M/S. Nm-Sem (Jv) vs Union Of India on 20 December, 2024

0
21

Kerala High Court

M/S. Nm-Sem (Jv) vs Union Of India on 20 December, 2024

AR NO.160/2024                    1



                                                   2024:KER:97585

              IN THE HIGH COURT OF KERALA AT ERNAKULAM

                              PRESENT

          THE HONOURABLE MR. JUSTICE SYAM KUMAR V.M.

FRIDAY, THE 20TH DAY OF DECEMBER 2024 / 29TH AGRAHAYANA, 1946

                         AR NO. 160 OF 2024

PETITIONER:

          M/S.NM-SEM (JV)
          AGED 57 YEARS
          HIGH SCHOOL ROAD, KOOTHATTUKULAM,
          REPRESENTED BY ITS LEAD PARTNER, NAJEEB MANNEL,
          MANNEL HOUSE, THODIYOOR VILLAGE EDAKULANGARA P.O.,
          PIN - 690 523, KARUNAGAPPALLY TALUK,
          KOLLAM DISTRICT, PIN - 686662

          BY ADVS.
          K.BABU THOMAS
          MARYKUTTY BABU
          DRISYA DILEEP


RESPONDENTS:

    1     UNION OF INDIA
          REPRESENTED BY THE GENERAL MANAGER,
          SOUTHERN RAILWAY HEADQUARTERS,
          PARK TOWN, CHENNAI, PIN - 600003

    2     THE CHIEF ENGINEER
          (CONSTRUCTION), SOUTHERN RAILWAY,
          ERNAKULAM, KOCHI, PIN - 682016

    3     THE DEPUTY CHIEF ENGINEER
          CONSTRUCTION-1, SOUTHERN RAILWAY,
          ERNAKULAM JUNCTION, KOCHI, PIN - 682016

          BY ADV SRI.RAJAGOPALAN.A., CGC

     THIS ARBITRATION REQUEST HAVING BEEN FINALLY HEARD ON
20.12.2024, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
 AR NO.160/2024                           2



                                                                 2024:KER:97585

                                   ORDER

Dated this the 20th day of December, 2024

Petitioner has filed this Arbitration Request, invoking Section 11 of the

Arbitration and Conciliation Act, 1996 (Hereinafter referred to as ‘the Act of

1996’) seeking to appoint a sole Arbitrator to adjudicate the disputes and

differences between the petitioner and the respondents/opposite parties

arising out of a works contract.

2. The petitioner participated in a tender for the work relating to the

doubling of the track between Kuruppanthara and Chingavanam. Being the

lowest bidder, the petitioner was awarded the said work, and accordingly,

they entered into Annexure A1 works contract with the 1 st respondent

through the 3rd respondent. The general conditions of contract that form

part of Annexure A1 stipulates in clause 64 that arbitration is the dispute

settlement mechanism agreed upon by the parties and lays down in detail

the mandates and methods for the invocation and conduct of the same.

3. Disputes arose between the parties, inter alia, regarding the

alleged delays/defaults, rider agreements, non-payment of market rates,

and withholding of payments. A Writ Petition was filed before this Court by

the petitioner concerning the recovery of Rs.16,57,950/- by the

respondents from the bill submitted by the petitioner. Annexure A2
AR NO.160/2024 3

2024:KER:97585

judgment was rendered therein subsequent to which the respondents vide

Annexure A3 inter alia intimated to the petitioner that the amount of

Rs.16,57,950/- recovered from the final bill purportedly towards vitiation

cannot be refunded. Faced with Annexure A3 refusal, the petitioner issued

Annexure A4 letter inter alia invoking the arbitration clause and seeking the

appointment of an Arbitrator. Annexure A8 letter was issued to the

petitioner on behalf of the 1st respondent calling upon them to select at

least two out of the panelists comprising of retired Railway Senior

Administrative Grade Officers as suggested by the respondents. Petitioner

was not amenable to such a process of appointment and since the

invocation and request were not favourably acted upon, the petitioner has

filed the above Arbitration Request seeking to appoint an Arbitrator.

4. The respondents entered appearance and filed a detailed counter

affidavit responding to the factual contentions put forth in the petition.

Execution of Annexure A1 agreement/works contract is admitted in the

counter affidavit. The existence of an arbitration clause therein is also

admitted. It is, however, averred that the Arbitration Request is not

maintainable since all payments due to the petitioner had been paid as and

when demanded after taking due note of the escalation factors which are

already built-in within the contract conditions. The contention that

liquidated damages should be paid including for the purported delay
AR NO.160/2024 4

2024:KER:97585

caused in the work is unsustainable. Such a demand is not as per the

agreement conditions and cannot be accepted and the petitioner has no

entitlement to claim the same. It is further submitted that the final bill had

been signed by the petitioner with no claim against the Railway in respect

of the relevant work. Hence the request now put forth to refer the claim to

arbitration is unsustainable. As regards the vitiation amount, it is submitted

in the counter affidavit that the same has been calculated as per the

relevant clause in the agreement and there is no illegality on the said

count. Referring to clauses 63 and 64 of the general conditions of contract,

it is contended that the General Manager is the competent authority

empowered to appoint Arbitrators and hence the petitioner has no right to

request a particular person to be appointed as Arbitrator. Reliance is

placed on Exts.R1 (a) to R 1 (o) which includes the no-claim certificate

issued by the petitioner to buttress the contentions put forth in the counter

affidavit.

5. A reply affidavit has been filed by the petitioner controverting the

factual averments in the counter affidavit and relying on Annexures A10 to

A12. The reply affidavit inter alia states that the petitioner has not

requested any particular person to be appointed as the Arbitrator and that

in view of Section 12 (5) of the Act of 1996, the panel suggested by the

respondents cannot be sustained.

AR NO.160/2024 5

2024:KER:97585

6. Heard Sri.Babu Thomas K., learned counsel appearing for the

petitioner and Sri.Rajagopalan A, Central Government Counsel on behalf

of the respondents.

7. The respondents have admitted in their counter affidavit the

existence of Annexure A1 agreement which contains the relevant

arbitration clause as part of the general conditions of contract. The factual

disputes concerning arbitrability and maintainability of the claims as

elaborated by the respondents in their counter affidavit are beyond the

purview of the referral jurisdiction as exercised in this petition under

Section 11 of the Act of 1996. The law on the point has been pithily laid

down by the Supreme Court in SBI General Insurance Co. Ltd V. Krish

Spinning [2024 SCC OnLine SC 1754]. It has been held therein that while

at the stage of deciding an application for appointment of Arbitrator, the

court must not conduct an intricate evidentiary enquiry into whether the

claims raised by the applicant are time-barred and should leave that

question for the Arbitrator to determine. Further it has been held that the

referral court should limit its enquiry to examining whether a Section 11(6)

application has been filed within the three-year period of limitation. Thus

the contours of the exercise of the referral powers under Section 11(6)

have been clearly circumscribed and laid down by the Supreme Court.

8. It is noted that the respondents have vide Annexure 8 letter called
AR NO.160/2024 6

2024:KER:97585

upon the petitioner to select from a panel of Arbitrators suggested by them.

Thus the arbitrability has in effect been admitted by the respondents and

the only question that remains is the choice of Arbitrators. The panel

mentioned in Annexure A8 letter comprises only of retired Railway Senior

Administrative Grade Officers. In view of Section 12 (5) of the Act of 1996,

the contention that the General Manager of the respondents is the

competent authority empowered to appoint Arbitrators is not sustainable.

Further, the dictum laid down by the Supreme Court in TRF Ltd. v. Energo

Engineering Projects Ltd. [(2017) 8 SCC 377] is unequivocal that by

virtue of Section 12(5) of the Act, if any person who falls under any of the

categories specified in the Seventh Schedule shall be ineligible to be

appointed as the Arbitrator.

9. In view of the above discussion, I conclude that the parties are at

ad idem regarding the existence of the arbitration agreement and the need

to appoint an Arbitrator. The disputes concern only the factual aspects of

the subject matter in issue and the same falls within the purview of the

Arbitrator to decide. Hence I find it fit and appropriate to allow the

Arbitration Request and to appoint a retired District Judge from the panel

of Arbitrators maintained by this Court as the Arbitrator.

Accordingly, this Arbitration Request stands allowed and it is

ordered as follows :

AR NO.160/2024 7

2024:KER:97585

(i) Sri.K.Sathyan, Retired District Judge, residing at 22/37, Saranga

Republic Road, Near Samooham High School, North Parur,

Ernakulam – 683 513, is nominated as the sole Arbitrator to resolve

the disputes that have arisen between the petitioner and the

respondents under Annexure-A1 agreement.

(ii) The learned Arbitrator may entertain all disputes/issues between

the parties in connection with the said agreement, including

questions of jurisdiction and limitation, if any, raised by the parties.

(iii) The Registry shall communicate a copy of this order to the

learned Arbitrator within ten days from today and obtain a Statement

of Disclosure from the learned Arbitrator as stipulated under Section

11(8) read with Section 12(1) of the Act of 1996.

(iv) Upon receipt of the Disclosure Statement, the Registry shall

issue to the learned Arbitrator a certified copy of this order with a

copy of the Disclosure Statement appended. The original of the

Disclosure Statement shall be retained in Court.

(v) The fees of the learned Arbitrator shall be governed by the

Fourth Schedule of the Act of 1996.

Sd/-

SYAM KUMAR V.M.
JUDGE
csl
AR NO.160/2024 8

2024:KER:97585

APPENDIX OF AR 160/2024

PETITIONER’S ANNEXURES

Annexure A1 TRUE COPY OF RELEVANT PORTION OF AGREEMENT
NO.04/DCE/ERS/2017 INCLUDING ARBITRATION
CLAUSE 64 IN THE GENERAL CONDITIONS OF
CONTRACT DATED 20-2-2017

Annexure A2 TRUE COPY OF JUDGMENT IN W.P.(C) NO.25263 OF
2022 DATED 16-11-2022

Annexure A3 TRUE COPY OF LETTER OF THE 2ND PARTY
INTIMATING REFUSAL TO PAY EVEN THE ADMITTED
AMOUNT DATED 9-2-2023

Annexure A4 TRUE COPY OF NOTICE OF THE APPLICANT
DEMANDING PAYMENT OF RS.3,21,65,829/- DATED
5-2-2024

Annexure A5 TRUE COPY OF REPLY OF THE 3RD OPPOSITE PARTY
TO ANNEXURE A4 NOTICE DATED 3-5-2024

Annexure A6 TRUE COPY OF LETTER ISSUED FOR THE FIRST
OPPOSITE PARTY DATED 27-6-2024

Annexure A7 TRUE COPY OF LETTER OF APPLICANT INTIMATING
OBJECTION IN THE PANEL IN ANNEXURE A6 DATED
12-7-2024

Annexure A8 TRUE COPY OF LETTER OF THE 1ST OPPOSITE PARTY
DATED 23-7-2024

Annexure A9 TRUE COPY OF REPLY OF THE APPLICANT TO
ANNEXURE A8 DATED 8-8-2024

RESPONDENTS’ EXHIBITS :

Exhibit R1(a) True Copy of the request made by the
petitioner on 27/10/2017 seeking extension of
the currency period for 6 months for
completing the work.

Exhibit R1(b) True copy of reply dated 08/11/2017 issued by
AR NO.160/2024 9

2024:KER:97585

the respondents granting extension of time
upto 28/04/2018.

Exhibit R1(c) True copy of the request made by the
petitioner on 27/04/2018 for extension of the
currency period upto 28/10/2018.

Exhibit R1(d) True Copy of reply dated 04/05/2018 issued by
the respondents granting extension of time
upto 31/07/2018.

Exhibit R1(e) True Copy of the rider agreement entered into
between the petitioner and the respondents on
12/05/2018.

Exhibit R1(f) True copy of the request made by the
petitioner on 30/07/2018 for extension of the
currency period upto 31/03/2019

Exhibit R1(g) True Copy of the reply dated 14/08/2018
issued by the respondents granting extension
of time upto 31/10/2018 and 31/01/2019
respectively.

Exhibit R1(h) True Copy of the rider agreement entered in
to between the petitioner and the respondents
on 20/12/2018.

Exhibit R1(i) True Copy of the request made by the
petitioner on 29/01/2019 for the extension of
the currency period upto 30/03/2019

Exhibit R1(j) True Copy of the rider agreement entered into
between the petitioner and the respondents on
30/01/2019

Exhibit R1(k) True Copy of the request made by the
petitioner on 27/05/2019 for extension of the
currency period upto 30/06/2019

Exhibit R1(l) True Copy of the rider agreement entered into
between the petitioner and the respondents on
29/05/2019

Exhibit R1(m) True Copy of the rider agreement entered into
AR NO.160/2024 10

2024:KER:97585

between the petitioner and the respondents on
09/03/2021

Exhibit R1(n) True Copy of the final bill dated 19/03/2021
issued by the 2nd respondent

Exhibit R1(o) True Copy of the no claim certificate issued
by the petitioner on 09/10/2020

PETITIONER’S ADDITIONAL DOCUMENTS:

Annexure A10 True copy of protest letter sent to the
respondents dated 5-3-2021

Annexure A11 True copy of clauses 17 A(ii), 17 B and 17(C)
of the GCC dated nil

Annexure A12 True copy of the Railway Board Circular
No.2017/Trans/01/POLICY dated 8-2-2018



Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here