2. Briefly summed up, the facts of the case, insofar as they are relevant for
the present appeal, are as follows:
a. The appellants had floated a tender for completion of “Remaining works
of Dam, Dyke and Spillway in connection with the Extension of Bandhu
Irrigation Scheme, in P.S. Arsa, District Purulia”.
b. The respondent participated in the tender process and emerged
successful. Thereafter the contract for the aforesaid work was awarded
to the respondent.
c. Disputes and differences arose between the parties relating to the
execution of the aforesaid work awarded to the respondent by the
appellants. In terms of the arbitration clause contained in the relevant
agreement governing the parties, an Arbitrator was appointed and the
disputes that had arisen between the parties were referred to the
Arbitrator for adjudication.