Srei Equipment Finance Limited vs Marina Piling Company Pvt. Ltd. And Anr on 9 June, 2025

0
38

Calcutta High Court

Srei Equipment Finance Limited vs Marina Piling Company Pvt. Ltd. And Anr on 9 June, 2025

Author: Shampa Sarkar

Bench: Shampa Sarkar

     ORDER                                                               OC-19
                       IN THE HIGH COURT AT CALCUTTA
                            COMMERCIAL DIVISION
                               ORIGINAL SIDE

                             AP-COM/198/2025
                     SREI EQUIPMENT FINANCE LIMITED
                                   VS
                 MARINA PILING COMPANY PVT. LTD. AND ANR.

BEFORE:
The Hon'ble JUSTICE SHAMPA SARKAR
Date: 9th June 2025.
                                                                       Appearance:
                                                       Mr. Swatarup Banerjee, Adv.
                                                            Mr. Sariful Haque, Adv.
                                                      Mr. Saubhik Chowdhury, Adv.
                                                            Ms. Tapasika Bose, Adv.
                                                                    ...for petitioner.



1.    This is an application for appointment of an arbitrator under Section 11(6)

      read with Sections 14 and 15 of the Arbitration and Conciliation Act,

      1996.

2.    The petitioner submits that the erstwhile learned arbitrator, who was

      unilaterally appointed by the petitioner, has recused.     The respondents

were represented by their learned advocate who had raised an objection

with regard to continuation of the proceedings. Upon consideration of the

objections raised as to the constitution of the tribunal, the learned

arbitrator recused. It appears that the matter did not progress at all.

3. As the respondents were not appearing before the Court, despite repeated

directions, the Court had directed substituted service. The affidavit of
2

service is taken on record. It appears that paper publications have been

effected in two new papers at Navi Mumbai.

4. The dispute arises out of a loan agreement. The petitioner claims to have

provided financial assistance of Rs.2,84,74,400/- to the respondents and

the loan-cum-hypothecation agreement was entered into on December 5,

2018. The respondent No. 1 is the borrower and the respondent No. 2 is

the guarantor. The repayment schedule required payment of

Rs.3,63,15,000/- including interest, in 45 instalments, commencing from

February 15, 2019. Each monthly instalment would become payable on

every 15th day of the succeeding calendar month.

5. It is submitted by Mr. Banerjee, that a part of the 7 th instalment had been

paid by the respondents. Thereafter, the respondents defaulted. Even

after repeated reminders, the respondents failed and did not pay the

monthly instalments. By a notice dated December 24, 2019, the

agreement dated December 5, 2018 was duly terminated and a demand

was raised for Rs.3,07,11,263.65/-. It is submitted that more than Rs. 3

crores is payable. The petitioner raised demand notice on December 24,

2019. It is submitted by the petitioner that the period excluded by the

Hon’ble Apex Court between March 15, 2020 and February 28, 2022

(Covid Period) shall be applicable in computing the period of limitation

with regard to the claim, in this case.

3

6. The petitioner had unilaterally appointed a learned advocate as the

arbitrator. Thereafter, the petitioner went into CIRP. The petitioner has

now come out of the CIRP and an asset reconstruction company namely

NARCL is the successful resolution applicant.

7. Upon recusal of the learned arbitrator who was unilaterally appointed,

this application has now been filed upon due service of a further notice

under Section 21 of the Arbitration and Conciliation Act, 1996. The

petitioner draws the attention of this Court to the order dated December

16, 2024, by an order of injunction on the secured asset was passed and

the Court had granted liberty to the petitioner to proceed for appointment

of a receiver. It is submitted that a receiver has since been appointed by

this Court.

8. Under such circumstances, this application is allowed, taking into

consideration the arbitration clause as also the jurisdiction clause. The

agreement provides that the same is subject to the exclusive jurisdiction of

the courts at Kolkata and all disputes arising out of the said agreement,

including interpretation thereof, shall be decided by an arbitrator.

Although, the clause provides for appointment of an arbitrator by the

company, in view of the settled principle of law, such procedure of

appointment is no longer permissible. Thus, the mechanism for

appointment of an arbitrator in the present matter has no legal sanction

in view of section 12(5) of the Arbitration and Conciliation Act, 1996..
4

9. Under such circumstances, the application is allowed. This Court

appoints Mr. Justice Subrata Talukdar, former Judge of this Court as the

learned arbitrator, to arbitrate upon the disputes between the parties.

This appointment is subject to compliance of Section 12 of the Arbitration

and Conciliation Act, 1996. The learned arbitrator shall fix his

remuneration as per the Schedule of the Act. All objections that are

available to the respondents, shall be raised before the learned Arbitrator.

The arbitrability of the dispute, admissibility of the claim, jurisdiction etc.

are all left open, to be decided by the learned arbitrator.

10. The application is disposed of.

(SHAMPA SARKAR, J.)

S. Kumar / R.D. Barua

[ad_1]

Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here