The plaintiff has filed an application being GA-COM/2/2025 praying for
judgment upon admission. The plaintiff has also filed an application being
GA-COM/1/2024 praying for interim order.
2. Initially this Court has passed an ad-interim order which is continuing till
date.
3. The plaintiff has filed the suit praying for decree for a sum of
Rs.84,69,294.13p. along with interest at the rate of 18% per annum. The
plaintiff and the defendant have entered into three Memorandum of
Understanding dated 1st April, 2004, 1st April, 2007 and lastly on 7th
November, 2010. As per the terms of the Memorandum of Understanding
executed between the parties dated 7/11/2010, the defendant was to
manufacture and supply Iron Casting to the plaintiff. The plaintiff shall
purchase such Iron Casting from the defendant. The plaintiff could
assemble the rough casting and export it to countries such as United
States and Canada.