M/S Soltown Infra Private Limited vs Central Transmission Utility Of India … on 1 July, 2025

0
1


Rajasthan High Court – Jodhpur

M/S Soltown Infra Private Limited vs Central Transmission Utility Of India … on 1 July, 2025

Author: Rekha Borana

Bench: Rekha Borana

[2024:RJ-JD:38136]

      HIGH COURT OF JUDICATURE FOR RAJASTHAN AT
                       JODHPUR
                 S.B. Civil Writ Petition No. 9702/2024

1.       M/s Soltown Infra Private Limited, Through Its Authorized
         Signatory Gouri Shankar Having Its Registered Office At
         R-1, Off No. -1, Shree S Mohar Plaza, Yudhisir Marg, C-
         Scheme, Jaipur, Rajasthan- 302001.
2.       Mr Rahul Gupta S/o Rajendra Prasad Gupta, Aged About
         35 Years, Director, Soltown Infra Private Limited Having
         His Office At R-1, Off No. -1, Shree S Mohar Plaza,
         Yudhistir Marg, C-Scheme, Jaipur, Rajasthan - 302001.
3.       Mr Arunabh Mohanty S/o Jagdish Chandra Mohanty, Aged
         About 36 Years, Director, Soltown Infra Private Limited,
         Having His Office At R-1, Off No. -1, Shree S Mohar Plaza,
         Yudhistir Marg, C-Scheme, Jaipur, Rajasthan - 302001.
                                                                    ----Petitioners
                                     Versus
Central Transmission Utility Of India Ltd., Through Its Chairman
Plot No. 2, Near Iffco Chowk Metro Station, Sector 29,
Gurugram- 122 001 Haryana.
                                                                   ----Respondent


For Petitioner(s)          :     Mr. Vikas Balia Sr. Adv. Asst by
                                 Mr. Aditya Kumar Singh
                                 Mr. Devendra Khatri
                                 Ms. Anukriti Jain
                                 Mr. Ashok Choudhary
For Respondent(s)          :     Mr. Alok Shankar
                                 Mr. Falgun Buch with
                                 Mr. Gopal Kishan Chhangani



              HON'BLE MS. JUSTICE REKHA BORANA

Order

01/07/2025

1. The present writ petition has been filed aggrieved of

letter/communication date 23.02.2023 (Annexure-1) whereby the

petitioner-firm had been black-listed from applying for and

obtaining any connectivity or open access with Central

(Downloaded on 02/07/2025 at 09:43:10 PM)
[2024:RJ-JD:38136] (2 of 20) [CW-9702/2024]

Transmission Utility of India Limited (hereinafter referred to as,

the ‘CTU/Nodal Agency’) for a period of three years.

2. The facts as pleaded in the writ petition and the reply to the

writ petition, in brief, are as under:

(i) The petitioner firm being authorized by the Government of

Rajasthan to develop Solar Park in the State of Rajasthan, applied

for Stage I connectivity for 600 MWs and 1200 MWs on

12.10.2021 and 30.11.2021 respectively. The Stage I connectivity

as applied for was granted to the petitioner-firm vide intimation

dated 21.12.2021 and 22.01.2022.

(ii) Clause 9.2.2 of Connectivity Procedure provides for

conditions to be complied with for the grant of Stage II

connectivity. The petitioner-firm finding itself eligible to apply for

Stage II connectivity, submitted three applications for 500 MWs,

600 MWs and 700 MWs for the purpose. The said Stage II

connectivity as applied for was granted to the petitioner- firm on

07.03.2022 vide three different intimation letters to the said

effect. All the said applications were granted qua the ISTS sub-

station at Bikaner II PS.

(iii) The transmission agreements to the effect were also

executed between the parties on 12.04.2022 (Annexure-10).

(iv) Anonymous complaints dated 14.07.2022 and 25.07.2022

were received by the respondent CTU/Nodal Agency pertaining to

the land documents as submitted by the petitioner-firm. A detailed

enquiry was made by the respondent CTU on the said complaints

and it was prima facie found that deliberate misrepresentations

(Downloaded on 02/07/2025 at 09:43:10 PM)
[2024:RJ-JD:38136] (3 of 20) [CW-9702/2024]

were made and misleading documents were submitted by the

petitioner-firm to CTU to approve the satisfaction of the conditions

for grant of Stage II connectivity in terms of Clause 9.2.2, which

amounted to fraud.

(v) Show cause notice dated 04.08.2022 was hence issued to

the petitioner-firm calling upon to explain the deliberate

misrepresentation. Petitioner-firm prayed for extension of time to

file reply to the said notice and also for a personal hearing. Both

the said requests were acceded to and the petitioner-firm was

granted a personal hearing on 29.08.2022.

(vi) However, the firm failed to satisfactorily explain the

infirmities in the applications as submitted by it for grant of Stage

II connectivity and admitted the mistakes on its part. Ultimately,

vide letter dated 30.08.2022, the firm withdrew the Stage II

connectivity as awarded to it, unconditionally.

(vii) Acting upon the request of the petitioner-firm for

unconditional withdrawal, vide letter dated 31.08.2022, CTU/Nodal

Agency revoked the connectivity granted to the petitioner-firm

cumulatively for 1800 MWs and further terminated the

transmission agreements dated 12.04.2022 with immediate effect.

Further, the bank guarantee as submitted by the firm was also

encashed by CTU and was credited to the Transmission Charges

Pool (POC pool) on 11.09.2022.

(viii) The above revocation and termination was made by

CTU/Nodal Agency reserving its right with regard to the infirmities

pointed out in its earlier communication.

(Downloaded on 02/07/2025 at 09:43:10 PM)
[2024:RJ-JD:38136] (4 of 20) [CW-9702/2024]

(ix) In pursuance to the right reserved, CTU/Nodal Agency

proceeded on to act further and after finding the reply/defence as

furnished/raised by the petitioner-firm to show cause notice dated

04.08.2022, to be unsatisfactory held that the petitioner-firm

committed a fraud. Consequently, vide order impugned dated

23.03.2023, it proceeded on to black-list the petitioner-firm for a

period of three years.

3. It is the above order dated 23.03.2023 which is under

challenge in the present petition.

4. Learned counsel for the petitioner raised the following grounds:

(i) The CTU being only a nodal agency has no authority to blacklist

the firm. It could only have acted in terms of the conditions of the

agreement and that having already done i.e. the bank guarantee

having been encashed and the agreement been terminated, no

further action so as to blacklist the firm could have been taken by

the said Nodal Agency. Once the agreement itself was terminated,

the Nodal Agency was not empowered to act further. Moreover, no

clause of the agreement governing the parties empowered the

respondent agency to blacklist the firm.

(ii) The action of blacklisting is in clear violation of statutory

right provided to the petitioner firm in terms of the Electricity

Act,2003. The Electricity Act provides for the right of open access

and connectivity and the CTU has no option but to allow

connectivity and open access if the firm complies with all the

technical requirements stipulated in the applicable regulations.

CTU being a mere Nodal Agency has no discretion to

(Downloaded on 02/07/2025 at 09:43:10 PM)
[2024:RJ-JD:38136] (5 of 20) [CW-9702/2024]

refuse/restrain open access and connectivity if the firm complies

with the regulations.

(iii) The right to connectivity, open access and generate

electricity is a statutory grant in terms of Electricity Act and not a

contractual grant. Further, open access is not a privilege but a

right as held by Hon’ble the Apex Court in Patel Engineering

Ltd. Vs. Union of India; (2012) 11 SCC 257 and Kulija

Industries Ltd. Vs. Western Telecom Project BSNL; (2014)

14 SCC 731. The said statutory right has been sought to be

curtailed by respondent CTU totally in contravention to the settled

position of law.

(iv) Even after show cause notice dated 04.08.2022 been

replied to, when no conclusion was arrived at, the petitioner firm,

of its own accord, withdrew the Stage II connectivity granted to it.

In pursuance to the said withdrawal, the agreements were

terminated and even the bank guarantee of the firm was

encashed. Once the said action was taken, cause if any, came to

an end/ceased. The further action in pursuance to same show

cause notice dated 04.08.2022 clearly amounted to ‘double

jeopardy’. Second penalty for the same cause of action amounting

to double jeopardy definitely needs interference by this Court. In

support of this submission, counsel relied upon the judgment of

Hon’ble Apex Court in Lt. Governor, Delhi & Ors. Vs. HC

Narinder Singh; (2004) 13 SCC 342.

(v) The whole action of CTU has been on the ground that the

firm had duplicated and submitted the same land rights related

documents in more than one application and further that the same

(Downloaded on 02/07/2025 at 09:43:10 PM)
[2024:RJ-JD:38136] (6 of 20) [CW-9702/2024]

computer generated endorsements had been submitted with

different land right related documents purporting them to be

registered. But no such action was proved to have been

committed by the firm. The specific contention of the petitioner

firm was that the firm did not gain any advantage by

incorporating/undertaking any wrong land documents as there

was no minimum land requirement either on the date of

application filed by the petitioner or on the date of issuance of the

blacklisting notice. When there was no minimum land

requirement, the alleged false representation even if any, could

not have granted any advantage to the petitioner-firm and hence,

no fraud can be concluded.

(vi) A fraud can be concluded only if a false representation is

made to gain some undue advantage. No undue advantage having

been proved in the matter, the action of the respondent – CTU was

clearly arbitrary.

(vii) The specific contentions of the petitioner-firm denying the

allegations of fraud were not even dealt with by the respondent-

CTU while passing the order/communication impugned. Had the

same been considered, it would very well have been clarified that

the discrepancies as pointed out by the respondent-CTU were just

the inadvertent errors which even stood rectified by the firm when

pointed out. The said inadvertent errors neither resulted into any

undue advantage to the petitioner-firm nor to any injury/loss to

respondent-CTU. In that situation, the petitioner-firm having

already penalized by encashment of bank guarantee, could not

have been further penalised by a major penalty of blacklisting.

(Downloaded on 02/07/2025 at 09:43:10 PM)
[2024:RJ-JD:38136] (7 of 20) [CW-9702/2024]

5. Responding to the grounds as raised by counsel for the

petitioner, counsel for the respondent submitted that the minimum

land requirement for Stage II connectivity was definitely provided

in the regulations. Counsel while relying upon Clause 9.2.2

submitted that one of the requisite milestone to apply for Stage II

connectivity was the ownership or lease rights or land use rights

for 50% of the land required for the capacity of Stage II

connectivity. Therefore, the submission made by counsel for the

petitioner that there was no minimum land requirement is totally

fallacious.

6. Responding to the ground that no fraud was proved on

record, Counsel submitted that the fact of petitioner-firm having

duplicated and submitted the same land documents in more than

one application and further, the same computer generated

endorsements having been submitted with different land

documents, was rather admitted by the petitioner-firm may be on

the pretext of an ‘inadvertent error’. It is only because of the said

admitted facts of misrepresentation and manipulation that the firm

on its own accord, moved an application for withdrawal of the

Stage II connectivity as granted to it. The said withdrawal of the

firm clearly amounted to admission and once the duplication of

documents and misrepresentation was admitted, no further

action/evidence to prove the fraud was even required. The facts

speak for themselves and same having been admitted, required no

further proof.

7. Responding to the ground of double jeopardy raised by

counsel for the petitioner, counsel for the respondent submitted

that the impugned action was in furtherance to show cause notice

(Downloaded on 02/07/2025 at 09:43:10 PM)
[2024:RJ-JD:38136] (8 of 20) [CW-9702/2024]

dated 04.08.2022 only. The termination of the agreements was

with a specific stipulation that the same was without prejudice to

CTUs rights in regard to infirmity pointed out in show cause notice

dated 04.08.2022 as well as the material shared during personal

hearing held on 29.08.2022.

8. Counsel further submitted that the plea of legitimate

expectation is barred in cases of express fraud and once the

fraudulent conduct of the petitioner-firm was crystal clear, it could

not have been ignored by the State agency and it deserved a

logical conclusion.

9. While arguing that the responent-CTU was very well

competent and empowered to blacklist the firm, counsel while

relying upon the judgment of Patel engineering (supra)

submitted that the authority of the State to blacklist a person is a

necessary concomitant to the executive part of the State to carry

on the trade or business and making all contracts for any purpose

and there need not be any statutory grant of such power. The only

legal limitation upon the exercise of such an authority is that the

State is to act fairly and rationally without in any way being

arbitrary.

10. With the above submissions counsel submitted that the

impugned order/communication was totally within the jurisdiction

of the respondent-CTU and hence, deserves to be affirmed.

11. Heard the counsels and perused the record.

12. The format of Application for Stage II connectivity

specifically provided for certain undertakings to be given by the

applicant. One of the said undertaking provided as under:-

(Downloaded on 02/07/2025 at 09:43:10 PM)

[2024:RJ-JD:38136] (9 of 20) [CW-9702/2024]

“I hereby undertake that the undertaking and other
documents (if any) submitted in order to meet the
eligibility conditions (e.g., LOA, ownership of land,
financial closure, auditor’s certificate regarding release
of funds etc. submitted for eligibility for Stage-II
connectivity) have not been and shall not be used as
eligibility documents for any other Stage-II application.
In case of any default in this regard, the application shall
be liable for rejection along with all associated legal and
regulatory liabilities.”

Admittedly, the above undertaking was given by the petitioner-

firm while applying for Stage II connectivity.

13. Show Cause Notice dated 04.08.2022 as served on the firm,

incorporated the following averments:-

“3. Whereas, SOLTOWN had submitted Title Report(s) by a
registered Advocate, Auditor’s certificate(s) by a Chartered
Accountant and Self Certificate Declaration-cum-
Undertaking(s) towards satisfaction of the prescribed
eligibility criteria under Clause 9.2.2 of the Revised
Procedure with its applications along with Affidavit in terms
of CTU advisory. In this regard, in the Declaration-cum-
Undertaking submitted along with the applications
SOLTOWN had undertaken and submitted the “We
undertake that the subject land has not been/will
not be used for any other purpose/project”. Further,
in the Affidavit submitted with these applications by
SOLTOWN, it had been submitted that:

“3. I am aware that if at any stage any
falsity/inaccuracy/incorrectness is detected in
the document/statements, the application itself
or the grant of Connectivity shall be liable for

(Downloaded on 02/07/2025 at 09:43:10 PM)
[2024:RJ-JD:38136] (10 of 20) [CW-9702/2024]

rejection or revocation (as the case may be) along
with all consequences in this regard.”

4. Whereas, upon receipt of information about certain
infirmities/anomalies in the Stage-II Connectivity
applications made by SOLTOWN, a post grant detailed
scrutiny by CTU was carried in respect of all the three
connectivity applications aggregating 1800 MW. This
examination inter alia revealed that SOLTOWN has
duplicated and submitted the same land right related
documents in more than one application and also, the
same computer-generated endorsements have been
submitted with different land right related documents
purporting it to be registered.

5. Whereas, prima facie it appears that SOLTOWN has,
deliberately misrepresented and misled CTU to approve the
satisfaction of the conditions for grant of Stage-II
connectivity under Clause 9.2.2 which constitutes a fraud.
Consequently, the grant of Stage-II connectivity in favour
of SOLTOWN is vitiated by reason of such wilful and
deliberate act on the part of SOLTOWN.

6. And, therefore, SOLTOWN is hereby called upon to
explain within 7(seven) days from the date of this notice
(addressed by both email/Registered AD), why 1800 MW
(aggregate) Connectivity granted to Soltown Infra Private
Limited vide CTU letter Ref No. C/CTU/N/05/1200003573,
C/CTU/N/05/1200003579, C/CTU/N/05/1200003603 dated
07.03.2022 cannot be revoked along with all associated
consequences for deliberately misrepresenting and
misleading CTU and for acting contrary to Clause 9.2.2 of
the Revised Procedure for grant of Stage-II connectivity. In
case no reply/representation is received within the
stipulated time, it will be presumed that you have no cause
and appropriate action will be initiated accordingly.”

(Downloaded on 02/07/2025 at 09:43:10 PM)
[2024:RJ-JD:38136] (11 of 20) [CW-9702/2024]

14. In reply dated 18.08.2022 to one of the notice dated

04.08.2022 as submitted by the petitioner-firm, it was responded

as under:-

“6. Because your Notice does not specify which land right
related documents are duplicated and which computer-
generated endorsements have been submitted with
different land right related documents purporting it to be
registered. During the discussions with your team,
following observations were pointed out:

a. In application No.120003573 (500 MW) two land
documents mentioned titled Harvindra Puri (15.61 Acre) in
page no. 129-136 and Devendra Puri (14.06 Acre) In page
no. 214-219 of the submitted land documents are not
included/claimed for qualification in the annexure (which
details the land parcels being used in the application no.
1200003573 (500 MW) to satisfy the requirements of
Clause 9.2.2 of the Revised Procedure). This means that
we had not used or claimed this additional land to satisfy
the land requirement in clause 9.2.2 of the Revised
Procedure. Due to a clerical mistake these two
additional and unclaimed documents got uploaded
with other land documents. Our application No.
1200003573 (500 MW) satisfies the land requirement
without counting the additional and unclaimed land in these
two land documents, and as such is complete without the
two land documents. The copy of the previously uploaded
documents with application No. 1200003573 after removal
of the two mistakenly added documents is enclosed
herewith as Enclosure (1). Kindly note that we gained no
benefit whatsoever by having made the mistake of placing
these two additional and unclaimed documents with the
application. The fact that these two documents were
mistakenly placed on record and not deliberately is evident

(Downloaded on 02/07/2025 at 09:43:10 PM)
[2024:RJ-JD:38136] (12 of 20) [CW-9702/2024]

from the fact that we did not use the land in these two
documents towards satisfying the land requirement as
stated in the ANNEXURE to the application. i.e. There is no
mention of these two parcels of additional and unclaimed
land in the application besides simply being annexed with
the application. It is clarified that there is a mention of
every other parcel of land (other than these two) in the
ANNEXURE to the application No. 1200003573 (500 MW)
as having satisfied the land requirement in Clause 9.2.2.
Kindly appreciate that all the land documents mentioned in
the ANNEXURE and uploaded with the application No.
120003573 (500 MW) are complete and sufficient without
considering the two afore-stated land parcels. As of today,
the project has much more than land required under clause
9.2.2.

b. Kindly appreciate that all the land documents mentioned
in the ANNEXURE and uploaded with the application No.
1200003573 (500 MW) are complete and sufficient without
considering the two afore-stated land parcels. As of today,
the project has much more land.”

15. In reply dated 18.08.2022 to the second notice dated

04.08.2022, it was responded by the petitioner-firm as under:-

“Because your Notice does not specify which land right
related documents are duplicated and which computer-
generated endorsements have been submitted with different
land right related documents purporting it to be registered.
During the discussions with your team, following
observations were pointed out:

a. In Application No. 1200003603 (700 MW), four land
parcels out of 27 were mistakenly uploaded. The fact
is that, there were other land parcels with the registry
of the same date which were to be uploaded with the
Application No. 1200003603 (700 MW), but among

(Downloaded on 02/07/2025 at 09:43:10 PM)
[2024:RJ-JD:38136] (13 of 20) [CW-9702/2024]

land documents of 80 land parcels uploaded, a clerical
error occurred, and these 4 wrong documents were
uploaded. A list of the details of these wrongly uploaded
documents is annexed herewith as Enclosure {3a}. The fact
that we had other three land documents, the registration
date of which land documents pre-date our application and is
infact of same day as of the 4 wrongly submitted land
parcels i.e. all dated 30.11.2021 demonstrates that this was
not done deliberately. We are submitting the correct land
documents with this reply as Enclosure {3b} (collectively).
Kindly appreciate that as on the date this mistake was
made, we had the requisite amount of land vis-à-vis the four
parcels of land which we mistakenly put in the application,
but we mistakenly did not place the correct land documents
on record. Copies of correct land documents relating to the
correct 3 land parcels is attached herewith as Enclosure
{3}.

b. The land documents attached with Application no.
1200003603 (700 MW) contains nine land documents
with which different registration endorsements were
uploaded due to a clerical mistake. These
endorsements are for different lands and not belong
to these 9 land agreements. These endorsements may
be ignored. It is stated that there is no duplication in these
nine land parcels. Kindly appreciate that we have registered
more then 80 lands for the application and over 2000 acres
in quantum,. While managing these almost 1000 papers, a
bonafide error happened during the uploading of the
documents.”

16. A bare perusal of the above averments as made by the

petitioner-firm in its replies to the show cause notice reflects that

the fact of 04 land documents being wrongly uploaded qua

application for grant of connectivity of 700 MWs out of 27 land

documents was admitted. Further, uploading of 09 land documents

(Downloaded on 02/07/2025 at 09:43:10 PM)
[2024:RJ-JD:38136] (14 of 20) [CW-9702/2024]

with different registration endorsement was also admitted, may be

on the pretext of ‘inadvertent error’ or a ‘clerical mistake’.

17. The fact of personal hearing being given to the petitioner-

firm has also not been denied. After the personal hearing being

given, admittedly the matter remained unresolved and hence, the

firm applied for withdrawal of Stage II connectivity vide its letter

dated 30.08.2022 (Annex.17) with the following averments:

“Based on the notice received on 4 th August 2022, we
responded by our letter dated 18.08.2022 & 21.08.2022.
We further interacted with the CTU team on 11.08.2022
and 29.08.2022. As the matter under discussion still
remain unresolved, Therefore we wish to
unconditionally withdraw our three Stage II
connectivity’s awarded as per the above mentioned
letters.

Request you to kindly acknowledge this letter. Thank you.”

18. Respondent-CTU acted upon communication dated

30.08.2022 of the petitioner-firm and vide communication/order

dated 31.08.2022 (Annex.18) revoked the Stage II connectivity

while observing as under:-

“Accordingly, in the light of the above representation by the
SOLTOWN in the communication dated 30.08.2022, the
Stage-II Connectivity granted to SOLTOWN vide intimation
nos. C/CTU/N/05/1200003573, C/CTU/N/05/1200003579,
and C/CTU/N/05/1200003603 all dated 07.03.2022 stand
revoked (along with bays allocated vide letter dated
12.07.2022) and Transmission Agreements dated
12.04.2022 stand terminated with immediate effect along
with the following consequences:

(Downloaded on 02/07/2025 at 09:43:10 PM)

[2024:RJ-JD:38136] (15 of 20) [CW-9702/2024]

(a) SOLTOWN shall not have any right to claim under
the subject Stage-II Connectivity grants and the same
shall stand terminated for all intent and purposes at the
instance of SOLTOWN;

(b) CTU shall be entitled to encash Connectivity Bank
Guarantee in the sum of Rs.Fifty (50) Lakh issued by
ICICI Bank in favor of CTU and appropriate the amount
irrevocably without any right of SOLTOWN to claim any
amount from CTU.

The above actions by CTU shall be without prejudice to
its rights in regard to the infirmities pointed out by
CTU in the communications resting with the CTU show
cause notice dated 04.08.2022 as well as the material
shared by CTU during the personal hearing held on
29.08.2022. Save as mentioned hereinabove, all claims
made by SOLTOWN in the representations made are denied.
Thanking you,”

19. A bare perusal of all the above facts clearly reveal that the

fact of duplication of documents and endorsement of wrong land

documents was rather admitted on part of the petitioner-firm and

it is only because of the said action that it proceeded on to apply

for withdrawal of the Stage II connectivity as granted to it,

unconditionally.

20. So far as the revocation of the grant and termination of the

transmission agreements is concerned, communication dated

31.08.2022 clearly reflects that the same was done by the CTU

without prejudice to its rights in regard to infirmity as pointed out

vide show cause notice dated 04.08.2022 as well as the material

shared on 29.08.2022 i.e. the date of personal hearing. In view of

the same, this Court is of the clear opinion that the revocation of

the grant and termination of the agreements cannot be concluded

(Downloaded on 02/07/2025 at 09:43:10 PM)
[2024:RJ-JD:38136] (16 of 20) [CW-9702/2024]

to be a final disposal of the matter for all purposes. CTU definitely,

vide communication dated 31.08.2022, reserved its rights to act

further regarding the infirmities. Therefore, it cannot be held that

after termination of the agreements, CTU could not have acted

further in the matter. The misrepresentations having been

admitted by the petitioner-firm, the action thereupon was a

necessary corollary, that too, in view of the fact that a specific

undertaking (as reproduced in the preceding para) was given by

the petitioner-firm to the effect that the land documents used qua

one application shall not be used as eligibility documents for any

other Stage II connectivity. Thereby, the firm specifically

undertook that in case of any default, it shall be liable for rejection

along with all associated legal and regulatory liabilities.

21. Black-listing a firm found to be evolved in fraudulent

practice is not a concept foreign to contractual law. The law

specifically provides for restraining any firm to enter into any

further business relations with a party if it is found to have

committed any fraud with the other party. As observed by Hon’ble

the Apex Court in Patel Engineering (supra), the decision of

State or its instrumentality not to deal with certain persons or

class of persons on account of undesirability of entering into

contractual relationship with such persons is called ‘blacklisting’

and the State can decline to enter into a contractual relationship

with a person or a class of persons for a legitimate purpose.

Therein, Hon’ble the Apex Court held as under:

“The authority of State to blacklist a person is a necessary
concomitant to the executive power of the State to carry on
the trade or the business and making of contracts for any

(Downloaded on 02/07/2025 at 09:43:10 PM)
[2024:RJ-JD:38136] (17 of 20) [CW-9702/2024]

purpose, etc. There need not be any statutory grant of
such power. The only legal limitation upon the exercise of
such an authority is that State is to act fairly and rationally
without in any way being arbitrary – thereby such a decision
can be taken for some legitimate purpose. What is the
legitimate purpose that is sought to be achieved by the
State in a given case can vary depending upon various
factors.”

22. Hon’ble the Apex Court in Kulija Industries ltd. (supra)

also laid down the same proposition of law. Therein, the Hon’ble

Court held as under:

“That apart, the power to blacklist a contractor
whether the contract be for supply of material or
equipment or for the execution of any other work
whatsoever is in our opinion inherent in the party
allotting the contract. There is no need for any such
power being specifically conferred by statute or
reserved by contractor. That is because “blacklisting”

simply signifies a business decision by which the party
affected by the breach decides not to enter into any
contractual relationship with the party committing the
breach. Between two private parties the right to take any
such decision is absolute and untrammelled by any
constraints whatsoever. The freedom to contract or not to
contract is unqualified in the case of private parties. But
any such decision is subject to judicial review when the
same is taken by the State or any of its instrumentalities.
This implies that any such decision will be open to scrutiny
not only on the touchstone of the principles of natural
justice but also on the doctrine of proportionality. A fair
hearing to the party being blacklisted thus becomes an
essential precondition for a proper exercise of the power
and a valid order of blacklisting made pursuant thereto.
The order itself being reasonable, fair and proportionate to

(Downloaded on 02/07/2025 at 09:43:10 PM)
[2024:RJ-JD:38136] (18 of 20) [CW-9702/2024]

the gravity of the offence is similarly examinable by a writ
court. The legal position on the subject is settled by a long
line of decisions rendered by this Court starting with
Erusian Equipment & Chemicals Ltd. v. State of West
Bengal and Anr.
(1975) 1 SCC 70 where this Court
declared that blacklisting has the effect of preventing a
person from entering into lawful relationship with the
Government for purposes of gains and that the Authority
passing any such order was required to give a fair hearing
before passing an order blacklisting a certain entity. This
Court observed:

“20. Blacklisting has the effect of preventing a person
from the privilege and advantage of entering into
lawful relationship with the Government for purposes
of gains. The fact that a disability is created by the
order of blacklisting indicates that the relevant
authority is to have an objective satisfaction.
Fundamentals of fair play require that the person
concerned should be given an opportunity to
represent his case before he is put on the blacklist.”

23. What can be concluded from the above ratio is that power

to blacklist a contractor is inherent in the party allotting the

contract. There is no need for any such power conferred by any

Statute or reserved by the contractor. The right to take such

decision if exercised between private parties, the same is absolute

and untrammelled by any constraints. If such right is exercised by

the State or any of its instrumentality, the same is subject to

judicial review. But then, the said scrutiny can also be only on the

touchstone of the principles of natural justice and the doctrine of

proportionality. Meaning thereby, a judicial review of an order of

blacklisting is permissible only if a fair opportunity of hearing has

(Downloaded on 02/07/2025 at 09:43:10 PM)
[2024:RJ-JD:38136] (19 of 20) [CW-9702/2024]

not been granted to the incumbent or the order of blacklisting is

highly disproportionate to the gravity of offence.

24. Applying the above ratio to the present matter herein, it is

not denied that the petitioner-firm after being served with notice

dated 04.08.2022, applied twice for extension of time to file reply

and the same was granted both the times. Further, the petitioner-

firm prayed for personal hearing and that too was granted.

Therefore, it is crystal clear that a fair opportunity of hearing was

very well granted to the petitioner-firm by the respondent-CTU.

25. So far as the proportionality of order of blacklisting is

concerned, this Court is of the opinion that in the present

circumstances wherein the fact of duplicating the land documents

and further endorsing the wrong documents with the registration

numbers of some other land documents is evident and rather

admitted on record. It is clear that the petitioner-firm annexed the

same land documents with two different applications which was in

total contravention to the conditions of the regulations and in

contravention to the undertaking given by it.

26. Further, it is also clear on record that the registration

number of some other land documents were furnished along with

the application form which did not even pertain to the land

documents as submitted. The same clearly was with an intent to

avail undue advantage in order to fulfill the criteria as provided in

Clause 9.2.2. The above fraud being proved on record, the same

definitely could not have been ignored by the respondent-CTU.

Fraud committed whenever and wherever, has to be taken care of

and the same cannot be permitted to be given a go-bye. Once it

was proved on record that the petitioner firm had committed a

(Downloaded on 02/07/2025 at 09:43:10 PM)
[2024:RJ-JD:38136] (20 of 20) [CW-9702/2024]

fraud, the respondent-CTU definitely was empowered to take a

decision not to enter into any contractual relationship with the

petitioner firm, in future. The action of the respondent-CTU

therefore cannot be said to be arbitrary or against any provision of

law. The same being totally in consonance with the settled

position of law, the order impugned does not deserve any

interference and the writ petition is hence, dismissed.

27. Stay petition and pending applications, if any, stand

disposed of.

(REKHA BORANA),J
186-Praveen/Devanshi/-

(Downloaded on 02/07/2025 at 09:43:10 PM)

Powered by TCPDF (www.tcpdf.org)



Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here