Niradhar Swavalamban Samiti And Anr vs The Executive Engineer Town Planning … on 30 June, 2025

0
2


Bombay High Court

Niradhar Swavalamban Samiti And Anr vs The Executive Engineer Town Planning … on 30 June, 2025

Author: G. S. Kulkarni

Bench: G. S. Kulkarni

2025:BHC-AS:25996-DB                                                                WP-2225-2022.DOC



                              IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                        CIVIL APPELLATE JURISDICTION

                                       WRIT PETITION NO. 2225 OF 2022

             Niradhar Swavalamban Samiti & Anr.               ...Petitioners
                   Versus
             The Executive Engineer, Town Planning Dept.
             Nashik Municipal Corporation & Ors.            ...Respondents
                                                _______
             Mr. Sachin Punde i/b Anuj Tiwari for the Petitioners.
             Mr. Subhash V. Gutte a/w Ms. Sayali Gutte for Respondent Nos. 1 to 3.
                                                     _______

                                       CORAM                    : G. S. KULKARNI &
                                                                  ARIF S. DOCTOR, JJ.
                                       RESERVED ON              : 24th JUNE 2025
                                       PRONOUNCED ON            : 30th JUNE 2025


             Judgment (Per: Arif S. Doctor, J.)

             The Parties

1. Petitioner No. 1 (‘the Petitioner’) is an educational trust established under the

provisions of the Maharashtra Public Trust Act, 1950, and runs schools for the

benefit of students who are from the economically weaker section of society. One

such school run by the Petitioner is ‘Nutan Prathamik VidyaMandir’, which is

stated to impart free education to about 568 students. Petitioner No. 2 is the

secretary of Petitioner No. 1.

2. Respondent No. 1 is the Executive Engineer, Town Planning Department,

which is an authority under the provisions of the Maharashtra Regional Town

Planning Act, 1966 (‘the MRTP Act’) and is the authority which grants

permissions for construction. Respondent No. 2 is the Commissioner, Nashik

Page 1 of 10
Ajit Pathrikar

::: Uploaded on – 30/06/2025 ::: Downloaded on – 30/06/2025 22:31:56 :::
WP-2225-2022.DOC

Municipal Corporation (‘NMC’), and Respondent No. 3 is the Administrative

Officer of the Department of Education of NMC.

The factual context in which the Petition arises:

3. Respondent No. 1 had, vide an order dated 23rd November 2020 (‘the

permission’), granted permission to the Petitioner for the construction of a

building (‘the said Building’) on a plot bearing Gat No. 60 situated near Shivar

Chunchle within the territorial limits of the Nashik Municipal Corporation (‘the

said plot’). It is not in dispute that the said plot is reserved for educational

purposes. The Petitioner, post the grant of the permission, commenced

construction and has completed construction up to the first floor.

4. However, on the basis of certain complaints addressed to Respondent No. 3

(the Administrative Officer of the Education Department, NMC) by the president

of one Ambika Mitra Mandal, stated to be a rival educational institute, Respondent

No. 3 has addressed a communication dated 30th July 2021, by which Respondent

No. 3 has inter alia stated that the construction of the said Building by the

Petitioner is illegal and that no primary or secondary school can be started on the

said plot.

5. The Petitioner responded to the aforesaid communication, inter alia,

informing Respondent No. 3 that the Petitioner has applied for all the permissions

and follow all the requisite rules prior to starting a primary or secondary school

from the said building. The Petitioner also questioned the authority of Respondent

No. 3 to refuse permission for construction of the said Building.

Page 2 of 10
Ajit Pathrikar

::: Uploaded on – 30/06/2025 ::: Downloaded on – 30/06/2025 22:31:56 :::
WP-2225-2022.DOC

6. However, on 25th August 2021, Respondent No. 3 addressed a further

communication to the Petitioner stating that under the provisions of the new

policy, permission of the State Government was necessary to start a new school.

Respondent No. 3 also called upon the Petitioner to file an Affidavit within 7 days

therefrom, stating as to what educational purpose the said Building would be used

for. The Petitioner was also put to notice that if the Petitioner failed to do so,

Respondent No. 3 would intimate the NMC to stop further construction of the

said Building.

7. The Petitioner, by its letter dated 17th September 2021, responded to the

above communication and reiterated that operations of the school would only be

started only after obtaining necessary permissions from the Education Department

of NMC and stated that such permissions could only be applied for after the

construction of the said Building was completed. Respondent No. 3, however,

thereafter issued a letter dated 21st September 2021 (‘the first impugned

communication’) calling upon the Petitioner to stop construction of the said

Building.

8. Subsequently, Respondent No. 1 also, vide an order dated 15th November

2021 (‘the impugned order’), stayed the operation of the permission granted and

called upon the Petitioner to submit a fresh proposal for a new construction.

9. The Petitioner responded to Respondent No. 1 inter alia, stating that such

suspension of the permission already granted was illegal and that Respondent No.

1 had failed to set out a single breach of the said permission committed by the

Page 3 of 10
Ajit Pathrikar

::: Uploaded on – 30/06/2025 ::: Downloaded on – 30/06/2025 22:31:56 :::
WP-2225-2022.DOC

Petitioners which would warrant such suspension of the permission already granted

and plans already sanctioned.

10. The Petitioner made a further representation to Respondent No. 3 on 19 th

January 2022, requesting Respondent No. 3 to reconsider the first impugned

communication. However, Respondent No. 3 refused to do so and vide a letter

dated 20th January 2022 (‘the second impugned communication’), confirmed the

stand taken by Respondent No. 3 in the first impugned communication.

11. It is on such backdrop that the Petitioners have filed the present Petition

seeking the following substantive reliefs:

“(a) Issue an appropriate Writ/Order, for quashing and setting aside the
Orders dated 21.09.2021 and 20.01.2022 issued by the Respondent No.3
the same being illegal, arbitrary and without jurisdiction.

(b) Issue an appropriate Writ/Order, for quashing and setting aside the Order
dated 15.11.2021 issued by the Respondent No.1 Executive Engineer,
Nashik Municipal Corporation the same being illegal, arbitrary and without
jurisdiction.”

Submissions on behalf of the Petitioners

12. Mr. Punde, Learned Counsel for the Petitioners, at the outset, submitted that

Respondent No. 3 had absolutely no authority in law to issue the impugned

communications dated 21st September 2021 and 20th January 2022. He submitted

that the construction being undertaken by the Petitioner had commenced pursuant

to the permission/order dated 23rd November 2020 issued by Respondent No. 1,

being the designated authority for granting permission for construction under the

provisions of the MRTP Act. He would urge that Respondent No. 3 was the

administrative officer of the Department of Education who had no jurisdiction or

Page 4 of 10
Ajit Pathrikar

::: Uploaded on – 30/06/2025 ::: Downloaded on – 30/06/2025 22:31:56 :::
WP-2225-2022.DOC

any role to play in the matter of construction and/or granting of building

permissions but was only concerned with the administration of the Education

Department of NMC. He thus submitted that Respondent No. 3 did not have any

authority in law to revoke building permission which had been validly issued by

Respondent No. 1.

13. Mr. Punde then pointed out from the Petition that Respondent No. 3 solely

on the basis of a complaint made by the president of one Ambika Mitra Mandal, a

rival educational institute, issued the impugned communications. He thus

submitted that not only was the issuance of the impugned communications beyond

the authority of Respondent No. 3 but also malafide. He therefore argued that the

impugned communications were clearly illegal.

14. Mr. Punde then pointed out that the proposal for development as made by

the Petitioners was in compliance with the provisions of the MRTP Act. He

submitted that it was only after considering the merits of such proposal,

Respondent No. 1 had granted the permission under Section 45 of the MRTP Act

and accordingly sanctioned the Petitioners’ plans and permitted the Petitioners to

commence construction of the said Building. He submitted that the issue of

granting permission to open a new school and/or to grant a recommendation of a

new school or shift an existing school was within the jurisdiction of the Deputy

Director of Education and/or the Education Officer and not the authority of the

Administrative Officer in the Education Department. He thus submitted that

Respondent No. 3 had clearly acted in excess of the authority vested in

Respondent No. 3.

Page 5 of 10
Ajit Pathrikar

::: Uploaded on – 30/06/2025 ::: Downloaded on – 30/06/2025 22:31:56 :::
WP-2225-2022.DOC

15. Mr. Punde then submitted that the construction of a building was a

prerequisite for transferring and/or shifting of the Petitioner’s school, and therefore

merely because some policy decision had been taken with regard to the shifting of

school, the same cannot bar the construction of a building by the Petitioners. He

reiterated that the construction being carried out was for a school and was therefore

in conformity with the reservation of the said plot. He would submit that any

decision regarding shifting the school could only be taken, after the completion of

the said Building and after all requisite permissions and approvals were obtained by

the Petitioner. He thus submitted that unless the construction of the building was

completed, the question of using the same for any purpose did not arise. He

submitted that, even though the same was explained and pointed out to

Respondent No. 3, Respondent No. 3 chose to ignore the same and issue the

impugned communications.

16. Mr. Punde thus submitted that the Petitioner having obtained permission

and having commenced construction in conformity with the purpose for which the

said plot was reserved, must therefore be allowed to complete the construction of

the said Building.

17. Mr. Punde then pointed out that even the impugned order dated 15th

November 2021, issued by Respondent No. 1, was completely silent and did not

inculcate a single breach of the provisions of the MRTP Act by the Petitioner or

any breach by the Petitioner of any conditions of the permission granted to the

Petitioner. He thus submitted that the impugned order was motivated solely on

account of communications addressed by the president of the Ambika Mitra

Page 6 of 10
Ajit Pathrikar

::: Uploaded on – 30/06/2025 ::: Downloaded on – 30/06/2025 22:31:56 :::
WP-2225-2022.DOC

Mandal to Respondent No. 3 and the consequent communications addressed by

Respondent No. 3 to Respondent No. 1.

18. He thus submitted that the aforesaid conduct of the Respondents was wholly

arbitrarily illegal and manifestly unjust. He submitted that the Petition was

required to be allowed.

Submissions on behalf of the Respondents

19. Mr. Subhash V. Gutte, Learned Counsel appearing on behalf of Respondent

Nos. 1 to 3, at the outset did not dispute that the said plot had been reserved for

educational purposes and that the Petitioner had been granted permission to carry

out construction thereon. He, however, submitted that, since such construction of

the said Building was for the purposes of a school, it was incumbent upon the

Petitioners to have obtained a No Objection Certificate (NOC) from the education

department prior to submitting the plans for construction, which he pointed out

had not been done. He thus submitted that the Petitioner had obtained the

permission from Respondent No. 1 based on a misrepresentation.

20. He then pointed out that, vide the communication dated 30 th July 2021,

Respondent No. 3, on directions from the Deputy Director of the Education

Department, had enquired into the complaints received from Ambika Mitra

Mandal and asked the Petitioners to submit an Affidavit stating what educational

purpose the said Building was being constructed for. However, instead of filing the

required Affidavit, the Petitioners submitted a casual reply and were thus in breach

of the mandatory requirement of stating the purpose of construction. He further

Page 7 of 10
Ajit Pathrikar

::: Uploaded on – 30/06/2025 ::: Downloaded on – 30/06/2025 22:31:56 :::
WP-2225-2022.DOC

submitted that, despite the misrepresentation on the part of the Petitioners,

Respondent No. 1 has merely stayed the permission granted to the Petitioners and

not revoked the same. He thus submitted that the impugned communications and

impugned order had been validly and legally issued and required no intervention

from this Court.

Analysis and Conclusion:

21. After having heard Learned Counsel for the Parties, we have no hesitation in

holding that the Writ Petition deserves to be allowed for the following reasons:

A. There is no dispute to the fact that (i) Respondent No. 1 is the authority

under the provisions of the MRTP Act who grants permission for

construction; (ii) the Petitioner was granted permission by Respondent No.

1 to carry out construction, which permission was valid and subsisting; and

(iii) the construction carried out by Respondent No. 1 was not in breach of

the permission granted by Respondent No. 1 nor under any of the

provisions of the MRTP Act or any other provisions of law.

B. It is also undisputed that Respondent No. 3 is the authority concerned with

the aspect of administration of the education department and not in any

manner concerned with or authorised to either issue and/or revoke building

permissions issued by Respondent No. 1. Thus, Respondent No. 3 does not

have the power or authority in law to issue directions pertaining to the

grant, refusal, or cessation of building permissions which have been issued

by Respondent No. 1. Thus, Respondent No. 3 has, in issuing the

Page 8 of 10
Ajit Pathrikar

::: Uploaded on – 30/06/2025 ::: Downloaded on – 30/06/2025 22:31:56 :::
WP-2225-2022.DOC

impugned communications acted in excess of its statutory authority, and the

impugned communications are thus an egregious overreach by Respondent

No. 3 of the authority vested in Respondent No. 3 by law.

C. Also, the impugned order passed by Respondent No. 1 staying the earlier

permission granted is also ex facie unsustainable. The impugned order does

not set out a single breach by the Petitioner of any provision of law or any

condition of the permission dated 23rd November 2020 granted to the

Petitioner. In our view, if Respondent No. 1 was to revoke the permission

granted, it was incumbent upon Respondent No. 1 to have specifically set

out the reasons for doing so, which Respondent No. 1 has not even so much

as attempted to do. The impugned communications have been issued by

Respondent No. 1 clearly at the instance of Respondent No. 3, which

therefore establishes that Respondent No. 1 has acted in a patently arbitrary,

illegal, and unfair manner, as also in complete abdication of its statutory

duties.

D. We also find that the principles of natural justice have been violated by

Respondent No. 1 since the Petitioner was not even afforded a reasonable

opportunity to establish how there was no breach by the Petitioner of any

provision of law or of any condition of the permission granted by

Respondent No. 1.

22. While parting, we may observe that the law confers distinct authority and

jurisdictions to the authorities functioning under the MRTP Act and the

Education Acts. There is no question of such compartmentalized jurisdiction and

Page 9 of 10
Ajit Pathrikar

::: Uploaded on – 30/06/2025 ::: Downloaded on – 30/06/2025 22:31:56 :::
WP-2225-2022.DOC

authority being usurped by the Education authority which has nothing to do with

construction permissions. If the law is to permit such inter-meddling into the

authority of one department into another department who are differently governed

under law, a situation of a total chaos would arise, not recognized by law. This is

one such case that the planning authority which had initially acted lawfully to grant

building permission to the petitioners is being influenced by the education

department. This is wholly impermissible looked from any angle.

23. Hence, for the aforesaid reasons, the Writ Petition is allowed in terms of

prayer clauses (a) and (b) as extracted above.

24. No Costs.

(ARIF S. DOCTOR, J.)                                     (G. S. KULKARNI, J.)




                                   Page 10 of 10
Ajit Pathrikar


    ::: Uploaded on - 30/06/2025                      ::: Downloaded on - 30/06/2025 22:31:56 :::
 



Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here