexus with the

functioning of the industry, cannot be brought within the fold of

the said definitions. Therefore, it was submitted that the alleged

settlement dated 07.03.2017 between petitioner and workmen

unions cannot be treated as a settlement under the 1947 Act,

particularly not one falling under Section 12(3). Accordingly,

petitioner contends that jurisdiction exercised by the 2nd

respondent and the subsequent action of the criminal court in

Crl.M.P. No. 1722 of 2023 are wholly untenable and without

legal basis. Such a matter cannot be adjudicated under the

scheme of the Act, nor under the provisions of the Criminal

Procedure Code in the manner presently undertaken. It is thus

asserted that Crl.M.P. No. 1722 of 2023 pending before the

Hon’ble XII Additional Metropolitan Magistrate at Hyderabad is

liable to be quashed in its entirety.

Additionally, learned counsel submitted that even

assuming without admitting that any enforceable right arises

out of the agreement dated 07.03.2017, the proper remedy

available to workmen or their unions would be to seek redressal
10

under the general civil law and not through invocation of

criminal jurisdiction or proceedings under the 1947 Act. It is

not the employer and has no privity with the industrial

establishment for the purposes of attracting the applicability of

the Industrial Disputes Act, 1947. Further, it was submitted

that reference application was filed before the Court only on

10.01.2023, which is more than five years after the date of the

agreement, i.e. 07.03.2017. Therefore, it is contended that

proceedings before the Hon’ble XII Additional Metropolitan

Magistrate, Hyderabad, vide Crl.M.P. No. 1722 of 2023 are

barred by limitation and are unsustainable.

Learned counsel submits that petitioner had

already filed Writ Petitions No. 1956 and 2011 of 2024 before

this Court, challenging the order dated 22.09.2023 passed in

I.A. No. 13 of 2021 in M.P. No. 5 of 2019 and I.A. No. 12 of 2021

in M.P. No. 4 of 2019 on the file of the Additional Industrial

Tribunal-cum-Additional Labour Court, Hyderabad. In the said

order, the petitioner was directed to deposit an amount of Rs.

49,00,000/- each in both cases to the credit of the respective

proceedings. It was further brought to the notice of this Court

that upon hearing petitioner, the impugned orders were
11

suspended and writ petitions are pending final adjudication. In

addition, petitioner placed reliance on the fact that M/s DBR

Mills also filed Writ Petition No. 33361 of 2023 before the

Hon’ble High Court, in connection with the same or similar

subject matter, wherein the Hon’ble Court was pleased to grant

an interim order on 11.12.2023, directing all the parties to

maintain status quo in all respects until further orders. The

petitioner submits that the present criminal proceedings are

sought to be continued in contravention of the status quo order

granted in W.P. No. 33361 of 2023.

5. In the counter filed on behalf of the 2nd respondent,

it is stated that petitioner deliberately and willfully refrained

from impleading the management of M/s DBR Mills Limited and

the Joint Action Committee of DBR Mills, which represents six

trade unions and employees with whom petitioner had entered

into a Memorandum of Settlement under Section 12(3) of the

Industrial Disputes Act, 1947. On this ground, the

maintainability of the writ petition is questioned.

It is further stated that petitioner executed a

Memorandum of Settlement on behalf of the management of

M/s DBR Mills Limited, pursuant to the Development
12

Agreement dated 15-03-1999, which was entered into in favour

of M/s Ashish Developers and Builders Private Limited. This

entity was later merged with M/s Maheswari Megaventures

Limited by virtue of the orders of the Hon’ble High Court dated

22-03-2005 in Company Petition Nos. 201, 202, and 203 of

2004, and is presently known as M/s Kshitij Infraventures

Private Limited, i.e., the present petitioner. According to the

terms of the said agreement, before any development activities

could be initiated, the claims of the workers were to be settled

either by the management of DBR Mills or by the developer. In

the event that the developer settled the claims, it would be done

in the account of M/s DBR Mills Limited.

The counter further avers that, in accordance with the terms of

the Development Agreement and having regard to the prolonged

suffering of the workers due to pending litigation,

M/s Maheswari Megaventures Limited (now M/s Kshitij

Infraventures Pvt. Ltd.), by virtue of the said agreement dated

15-03-1999, had given an undertaking to the Commissioner of

Labour to settle the workers’ claims subject to mutually agreed

terms and conditions.

13

It is asserted that out of a total extent of Acs. 26.00

possessed by DBR Mills Limited, an extent of Acs. 6.00 of land

fell to the share of M/s Maheswari Megaventures Limited, now

M/s Kshitij Infraventures Pvt. Ltd., by virtue of a compromise

that attained finality before the Hon’ble Supreme Court.

Petitioner acquired absolute rights of ownership and possession

over the said land and is free to deal with it. When petitioner

commenced development works over this land, objections were

raised by the Joint Action Committee representing various trade

unions and workers which led to law and order issues and

demands for settlement in accordance with the Development

Agreement. To avoid further litigation, petitioner entered into a

Memorandum of Settlement under Section 12(3) read with Rule

60 of the Telangana State Industrial Disputes Rules, 1958. The

management of DBR Mills then filed Writ Petition No. 33361 of

2023 to quash Crl.M.P.No.1722 of 2023 and upon failing to

obtain relief, colluded with petitioner to file the present Writ

Petition to avoid compliance with the workers’ settlement.

Hence, the 2nd respondent contends that Writ Petition is liable

to be dismissed as devoid of merit.

14

The 2nd respondent further states that in view of the

terms of the Development Agreement and continuing suffering

of workers due to the prolonged litigation, M/s Kshitij

Infraventures Pvt. Ltd. informed the Commissioner of Labour of

their undertaking to settle the claims of the workers of DBR

Mills Ltd. subject to mutually agreed terms. Therefore, they

cannot now deny its joint and several liability and responsibility

on account of the management’s failure to fulfil its obligations.

The counter also details that land bearing Survey Nos. 157/1 to

3, 158/1 & 2, 159/1, 28, 160/1 to 28, and 161/3 to 7,

measuring Acs. 34.00, situated at Elchiguda, Bakaram Village,

had fallen to the share of Mrs. Khorshed Shapoor Chenoy by

virtue of a compromise decree dated 20-10-1967 in O.S. No. 38

of 1967 on the file of the Chief Judge, City Civil Court,

Hyderabad. It is further stated that prior to the said compromise

decree, an extent of 26 acres forming part of these survey

numbers was leased to M/s DBR Mills Ltd. under a lease deed

dated 17th Aban 1328 Fasli (corresponding to the year 1918

A.D.). In 1994, M/s DBR Mills stopped paying rents and claimed

ownership under the Inams Abolition Act, prompting Mrs. K.S.
15

Chenoy to file O.S. No. 1201 of 1995 for eviction and damages.

During pendency of the suit, Mrs. Chenoy entered into an

agreement of sale dated 03-12-1998 with M/s Ashish

Developers and Builders Pvt. Ltd., which was subsequently

merged with M/s Maheswari Megaventures Ltd. under orders of

this Court dated 22-03-2005 in C.P. Nos. 201, 202, and 203 of

2004. The said company then came on record as plaintiff No. 2

in the eviction suit. The counter further narrates that after

prolonged litigation, the issue relating to mill land attained

finality upon dismissal of SLP Nos. 13630-13633/2005 and SLP

No. 19446/2005 by the Hon’ble Supreme Court. Thereafter,

Mrs. Chenoy executed two registered documents conveying 6

acres of land in favour of M/s Maheswari Megaventures Ltd.

through Document Nos. 1349/2009 dated 27-10-2006 and

1350/2009 dated 28-10-2006. One of the conditions (Condition

No. 26) of these documents specifically states that the second

party (the developer) will settle and compromise with the

landlady, and this compromise was filed on 17-03-1999. These

documents were registered pursuant to the directions in Writ

Petition No. 25181 of 2005 dated 01-02-2007 and Contempt

Case No. 829 of 2009 dated 08-04-2009. Accordingly, in respect
16

of this 6-acre land, M/s Maheswari Megaventures Ltd. (now M/s

Kshitij Infraventures Pvt. Ltd.) possesses absolute rights of

ownership and possession and is free to deal with the same.

It is finally stated that pursuant to the offer made by M/s

Maheswari Megaventures Ltd., which was accepted by the

workers of the erstwhile DBR Mills Ltd. in the presence of all

parties and their representatives, a statutory settlement was

recorded under Section 12(3) of the Industrial Disputes Act,

1947, on mutually agreed terms and conditions in order to bring

about a fair and amicable resolution of the longstanding

dispute.

It is stated in the counter that although petitioner is

a party to the Certificate for Recovery Amount, which stems

from a Statutory Agreement and is binding on him, the

employees originally belonging to M/s DBR Mills Limited were

treated as the employees of petitioner. This treatment formed

the basis for execution of a Memorandum of Settlement. The

said settlement continued the employer-employee relationship

until final settlement of dues was made in full. Petitioner had

stepped into the picture by virtue of the Development Agreement

with M/s Ashish Developers and Builders Private Limited, a
17

company that was subsequently merged into M/s Maheshwari

Megaventures Limited, which has since changed its name and is

now known as Kshitij Infraventures Private Limited, writ

petitioner. The counter further clarifies that one of the clauses

in the said Development Agreement expressly allowed

M/s Ashish Developers and Builders Private Limited the liberty

to enter into any Statutory Agreements required for the smooth

operation and completion of the project.

Following completion of the project, the procedure

for recovery of fine amounts imposed by Criminal Courts is

governed by Section 421(1) of the Criminal Procedure Code

which mandates that Court shall issue a warrant for levy of

such amounts by attachment and sale of any immovable

property belonging to the offender. All parties who have a share

or interest in the said property are to be made parties to the

proceedings to the extent of their respective shares. In this

context, the execution of the Memorandum of Settlement with

the Joint Action Committee of M/s DBR Mills Limited was done

in good faith and in conformity with statutory procedure.

Petitioner, as per the counter, is bound to honour the same and

complete all pending and remaining transactions.
18

            The        counter   further     states   that   as    the

Memorandum        of   Settlement    dated   07-03-201       was   not

implemented in its entirety, the competent authority, i.e., the

Conciliation Officer under the Industrial Disputes Act, 1947,

who also holds the post of Joint Commissioner of Labour, Twin

Cities, was within his statutory right to issue a Certificate of

Recovery. Accordingly, the said matter was referred to the Court

of the XII Additional Metropolitan Magistrate, Hyderabad, under

Section 33C(1) of the Industrial Disputes Act, for effectuating

the terms of the Memorandum of Settlement dated 07-03-201.

Petitioner is under a continuing obligation to settle the dues of

workers, as per the terms of the Memorandum of Settlement.

While full payments have been made to some workers, balance

amounts are yet to be paid to others.

6. In the reply filed by petitioner, it is denied that

rights of management of M/s DBR Mills Limited or the Joint

Action Committee representing six trade unions would be

affected by any order in the writ petition, as they were not

parties to the criminal proceedings initiated by the second

respondent. It is stated, it became the owner of Acs.6.00 of land

through a registered sale deed executed by Mrs. Khorshed
19

Shapoor Chenai, pursuant to orders from this Court in Writ

Petition No. 25181 of 2006 and Contempt Case No. 1344 of

2007. Petitioner asserts that it did not step into the shoes of

M/s DBR Mills Limited and acquired the land independently,

and any settlement with labour unions could only be enforced

through a Civil Court, not under Section 12(3) of the Industrial

Disputes Act. Additionally, M/s DBR Mills Limited filed

objections before the Joint Commissioner of Labour, stating that

petitioner had no rights to settle workers’ dues. Petitioner

argues that any settlement entered into with labour unions

cannot be treated as a settlement under the Industrial Disputes

Act, and the 2nd respondent lacks jurisdiction to invoke Section

33C(1) based on such a settlement.

7. The key issue in this writ petition is whether

petitioner, as a development agreement holder, can be held

liable for the workers’ claims under the Industrial Disputes Act,

1947, and whether the 2nd respondent acted within its

jurisdiction in issuing the Certificate of Recovery under Section

33-C(1).

8. The record discloses that petitioner entered into a

Memorandum of Settlement dated 07-03-2017 with the six
20

registered workers’ unions of M/s DBR Mills Limited in the

presence of the Conciliation Officer, under Section 12(3) of the

1947 Act and Rule 60 of the Telangana State Industrial

Disputes Rules, 1958. A settlement arrived at during

conciliation proceedings before a Conciliation Officer in terms of

Section 12(3) is binding not only on the parties to the settlement

but also on all workmen employed in the establishment. The

contention that petitioner is not an ’employer’ under the Act is

inconsequential in the light of the admitted fact that petitioner

voluntarily undertook liability to pay workmen as part of the

compromise and further participated in the conciliation process

leading to the settlement.

9. It is not in dispute that M/s Ashish Developers and

Builders Pvt. Ltd. (predecessor of petitioner) executed

Development Agreement dated 15-03-1999 with DBR Mills Ltd.,

under which petitioner undertook to settle the monetary claims

of workmen, subject to mutually agreed terms. Clause 6 of the

said agreement provides that repayment of liabilities, including

workers’ dues, was a pre-condition for commencement of any

development activity. Petitioner, having derived commercial

benefit and development rights under the said agreement,
21

cannot now disclaim the obligations that form an integral part

of such commercial arrangement. Petitioner’s plea that 12(3)

settlement is not legally-binding on it, is contrary to the record

for they participated in the conciliation proceedings and

executed the settlement in the presence of the Conciliation

Officer. Once such a settlement is reached, its enforceability is

not contingent upon the petitioner’s classification as a statutory

employer under Section 2(g) or 2(k) of the Act. The doctrine of

estoppel would apply to preclude petitioner from challenging a

settlement it voluntarily entered into and acted upon.

10. Section 33-C(1) of the Act empowers the Labour

Commissioner to issue a Certificate of Recovery for amounts due

to workers, which are determined by an industrial adjudication

or settlement. In the present case, petitioner entered into a

settlement under Section 12(3) of the Act with the workers’

unions, agreeing to pay the workers a specified sum in full and

final settlement of their claims. The settlement was binding, and

petitioner, having voluntarily undertaken responsibility for the

settlement, cannot deny its obligations on the basis that it is not

the employer. The core purpose of the Industrial Disputes Act

is to ensure that workers are protected and their claims are
22

enforced in a timely manner. The Act recognizes the principle of

justice and fairness for workers, even if the claims arise from

complex contractual relationships, as in this case where

petitioner entered into the settlement as part of its development

agreement. Petitioner’s claim of being a third party or not an

employer is, therefore, not sufficient to absolve it of its

obligations under the Act. They are not merely a passive third

party but a central participant in the process, assuming

responsibility for the workers’ claims in exchange for the

development rights granted by DBR Mills.

11. It is pertinent to observe that petitioner cannot rely

on the notion that it was not directly involved in the employer-

employee relationship, as the settlement was designed to

address workers’ dues directly with petitioner taking on the

responsibility of making payments. Petitioner thus assumed the

obligations of the employer in this context and the workers were

entitled to seek recovery from the party responsible for the

settlement. The recovery certificate issued by the 2nd respondent

is referable to Section 33-C(1), which allows recovery of money

due to a workman under a settlement. The existence of a

binding 12(3) settlement suffices to trigger the provisions of
23

Section 33-C(1). The contention that petitioner is not an

employer is irrelevant once it is established that they voluntarily

accepted liability and undertook to make payments under a

statutory settlement. The Authority acted within its jurisdiction

in initiating recovery proceedings based on the settlement.

12. Further, petitioner has not impleaded either

management of DBR Mills or the Joint Action Committee

representing the workers’ unions, despite their direct

involvement in the matter. This suppression of necessary

parties renders Writ Petition liable to be dismissed on the

ground of non-joinder. Moreover, petitioner’s conduct, including

development activities undertaken on the land and negotiations

with the workers, belies the claim of being a mere third party.

The contention that workers must pursue a civil suit is

untenable. Section 33-C(1) is a complete statutory mechanism

for enforcing monetary claims under a settlement. The

availability of a civil remedy does not oust the jurisdiction of

statutory authorities to act under special legislation designed for

the benefit of workmen.

13. In that view of the matter, petitioner, despite not

being the direct employer of the workers, undertook
24

responsibility for their claims under the settlement and cannot

escape liability on technical grounds. The settlement entered

into was binding and the Labour Commissioner’s issuance of

the Certificate of Recovery was well within the statutory powers

granted under Section 33-C(1) of the Industrial Disputes Act.

The Writ Petition therefore, must fail.

14. The Writ Petition is accordingly, dismissed. No

costs.

15. Consequently, the interim order dated 14.03.2024

shall stand dissolved automatically.

——– —————————–

NAGESH BHEEMAPAKA, J

29th April 2025

ksld



Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here