Patna High Court
M/S Rana Amrendra Electricals vs The State Of Bihar And Ors on 20 January, 2025
Author: Partha Sarthy
Bench: Partha Sarthy
IN THE HIGH COURT OF JUDICATURE AT PATNA
Civil Writ Jurisdiction Case No.19096 of 2016
======================================================
M/S Rana Amrendra Electricals, Patna through proprietor Rana Amrendra
Kumar Singh, Son of Ran Haribansh Singh, resident of Gaya Niketan, Yarpur
Shivaji Path, P.S. - Gardanibagh, District and in the Town of Patna.
... ... Petitioner/s
Versus
1. The State of Bihar though the Principal Secretary, Building Construction
Department, Vishweshraiya Bhawan, Patna.
2. The Electrical Chief Engineer, Building Construction Department,
Vishweshraiya Bhawan, Patna.
3. The Electrical Superintending Engineer, B.C.D., South Bailey Road, Patna.
4. The Electrical Executive Engineer, Electrical Division No. 1, B.C.D., South
Bailey Road, Patna.
5. The Junior Engineer, Electrical Division No. 1, B.C.D., South Bailey Road,
Patna.
6. The Bihar Public Works Contracts Disputes Arbitration Tribunal through its
Chairman at 3rd Floor Maurya Complex Budha Marg, Patna.
... ... Respondent/s
======================================================
Appearance :
For the Petitioner/s : Mr. Raghwendra Sharan Pandey, Advocate
For the State : Mr. K.K. Singh, A.C. to G.P.-22
======================================================
CORAM: HONOURABLE THE ACTING CHIEF JUSTICE
and
HONOURABLE MR. JUSTICE PARTHA SARTHY
ORAL JUDGMENT
(Per: HONOURABLE THE ACTING CHIEF JUSTICE)
Date : 20-01-2025
Heard Mr. Raghwendra Sharan Pandey, the
learned Advocate for the writ petitioner and Mr. K.K.
Singh, the learned counsel for the State.
2. The petitioner, a contractor, had entered
into an agreement with the Electricity Department for
Patna High Court CWJC No.19096 of 2016 dt.20-01-2025
2/4
carrying out repair works in the M.L.A. Flats with the
stipulation that the work shall be concluded within a
period of ten days.
3. The work order, dated 06.03.2012,
indicated that the payments would be made on the basis
of progress of work report attached with the bills, duly
countersigned by A.E.E. as well as the custodian of the
building.
4. By around 10.03.2012, the Government
took a decision of dismantling all the M.L.A. Flats for
constructing a multi-storied building.
5. This was communicated to the petitioner,
which is being denied by him presently.
6. The matter was taken to the Bihar Public
Works Contracts Disputes Arbitration Tribunal Act, 2008
for a direction to the respondents to make good the
payment of the bills raised by the petitioner.
7. The claim of the respondents is that the
petitioner had not started his work till 10.03.2012 and
Patna High Court CWJC No.19096 of 2016 dt.20-01-2025
3/4
shortly, thereafter, he was instructed to cease any further
repair for the decision of the Government to dismantle
the houses. In fact, the respondents before the Tribunal
asserted that a spot verification was made and it was
found that no work had been started/executed till
10.03.2012.
8
. There is also no entry in the measurement
book by the respondents.
9. The petitioner seeks to rest his claim on a
proceeding of Bihar Vidhan Sabha where an issue was
raised that the Government money is being mis-spent
over repairs, electrical and civil, even when the buildings
are under demolition.
10. In answer to the afore-noted question
on 28.03.2012, the Government responded that some
repair works have been done.
11. This, we are afraid, is no indication of
the petitioner having carried out the electrical repair
works in the concerned M.L.A. Flats.
Patna High Court CWJC No.19096 of 2016 dt.20-01-2025
4/4
12. For the absence of any counter signature
of any one of the respondent authorities in the
measurement book and no certification of the work having
been completed, the claim of the petitioner remains only
an affidavit against a counter affidavit.
13. Though the learned counsel for the
petitioner has tried to impress upon this Court that the
entire work entrusted to him was executed by him, but
there does not appear to be any material for us to decide
the correctness of such claim.
14. In view of such situation, we do not find
any fault with the order passed by the Tribunal rejecting
the claim of the petitioner.
15. The writ petition is dismissed.
(Ashutosh Kumar, ACJ)
(Partha Sarthy, J)
Praveen-II/-
AFR/NAFR NAFR CAV DATE N/A Uploading Date 21/01/2025 Transmission Date N/A
[ad_1]
Source link
