The petitioners in both these Writ Petitions challenges the
Land Acquisition proceedings, produced at Ext.P1 in W.P.(C)
No.951/2025. The essential grievance of the petitioners in
both these Writ Petitions is with respect to the proceedings
produced at Ext.P3 in W.P.(C) No.951/2025 [Ext.P1 in W.P.(C)
No.1548/2025], which reduced the value of the land by 80%, on
the allegation that quarrying operations were conducted in
such land entailing diminution of land value.
2. It is submitted by the learned counsel appearing for the
petitioners that the procedure contemplated in the Right to
Fair Compensation and Transparency in Land Acquisition,
Rehabilitation and Resettlement Act, 2013 (‘2013 Act’, for
short) has not been followed. Learned counsel for the
petitioners in W.P.(C) No.951/2025 would invite the attention
of this Court to the various stages/procedures contemplated
in the Act. Section 4 deals with the Social Impact Assessment
W,P(C) Nos. 951 and 1548 of 2025
. .22..