Rakesh Kumar Chaudhary vs Steel Authority Of India Limited on 3 March, 2025

Date:

Calcutta High Court

Rakesh Kumar Chaudhary vs Steel Authority Of India Limited on 3 March, 2025

Author: Shampa Sarkar

Bench: Shampa Sarkar

                    IN THE HIGH COURT AT CALCUTTA
                     Ordinary Original Civil Jurisdiction
                          COMMERCIAL DIVISION
                              ORIGINAL SIDE

                           AP-COM/1007/2024


                   RAKESH KUMAR CHAUDHARY
                                VS
     STEEL AUTHORITY OF INDIA LIMITED, DURGAPUR STEEL PLANT

BEFORE:
The Hon'ble JUSTICE SHAMPA SARKAR


For the petitioner ...                            Mr. Sourajit Dasgupta,
                                                Mr. Soumik Sen, Adv.


For the respondent ...                Mr. Lakshmi Kumar Gupta, Sr. Adv.

Hearing concluded on: 08.01.2025
Judgment on: 03.03.2025

Shampa Sarkar, J.:-

1. This is an application for appointment of an arbitrator. The dispute

arose out of a Notice Inviting Tender No. PUR/PC/NOP/2.0/782 for the

work of “additional infrastructure for road dispatch near Oxygen Plant- Civil

& Electrical Works”.

2. The need to narrate the facts and the sequence of events is

necessitated by the vehement objection raised by the respondent on the

ground that the claim of the petitioner was hopelessly time-barred.

3. The case run by the petitioner was that, as the successful bidder in

the tendering process, a letter of acceptance was issued on November 15,

2005 by the respondent. The contract value was Rs.4,52,98,296/-. The
2

contract was to be completed within 9 months from the date of issuance of

the letter. 90% of the payment was to be released by the authorised officer of

the respondent on pro rata basis, upon completion of the work and the

balance 10% was to be released upon issuance of the completion certificate.

4. The provisions of the General Conditions of the Contract (in short

GCC), that is, the standard dotted line contract of the respondent were made

applicable to the said work. The petitioner alleged to have invested in plant

and machinery immediately, on receipt of the letter of acceptance. The

petitioner also mobilized labour force. The obligations of the petitioner were

dependent on reciprocal obligations of the authorised officer of the

respondent. The authorised officer of the respondent was required to

discharge the primary obligation of providing a hindrance-free site. The

authorised officer of the respondent was further obliged to provide drawings,

sketches, schemes, etc., to enable the petitioner to discharge its reciprocal

obligations under the contract. Allegation is that, the authorised officer of

the respondent failed and neglected to provide a hindrance-free site to the

petitioner for a long time. As a result of which, the labourers and machinery

of the petitioner remained idle. The petitioner suffered immense loss and

damage. However, despite such breach and delay committed by the

authorised officer of the respondent, the petitioner performed its obligation.

On account of the delay, the price of goods, raw materials, hire charges,

labour costs, etc., increased. The petitioner had to incur further expenses on

such account.

5. Upon the expiry of the initial duration of the contract, the term was

extended by the authorised officer of the respondent till May 31, 2008,
3

without imposing any liquidated damages. The extension stood ratified by a

letter dated July 19, 2008. Allegation is that, the authorised officer of the

respondent accepted the work done by the petitioner at enhanced rates and

promised to make payment for the same. The authorised officer of the

respondent also requested the petitioner to perform extra work, which did

not cover the terms of the contract. Such extra work was done by the

petitioner, solely on the condition that, the authorised officer of the

respondent would make additional payment for such work, as per the

revised offer submitted by the petitioner.

6. According to the petitioner, the plant unit was commissioned on May

31, 2008. The completion certificate was issued on July 5, 2008. For the

work performed by the petitioner, invoices were raised amounting to

Rs.7,51,91,637/- which included service tax under various heads. Out of

the outstanding of Rs.7,51,91,637/-, the authorised officer of the

respondent paid Rs.4,44,51,04.00/-. The outstanding, according to the

petitioner, was around Rs.3,07,40,597.59/-, which included unpaid service

tax.

7. The petitioner alleged to have repeatedly called upon the authorised

officer of the respondent to release the balance payments from time to time,

but the authorised officer of the respondent did not discharge its obligation.

The authorised officer of the respondent caused fundamental breach of its

obligation under the contract.

8. By a letter dated May 17, 2010, the authorised officer of the

respondent asked the petitioner to accept a lesser amount. Allegedly, the

petitioner was forced to sign some papers under duress, including a letter
4

dated July 3, 2010, indicating that the petitioner was willing to settle the

amount at Rs.73,35,000/-. However, the said amount was not paid and

instead, the petitioner was paid Rs.17,81,212/-. The payment was made

sometime in November 2013. On the basis of such exercise, the authorised

officer of the respondent unilaterally amended the contract value to

Rs.4,62,60,597/-, on September 23, 2013.

9. As the outstanding dues were not paid, the petitioner filed a writ

petition challenging the inaction and/or non-action of the respondent. The

writ petition was registered as WP No.9173 (W) of 2015. By an order dated

September 11, 2015, the writ court directed the authorised officer of the

respondent to take appropriate steps to ameliorate the grievances of the

petitioner and pay the outstanding, if found, due and payable. The

authorised officer of the respondent, thereafter, issued various letters

informing the petitioner that the claims were being examined. By a letter

dated December 31, 2015, the authorised officer of the respondent called

upon the petitioner to invoke the arbitration clause contained in the

agreement between the parties. The authorised officer of the respondent

relied upon an contract dated March 23, 2012. The petitioner denied the

existence thereof. As the decision was not taken by the authorised officer of

the respondent as directed by the High Court, a contempt application was

filed. During the pendency of the contempt application, the authorised

officer of the respondent hurriedly passed an order dated November 6, 2017,

thereby repudiating the claims of the petitioner.

10. Being aggrieved by such repudiation, by a letter dated May 23, 2018,

the petitioner called upon the authorised officer of the respondent to appoint
5

a conciliator to settle the dispute in terms of the contract. The authorised

officer of the respondent, accordingly, appointed a conciliator. A letter dated

November 22, 2018 was issued by the authorized officer of the respondent

recording failure of the conciliation process. The petitioner issued a protest

letter dated November 28, 2018. By a letter dated June 13, 2019, the claims

of the petitioner were again rejected by the respondent and the authorised

officer of the respondent asked the petitioner to take appropriate steps in

view of the failure of the conciliation.

11. By a letter dated July 1, 2019, the petitioner claims to have invoked

the arbitration clause i.e. clause 6 of the GCC and proposed the name of an

arbitrator. Various letters were exchanged between the parties and by a

letter dated August 31, 2019, the petitioner called upon the authorised

officer of the respondent to appoint an arbitrator in accordance with the

provisions of the Arbitration and Conciliation Act, 1996. Again, by a letter

dated November 23, 2020, the petitioner proposed the name of another

arbitrator and informed the authorised officer of the respondent that, the

petitioner would be constrained to approach the High Court in the event the

authorised officer of the respondents failed to accord consent to such

appointment.

12. By a letter dated January 23, 2021, the authorised officer of the

respondent refused to give consent for appointment of the suggested

arbitrator. By an e-mail dated June 17, 2022, the authorised officer of the

respondent informed the petitioner that the petitioner’s case was being

discussed and that the petitioner would be informed once a decision was

arrived at. By a letter dated August 2, 2022, the petitioner called upon the
6

authorised officer of the respondent to communicate a decision. By another

letter dated January 12, 2023, the petitioner asked the authorised officer of

the respondent to release the dues. On March 3, 2023, the authorised officer

of the respondent, inter alia, contended that the entire outstanding

contractual amount had been paid. By a letter dated July 19, 2023, the

petitioner asked the Director-in-Charge of the respondent to release

payments. Such request was rejected by a letter dated August 10, 2023.

Again, the authorised officer of the respondent amended the contract

unilaterally and by a letter dated May 5, 2024, the authorised officer of the

respondent informed the petitioner that the contract value was amended to

Rs.4,60,71,807/-, and the petitioner would be entitled to Rs.55,53,646/- as

per the signed voucher which were supplied. The petitioner contended that

the vouchers were not signed by him. The petitioner contended that the

entire outstanding would be Rs.2,52,67,752.59/-. The petitioner called upon

the higher authorities and requested for further payment by a letter dated

March 15, 2024.

13. The authorised officer of the respondent accordingly made payment of

Rs.36,33,015/-, on March 23, 2024. As the entire claim was not satisfied,

the petitioner enquired from the officers and was shocked to receive an

undated memorandum of payment which recorded that the petitioner had

accepted Rs.55,53,646/-, as full and final settlement of its dues. The

petitioner contended that the signatures of the petitioner were obtained on

blank papers and the same were used for the purpose of preparing the

memorandum of payment, behind the back of the petitioner. The petitioner

informed the Commissioner of Police, Durgapur, by a letter dated July 27,
7

2024, about such alleged forgery. The petitioner also raised protests and

claimed its lawful dues of Rs.2,52,28,545/-, by letters dated July 24, 2024,

and July 31, 2024. As the authorised officer of the respondent did not

accept the request for arbitration and also did not make the payments as

claimed by the petitioner, disputes and differences arose and the petitioner

has moved this court for appointment of an arbitrator.

14. Mr. Dasgupta, Learned Advocate for the petitioner submits that the

fact that the letter of acceptance was issued was not in dispute and as per

Clause 12 of the letter of acceptance, all the terms of the GCC, had been

made applicable. Clause 6 of the GCC contained the arbitration clause. The

clause stated that disputes and differences arising between the parties or

relating to the construction, meaning, scope and operation of the contract,

would be settled between the parties amicably and if the amicable

settlement failed, the differences would be settled by arbitration in

accordance with the rules of the Indian Council of Arbitration (ICA), and

award made in pursuance thereof, shall be binding between the parties. The

venue of the arbitration would be the site.

15. According to Mr. Dasgupta, the conduct of the authorised officer of

the respondent would clearly indicate acceptance on the part of the

respondent that the petitioner incurred additional expenses and had

executed additional work, which were beyond the scope of the contract. The

difference in the claim and what was admitted by the authorised officer of

the respondent and subsequent payment thereof, after unilateral

amendment of the contract value, gave rise to the dispute. Further dispute

was with regard to the memorandum of payment which was disclosed to the
8

petitioner, indicating settlement of the claim. The supply of the

memorandum of payment indicating full and final settlement of the claim at

Rs.55,53,646/- and the unilateral amendment of the contract value to

Rs.4,60,71,807/-, which was informed to the petitioner by letter dated

March 5, 2024, were all subject matters of the dispute.

16. Although, the dispute arose out of a letter of acceptance dated

November 15, 2005, the dispute was alive. In March, 2024, the authorised

officer of the respondent amended the contract value. Thus, the question of

the claim being barred by limitation did not arise. The dispute arose out of a

contract which was amended unilaterally twice, lastly on March 5, 2024.

The payment voucher which was relied upon by the authorised officer of the

respondent allegedly indicating settlement of the claim, was also issued

sometime in March, 2024.

17. Relying on the communications dated November 23, 2020 and

January 23, 2021, Mr. Dasgupta contended that those were the notices

invoking arbitration in terms of Section 21 of the Arbitration and

Conciliation Act, 1996. Support had been drawn from the order of the

Hon’ble Apex Court by which the period of limitation had been extended,

upon excluding the pandemic period. The period between March 15, 2020 to

February 2022 had been exempted and the petitioner was entitled to a

period of 3 years from February 2022 to approach this court for

appointment of an arbitrator. The authorised officer of the respondent

refused to accept the proposal of the petitioner by the letter dated November

23, 2020.

9

18. Mr. Dasgupta emphasized that even after the authorised officer of the

respondent had repudiated the claim by a reasoned order dated November

6, 2017, the parties agreed to solve the dispute by a conciliation process.

The authorised officer of the respondent by a letter dated May 19, 2018,

nominated the General Manager (BE), Sri S.P. Gupta as the conciliator for

settlement of the dispute. Such action of the authorised officer of the

respondent were proof of the fact that according to the respondent, the

dispute was alive and the parties were willing to settle the same amicably.

19. The claims of the petitioner which were forwarded by letter dated

November 28, 2018, after termination of the conciliation proceeding were

again rejected by the authorised officer of the respondent. The letter

recorded that the authorised officer of the respondent had gone through the

claims and found the same to be untenable. Nothing was found due and

payable.

20. By a letter dated July 1, 2019, the petitioner requested the authorised

officer of the respondent to appoint an arbitrator as per clause 6 of the GCC.

The petitioner proposed to appoint Mr. Mahadev Ghosh, District Judge

(retired) as the sole arbitrator. The authorised officer of the respondent

responded to such proposal by a letter dated July 30, 2019, and submitted

that the dispute was to be settled by arbitration in accordance with the rules

of the Indian Council of Arbitration and the unilateral choice of the sole

arbitrator by the petitioner was not in accordance with the provisions of the

arbitration clause. By letter dated August 31, 2019, the petitioner once

again approached the authority for substitution of the Arbitration Clause

No.6 and for an agreement to settle the dispute by a sole arbitrator. The said
10

proposal was not responded to and admittedly no agreement had been

reached for settlement of the dispute by a sole arbitrator.

21. By another letter dated November 23, 2020, the petitioner again

requested the authorised officer of the respondent to settle the dispute by

arbitration and proposed the name of a learned Senior Advocate as its

nominee.

22. The documents were relied upon by Mr. Dasgupta in support of his

contention that, the reference to arbitration and invocation of the Clause 6

of the GCC had been properly done.

23. Mr. Lakshmi Kumar Gupta, learned Senior Advocate for the

respondent, submitted that the claim was highly belated. It was ‘deadwood’.

Not only the so called invocation was belated, but the same was not in

proper form. The application before this court for appointment of an

arbitrator was also belated and contrary to what had been agreed upon by

the parties. Mr. Gupta submitted that final payments had been made in

September 2013, upon amendment of the contract value to

Rs.4,62,60,597/-. Thereafter, in compliance of the order of the High Court

passed in the writ petition, the claims were repudiated by a letter dated

November 6, 2017.

24. The period of limitation to invoke the arbitration clause expired within

three years from November 6, 2017. The petitioner did not invoke arbitration

in the proper manner as provided in Clause 6 of GCC. According to Mr.

Gupta, arbitration was to be conducted as per the Rules of the Indian

Council of Arbitration. The petitioner requested for amendment of the

arbitration clause and requested the respondent to agree to arbitration by a
11

sole arbitrator. The petitioner unilaterally proposed names of sole

arbitrators, which were contrary to the provisions of Clause 6 of the GCC

and the ICA Rules. Till date, there was no invocation in terms of the

arbitration clause.

25. Thus, Mr. Gupta’s contention was that, the application should be

rejected on three grounds. First, that the claim was barred by limitation and

neither the subsequent communications between the parties nor the

conciliation proceedings held at the behest of the parties, would arrest the

period of limitation. Secondly, till date, there was no notice invoking

arbitration in terms of Clause 6 of the GCC. Thirdly, the petitioner could not

have approached this court at such a belated stage, when the claims were

denied way back in 2017.

26. Mr. Gupta also relied on Section 18 of the Limitation Act, 1963, to

submit that the documents relied upon by the petitioner would not indicate

that, within a period of three years from November 6, 2017, the authorised

officer of the respondent had either admitted a part of the claim or made

payment of such amount. Subsequent efforts to settle the dispute and

partial payment made after the period of three years form rejection of the

petitioner’s clam, would not extend the period of limitation.

27. Mr. Gupta relied on the following decisions:-

(a) B.K. Consortium Engineers Private Ltd. vs Indian Institute of

Management, Calcutta reported in 2023(4) CHN (CAL) 242,

(b) Bharat Sanchar Nigam Ltd. vs Nortel Networks India Private

Ltd. reported in (2021) 5 SCC 738.

12

28. The rival contentions and the facts have been discussed in details.

This court finds that the documents which have been considered, indicate

that the dispute was continuing and the parties had made a sincere effort to

resolve the same by amicable settlement and through a conciliator

appointed by the authorised officer of the respondent. The conciliator was

an employee of the respondent. Even after the reasoned order of November

6, 2017, (which according to Mr. Gupta was the starting point of limitation

to invoke arbitration), the records reveal that conciliation continued and

several correspondences were exchanged between the parties. The

authorised officer of the respondent had specifically informed the petitioner

that the claim was under consideration. An email dated June 17, 2022,

reads as follows:-

” M/s RK Engineering Works
Durgapur – 713216

This has reference to your claim against the project “Additional
infrastructure for road despatch”. This case is being discussed
internally by the committee and on the finalization of the same, it will
be informed to you.

T. Muthukumar
CGM(Projects)”

29. Most importantly, it appears that the contract value was amended on

March 5, 2024, by the authorised officer of the respondent. Thus, the

closure of the contract, prima facie, appears at that relevant time when the

contract value was lastly amended. Another letter dated March 3, 2023,

issued by the Senior Manager of the authorised officer of the respondent,

indicates that the claims contained in the petitioner’s letter dated January

12, 2023, addressed to the Secretary, Ministry of Steel, were examined by
13

the authorised officer of the respondent and an amicable settlement was

requested. The contents of the letter is quoted below:-

“Sir/Madam

We acknowledged the receipt photocopy attachment of your letter
dated 03.03.2023 and the contents of the attachment has surprised
us because the full facts have not been mentioned. The meeting with
DSP dated 07.02.2023 have been mentioned in the said letter but
outcome for the same has not been mentioned anywhere in the
attachment.

Sir, we are of your very oldest contractor working since 1986 and
heave done various challenging projects to the entire satisfaction of
our valued client DSP such as installation of Bloom Caster,
installation of Re-Heating Furnaces, Installation of Ladle Furnaces
No. 1 and 2, Tank No. 1 and 2 SGP of BF#4, Construction, installation
of INBA BF#3 and its galleries, conveyors complete, repeatedly Capital
Repair of all Blast Furnaces. Dismantling of Collapsed Buffer Water
Tank in BF#4, Construction of various Roads, Restoration of Railway
Tracks more than 100 KM along with 80 nos. of Turnots, construction
of chimney of COB#2 and others, structural work of New Slag Yard
and Open Slag Yard Phase-II, various challenging jobs under
shutdown, dismantling and modification of many collapsed galleries
earlier in past and various others repair maintenance jobs directly and
indirectly.

But such type of peculiar situation have never been faced earlier other
than the subject. All and entire works as per requirement of DSP we
have submitted our most competitive offer in advance and after
getting clearance the said jobs has been completed/commissioned and
are commercial production since then. Hence there is no problem
about release of our payables. During execution the concerned
authority communicated us that all payments will be released after
completion of the unit. Much after completion 3/4 years the
concerned started bargaining which is not at all acceptable to us. Sir,
in the case of local contractors the concerned authority have no
problem to pay them Rs. 5 Lakh per Tonne with free issue of
fabricated structures and open the flood gate of DSP and for outsider
like us when we ask you 20%/30% even then the payment are not
releasing even after expiry of 10/15 years we are facing financial
disastrous and hand to mouth situation. Due to non release of our
payables we become handicapped and not able to bag any job in the
open market.

We request you to kindly look into so that our payment can release
without bargaining for which we shall be thankful to you. Attached
please find herewith 5 pages of attachment mentioning the details
14

Thanking you,”

30. Along with the said letter, the views of the authorised officer of the

respondent were annexed. The views justified negation of the claims of the

petitioner. Thus, in my view, it is a debatable question as to whether the

period of limitation to invoke arbitration should be calculated from

November 6, 2017, or from June 13, 2019 when there was another denial of

the claim, upon the conciliation having failed, or from March 3, 2023 or

lastly from March 5, 2023, when the contract was once again amended and

the authorised officer of the respondent referred to an invoice, memorandum

of payment and payment vouchers, dated March 22, 2024. In this case,

limitation is a mixed question of facts and law.

31. In my prima facie view, the dispute continued and the conduct of the

authorised officer of the respondent does not indicate that the contract was

not closed until March 5, 2024, when the second amendment of the contract

value was made by the authorised officer of the respondent. The petitioner

also disputes having signed the memorandum of payment and having

accepted the full and final payment as contended by the authorised officer of

the respondent. This is also a dispute which arose in March 2024.

32. Thus, in my view, whether the claim is time barred or not or whether

the petitioner failed to take steps within the period of limitation will have to

be proved in evidence. The dispute with regard to non-payment, unilateral

amendment of the contract in March 5, 2024, memorandum of payment

allegedly signed by the petitioner and acceptance of the payment vouchers
15

dated March 22, 2024 by the petitioner, are very much alive. These disputes

cannot be considered to be “deadwood”.

33. The decision of B.K Consortium (supra) will not be applicable in this

case. The discussions made herein above and the documents relied upon

and referred to by this court, do not, prima facie, indicate that the disputes

are ex facie time barred. This is not a case where the referral court can hold

that there is no surviving dispute. The decision cited/laid down the principle

that vexatious and frivolous claims should be weeded out at the initial stage,

by the referral court. However, in the facts and circumstances of this case,

for the referral court to hold thus, would tantamount to stepping into the

arbitrator’s jurisdictional territory.

34. The decision of Bharat Sanchar Nigam Limited and another

(supra) also does not apply, as this court has, prima facie, opined with

reference to the documents that the order of November 6, 2017, may not be

considered as the final rejection of the claim of the petitioner. In the decision

relied upon, the ratio laid down was that, subsequent communications and

exchange of letters between the parties or discussions for settlement of the

dispute, would not extend the period of limitation.

35. The next contention of Mr. Gupta is accepted by the Court. That the

invocation of the arbitration clause was not proper. Clause 6 of GCC

provides as follows.

“6. Settlement of Disputes.- Any disputes or differences, whatsoever,
arising between the parties out of or relating to the construction,
meaning, scope, operation or effect of this Contract shall be settled
between the Employer and the Contractor amicably. If however, the
Employer and the Contractor are not able to resolve their disputes /
differences amicably as aforesaid the said disputes / differences shall
be settled by Arbitration in accordance with the Rules of Arbitration of
16

the Indian Council of Arbitration and the award made in pursuance
thereof shall be binding on the parties.

The arbitration shall be governed and regulated in all respect
according to the laws of India and the Arbitration proceedings shall be
regulated and governed by Indian Arbitration and Conciliation Act
1996 or such modifications or re-enactment thereof. The venue of
Arbitration in case of Indian Contractors shall be the place where site
is situated and in case of Overseas Contractors shall be New Delhi,
India.”

36. Admittedly, the parties agreed that the dispute would be settled by

arbitration in accordance with Rules of Indian Council of Arbitration.

37. Rule 15 deals with initiation of arbitration and provides as follows:-

“Rule 15

(i) Any Party wishing to commence arbitration proceedings under
these rules (Claimant) shall give a notice of request for
arbitration to the Registrar of ICA and to the Respondent.

(ii) The notice of request (application) for arbitration to the
Registrar shall be accompanied by:-

(a) the names and full addresses of the parties to the dispute
including emails, phone numbers, hand/mobile phone
numbers, fax nos. of the parties to the dispute and their legal
representative, it any.

(b) statement of the claim and facts supporting the claim, points
at issue and relief or remedies sought with other details of the
Claimant’s case.

(c)original or duly certified copies of the arbitration agreement,
any contract or agreement out of or in connection with which
the dispute has arisen and such other documents and
information relevant or relied upon.

(d) Non-Refundable Registration Fee of Rs.15,000/- plus any
applicable tax for claims up to Rs. Two Crore and Rs. 30,000/-

plus any applicable tax for claims more than Rs. Two Crore.
(e ) The Arbitral proceedings in respect of dispute commence on
the date on which a request for that dispute to be referred to
arbitration is received by the Respondent.

(f) In the event that the Claimant fails to comply with any of the
requirements referred to herein above, the Registrar may fix a
time limit not exceeding 15 days within which the Claimant
must comply, failing which the file shall be closed without
prejudice to the Claimant’s right to resubmit the same claims at
a later date in another notice of request for arbitration.”
17

38. In terms of Rule 15(1), a party wishing to commence arbitration

proceedings (claimant) is required to give a notice of request for arbitration

to the Registrar of ICA and to the authorised officer of the respondent. In the

present scenario, the petitioner issued letters to the authorised officer of the

respondent requesting amendment of the clause and settlement of dispute

by a sole arbitrator, but the authorised officer of the respondent did not

accede to the same and continuously maintained a stand that the clause

provided for resolution of dispute as per the ICA Rules. The petitioner

unilaterally referred certain names of sole arbitrators as its nominee,

contrary to the provisions of the arbitration clause.

39. Thus, in my view, the invocation was not in terms of the requirement

of the agreement and the ICA Rules have not been followed. The court has

already opined that the issue of limitation at this stage is a mixed question

of law and fact and the actions of the authorised officer of the respondent

which were taken in March 2024, were also part of the dispute raised by the

petitioner. The petitioner is at liberty to approach the Registrar ICA in terms

of the Rules of the Indian Council of Arbitration, thereby invoking

arbitration as per the said Rules.

40. Accordingly, the application is disposed of.

41. There will be no order as to cost.

42. Parties are directed to act on the server copy of this judgment.

(Shampa Sarkar, J.)



Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Share post:

Subscribe

spot_imgspot_img

Popular

More like this
Related