M/S. National Aluminium Company vs Indo Power Projects Limited on 24 July, 2025

0
1

Orissa High Court

M/S. National Aluminium Company vs Indo Power Projects Limited on 24 July, 2025

Author: S.K. Panigrahi

Bench: S.K. Panigrahi

                                                          Signature Not Verified
                                                          Digitally Signed
                                                          Signed by: BHABAGRAHI JHANKAR
                                                          Reason: Authentication
                                                          Location: ORISSA HIGH COURT, CUTTACK
                                                          Date: 28-Jul-2025 17:28:24




              IN THE HIGH COURT OF ORISSA AT CUTTACK

                           ARBA No.16 of 2023
    (From the judgment dated 18.05.2023 passed by the learned District
    Judge, Koraput at Jeypore in Arbitration Proceeding No.1 of 2020)

     M/s. National Aluminium Company ....                               Appellant (s)
     Limited, Bhubaneswar, Odisha
                                -versus-

     Indo Power Projects Limited,           ....                    Respondent (s)
     Kolkata

  Advocates appeared in the case through Hybrid Mode:

     For Appellant (s)          :              Ms. Pami Rath, Senior Advocate
                                                                   Along with
                                                    Miss. Guman Singh, Adv.

     For Respondent (s)         :                 Mr. Dayananda Mohapatra,
                                                               Senior Advocate
                                                                    Along with
                                                 Mr. Subhasis Sarkar, Advocate


                    CORAM:
                    DR. JUSTICE S.K. PANIGRAHI

                   DATE OF HEARING:-22.07.2025
                  DATE OF JUDGMENT: -24.07.2025
  Dr. S.K. Panigrahi, J.

1. This Appeal under Section 37 of the Arbitration and Conciliation Act,

1996 (hereinafter referred to as “A&C Act”) has been filed against the

judgment dated 18.05.2023 passed by the learned District Judge,

Koraput at Jeypore in Arbitration Proceeding No.1 of 2020 wherein the

learned District Judge has dismissed the petition filed under Section 34

Page 1 of 27
Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
Reason: Authentication
Location: ORISSA HIGH COURT, CUTTACK
Date: 28-Jul-2025 17:28:24

of the A&C Act thereby confirming the award dated 17.12.2019 passed

by the learned Sole Arbitrator in Arbitration Proceeding No.5 of 2017.

I. FACTUAL MATRIX OF THE CASE:

2. Pursuant to an invitation to tender floated by the present Appellant for

execution and completion of the work of Electrical works for Phase-2

Expansion Project of Alumina Refinery at Damonjodi (Orissa). The

present Respondent participated in the tender and was declared

successful. Formal agreement between the parties was executed on

10.10.2007 with the stipulation that the work in question would be

completed within a period of 12 months beginning from 15.9.2007.

3. However, the work could not be completed by the Respondent within

the time stipulated i.e. 12 months. As many as 12 extensions were

granted by the Appellant and the work was completed by the

Respondent on 31.7.2012. The Designated Engineer- in-Charge issued a

letter of completion on 1.7.2015 indicating that the work of the

Respondent amounted to a total of Rs. 9,53,61,442/- The Engineer-in-

Charge recommended payment of the 24th R.A. bill for an outstanding

amount of Rs. 1,59,40,585 subject to statutory deductions and other

legal recoveries to be decided by the present Appellant. Soon thereafter,

the Appellant replied vide letter dated 30.9.2015 that this

recommended amount was tentative and several deductions towards

liquidated damages, cost of unreturned free issue materials and scraps,

rebate items, cost of the items lost, etc. would be deducted from the

Respondent. Upon calculation, the Appellant determined that the

Page 2 of 27
Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
Reason: Authentication
Location: ORISSA HIGH COURT, CUTTACK
Date: 28-Jul-2025 17:28:24

Respondent was liable to pay an amount of Rs. 89,63,093/- to the

Respondent. And at this juncture, the dispute arose.

4. The Respondent questioned the proposed deductions terming them as

illegal and beyond the terms of the contract. The Respondent issued a

notice raising several claims and demanded reference of the matter for

arbitration. As the Appellant did not respond to the notice, the

Respondent approached the High Court of Orissa in ARBP No. 42 of

2016 u/s 11 of the Act. This Court was pleased to appoint former Judge

of Orissa High Court Justice A.K. Parichha as the Sole Arbitrator in the

matter.

5. Before the Sole Arbitrator both the parties, tendered oral and

documentary evidence. Upon analysis and consideration of the

evidence adduced by the parties, the Sole Arbitrator was pleased to

pass an award in favour of the present Respondent vide award dated

17.12.2019.

6. Aggrieved, the present Appellant preferred an application u/s 34 of the

A&C Act. Vide judgment dated 18.5.2023 in Arbitration Proceeding

No.1 of 2020, the Ld. District Judge, Koraput at Jeypore was pleased to

dismiss the said application on the ground that the Appellant has failed

to point out any illegality in the Award. Hence, the present petition.

7. Now that the facts leading up to the instant Appeal has been laid down,

this Court shall endeavour to summarise the contentions of the Parties

and the broad grounds that have been raised to seek the exercise of this

Court’s limited jurisdiction available under S. 37 of the A&C Act.

Page 3 of 27
Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
Reason: Authentication

Location: ORISSA HIGH COURT, CUTTACK
Date: 28-Jul-2025 17:28:24

II. APPELLANT’S SUBMISSIONS:

8. During course of hearing, learned counsel for the Appellants submitted

that the award dated 17.12.2019 suffers from patent illegality due to the

fact that the Ld. Tribunal had awarded the claim towards escalation of

price of materials and labour costs during the extended period of

execution of work, thereby completely ignoring that the works contract

is a firm/fixed contract.

9. Furthermore, it was submitted that the Ld. District Judge passed the

impugned order without applying its independent mind and has only

reiterated what the arbitrator has held and copy pasted the award

without application of its own judicial mind.

III. RESPONDENT’S SUBMISSIONS:

10.On the contrary, learned counsel for the Respondent contends that

while considering an application under Section 37 of the Act, the Court

is not to act as an Appellate Court. The Court is to see as to whether

challenge to the award comes within the grounds contained in sub-

Section (2) of Section 34 of the Act. According to the learned counsel,

the contentions advanced on behalf of the Appellants for challenging

the award are factual in nature and, more or less, are pure surmises.

None of such contentions come within the purview of Section 34(2) of

the Act. Therefore, the award may not be interfered with.

11.It was earnestly contended that there is absolutely no illegality in the

award for which the Court may feel inclined to interfere with the same.

Page 4 of 27
Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
Reason: Authentication

Location: ORISSA HIGH COURT, CUTTACK
Date: 28-Jul-2025 17:28:24

IV. ISSUE FOR CONSIDERATION:

12.Having heard the parties and perused the materials available on

record, this court here has identified the following solitary issue to

be determined:

A. Whether the order of the Ld. District Judge warrants

interference keeping in mind the limitations of this court’s

powers under Section 37 of the A&C Act?

V. ISSUE A: WHETHER THE ORDER OF THE LD. DISTRICT
JUDGE WARRANTS ANY INTERFERENCE KEEPING IN
MIND THE LIMITATIONS OF THIS COURT’S POWERS
UNDER SECTION 37 OF THE A&C ACT?

13. Before going into the merits of the contentions, it is necessary to outline

the ambit and scope of Section 37(2)(b) of the 1996 Act. The said section

is extracted below:

“37. Appealable orders.–(1)[Notwithstanding anything
contained in any other law for the time being in force, an
appeal] shall lie from the following orders (and from no
others) to the court authorised by law to hear appeals from
original decrees of the court passing the order, namely:

∗∗∗
(2) Appeal shall also lie to a court from an order of the
Arbitral Tribunal–

(a) accepting the plea referred to in sub-section (2) or sub-
section (3) of Section 16; or

(b) granting or refusing to grant an interim measure under
Section 17.”

14.The Supreme Court and this Court in catena of judgments have held

that the powers of appellate court while exercising jurisdiction under

Section 37(2)(b) of the 1996 Act against orders passed by the Arbitral

Page 5 of 27
Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
Reason: Authentication
Location: ORISSA HIGH COURT, CUTTACK
Date: 28-Jul-2025 17:28:24

Tribunal is very restricted and narrow and the same should be

exercised when the orders seems to be perverse, arbitrary and contrary

to law. The judgment of Wander Ltd. v. Antox India (P) Ltd.1 passed by

the Apex Court, elaborates the ambit and scope of the appeals.

Although the aforesaid judgment is not dealing with the arbitration

proceedings but the same deals with the power of appellate court in

the Civil Procedure Code, 1908 (CPC). Operative paragraphs of the

aforesaid judgment are extracted below:

“13. On a consideration of the matter, we are afraid, the
Appellate Bench fell into error on two important
propositions. The first is a misdirection in regard to the very
scope and nature of the appeals before it and the limitations
on the powers of the appellate court to substitute its own
discretion in an appeal preferred against a discretionary
order. The second pertains to the infirmities in the
ratiocination as to the quality of antox’s alleged user of the
trade mark on which the passing-off action is founded. We
shall deal with these two separately.

14. The appeals before the Division Bench were against the
exercise of discretion by the Single Judge. In such appeals, the
appellate court will not interfere with the exercise of
discretion of the court of first instance and substitute its own
discretion except where the discretion has been shown to have
been exercised arbitrarily, or capriciously or perversely or
where the court had ignored the settled principles of law
regulating grant or refusal of interlocutory injunctions. An
appeal against exercise of discretion is said to be an appeal on
principle. Appellate court will not reassess the material and
seek to reach a conclusion different from the one reached by
the court below if the one reached by that court was
reasonably possible on the material. The appellate court

1
1990 Supp SCC 727

Page 6 of 27
Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
Reason: Authentication
Location: ORISSA HIGH COURT, CUTTACK
Date: 28-Jul-2025 17:28:24

would normally not be justified in interfering with the
exercise of discretion under appeal solely on the ground that
if it had considered the matter at the trial stage it would have
come to a contrary conclusion. If the discretion has been
exercised by the trial court reasonably and in a judicial
manner the fact that the appellate court would have taken a
different view may not justify interference with the trial
court’s exercise of discretion. After referring to these
principles Gajendragadkar, J. in Printers (Mysore) (P)
Ltd. v. Pothan Joseph
(SCC OnLine SC para 9)
‘9. …These principles are well established, but as has been
observed by Viscount Simon in Charles Osenton &
Co. v. Johnston “the law as to the reversal by a court of
appeal of an order made by a Judge below in the exercise
of his discretion is well established and any difficulty that
arises is due only to the application of well-settled
principles in an individual case.”‘
The appellate judgment does not seem to defer to this
principle.”

15.The said judgment is consistently followed in adjudicating petitions

pertaining to the A&C Act by Courts across the Country in Green Infra

Wind Energy Ltd. v. Regen Powertech (P) Ltd.2; Sona Corpn. India (P)

Ltd. v. Ingram Micro India (P) Ltd.3; Manish Aggarwal v. RCI

Industries & Technologies Ltd.4; Tahal Consulting Engineers India (P)

Ltd. v. Promax Power Ltd.5 and Handicraft & Handlooms Exports Co.

of India v. SMC Comtrade Ltd.6.

2
2018 SCC OnLine Del 8273
3
2020 SCC OnLine Del 300
4
(2022) 3 HCC (Del) 289
5
2023 SCC OnLine Del 2069
6
2023 SCC OnLine Del 3981

Page 7 of 27
Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
Reason: Authentication
Location: ORISSA HIGH COURT, CUTTACK
Date: 28-Jul-2025 17:28:24

16.In Reliance Infrastructure Ltd. v. State of Goa7, the Apex Court

noticing its previous decision in MMTC Ltd. v. Vedanta Ltd.8 has noted

the limited scope of interference under Section 34 and further narrower

scope of appeal under Section 37 of the Act particularly when dealing

with the concurrent findings of the arbitrator and that of the Court.

Relevant paragraph ’14’ of MMTC Ltd.(supra) as noted in paragraph

’26’ in Reliance Infrastructure Ltd.(supra) is to be extracted

hereinunder:–

“14. As far as interference with an order made
under Section 34, as per Section 37, is concerned, it cannot
be disputed that such interference under Section 37 cannot
travel beyond the restrictions laid down under Section 34. In
other words, the court cannot undertake an independent
assessment of the merits of the award, and must only
ascertain that the exercise of power by the court
under Section34 has not exceeded the scope of the provision.
Thus, it is evident that in case an arbitral award has been
confirmed by the court under Section 34 and by the court in
an appeal under Section 37, this Court must be extremely
cautious and slow to disturb such concurrent findings.”

17.The same view has been expressed in UHL Power Company

Ltd. v. State of Himachal Pradesh9 in paragraph ’16’ while noticing

paragraph ’11’ in MMTC Ltd.(supra):–

“16. As it is, the jurisdiction conferred on courts
under Section 34 of the Arbitration Act is fairly narrow,
when it comes to the scope of an appeal under Section 37 of
the Arbitration Act, the jurisdiction of an appellate court in

7
(2024) 1 SCC 479
8
(2019) 4 SCC 163
9
(2022) 4 SCC 116

Page 8 of 27
Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
Reason: Authentication
Location: ORISSA HIGH COURT, CUTTACK
Date: 28-Jul-2025 17:28:24

examining an order, setting aside or refusing to set aside an
award, is all the more circumscribed. In MMTC
Ltd. v. Vedanta Ltd. [MMTC Ltd.
v. Vedanta Ltd., (2019) 4
SCC 163 : (2019) 2 SCC (Civ) 293], the reasons for vesting
such a limited jurisdiction on the High Court in exercise of
powers under Section 34 of the Arbitration Act have been
explained in the following words : (SCC pp. 166-67, para 11)
“11. As far as Section 34 is concerned, the position is well-

settled by now that the Court does not sit in appeal over the
arbitral award and may interfere on merits on the limited
ground provided under Section 34(2)(b)(ii) i.e. if the award
is against the public policy of India. As per the legal position
clarified through decisions of this Court prior to the
amendments to the 1996 Act in 2015, a violation of Indian
public policy, in turn, includes a violation of the fundamental
policy of Indian law, a violation of the interest of India,
conflict with justice or morality, and the existence of patent
illegality in the arbitral award. Additionally, the concept of
the “fundamental policy of Indian law” would cover
compliance with statutes and judicial precedents, adopting a
judicial approach, compliance with the principles of natural
justice, and Wednesbury [Associated Provincial Picture
Houses Ltd. v. Wednesbury Corpn., [1948] 1 K.B. 223(CA)]
reasonableness. Furthermore, “patent illegality” itself has
been held to mean contravention of the substantive law of
India, contravention of the 1996 Act, and contravention of
the terms of the contract.”

18.In Haryana Tourism Ltd. v. Kandhari Beverages Ltd.10 as noted in

paragraph ’30’ in Reliance Infrastructure Ltd.(supra), it was held on the

scope of interference under Sections 34 and 37 of the Act’ 1996 as

under:–

10

2022) 3 SCC 237

Page 9 of 27
Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
Reason: Authentication
Location: ORISSA HIGH COURT, CUTTACK
Date: 28-Jul-2025 17:28:24

“30. In Haryana Tourism [Haryana Tourism
Ltd. v. Kandhari Beverages Ltd.
, (2022) 3 SCC 237 : (2022)
2 SCC (Civ) 87], this Court yet again pointed out the limited
scope of interference under Sections 34 and37 of
the Act; and disapproved interference by the High Court
under Section 37 of the Act while entering into merits of the
claim in the following words : (SCC p. 240, paras 8-9)
“8.
So far as the impugned judgment and order [Kandhari
Beverages Ltd. v. Haryana Tourism Ltd., 2018 SCC
OnLine P&H 3233] passed by the High Court
quashing and setting aside the
award and the order passed by the Additional District
Judge under Section 34 of the Arbitration Act are
concerned, it is required to be noted that in an appeal
under Section 37 of the Arbitration Act, the High Court
has entered into the merits of the claim, which is not
permissible in exercise of powers under Section 37 of
the Arbitration Act.

9. As per settled position of law laid down by this Court
in a catena of decisions, an award can be set aside only if
the award is against the public policy of India. The award
can be set aside under Sections 34/37 of
the Arbitration Act, if the award is found to be contrary
to : (a) fundamental policy of Indian Law; or (b) the
interest of India; or (c) justice or morality; or (d) if it is
patently illegal. None of the aforesaid exceptions shall be
applicable to the facts of the case on hand. The High Court
has entered into the merits of the claim and has decided
the appeal under Section 37 of the Arbitration Act as if
the High Court was deciding the appeal against the
judgment and decree passed by the learned trial court.

Thus, the High Court has exercised the jurisdiction not
vested in it under Section 37 of the Arbitration Act. The
impugned judgment andorder [Kandhari Beverages
Ltd. v. Haryana Tourism Ltd., 2018 SCC OnLine P&H
3233] passed by the High Court is hence not sustainable.”

Page 10 of 27
Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
Reason: Authentication

Location: ORISSA HIGH COURT, CUTTACK
Date: 28-Jul-2025 17:28:24

19.It was, thus, observed in paragraph ’33’ of Reliance Infrastructure

Ltd.(supra) as under:–

“33. Keeping in view the aforementioned principles
enunciated by this Court with regard to the limited scope of
interference in an arbitral award by a Court in the exercise of
its jurisdiction under Section34 of the Act, which is all the
more circumscribed in an appeal under Section 37, we may
examine the rival submissions of the parties in relation to the
matters dealt with by the High Court.”

20.It is observed in Punjab State Civil Supplies Corpn. Ltd. v. Sanman

Rice Mills11 that:

“9. The object of the Act is to provide for a speedy and
inexpensive alternative mode of settlement of dispute with the
minimum of intervention of the courts. Section 5 of the Act
is implicit in this regard and prohibits interference by the
judicial authority with the arbitration proceedings except
where so provided in Part-I of the Act. The judicial
interference, if any, is provided inter-alia only by means of
Sections 34 and 37 of the Act respectively.

10. Section 34 of the Act provides for getting an arbitral
award set aside by moving an application in accordance with
sub-Section (2) andsub-Section (3) of Section 34 of the Act
which inter-alia provide for the grounds on which an arbitral
award is liable to be set aside. One of the main grounds for
interference or setting aside an award is where the arbitral
award is in conflict with the public policy of India i.e. if the
award is induced or affected by fraud or corruption or is in
contravention with the fundamental policy of Indian law or
it is in conflict with most basic notions of morality and
justice. A plain reading of Section 34 reveals that the scope of
interference by the court with the arbitral award under
Section 34 is very limited and the court is not supposed to

11
2024 SCC OnLine SC 2632
Page 11 of 27
Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
Reason: Authentication
Location: ORISSA HIGH COURT, CUTTACK
Date: 28-Jul-2025 17:28:24

travel beyond the aforesaid scope to find out if the award is
good or bad.

11. Section 37 of the Act provides for a forum of appeal inter-
alia against the order setting aside or refusing to set aside an
arbitral award under Section 34 of the Act. The scope of
appeal is naturally akin to andlimited to the grounds
enumerated under Section 34 of the Act.

12. It is pertinent to note that an arbitral award is not liable
to be interfered with only on the ground that the award is
illegal or is erroneous in law that too upon reappraisal of the
evidence adduced before the arbitral trial. Even an award
which may not be reasonable or is non-speaking to some
extent cannot ordinarily be interfered with by the courts. It
is also well settled that even if two views are possible there is
no scope for the court to reappraise the evidence and to take
the different view other than that has been taken by the
arbitrator. The view taken by the arbitrator is normally
acceptable and ought to be allowed to prevail.
xxxxxx

14. It is equally settled law that the appellate power
under Section 37of the Act is not akin to the normal appellate
jurisdiction vested in the civil courts for the reason that the
scope of interference of the courts with arbitral proceedings
or award is very limited, confined to the ambit of Section 34
of the Act only and even that power cannot be exercised in a
casual and a cavalier manner.

xxxxxx

16. It is seen that the scope of interference in an appeal
under Section37 of the Act is restricted and subject to the
same grounds on which an award can be challenged
under Section 34 of the Act. In other words, the powers
under Section 37 vested in the court of appeal are not beyond
the scope of interference provided under Section 34 of
the Act.”

Page 12 of 27
Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
Reason: Authentication

Location: ORISSA HIGH COURT, CUTTACK
Date: 28-Jul-2025 17:28:24

Here, the Supreme Court has once again reiterated that even an award

which may not be reasonable or is nonspeaking to some extent cannot

ordinarily be interfered with by the courts. It is also well settled that

even if two views are possible there is no scope for the court to

reappraise the evidence and to take the different view other than that

has been taken by the arbitrator. The view taken by the arbitrator is

normally acceptable and ought to be allowed to prevail.

21.In Konkan Railway Corpn. Ltd. v. Chenab Bridge Project12 referring

to MMTC Limited (supra) it has been held that:

“19….The scope of jurisdiction
under Section 34 and Section 37 of the Act is not akin to
normal appellate jurisdiction. It is well-settled that courts
ought not to interfere with the arbitral award in a
casual and cavalier manner. The mere possibility of an
alternative view on facts or interpretation of the contract does
not entitle courts to reverse the findings of the arbitral
tribunal…”

22.In Dyna Technology Private Limited v. Crompton Greaves Limited13,

the Apex Court observed as under:

“24. There is no dispute that Section 34 of the Arbitration
Act limits a challenge to an award only on the grounds
provided therein or as interpreted by various courts. We need
to be cognizant of the fact that arbitral awards should not be
interfered with in a casual and cavalier manner, unless the
court comes to a conclusion that the perversity of the award
goes to the root of the matter without there being a possibility
of alternative interpretation which may sustain the arbitral
award. Section 34 is different in its approach and cannot be

12
(2023) 9 SCC 85
13
(2019) 20 SCC 1
Page 13 of 27
Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
Reason: Authentication
Location: ORISSA HIGH COURT, CUTTACK
Date: 28-Jul-2025 17:28:24

equated with a normal appellate jurisdiction. The mandate
under Section 34 is to respect the finality of the arbitral award
and the party autonomy to get their dispute adjudicated by
an alternative forum as provided under the law. If the courts
were to interfere with the arbitral award in the usual course
on factual aspects, then the commercial wisdom behind
opting for alternate dispute resolution would stand
frustrated.

25. Moreover, umpteen number of judgments of this Court
have categorically held that the courts should not interfere
with an award merely because an alternative view on facts
and interpretation of contract exists. The courts need to be
cautious and should defer to the view taken by the Arbitral
Tribunal even if the reasoning provided in the award is
implied unless such award portrays perversity unpardonable
under Section 34 of the Arbitration Act.”

23.Judicial scrutiny of arbitral awards is quite limited in nature under

Indian law. Section 34 of the Arbitration and Conciliation Act, 1996,

prescribes the exclusive grounds upon which an arbitral award can be

challenged. Courts, therefore, are very conservative in interfering

merely because another interpretation or outcome may seem more

reasonable. The jurisdiction under Section 34 is confined to procedural

and legal infirmities such as lack of jurisdiction, violation of natural

justice, or patent illegality. Consequently, appellate jurisdiction under

Section 37 is even narrower in its scope. Its purpose is to evaluate

whether the court adjudicating under Section 34 has remained within

the permissible statutory boundaries. The appellate court cannot re-

evaluate evidence or reconsider the factual matrix afresh. The statutory

framework thus reflects an overarching legislative intent to insulate

Page 14 of 27
Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
Reason: Authentication
Location: ORISSA HIGH COURT, CUTTACK
Date: 28-Jul-2025 17:28:24

arbitral decisions from excessive judicial intervention. The entire

architecture of Sections 34 and 37 reinforces the finality and autonomy

of arbitral proceedings. Arbitration is designed to offer an efficient,

expert-led, and expedited alternative to litigation. Courts must

therefore resist the temptation to intervene unless the decision by the

court under Section 34 itself amounts to a significant transgression of

the well-defined legal boundaries.

24.It is now firmly established in law that appellate review under Section

37 of the Act does not permit the court to act as a second court of first

instance. The appellate Court’s task is not to reassess the arbitral

tribunal’s findings on merits or evidence, but only to determine

whether the court under Section 34 has exercised its discretion legally

and within its jurisdiction. This means the appellate court must limit

itself to checking if the Section 34 court has adhered to the narrow scope

prescribed by the Act. It is not sufficient for the appellate court to

identify an alternative or even preferable view–interference is justified

only if the lower court has committed a jurisdictional error, or it has

failed to apply the law correctly. The structure of the Act ensures that

arbitration remains an autonomous dispute resolution mechanism,

minimally impacted by judicial oversight. The Court under Section 37

is not an appellate authority like the conventional civil law sense; it

cannot substitute its own interpretation for that of the arbitrator unless

a clear and grave legal error is demonstrated. In essence, the appellate

court serves as a watchdog over the procedural fidelity of the Section

34 court–not the substantive reasoning of the arbitrator.

Page 15 of 27
Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
Reason: Authentication

Location: ORISSA HIGH COURT, CUTTACK
Date: 28-Jul-2025 17:28:24

25.When interpreting Section 37, it is imperative to contextualize it

alongside the Section 5 of the Act, which serves as a foundational

provision reinforcing the ethos of minimal interference. Section 5

makes it clear that courts shall not intervene in arbitral issue except as

expressly provided in the Act. This legislative mandate is not merely

procedural–it is a substantive limitation on judicial power. Appeals

under Section 37, especially those arising under Section 37(2)(b), are

therefore constrained by both the statutory scheme and overarching

judicial philosophy. Unlike appeals under other civil statutes, where

courts may dive deep into factual findings or discretionary decisions,

the Arbitration Act imposes a tight statutory leash. The objective is to

prevent the unraveling of arbitration outcomes through prolonged

court battles. Any order passed by an arbitral tribunal, particularly at

interlocutory stages, must be accorded due deference unless it reveals

clear arbitrariness, irrationality, or breach of the fundamental legal

principles. Courts must, therefore, resist the impulse to interfere merely

because a different view appears plausible or even more just in

hindsight. Arbitration focuses on party autonomy, and any judicial

incursion must align strictly with the boundaries demarcated by

Sections 5, 34, and 37.

26.The judiciary’s intervention in arbitral matters must be exercised with

utmost caution, especially where the arbitral tribunal’s decisions reflect

reasonable interpretations of contractual terms or factual matrices. The

1996 Act was introduced with the explicit objective of limiting the role

of courts, ensuring faster and more efficient resolution of disputes

Page 16 of 27
Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
Reason: Authentication
Location: ORISSA HIGH COURT, CUTTACK
Date: 28-Jul-2025 17:28:24

outside traditional litigation. Consequently, appellate courts under

Section 37 must act with deliberate restraint, only intervening when the

arbitral process has clearly deviated from established legal standards.

This includes instances of perversity, gross arbitrariness, or when

settled legal principles have been ignored or misapplied. Importantly,

arbitral decisions–even at interim stages–deserve judicial respect

unless a substantial illegality is apparent. The appellate court’s function

is supervisory, not substitutive. It is not tasked with forming a fresh

opinion but must ensure that the arbitral tribunal’s discretion has been

exercised within legal bounds. In other words, Section 37 does not

allow for wholesale re-litigation of disputes that have already been

adjudicated by an arbitral forum. The credibility of the arbitration

system hinges on this judicial discipline. Allowing appeals to turn into

de facto retrials would defeat the very purpose of choosing arbitration

over courtroom adjudication.

27.The foundational framework of the Arbitration Act reflects an express

intent to exclude ordinary civil appellate practices in arbitral matters.

The powers conferred under Section 37(2)(b) are not akin to those

under civil appellate jurisdiction, where factual reappraisal and

discretionary judgments are routine. Rather, the Act envisions a system

where arbitral orders are largely immune from judicial revisitation

unless a serious and demonstrable breach of procedure or law occurs.

This philosophy is rooted in the recognition that arbitration is a

consensual mechanism designed to bypass the complexities and delays

of civil litigation. Courts, therefore, must respect the principle of

Page 17 of 27
Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
Reason: Authentication
Location: ORISSA HIGH COURT, CUTTACK
Date: 28-Jul-2025 17:28:24

finality, stepping in only where an order of the arbitral tribunal is

tainted by evident perversity or gross misapplication of law.

28.In view of the above position in law on the subject, the scope of the

intervention of the court in arbitral matters is virtually prohibited, if not

absolutely barred and that the interference is confined only to the extent

envisaged under Section 34 of the Act. The appellate power

of Section 37 of the Act is limited within the domain of Section 34 of

the Act. It is exercisable only to find out if the court, exercising power

under Section 34 of the Act, has acted within its limits as prescribed

thereunder or has exceeded or failed to exercise the power so

conferred. The Appellate Court has no authority of law to consider the

matter in dispute before the arbitral tribunal on merits so as to find out

as to whether the decision of the arbitral tribunal is right or wrong upon

reappraisal of evidence as if it is sitting in an ordinary court of appeal.

It is only where the court exercising power under Section 34 has failed

to exercise its jurisdiction vested in it by Section 34 or has travelled

beyond its jurisdiction that the appellate court can step in and set aside

the order passed under Section 34 of the Act. Its power is more akin to

that superintendence as is vested in civil courts while exercising

revisionary powers. The arbitral award is not liable to be interfered

unless a case for interference as set out in the earlier part of the decision,

is made out. It cannot be disturbed only for the reason that instead of

the view taken by the arbitral tribunal, the other view which is also a

possible view is a better view according to the appellate court.

Page 18 of 27
Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
Reason: Authentication

Location: ORISSA HIGH COURT, CUTTACK
Date: 28-Jul-2025 17:28:24

29.It must also be remembered that proceedings under Section 34 of

the Act are summary in nature and are not like a full-fledged regular

civil suit. Therefore, the scope of Section 37 of the Act is much more

summary in nature and not like an ordinary civil appeal. The award as

such cannot be touched unless it is contrary to the substantive provision

of law; any provision of the Act or the terms of the agreement.

30.It is within this statutory and jurisprudential framework that the

present appeal must be evaluated. The core issue for consideration here

is whether the Arbitral Award, as upheld by the Ld. District Court,

suffers from patent illegality warranting interference

under Section 37 of the Act.

31.At the outset, the contentions raised by the Appellants fail to establish

any of the statutory grounds for setting aside an arbitral award as

outlined in Section 34(2) of the Arbitration and Conciliation Act, 1996.

The objections do not invoke violation of the fundamental policy of

Indian law, public interest, or morality, nor is there any indication that

the award is in conflict with justice in a manner envisaged by the Act.

32.A careful examination of the impugned arbitral award demonstrates

that the Sole Arbitrator has undertaken a detailed evaluation of the

rival contentions advanced by both the Appellant and the Respondent.

The award appears to be the outcome of thorough consideration of the

oral and documentary evidence presented by the parties. It reflects

reasoned findings on the respective claims and counterclaims, without

any indication of oversight or arbitrariness. The Appellant, while

seeking to assail the award, has not been able to highlight any element

Page 19 of 27
Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
Reason: Authentication
Location: ORISSA HIGH COURT, CUTTACK
Date: 28-Jul-2025 17:28:24

that would place the award in conflict with the public policy of India, a

prerequisite under Section 34 of the Arbitration and Conciliation Act,

1996 for setting aside an arbitral award.

33.The Appellant, in an attempt to repudiate the claims allowed in favour

of the Respondent, had placed reliance on five principal grounds. The

first of these was that although the Respondent was contractually

obliged to complete the work within a period of 12 months, it allegedly

took 57 months and 12 extensions to conclude the same. Consequently,

the Appellant contended that the Respondent was liable to pay

liquidated damages amounting to Rs.19,07,228.80 (Counter Claim No.

1). This delay, in the Appellant’s view, was attributable solely to the

Respondent and not to any default on the Appellant’s part.

34.Secondly, the Appellant claimed that the Respondent failed to return

or properly account for free-issue materials and scrap provided during

the execution of the work. It was alleged that this resulted in a financial

loss, for which the Respondent was liable to compensate the Appellant

to the tune of Rs.74,13,396.00 (Counter Claim No.2). The third

counterclaim involved a rebate of Rs.21,202/- (Counter Claim No. 3),

which the Appellant asserted had not been accounted for. Each of these

counterclaims was presented with the assertion that they arose out of

breaches of contractual obligations by the Respondent.

35.The fourth counterclaim raised by the Appellant was a demand for

compensation amounting to Rs.1,39,48,190/- on account of loss of

materials allegedly stolen while in the custody of the Respondent

(Counter Claim No. 4). Lastly, under Counter Claim No. 5, the

Page 20 of 27
Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
Reason: Authentication
Location: ORISSA HIGH COURT, CUTTACK
Date: 28-Jul-2025 17:28:24

Appellant sought recovery of statutory dues, comprising Rs.3,32,179/-

towards income tax, Rs.6,64,357/- towards VAT on WCT, and

Rs.5,00,000/- towards RF dues. The aggregate of these counterclaims

formed the core of the Appellant’s challenge to the award, with the

Appellant asserting that these claims were either not addressed or

inadequately considered by the Sole Arbitrator.

36.In response to these allegations, the Respondent argued that the Sole

Arbitrator had comprehensively dealt with the issues raised, including

all claims and counterclaims. It was contended that the Arbitrator had

extensively deliberated upon the evidence, both oral and documentary,

and delivered a well-reasoned award. The argument put forth was that

the Court, in exercise of its jurisdiction under Section 34, cannot act as

an appellate forum and re-evaluate the evidence or second-guess the

reasoning of the Arbitrator merely because another view is possible on

the same set of facts.

37.This Court, upon reviewing the award, finds that the Arbitrator had

specifically considered the Appellant’s counterclaims in para 6 of the

award while dealing with Issue Nos.1 and 10 to 14. It is clearly recorded

that the Arbitrator took into account all relevant facts and

circumstances. Notably, Counter Claims No. 1, 4, and 6 (interest) were

rejected after a reasoned analysis. Conversely, Counter Claims No. 2, 3,

and 5 were allowed either wholly or in part. This balanced treatment of

claims, accompanied by justifications grounded in the record, shows

that the award is not arbitrary or perverse.

Page 21 of 27
Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
Reason: Authentication

Location: ORISSA HIGH COURT, CUTTACK
Date: 28-Jul-2025 17:28:24

38.Regarding Counter Claim No. 1 on liquidated damages, the Arbitrator

relied on Clause 24 of the General Conditions of Contract (GCC), which

stipulated liability for delay. However, after evaluating the factual

matrix, it was found that the delays were largely due to the Appellant’s

lapses. The Arbitrator noted that by 15.6.2010, only 77.03% of work

fronts had been made available to the Respondent, and it was only by

2012 that full access was granted. The Appellant had also agreed to pay

Rs. 2.4 lakhs per month as compensation for idle labour and equipment,

which indicated acknowledgment of its own responsibility in causing

the delay.

39.The Arbitrator’s rejection of Counter Claim No. 4 (loss due to theft) is

also based on cogent reasoning. It was held that the Appellant failed to

furnish specific evidence regarding the identity or value of the missing

materials. Reference was made to the 22nd R.A. Bill, where a sum of

Rs.3,23,265/- had already been recovered on this count. Further, it was

observed that Rs.5,03,706/- was to be recovered from the final bill,

indicating a total assessed loss of Rs.8,27,971/-. This was found to be

significantly lower than the claimed amount of Rs.1,39,48,190/-, and

thus, the Arbitrator rightly refused to allow the inflated claim.

40.The award also demonstrates that the Arbitrator did not

indiscriminately accept all claims of the Respondent. It is evident from

the record that Claim Nos.2, 3, 7, 8, and 10 of the Respondent were

disallowed after due consideration. This further dispels the Appellant’s

allegation of bias or one-sided adjudication. The detailed approach

adopted by the Arbitrator reflects a judicious application of mind. The

Page 22 of 27
Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
Reason: Authentication
Location: ORISSA HIGH COURT, CUTTACK
Date: 28-Jul-2025 17:28:24

reasoning, even if not aligned with the Appellant’s views, does not in

any way reflect perversity or patent illegality that would warrant

intervention by the Court under the limited grounds available for

setting aside an arbitral award.

41.Moreover, with regards to the cost escalation that was awarded in

favour of the present Respondent, the Respondent had raised a claim

amounting to Rs.76,56,856/-, which included Rs.31,87,740/- towards

escalation in labour cost and Rs.41,76,357/- for escalation in material

cost, asserting that the delay in project execution up to 31.07.2012 was

attributable to the Appellant’s failure to provide timely and adequate

work fronts. It is submitted that the Respondent had to retain its

workforce and establishment until the issuance of the completion

certificate on 9.10.2015 by the Engineer-In-Charge, thereby incurring

increased costs during the extended period. The claim was based on

compensation due to prolonged execution arising out of the

Appellant’s contractual defaults.

42.The Appellant resisted the claim on the ground that the contract was a

fixed-price agreement with an explicit clause disallowing price

escalation. It is further argued that the Respondent had provided a

written undertaking confirming that it had no claims beyond the final

bill, and thus the demand for escalation in costs was contractually

barred. The Appellant also alleged that delays occurred due to the

Respondent’s inability to mobilize sufficient labour, material, and

finances, suggesting that the Respondent bore responsibility for the

delay and therefore was not entitled to any such compensation.

Page 23 of 27
Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
Reason: Authentication

Location: ORISSA HIGH COURT, CUTTACK
Date: 28-Jul-2025 17:28:24

43.In rebuttal, the Respondent relied on Sections 55 and 73 of the Indian

Contract Act and submitted that a contractor may still claim

compensation if the delay was due to the employer’s fault and the

contractor incurred loss performing work during the extended period.

The Respondent also submitted that “no claim certificates” do not

automatically preclude genuine post-contractual claims if they can be

substantiated.

44.In the present matter, although the Respondent did submit a “no claim

certificate” along with the 24th R.A.-cum-final bill, the Ld. Arbitrator

found that this did not preclude the Respondent from seeking

legitimate compensation. The delay of approximately 46 months was

found to be primarily due to the Appellant’s failure to provide

necessary work fronts, which justified the Respondent’s continued

incurrence of labour and material costs. Although there was some

evidence of minor lapses by the Respondent–such as failure to

promptly pay subcontractors and insufficient resource deployment–

the Ld. Arbitrator held that the predominant cause of delay lay with

the Appellant. Consequently, the Arbitrator determined that the

Appellant bore major liability for the increased cost incurred during the

extended period despite the clause disallowing price escalation and

considering both parties’ contributions to the delay, the Arbitrator

judiciously awarded 50% of the revised escalation amounts to the

Respondent–Rs.15,93,870/- for labour cost escalation and

Rs.20,88,178/- for material cost escalation. This Court finds no error in

the Arbitrator’s interpretation of the contractual terms or in the

Page 24 of 27
Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
Reason: Authentication
Location: ORISSA HIGH COURT, CUTTACK
Date: 28-Jul-2025 17:28:24

application of relevant legal provisions. Clause 88(b) of the General

Conditions of Contract states that the contract shall be governed by the

relevant laws of India and therefore, the Ld. Arbitrator’s reliance on the

Indian Contract Act is tenable in law.

45.The fact that the underlying agreement was a fixed-price contract does

not, in any manner, imply that the Appellant was at liberty to delay the

execution of the contractual obligations without facing any financial or

legal consequences. A fixed-price contract merely stipulates that the

consideration for the work to be performed remains predetermined and

unaltered under normal circumstances; it does not operate as a blanket

protection against repercussions arising from breaches or defaults

committed by either party. If the delay in completion of the contract is

attributable, either wholly or substantially, to the Appellant’s own

lapses–such as failure to provide timely work fronts, inadequate

coordination, or delays in releasing payments–then the Appellant

cannot claim immunity merely on the ground of the fixed-price nature

of the contract. Parties to a contract are expected to act in good faith and

adhere to their respective obligations, and any deviation attracting loss

to the other side invites proportionate legal and contractual liability.

46.In view of the above analysis, it is clear that the award has been passed

after a careful and reasoned consideration of the evidence on record.

The Arbitrator has acted within his jurisdiction and has not committed

any illegality–much less a patent illegality–that would justify setting

aside the award. This Court cannot interfere merely because a different

conclusion could be drawn from the same evidence. The Arbitrator is

Page 25 of 27
Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
Reason: Authentication
Location: ORISSA HIGH COURT, CUTTACK
Date: 28-Jul-2025 17:28:24

the sole judge of the quality and sufficiency of the evidence presented

before him, and unless the findings are perverse or shock the

conscience of this Court, no interference is warranted. The appeal,

therefore, fails to make out any valid ground for intervention.

VI. CONCLUSION:

47.In light of the above discussion, it is evident that the Appellant has not

identified any infirmity in the arbitral award that would rise to the level

of patent illegality or jurisdictional error as contemplated under Section

34(2A) of the Act. The Arbitrator has provided reasoned findings,

grounded in documentary evidence and consistent with legal

principles applicable to contractual breaches and delay. These findings

were not only comprehensive but were also examined and upheld by

the District Court. It is now well settled that neither the re-evaluation

of facts nor the mere possibility of a more favourable interpretation can

form the basis for setting aside an award. The appellate court,

particularly while exercising powers under Section 37, must adhere

strictly to the limited scope of judicial review. It cannot act as a court of

first appeal, nor can it re-assess the arbitral process as if the award is

being tried afresh. Given that the Arbitrator acted within his

jurisdiction, followed due process, and arrived at a decision through a

reasoned and evidentiary process, there is no warrant for interference.

The appeal, therefore, lacks merit and must be dismissed in keeping

with the principles governing limited judicial oversight in arbitration.

48.In the circumstances, there is no justification to interfere with the

findings in the impugned award in respect of the aforesaid claims,

Page 26 of 27
Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
Reason: Authentication
Location: ORISSA HIGH COURT, CUTTACK
Date: 28-Jul-2025 17:28:24

having regard to the scope of jurisdiction under Section 34 and/or 37 of

the A&C Act.

49.ARBA No.16 of 2023 is disposed on the abovementioned terms. No

order as to costs.

50. Interim order, if any, passed earlier stands vacated.

(Dr.S.K. Panigrahi)
Judge

Orissa High Court, Cuttack,
Dated the 24th July, 2025/

Page 27 of 27



Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here