The State Of Bihar And Ors vs M/S Komal Construction Chhawani on 1 May, 2025

0
2


Patna High Court – Orders

The State Of Bihar And Ors vs M/S Komal Construction Chhawani on 1 May, 2025

Author: Khatim Reza

Bench: Khatim Reza

         IN THE HIGH COURT OF JUDICATURE AT PATNA
                          CIVIL REVISION No.9 of 2017
     ======================================================
1.    The State Of Bihar through the Secretary, Road Construction Department,
      Vishweshwarraiya Bhawan, Bailey Road, Patna
2.   The Engineer in Chief, Road Construction Department, 'Vishweshwaraiya
     Bhawan' Bailey Road, Patna.
3.   The Chief Engineer (South Bihar Wing) Road Construction Department,
     'Vishweshwaraiya Bhawan' Bailey
4.   The Superintending Engineer, Road Construction Department, Magadh
     Road Circle, Gaya.
5.   The Executive Engineer, Road Construction Department, Road Division 01
     Aurangabad.
6.   The Assistant Engineer, Road Construction Department, Road Sub Division
     No. 01, Aurangabad.
                                                             ... ... Petitioner/s

                                       Versus
     M/s Rambriksha Singh, Partner Sri Sheo Shankar Prasad Singh Son of Late
     Ram Briksha Singh, Resident of Jaiprakash Nagar, Karma Road, Aurangabad,
     District Aurangabad.
                                                         ... ... Opposite Party/s
     ======================================================
                                         with
                        CIVIL REVISION No. 203 of 2017
     ======================================================
1.    The State Of Bihar through the Secretary, Road Construction Department,
      Vishweshwarraiya Bhawan, Bailey Road, Patna
2.   The Chief Engineer N.H. Wing, Road Construction Department, Govt. of
     Bihar, Vishweshwaraiya Bhawan, Bailey Road, Patna
3.   The Superintending Engineer, Road Construction Department, N.H. Circle,
     Vishweshwaraiya Bhawan, Bailey Road, Patna
4.   The Executive Engineer, Road Construction Department, N.H. Division,
     Biharsharif.
                                                          ... ... Petitioner/s

                                    Versus
     M/s Jai Maa Bhawani Construction Pvt. Ltd. Managing Director Sri Lalit
     Kumar Singh S/o Bhishm Narayan Singh R/o Devdha, P.S. - Deep Nagar,
     Distt. - Nalanda.
                                                      ... ... Opposite Party/s
     ======================================================
                                         with
                        CIVIL REVISION No. 208 of 2017
     ======================================================
1.    The State Of Bihar through the Principal Secretary, Road Construction
      Department, Vishweshwarraiya Bhawan, Bailey Road, Patna
 Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
                                             2/66




  2.    The Engineer-in-Chief, Road Construction Department, Vishweshwaraiya
        Bhawan, Bailey Road, Patna - 15
  3.    The Chief Engineer South wing, Road Construction Department,
        Vishweshwaraiya Bhawan, Bailey Road, Patna - 15
  4.    The Superintending Engineer, Road Construction Department, Works Circle,
        Ara Bhojpur.
  5.    The Executive Engineer, Road Construction Department, Road Division,
        Dehri-on-Sone.
  6.    Mr. Brindawan Rai, the Assistant Engineer, S.D.O., Road Construction
        Department, Road Sub-Division, Sasaram, Rohtas.
  7.    Md. Sadik Ali, the Junior Engineer, Road Construction Department, Road
        Division, Dehri-on-Sone.
                                                               ... ... Petitioner/s

                                                Versus

       M/s Birendra Prasad Singh through its working partner Mr. Devesh Kumar,
       Son of Sri Birendra Prasad Singh Resident of Village + P.O. - Barki Mahuli
       Via Takia Bazar, P.S. - Karahgar, District - Rohtas Sasaram, Correspondence
       Address - Mohalla - New Bank Colony, Faizal Ganj, Kaushalya Kutir, P.O.+
       P.S. - Sasaram, District - Rohtas Sasaram.
                                                              ... ... Opposite Party/s
       ======================================================
                                                 with
                          CIVIL REVISION No. 225 of 2017
       ======================================================
  1.    The State Of Bihar through the Secretary, Road Construction
        Vishweshwarraiya Bhawan, Bailey Road, Patna
  2.    The Engineer-in- Chief, Road Construction Department, 'Vishweswaraiya
        Bhawan', Bailey Road, Patna.
  3.    The Chief Engineer (N.H. Wing), Road Construction Department,
        'Vishweshwaraiya Bhawan, Bailey Road, Patna
  4.    The Superintendent Engineer, Road Construction Department, N.H. Circle,
        'Vishweshwaraiya Bhawan', Bailey Road, Patna
  5.    The Executive Engineer, Road Construction Department, N.H. Division No.-
        2, Biharsharif (Nalanda).
                                                                ... ... Petitioner/s

                                         Versus
       Shri Shailendra Kumar Akela son of Late Keshwar Prasad resident of
       Quamruddinganj, P.O.- Biharsharif, P.S.- Laheri, Muradpur, District- Nalanda
       Bihar.
                                                            ... ... Opposite Party/s
       ======================================================
                                                 with
                         CIVIL REVISION No. 258 of 2017
       ======================================================
  1.    The State Of Bihar through the Principal Secretary, Road Construction
 Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
                                             3/66




        Department, Govt. of Bihar, Vishweshwarraiya Bhawan, Bailey Road, Patna
  2.    The Engineer-in-chief, Road Construction Department, Govt. of Bihar,
        'Vishweshwaraiya Bhawan' Bailey Road, Patna
  3.    The Chief Engineer, Road Construction Department, National Highway
        Wing, Campus of 'Vishweshwaraiya Bhawan' Bailey Road, Patna
  4.    The Superintending Engineer, Road Construction Department, National
        Highway Circle, Bihar, Patna.
  5.    The Executive Engineer, Road Construction Department, National Highway
        Division, Gulzarbagh, Patna.
  6.    The Assistant Engineer, Road Construction Department, N.H. Sub Division
        No. 1, Gulzarbagh, Patna.
  7.    The Junior Engineer, Road Construction Department, N.H. Section,
        Gulzarbagh-1, Patna.
                                                          ... ... Petitioner/s

                                           Versus
  1.    M/s Maruti Enterprises, Gudari, Rajendra Chowk, Hazipur, Vaishali-844101
        through one of its partner namely, Niket Kumar Sinha, Son of Late Ashwani
        Kumar Verma, resident of Mohalla- Pokhara, Police Station- Town, District-
        Vaishali.
  2.    The Branch Manager, Bank of India, Hajipur Branch, Hazipur.
                                                           ... ... Opposite Party/s
       ======================================================
                                                 with
                             CIVIL REVISION No. 5 of 2018
       ======================================================
  1.    The State Of Bihar through the Secretary, Road Construction Department,
        Govt. of Bihar, Vishweshwarraiya Bhawan, Bailey Road, Patna
  2.    The Engineer in Chief, Road Construction Department, Government of
        Bihar, Patna.
  3.    The Chief Engineer, South Bihar (Traffic) Wing, Road Construction
        Department, Government of Bihar, Patna
  4.    The Superintending Engineer, Road Construction Department, Bhojpur
        Road Circle, Ara.
  5.    The Executive Engineer, Road Construction Department, Sahabad Road
        Division, Ara.
                                                            ... ... Petitioner/s

                                          Versus
       M/s Shaligram Singh prop. Sri Shaligram Singh, S/o Late Jadunandan Singh
       R/o Deokali, P.S. Daudnagar, District - Aurangabad.
                                                           ... ... Opposite Party/s
       ======================================================
                                                 with
                      CIVIL REVISION No. 194 of 2018
       ======================================================
 Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
                                             4/66




  1.    The State Of Bihar through the Principal Secretary, Water Resources
        Department, Sinchai Bhawan, Harding Road, Bihar Patna-800001
  2.    The Engineer in Chief, (North) Water Resources Department, Sinchai
        Bhawan, Harding Road, Bihar Patna
  3.    The Chief Engineer, Water Resources Department, Bhagalpur
  4.    The Superintending Engineer, Water Resources Department, Sinchai Anchal
        Bhagalpur
  5.    The Executive Engineer, Water Resources Department, Flood Control
        Division, Naugachia, Distt. Bhagalpur
                                                           ... ... Petitioner/s

                                        Versus
       Dilip Kumar Munka, son of Late Navrang Lal Munka, resident of Ward No.
       16, PO+PS Naugachia, Distt. Bhagalpur
                                                       ... ... Opposite Party/s
       ======================================================
                                                 with
                           CIVIL REVISION No. 9 of 2019
       ======================================================
  1.    The State of Bihar through the Secretary, Water Resources Department,
        Sinchai Bhawan, Bihar Patna-800001
  2.    The Chief Engineer, Water Resources Dept. Dehri Rohtas
  3.    The Superintending Engineer, Durgawati Construction Circle Bhitari Bandh
        Camp Chenari, Distt. Rohtas, Sasaram
  4.    The Executive Engineer, Durgawati Right Bank Canal Division, Chenari,
        Rohtas Sasaram
        The Deputy Director, Quality Control Division, Dehri, Rohtas
                                                                  ... ... Petitioner/s

                                       Versus
        M/s Komal Construction Chhawani Mohalla Ward No. 1 Bhabhua (Kaimur)
        through its Partner Komal Singh Son of late Bachnu Singh Resident of
        Village Ward No. 1 Chhawani Mohalla, P.S. Bhabhua, District- Kaimur,
                                                           ... ... Opposite Party/s
       ======================================================
                                                 with
                           CIVIL REVISION No. 20 of 2019
       ======================================================
  1.    The State Of Bihar through the Secretary, Road Construction Department,
        Vishwesharraiya Bhawan, Bailey Road, Patna.
  2.    The Executive Engineer, Road Construction Department, N.H. West
        Division, Gulzarbagh, Patna.
                                                         ... ... Petitioner/s

                                                Versus
 Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
                                             5/66




       M/s Umesh Kumar and Com, Prop. Sri Umesh Kumar Roy Son of Raja
       Prasad Roy Resident of Ranjan Path, Near Basudeo Palace, Bailey Road, P.S.
       Rupaspur, District- Patna.
                                                          ... ... Opposite Party/s
       ======================================================
                                                 with
                           CIVIL REVISION No. 21 of 2019
       ======================================================
  1.    The State of Bihar through the secretary, Road Construction Department,
        Vishwesharraiya Bhawan, Bailey Road, Patna
  2.    The Chief Engineer (N.H) Road Construction Department, Vishwesharraiya
        Bhawan Bailey Road, Patna Bihar
  3.    The Superintending Engineer, Road construction Department, N.H.Circle
        Patna Bihar
  4.    The Executive Engineer, Road Construction Department, N.H.Division
        Gulzarbagh, Patna Bihar
                                                           ... ... Petitioner/s

                                          Versus
       M/s Saran construction, Prop. Sri Triguna Nand Singh S/o Late Baldeo Singh
       R/O Laxmipur, Kakadia P.S- Dighwara, Saran at Chapra
                                                            ... ... Opposite Party/s
       ======================================================
       Appearance :
       (In CIVIL REVISION No. 9 of 2017)
       For the Petitioner/s     :    Mr. R.B. Prasad Yadav, AAG-11
                                     Mr. Ashok Kumar Dubey, AC to AAG 11
                                     Mr. Dinesh Maharaj, Advocate
                                     Mr. Ramashray Ray, Advocate
       For the Opposite Parties :    Mr. Rajendra Narayan, Sr. Advocate
                                     Mr. Raj Kishore Prasad, Advocate
       (In CIVIL REVISION No. 203 of 2017)
       For the Petitioner/s     :    Mr. Amit Prakash, GA 13
                                     Mr. Sanjay Kumar, AC to GA 13
                                     Mr. Ravi Bhardwaj, Advocate
       For the Opposite Parties :    Mr. Rajendra Narayan, Sr. Advocate
                                     Mr. Lal Babu Singh, Advocate
       (In CIVIL REVISION No. 208 of 2017)
       For the Petitioner/s     :    Mr. Amit Prakash, GA 13
                                     Mr. Sanjay Kumar, AC to GA 13
       For the Opposite Parties :    Mr. Rajendra Narayan, Sr. Advocate
                                     Mr. Manish Sahay, Advocate
                                     Mr. Anil Kumar Sinha, Advocate
                                     Mr. Siddharth Aditya, Advocate
                                     Mr. Aman Raj, Advocate
       (In CIVIL REVISION No. 225 of 2017)
       For the Petitioner/s     :    Mr. Amit Prakash, GA 13
                                     Mr. Sanjay Kumar, AC to GA 13
       For the Opposite Parties :    Mr. Rajendra Narayan, Sr. Advocate
                                     Mr. Manish Sahay, Advocate
                                     Mr. Anil Kumar Sinha, Advocate
                                     Mr. Siddharth Aditya, Advocate
                                     Mr. Aman Raj, Advocate
           Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
                                                       6/66




                  (In CIVIL REVISION No. 258 of 2017)
                  For the Petitioner/s     :    Mr. Amit Prakash, GA 13
                                                Mr. Sanjay Kumar, AC to GA 13
                  For the Opposite Parties :    Mr. Rajendra Narayan, Sr. Advocate
                                                Mr. Manish Sahay, Advocate
                                                Mr. Anil Kumar Sinha, Advocate
                                                Mr. Siddharth Aditya, Advocate
                                                Mr. Aman Raj, Advocate
                  (In CIVIL REVISION No. 5 of 2018)
                  For the Petitioner/s     :    Mr. Ashok Kumar Dubey, AC to AAG 11
                                                Mr. Dinesh Maharaj, Advocate
                                                Mr. Ramashray Ray, Advocate
                  For the Opposite Parties :    Mr. Rajendra Narayan, Sr. Advocate
                                                Mr. Raj Kishore Prasad, Advocate
                  (In CIVIL REVISION No. 194 of 2018)
                  For the Petitioner/s     :    Mr. Sanjay Kumar Ac To Aag 4
                  For the Opposite Parties :    Mr. Rajendra Narayan, Sr. Advocate
                                                Mr. Manish Sahay, Advocate
                                                Mr. Anil Kr. Sinha, Advocate
                                                Mr. Siddharth Aditya, Advocate
                                                Mr. Aman Raj, Advocate
                                                Mr. Lal Babu Singh, Advocate
                  (In CIVIL REVISION No. 9 of 2019)
                  For the Petitioner/s     :    Mr. Sanjay Kumar, AC to Aag 4
                  For the Opposite Parties :    Mr. Ram Nath Singh Yadav, Advocate
                  (In CIVIL REVISION No. 20 of 2019)
                  For the Petitioner/s     :    Mr. Ashok Kumar Dubey, AC to AAG 11
                                                Mr. Dinesh Maharaj, Advocate
                                                Mr. Ramashray Ray, Advocate
                  For the Opposite Parties :    Mr. Lal Babu Singh, Advocate
                  (In CIVIL REVISION No. 21 of 2019)
                  For the Petitioner/s     :    Mr. Ashok Kumar Dubey, AC to AAG 11
                                                Mr. Dinesh Maharaj, Advocate
                                                Mr. Ramashray Ray, Advocate
                  For the Opposite Parties :    Mr. Lal Babu Singh, Advocate
                  ======================================================
                  CORAM: HONOURABLE MR. JUSTICE KHATIM REZA
                                         CAV ORDER

32   01-05-2025

Heard Mr. Ashok Kumar Dubey, AC to AAG-11, Mr.

Amit Prakash, GA-13 assisted by Mr. Sanjay Kumar, AC to GA-

13, Mr. Sanjay Kumar AC to AAG-4 and Mr. Dinesh Maharaj,

learned counsel for the petitioners and Mr. Rajendra Narayan,

learned senior advocate, Mr. Manish Sahay, Mr. Ramnath Singh

Yadav, learned counsels for the opposite parties.

2. These Revision applications have been filed against
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
7/66

the separate Awards passed on different dates by the Bihar

Public Works Contract Dispute Arbitration Tribunal (hereinafter

referred to as ‘Arbitration Tribunal’) in different Reference

Cases.

3. All these Civil Revision Applications have been

filed much after statutory period of limitation and in the

aforesaid revision applications separate interlocutory application

has been filed for condoning the delay in filing the Civil

Revision application which have been heard separately and are

being disposed of by this common order.

Re:- I.A. No. 161 of 2017 in C.R. No. 09 of 2017

4. This application has been filed for condoning the

delay of 889 days (2 years 5 months 6 days) in filing the instant

application which has been filed on 12.01.2017 against the

Award dated 06.05.2014 passed in Reference Case No. 85 of

2010.

5. The remedy against the Award passed by the

Arbitration Tribunal is provided under Section 13 of the Bihar

Public Works Contracts Disputes Arbitration Tribunal Act, 2008

whereby any party aggrieved by the Award may file Revision

Application within three months from the date of the Award.

6. The said Award has been communicated by the
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
8/66

Secretary of the Arbitration Tribunal on 25.05.2014.

7. The instant interlocutory application comprises of 8

paragraphs but it does not disclose the sufficient cause of delay

for filing the instant Civil Revision application. Later on, a

supplementary affidavit in limitation petition has been filed on

16.05.2017 in which the petitioners have tried to explain the

delay caused in filing the Civil Revision application.

8. It is contended that after the knowledge of the

Award, the Superintending Engineer vide its letter no. 587 dated

05.06.2014 directed the Executive Engineer to ensure

compliance of the Award. In compliance of the said direction,

the Executive Engineer vide its letter no. 1093 dated 24.06.2014

requested the Superintending Engineer for guideline with

respectful allotment of funds for the same. The Superintending

Engineer requested the then Engineer-in-Chief to provide

allotment of funds. The Executive Engineer was informed about

the aforesaid facts vide memo no. 882 dated 26.07.2014. It is

further contended that the then Engineer-in-Chief directed the

Executive Engineer to assail the Award passed in Reference

Case No. 85 of 2010. The Executive Engineer on 28.08.2014

was directed by the Superintending Engineer to provide the

grounds of revision against Award, if any, which was received in
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
9/66

the office of Executive Engineer on 03.09.2014. The Executive

Engineer was again directed on 13.09.2014 to provide the

grounds of revision against the Award under challenge. It is

further contended that the Executive Engineer requested to

provide the allotment of fund vide letter no. 90 dated

16.01.2015. The then Engineer-in-Chief vide letter dated

29.01.2015 asked to provide the Award along with claim

petition and counter affidavit filed in Reference case which was

provided on 23.02.2015 and thereafter file of this case was sent

to the Law Department on 14.05.2015 which was returned on

10.07.2015 with some queries. The queries of the Law

Department was explained by the Executive Engineer vide letter

no. 1928 dated 03.11.2015 which was received in the

department on 26.11.2015. It is further pleaded that vide letter

no. 1747 dated 08.03.2016, the Executive Engineer was directed

to provide certified copy of Award which was provided by him

vide letter dated 11.03.2016 and thereafter on 29.03.2016 the

file of this case was again sent to the Law Department but again

the file was returned on 22.04.2016 with further queries. The

said file was produced on 18.05.2016 before the Secretary of the

Department to endorse the file to the Law Department.

9. On perusal of the said file, the Secretary of the
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
10/66

Department approved to file revision against the Award. The

Executive Engineer was directed to provide statement of facts

for filing the Revision Application. Whereafter Executive

Engineer was provided statement of facts by the Road

Construction Department and thereafter on 11.11.2016, the said

file was again sent to Law Department for filing revision

application against the Award. The said file was sent by the Law

Department to the office of the Advocate General for filing

Revision petition. It was marked to AAG-11 for filing Revision

Application thereafter, the Revision Application as well as

interlocutory application for condoning the delay in filing the

application was filed on 12.01.2017 before this Court.

10. Learned counsel for the petitioners has submitted

that there is no deliberate laches on the part of the petitioners

rather the delay has occurred because of some necessary official

formalities which consumed time due to reason beyond the

control of the petitioners. The petitioners should not be

penalized for the fault of the individual. Reliance has been

placed on the judgment in the case of Sheo Raj Singh (d)

through Lrs. & Ors. Vs. Union of India and Anr. reported in

(2023) 10 SCC 531.

11. In the aforesaid judgment, the Hon’ble Apex
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
11/66

Court has also referred the case of State of Manipur & Ors. Vs.

Koting Lamkang reported in (2019) 10 SCC 408 and quoted

paragraph nos. 7 & 8 of the said judgment which reads as

under:-

“7. But while concluding as above, it
was necessary for the Court to also be
conscious of the bureaucratic delay
and the slow pace in reaching a
government decision and the routine
way of deciding whether the State
should prefer an appeal against a
judgment adverse to it. Even while
observing that the law of limitation
would harshly affect the party, the
Court felt that the delay in the appeal
filed by the State, should not be
condoned.

8. Regard should be had in similar
such circumstances to the impersonal
nature of the Government’s
functioning where individual officers
may fail to act responsibly. This in
turn, would result in injustice to the
institutional interest of the State. If the
appeal filed by the State are lost for
individual default, those who are at
fault, will not usually be individually
affected.”

Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
12/66

12. The Hon’ble Apex Court considering the aforesaid

judgment observed that an exercise of jurisdiction does, at

times, call for liberal and justice oriented approach by the courts

where certain leeway could be provided to the State. The hidden

forces that are at work in preventing an appeal by the State

being presented within the prescribed period of limitation so as

not to allow a higher court to pronounce upon the legality and

validity of an order on lower court and thereby secure unholy

gains, can hardly be ignored.

13. Learned senior counsel for the opposite party

vehemently submitted that the learned Arbitration Tribunal after

hearing both the parties, in detail, has passed an Award dated

06.05.2014 in favour of the opposite party in presence of

learned counsel for the petitioners. Immediately thereafter, the

opposite party submitted an application before the Executive

Engineer along with a copy of the Award and requested him to

make payments as per the Award. In compliance of said Award,

the Executive Engineer requested the Superintending Engineer

on 24.06.2014 to make allotment of fund so that payment could

be made to the opposite party. The Superintending Engineer has

asked Executive Engineer to send the demand letter for sanction

of fund in prescribed format. The Executive Engineer again
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
13/66

send the demand letter to the Superintending Engineer in

prescribed format on 06.09.2014. It is further contended that

Superintending Engineer vide its letter dated 29.09.2014 has

directed the Executive Engineer to send an inquiry report in

prescribed format and details of calculation of interest so that

further action be taken for obtaining approval of Law

Department and for allotment of fund. Again, the

Superintending Engineer had requested the then Engineer-in-

Chief to sanction the amount, as the enquiry report in prescribed

format is being sent for obtaining approval of Law Department.

It is further submitted that after the repeated request made by

the Executive Engineer and the Superintending Engineer, the

funds has not been allocated for payment to the opposite party

in terms of the Award. Lastly, the Executive Engineer vide letter

dated 01.01.2015, requested the Secretary of Department to

make allotment of fund so that payment could be made to the

opposite party. Even thereafter, no payment was made to the

opposite party for want of allotment of fund by the higher

authority of the department. It is further contended that after

great persuasion by the opposite party, the Executive Engineer

vide letter dated 11.05.2016 had requested the Engineer in-Chief

to make allotment of required fund. Despite the request for
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
14/66

allotment of fund, the Engineer in-Chief vide letter dated

09.06.2016 had directed the Executive Engineer to file revision

application before this Court with a petition for condonation of

delay, if the grounds for the same exists. If no revision

application could be filed, then send a reasoned and clear report

from the same.

14. It is further submitted by the learned senior

counsel that the petitioner has filed the present revision

application just to frustrate the claim of the opposite party.

There is no plausible explanation for condoning the delay in

filing the limitation petition. Moreover, it has not been stated

that when the advice of the Law Department was received by

the petitioner and no sufficient cause for the delay has been

pleaded in filing the said revision application.

Re:- I.A. No. 7500 of 2017 in C.R. No. 203 of 2017.

15. This application has been filed under Section 5 of

the Limitation Act for condoning the delay of 477 days (1 year 3

months 22 days) in filing the revision application from the date

of Award dated 01.03.2016 (limitation expired on 01.06.2016

during summer vacation). Stamp reporter has calculated period

of limitation from 1st day of opening of the Court i.e.

20.06.2016. The Civil Revision application has been filed on 11
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
15/66

October, 2017 against the Award dated 01.03.2016 passed in

Reference Case No. 115 of 2012 by the learned Arbitration

Tribunal.

16. The requisition for obtaining certified copy of

Award dated 01.03.2016 passed in Reference Case No. 115 of

2012 was filed on 02.08.2017 which was supplied on

08.08.2017.

17. Learned counsel for the petitioners has submitted

that the Award dated 01.03.2016 passed in Reference Case No.

115 of 2012 was communicated to the Secretary, Road

Construction Department Bihar, Patna, where it was received on

17.03.2016. The said Award was also communicated to the

Superintending Engineer, Road Construction Department, Patna

vide letter no. 21.03.2016 for its compliance.

18. The Executive Engineer also informed the

Superintending Engineer for necessary guideline in response to

the said letter. The Superintending Engineer on 07.04.2016

sought necessary guideline from the Engineer in-Chief, Road

Construction Department. In response to the said memo no. 362,

the Engineer in-Chief cum-Additional Commissioner cum-

Special Secretary, Road Construction Department Bihar, Patna

directed the Executive Engineer to make available grounds of
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
16/66

Revision Application to file Revision Application against the

Award dated 01.03.2016. The then Superintending Engineer

again directed the Executive Engineer on 13.05.2016 to make

available grounds to file revision application against the said

Award. In compliance of the said letter dated 13.05.2016, the

Executive Engineer made available the grounds to the

Superintending Engineer. After perusing said grounds, it was

found unsatisfactory and, as such, the Executive Engineer was

directed to make available grounds after getting it drafted by

empaneled Advocate of the department vide letter dated

25.05.2016. It is further contended that the entire file of the case

as well as copy of the Award dated 01.03.2016 was made

available to the Panel Advocate of the Department, who

received the same on 25.05.2016. It is further alleged that the

Advocate of the department kept the file pending for long and

did not return the same after drafting of grounds of revision and,

as such vide letters dated 03.11.2016, 18.01.2017, 30.01.2017,

13.02.2017, 27.02.2017 and 15.04.2017, the Executive Engineer

requested him to return the file. On 30.04.2017, the concerned

Lawyer returned the file along with grounds of Revision

Application as well as limitation petition and stay petition. It is

further contended that after receiving the said file, the Executive
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
17/66

Engineer sent the said file to the Superintending Engineer vide

letter dated 31.07.2017. The Superintending Engineer sent the

said file to the Chief Engineer, who, in turn, sent the said file to

the Engineer in-Chief cum-Additional Engineer cum- Special

Secretary Road Construction Department on 18.08.2017 for its

approval. On 11.09.2017, the Engineer in-Chief approved for

filing Revision application against the said Award and sent the

file to the Law Department on 15.09.2017. On the same day,

Law Department gave the opinion for filing Revision

Application against the said Award and the file was sent to the

learned Advocate General on 18.09.2017 which was received in

the office of learned Advocate General on 19.09.2017. It is

further contended that the learned Advocate General marked the

file to the concerned Law Officer for filing Revision Application

on 20.09.2017. Thereafter, the concerned Law Officer filed

instant Revision Application on 11.10.2017 along with

limitation petition as well as stay petition. It is submitted that

there is no deliberate or willful delay or laches on the part of the

petitioners in filing the instant revision application rather the

delay caused on account of procedural formalities.

19. Upon notice, the sole opposite party appeared and

filed his rejoinder to the limitation petition bearing I.A. No. 02
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
18/66

of 2017. Learned senior counsel for the opposite party submitted

that the Revision Application has been filed on 11.10.2017

against the Award dated 01.03.2016 passed in Reference Case

No. 115 of 2012. The said Award was passed on 01.03.2016 in

presence of learned counsel for the petitioner who had

knowledge about the passing of the Award. It is further

submitted that the explanation for condonation of huge delay

does not contain acceptable and plausible reason. It appears

from the pleading of the limitation petition that the petitioners

have failed to explain the delay. They have also failed to give

plausible and acceptable reason for the delay in filing the

Revision application. It is admitted fact that the Award was

pronounced in the presence of learned counsel for the

petitioners. The instant revision application has been filed on

11.10.2017 after 477 days (1 year 3 months 22 days). The

petitioner has failed to give sufficient explanation for

condonation of delay in filing the instant Civil Revision

application. It is apparent from the limitation petition, the Award

dated 01.03.2016 was communicated through Secretary of the

Arbitration Tribunal which was received on 17.03.2016. The file

of this instant case was sent to the empaneled Advocate on

25.05.2016 and on the same day he received the file but the
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
19/66

instant revision application has been filed on 11.10.2017. It is

further submitted that condonation of delay is an exception and

should not be used as an anticipated benefit for Government

departments. It is also submitted that Hon’ble Supreme Court as

well as this Court have already held that “The government

departments are under a special obligation to ensure that they

perform their duties with diligence and commitment.

Condonation of delay is an exception and should not be used as

an anticipated benefit for the government departments. The law

shelters everyone under the same light and should not be

swirled for the benefit of a few”. It is held that the claim on

account of impersonal machinery and inherited bureaucratic

methodology of making several notes cannot be accepted in

view of the modern technologies being used and available. The

law of limitation undoubtedly binds everybody, including the

Government. It is further submitted that the petitioner again

acted leisurely and claim condonation of delay as a matter of

fact only because the petitioners are the officers of the

Government department. The petition for condonation of delay

is completely devoid of any merit without any plausible

explanation.

Re: I.A. No. 7717 of 2017 in Civil Revision No. 208
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
20/66

of 2017

20. This interlocutory application has been filed under

Section 5 of the Limitation Act for condoning of delay of 8

months 22 days (date of Award dated 25.10.2016 and the date of

filing is 17.10.2017) in filing the Civil Revision application. The

date of filing of requisition for certified copy of Award is

16.10.2017 and the same was supplied on the same day.

21. The instant civil revision application has been

filed against the Award dated 25.10.2016 passed by the learned

Arbitration Tribunal in Reference Case No. 152 of 2014. The

remedy against the Award passed by the Tribunal is provided

under Section 13 of the Bihar Public Works Contracts Disputes

Arbitration Tribunal Act, 2008 whereby any party aggrieved by

the Award may file revision application within three months

from the date of Award.

22. From perusal of the averments made in the

limitation petition, it appears that vide letter No. 736 dated

15.11.2016, under the signature of the Secretary of the

Arbitration Tribunal Award dated 25.10.2016 passed in

Reference Case No. 152 of 2014 was communicated which was

received on 01.12.2016. After receipt of the Award, the

petitioners for the first time came to know about the Award
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
21/66

dated 25.10.2016 passed by the learned Arbitration Tribunal in

Reference Case No. 152 of 2014. It was brought to the notice to

the empaneled Advocate by the Executive Engineer to prepare

statement of facts to file revision application against the said

Award. It is contended that the concerned Advocate of the

Department prepared the statement of facts and returned the file

to the Executive Engineer on 28.07.2017, who, in turn, sent the

statement of facts to the Superintending Engineer on 31.07.2017

for its approval. The Superintending Engineer thereafter

forwarded the statement of facts to the Chief Engineer, Patna for

approval. The Chief Engineer forwarded the statement of facts

to the Engineer-in-Chief cum Additional Commissioner cum

Special Secretary, Road Construction Department Bihar, Patna

vide letter dated 18.08.2017 for its approval. The Engineer-in-

Chief gave an approval on 11.09.2017 and the file was then sent

to the Law Department which was received there on 15.09.2017.

The Law Department after giving its approval on 15.09.2017

sent the file to the learned Advocate General on 18.09.2017 for

filing Civil Revision. Thereafter, the present revision application

along with limitation petition and stay petition was filed on

17.10.2017. There is no deliberate laches on the part of the

petitioners, rather, some delay has occurred in completing
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
22/66

necessary formalities.

23. Upon summon, the sole opposite party has

appeared and filed counter affidavit in the limitation matter.

24. Learned senior counsel for the opposite party has

submitted that the averments made in the limitation petition are

vague, misleading and incorrect. It is admitted fact that the

Award dated 25.10.2016 passed in Reference Case No. 152 of

2014 was delivered in presence of both the parties. The

Petitioners cannot deny that they had no knowledge about such

Award dated 25.10.2016 before 01.12.2016. The Secretary of

Arbitration Tribunal sent the Award dated 25.10.2016 passed in

Reference Case No. 152 of 2014 for its compliance. It appears

from the record that the requisition for obtaining certified copy

of the same Award was filed on 16.10.2017 much after expiry of

limitation period and the same was delivered on 16.10.2017.

The petitioners have also failed to give the reason for the delay

in obtaining certified copy while the said Award was passed on

25.10.2016 in presence of the petitioners. It is also contended

that the petitioners have not given plausible explanation for the

delay and the petitioners have also failed to annex the required

documents in support of the averments made in the limitation

petition. In the aforesaid facts, the petitioners were not serious
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
23/66

about filing of the present revision application within limitation

period. There is no plausible explanation for delay in the said

limitation petition. In the aforesaid facts and circumstances of

the case, the limitation petition may be dismissed for the ends of

justice.

I.A. No. 9374 of 2017 in Civil Revision No. 258 of

2017

25. This interlocutory application has been filed under

Section 5 of the Limitation Act for condoning the delay of 1

year 1 month & 3 days in filing Civil Revision No. 258 of 2017.

26. This Civil Revision application has been filed on

20th December, 2017 against the Award dated 17.08.2016 passed

in Reference Case No. 59 of 2015 by the learned Arbitration

Tribunal. The limitation expired on 17.11.2016. However this

Civil Revision application has been filed after 1 year 1 month &

3 days.

27. From the perusal of the averments made in the

limitation petition, it appears that the Award was passed by the

learned Tribunal on 17.08.2016 which was duly received by the

Petitioners on 07.09.2016 sent by the Secretary of the

Arbitration Tribunal on 06.09.2016. The main plea explaining

the delay is based upon the time consumed in movement of the
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
24/66

file at different stages. It is contended that on 14.09.2016, the

Superintending Engineer sent the file to the Chief Engineer for

guidelines in view of letter dated 05.09.2016 of Executive

Engineer and in turn, the Engineer-in-Chief vide letter dated

23.09.2016 sent the file to the Executive Engineer. The

Executive Engineer sent the file to the panel Advocate of the

Department for preparing the ground of appeal/revision for

filing revision application. The said panel lawyer returned the

file to the Executive Engineer on 03.10.2016 along with the

grounds of revision application. The Executive Engineer sent

the drafted copy of ground for revision to the Superintending

Engineer vide letter dated 14.10.2016 for filing the revision

application before this Court. The approval for filing of revision

application was sought by the Superintending Engineer on

24.10.2017 by the Chief Engineer. On 15.12.2016, the Chief

Engineer directed the Executive Engineer to obtain the certified

copy of the impugned Award and send the same. In compliance

of the said direction, the Executive Engineer applied requisition

for obtaining certified copy of the said Award on 06.12.2016.

The said Award was supplied on 07.12.2016. It is further

pleaded that due to procedural formalities, the limitation period

for filing of revision application has elapsed. The Executive
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
25/66

Engineer sent the file along with limitation petition to the

Superintending Engineer on 07.11.2017, who sent the file to the

Chief Engineer on 11.11.2017. The Chief Engineer sent the file

to Engineer-in-Chief for approval who gave the approval on

07.12.2017 and on the same day, the file was sent to the

Principal Secretary of the Department. The Principal Secretary

forwarded the file to the Law Department for filing revision on

the same day. Thereafter, the said file was sent to the office of

the learned Advocate General on 13.12.2017. The learned

Advocate General marked the file to the concerned Law Officer

for filing revision application on 15.12.2017. Soon thereafter,

the revision application along with limitation and stay petition

was filed on 20th December, 2017. It is further contended that

there is no deliberate laches on the part of the petitioners rather

the delay has occurred due to some necessary official

formalities.

28. On notice, the opposite parties appeared and O.P.

No. 1 has filed counter affidavit in limitation petition. It is

pleaded that the petitioners have not come before this Court

with clean hand because they have failed to give acceptable and

cogent reason for delay. From perusal of the entire pleadings of

the limitation petition, it appears that they have failed to give
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
26/66

plausible and acceptable explanation of delay for filing the

instant revision application. It is further submitted that all the

authorities concerned were aware that the limitation period for

filing this revision application was only three months from the

date on which the Award is made, despite that after about eight

(8) months, i.e. on 15.12.2016, the Chief Engineer directed the

Executive Engineer to obtain the certified copy for filing the

civil revision. The limitation period was expired on 17.11.2016.

It is apparent from the limitation application that the petitioners

failed to furnish acceptable and cogent explanation for delay in

filing the revision application. In the aforesaid facts and

circumstances, this limitation petition is fit to be dismissed for

the ends of justice.

Re: I.A. No. 8105 of 2017 in Civil Revision No. 225

of 2017

29. This interlocutory application has been filed under

Section 5 of the Limitation Act for condoning the delay of 2

years 11 months 18 days in filing the Civil Revision application.

30. This Civil Revision application has been filed on

09.11.2017 against the Award dated 21.08.2014 passed in

Reference Case No. 38 of 2013 by the learned Arbitration

Tribunal whereby the claim of the opposite party for payment of
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
27/66

interest at the rate of 10 per cent per annum with effect from

13.09.2009 till 12.09.2012 over an amount of Rs. 2,45,777/-

only as also for cost was allowed.

31. In the light of the aforesaid Award, the opposite

party filed representation on 08.09.2014 to the Executive

Engineer, NH Division-2, Road Construction Department,

Biharsharif and requested to make payment in view of Award

dated 21.08.2014. It is further pleaded that the Executive

Engineer had made a request to Chief Engineer to release the

fund so that payment may be made to the opposite party in

compliance of order passed by the Arbitration Tribunal. In

response to that the Chief Engineer wrote a letter to the

Executive Engineer on 05.11.2014 to make available grounds of

review for filing the review petition against the said Award. The

same was made available to the Superintending Engineer for

filing review petition on 29.12.2014 and the same was sent to

the Chief Engineer on 12.01.2015 for its approval. The Chief

Engineer sent the file to the Engineer-in-Chief on 04.02.2015,

who authorised the Executive Engineer on 20.03.2015 to file

review petition before the Arbitration Tribunal. Soon thereafter,

the review petition was filed on 22.04.2015 before the

Arbitration Tribunal which was dismissed on 27.04.2016.
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
28/66

Thereafter, the Chief Engineer directed for filing revision

application against the Award dated 21.08.2014 as well as order

passed in Review case no. 4 of 2015 dated 27.04.2016. On the

request of the Executive Engineer, the empaneled Advocate

prepared grounds of revision for filing civil revision. The same

was forwarded to Superintending Engineer. The Superintending

Engineer sent the file to Chief Engineer on 07.12.2016 for its

approval. It is further contended that the Chief Engineer directed

Executive Engineer on 29.12.2016 to obtain certified copy of

Award dated 21.08.2014 and order dated 27.04.2016 passed in

the aforesaid review petition. However, the Executive Engineer

superannuated from his service on 31.01.2017 and the present

Executive Engineer took charge on 23.02.2017. It is also

pleaded that after the knowledge of the said matter, the present

Executive Engineer obtained certified copy from Arbitration

Tribunal and sent it to Superintending Engineer on 13.07.2007.

The Chief Engineer sent the file to Engineer-in-Chief on

14.07.2017 for its approval, who, in turn, sent the file to

Principal Secretary of the Department on 19.07.2017. The

Principal Secretary made some query and returned the file

which was again submitted on 04.10.2017. The Principal

Secretary gave approval on 05.10.2017 and sent it to the Law
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
29/66

Department for opinion/advice. The Law Department gave

permission to file revision application and sent it to the office of

learned Advocate General on 10.10.2017. Soon thereafter, on

09.11.2017, the aforesaid revision application was filed. There is

no deliberate or willful delay or laches on the part of the

petitioners in filing the revision application rather the delay has

been caused on account of procedural formalities and prayed for

condoning the delay in filing the civil revision application.

32. On notice in the limitation matter, the opposite

party appeared and filed his counter affidavit and vehemently

opposed the limitation petition. It is contended that the

petitioners have failed to explain the delay. They have also

failed to give plausible and acceptable explanation of huge

delay in filing the present civil revision application. It is further

contended that the remedy against the Award passed by the

Arbitration Tribunal is provided under Section 13 of the Bihar

Public Works Contracts Disputes Arbitration Tribunal Act, 2008

whereby any party aggrieved by the Award may file revision

application within three months from the date of Award. The

instant revision application has been filed on 09.11.2017 while

the limitation expired on 21.11.2014 after delay of 2 years 11

months 18 days (wrongly noted as 3 years 2 months 19 days). It
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
30/66

is further pleaded that the petitioners have not filed any

paper/documents in support of their averments. It is submitted

that the petitioners themselves admit that on 08.09.2014, they

have got knowledge about the Award dated 21.08.2014 and

despite that they applied for obtaining certified copy of the

Award on 10.07.2017 which was supplied to them on

13.07.2017 and the revision application has been filed on

09.11.2017 before this Court. It is apparent from the pleadings

of the petitioners that they were fully aware about the Award

dated 21.08.2014. In such view of the matter, the petitioners

have failed to furnish acceptable and cogent explanation for

delay in filing the civil revision application. The opposite party

has relied upon the decision in the case of Postmaster General

Vs. Living Media India Ltd. Reported in (2012) 3 SCC 563 and

in the case of State of U.P. v. Amar Nath Yadav reported in

(2014) 2 SCC 422. It is vehemently submitted that the State and

its officers cannot be treated differently while considering the

prayer for condonation of delay and prayed for dismissal of the

limitation petition.

Re: I.A. No. 201 of 2018 in C.R. No. 05 of 2018

33. This application has been filed under Section 5 of

the Limitation Act, 1963 for condoning the delay of 10 months 9
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
31/66

days in filing the instant Civil Revision application.

34. The instant application has been filed against the

Award dated 30.11.2016 passed in Reference Case No. 106 of

2012 by the learned Bihar Public Works Contracts Disputes

Arbitration Tribunal, Patna.

35. The aforesaid revision application along with

limitation petition has been filed on 09.01.2018. The period of

limitation expired on 28.02.2017. The requisition for certified

copy of Award was filed on 08.03.2017 which was ready for

delivery on the same day. The said certified copy was obtained

on 10.03.2017.

36. From perusal of the averments made in the

limitation petition, it is appears that the petitioners got

knowledge of the Award dated 30.11.2016 passed in Reference

Case No. 106 of 2012 on 19.12.2016. Soon thereafter, the

deponent sent the file to the department for necessary action.

37. In view of the legal opinion obtained from Panel

Advocate of the Department, the Department had taken decision

to assail the matter by filing Civil Revision application before

this Court. On the direction of Engineer-in-Chief cum-

Additional Commissioner cum Special Secretary of the

department vide its letter dated 23.12.2016 for preparation of
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
32/66

statement of facts and grounds for Civil Revision and in

compliance of the same, the Executive Engineer vide letter

dated 10.02.2017 and submitted the formal draft prepared by

Panel Advocate to the Superintending Engineer on 10.02.2017.

Thereafter, the Chief Engineer issued letter dated 08.03.2017

with a direction to the Superintending Engineer to make

available the statement of facts and grounds of Revision

application. The Superintending Engineer issued letter dated

09.03.2017 to the Executive Engineer to submit the statement of

facts and grounds as required. The Executive Engineer sent a

letter to the Superintending Engineer on 18.03.2017 whereby

the Executive Engineer has replied that the required certified

copy of the Award has already been submitted in the

department. The Engineer-in-Chief- cum- Special Secretary

issued the letter dated 28.04.2017 to the Chief Engineer, South

Bihar with specific direction to make available the grounds of

revision and application for condonation of delay. A reminder

was also sent by the Engineer-in-Chief to the Chief Engineer,

South Bihar on 25.07.2017. It is further contended that after

receiving the statement of facts and grounds for filing Civil

Revision application, the same was sent for approval. The

Engineer-in-Chief approved the statement of facts and grounds
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
33/66

for filing the Civil Revision and file was sent to the Law

Department on 13.10.2017 for filing the Civil Revision

application. The Law Department sent the file to the office of

the learned Advocate General, Bihar, on 17.10.2017 and

subsequently the present case was allotted to the learned AAG-

11. Thereafter, the present Civil Revision application has been

filed on 09.01.2018. It is further contended that there is no

deliberate or intentional laches on the part of the petitioner

rather the same has occurred due to lack of knowledge of the

Award as well as due to procedural formalities.

38. Learned counsel for the opposite party appeared

suo moto but did not file counter affidavit to the limitation

petition.

Re: I.A. No. 9684 of 2018 in C.R. No. 194 of 2018

39. This application has been filed under Section 5 of

the Limitation Act, 1963 for condoning the delay of 2 years 21

days (date of Award is 31.08.2016) in filing the instant Civil

Revision application.

40. The present Revision application has been filed

against the Award dated 31.08.2016 passed in Reference Case

No. 134 of 2013 by the Arbitration Tribunal. The period of

limitation for filing the instant Revision application expired on
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
34/66

30.11.2016 (90 days from the date of Award).

41. In the limitation petition, it is contended that the

impugned Award was passed on 31.08.2016 in Reference Case

No. 134 of 2018 by the Arbitration Tribunal and the same was

received on 29.09.2016. It was brought to the notice of Under

Secretary of the department on 24.11.2016, who placed the file

before the Joint Secretary on 25.11.2016. The same was

produced before the Engineer-in-chief on 04.12.2016.

Thereafter, the file was placed before the Principal Secretary of

the department on 05.12.2016. The Engineer-in-chief sent the

file to the Law Department seeking opinion for filing Civil

Revision application against the impugned Award. The

Secretary-cum-Legal Remembrance, Department of Law, Bihar

gave its opinion thereafter the file was sent to office of learned

Advocate General on 16.12.2016. It is further contended that

file was kept in the bunch of regular cases by mistake of

Advocate’s clerk of the concerned Lawyer due to which the

present Civil Revision application could not be filed in time. It

is further contended that in course of verification, the file was

located by the learned AC to AAG-4 on 05.10.2018. Soon

thereafter, the present Revision application along with the

limitation petition has been filed on 20.12.2018. Due to mistake
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
35/66

of the Advocate’s clerk delay has been caused in filing the Civil

Revision application and there is no deliberate or intentional

laches on the part of the petitioners in filing the instant Civil

Revision application.

42. Learned senior counsel for the opposite party

submitted that the explanation for condonation of huge delay

does not contain acceptable and plausible reason. The impugned

Award was passed on 31.08.2016 and the requisition for

certified copy of the Award was filed on 18.12.2018, i.e. just 2

days before filing the instant Revision application and the same

was delivered on the same date despite the fact that the said

Award dated 31.08.2016 was pronounced in presence of both

the parties. Further, it is admitted by the petitioners that the

impugned Award was received on 29.09.2016 sent by the office

of Arbitration Tribunal. The petitioners cannot deny knowledge

of such Award within statutory period of limitation. It is

apparent from the plea taken by the petitioners in its limitation

petition that each and every stage of movement of file

lackadaisical approach was taken for obtaining necessary

approval/ formalities. From the pleading of limitation petition, it

appears that the petitioners have failed to explain delay by

giving plausible and acceptable reason of delay in filing the
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
36/66

present Civil Revision application.

Re: I.A. No. 1 of 2019 in Civil Revision No. 9 of

2019

43. This interlocutory application has been filed under

Section 5 of the Limitation Act for condonation of delay of 1

year, 10 months 24 days (693 days) in filing this Civil Revision

application against the Award dated 22.11.2016 passed by the

learned Tribunal in Reference Case No. 110 of 2011, whereby

the petitioners’ Reference Case has been dismissed.

44. From perusal of the averments made in the

limitation petition, it appears that the Section Officer of the

Department received the copy of Award dated 22.11.2016 on

06.12.2016. The file was sent to the Superintendent Engineer

and opinion was sought from the Chief Engineer of the

Department through proper channel. It is further contended that

statement of facts for filing Civil Revision was received from

Chief Engineer on 20.12.2016. The same was forwarded to the

Law Department for obtaining opinion on the same day. The file

was brought to the notice of Engineer in Chief, who forwarded

the same to Principal Secretary on 15.03.2017 for obtaining

legal formalities and lastly Secretary-cum-Legal Remembrance,

Bihar rendered its sanction and thereafter, on 28.03.2017, file
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
37/66

was sent to the learned Advocate General and on his advice for

filing Civil Revision Application, against the said Award, the

file was allotted to the AAG-4 on 30.03.2017. It is further

contended that the file was locked in the Almirah and the

Advocate’s Clerk inadvertently kept the file alongwith other

files in a bundle. The said file got tied up with other files and

only in the month of September, 2018, when officer of the

department approached the office of AAG-4, then on search, the

file was located on 28.09.2018. Thereafter, the said file along

with statement of facts was allotted to Assistant Counsel on

03.10.2018 for preparing Revision Petition and limitation

petition and soon thereafter, revision application was drafted

finally on 26.10.2018 the brief became ready for oath. A letter

was sent to the Department for deputing the authorised person to

swear the affidavit of the revision application. Lastly on

15.01.2019, the present revision application alongwith

limitation petition has been filed. It is further case of the

petitioners that due to mistake of the Advocate’s clerk, some

delay has caused in filing this revision application and there is

no intentional and deliberate laches on the part of the

petitioners.

45. On notice in limitation matter, opposite party
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
38/66

appeared and filed rejoinder to the limitation petition and

vehemently opposed the prayer for condonation of huge delay

of 599 days (wrongly noted as 693 days). It is contended that

the explanation for condonation of delay does not contain any

acceptable and plausible reason. It is further contended that it is

admitted by the petitioners that the Award dated 22.11.2016

was received by the Section Officer on 06.12.2016 itself. The

requisition for obtaining certified copy of Award dated

22.11.2016 passed in Reference Case No. 110 of 2011 was filed

on 04.01.2019 which was ready on the same day i.e.

04.01.2019, despite the knowledge of the Award and the same

was received on 06.12.2016. It is apparent from the certified

copy of the Award that the requisition for obtaining certified

copy was filed on 04.01.2019 much beyond the prescribed

period of limitation for filing the Civil Revision application. It is

apparent from the limitation petition that the petitioners have

failed to furnish acceptable and cogent explanation for delay of

1 year 10 months 24 days in filing the revision application. It is

further contended that it is the usual explanation that the file

was kept pending for several months and time was consumed in

procedural formalities and also the file was kept in the Almirah

of the office of the advocates for several months. In such view
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
39/66

of the matter, the limitation petition may be dismissed having no

acceptable explanation of huge delay.

Re: I.A. No. 1 of 2019 in Civil Revision No. 20 of

2019

46. This application has been filed under Section 5 of

the Limitation Act for condoning the delay of 3 years 9 months

16 days. The limitation expired on 20.04.2015 which was the

last date of filing this Civil Revision.

47. The aforesaid revision application has been filed

against the Award dated 20.01.2015 passed in Reference Case

No. 102 of 2011 by the Arbitrator Tribunal, Patna whereby

learned Arbitration Tribunal directed to refund the amount under

different heads with costs.

48. From perusal of the pleadings made in the

limitation petition, it appears that the petitioners came to know

about the Award dated 20.01.2015 passed in Reference Case No.

102 of 2011 on 21.03.2015 on receiving the intimation from

conducting lawyer of the said case. The department vide its

Letter No. 652 dated 27.01.2016 requested the empaneled

Advocate for drafting the statement of facts for assailing the

Award dated 20.01.2015 passed in Reference Case No. 102 of

2011 by the Arbitrator Tribunal. However, the present matter
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
40/66

was earlier under the Road Construction Department NH

Division, Aurangabad but from 22.09.2015 onwards, this matter

was transferred to NH Division Gulzarbagh. It is further pleaded

that the concerned advocate of the department could not prepare

the grounds to file civil revision application due to paucity of

time. Then, the file was sent to another counsel on 22.08.2016.

The learned counsel for the department returned the file to the

department on 22.09.2017 along with statement of facts for

filing civil revision application. The same was sent to the

department for its approval by the Executive Engineer NH

Division Gulzarbagh vide Letter No. 1127 dated 21.09.2017

through the concerned Superintending Engineer. It is further

contended that the said file was again sent to another advocate

of the department for preparing grounds for condonation of

delay on 09.11.2017. The same was returned along with the

statements of facts with regard to the condonation of delay by

the concerned advocate of the department on 24.11.2017.

Thereafter the present revision application has been filed on

06.02.2019. Hence, there is no deliberate or intentional laches

on the part of the petitioners and prayer has been made to

condone the delay in the interest of justice.

49. On 17.02.2020 suo moto opposite party appeared
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
41/66

through his learned counsel by filing Vakalatnama on behalf of

the opposite party and also filed rejoinder to I.A. No. 1 of 2019

(wrongly typed as I.A. No. 1 of 2020) and vehemently opposed

the condonation of huge delay of 3 years 9 months 16 days.

50. It is contended that the work in question was

under Road Construction Department, NH West Division, Patna

and not under NH Division Aurangabad. The said Reference

Case was filed against the State of Bihar through the Secretary,

Road Construction Department, Patna and the Executive Road

Construction Department, NH West Division Patna. The

statement of petitioners itself stands falsified from the records.

The petitioners appeared in the said Reference Case before the

Arbitration Tribunal and filed their rejoinder in the Reference

Case on 04.12.2013 itself. The department misled this Court by

making false statements. As such, the petitioners are not entitled

to equitable reliefs for condonation of delay. It is well settled

that whoever has approached the court with unclean hands, as in

the instant case, no equitable relief can be granted to such unfair

litigants. It is also contended that the petitioners have no

explanation or sufficient reason for delay in filing the present

revision application except saying that delay has occurred due to

movement of file from one office to another office. It is
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
42/66

contended that the lame excuse and reasons are not sufficient for

condonation of delay. The statement made by the petitioners is

totally misleading, laxity on the part of petitioner as well as

casualness of the petitioners. It is further contended that the

Apex Court as well as this Court has already held that “the

Government departments are under a special obligation to

ensure that they perform their duties with diligence and

commitment. Condonation of delay is an exception and should

not be used as as an anticipated benefit for Government

departments. The law shelters everyone under the same light

and should not be swirled for the benefit of a few”. In such

view of the matter, the huge delay of 3 years 9 months 16 days

cannot be condoned in the interest of justice.

Re: I.A. No. 01 of 2020 in C.R. No. 21 of 2019

51. This application has been filed under Section 5 of

the Limitation Act for condoning the delay of 3 years 2 days in

filing the instant Civil Revision application. The said Revision

application has been filed against the judgment and Award dated

04.11.2015 passed in Reference Case No. 61 of 2012 by the

learned Arbitration Tribunal whereby an Award was passed in

favour of opposite party.

52. It is contended that a notice was issued by the
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
43/66

Executing Court which was received on 28.05.2018 and on

getting the said information with regard to execution case

arising out of Award dated 04.11.2015 passed in Reference Case

No. 61 of 2012, the then Superintending Engineer, N.H.

Division, Gulzarbagh, issued letter no. 1636 dated 30.05.2018

and directed the Executive Engineer, N.H. Division,

Gulzarbagh, to appear before the learned Execution Court

through Government Pleader and also directed to submit the

stand of the Government in this regard and further directed that

statement of facts would be prepared and the same would be

sent for approval. In compliance of aforesaid letter, the

Executive Engineer N.H. Division, Gulzarbagh, issued letter

dated 04.06.2018 and requested the Government Pleader to

make pairvi in the matter. It is further submitted that the

Engineer-in-chief, Road Construction Department also issued

memo No. 4131(E) dated 14.06.2018 and directed the Executive

Engineer N.H. Division, Gulzarbagh, to prepare the statement of

facts for filing show cause in the Execution Case No. 284 of

2017 on the direction of the superior authority of the concerned

department. The Executive Engineer N.H. Division,

Gulzarbagh, enquired about the Reference Case No. 61 of 2012

from the learned Arbitration Tribunal and then they learnt that
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
44/66

the matter has already been disposed of by order/ Award dated

04.11.2015. Thereafter, on 14.09.2018 he applied for obtaining

certified copy of Award dated 04.11.2015 passed in Reference

Case No. 61 of 2012. The same was supplied on the same day.

After perusal of the said Award dated 04.11.2015 passed by the

learned Arbitration Tribunal, it was decided to challenge the

Award of Arbitration Tribunal and before this Court by way of

filing Civil Revision application. Accordingly, statement of facts

and grounds for filing Revision application was prepared and

the same was put up before the authority concerned on

19.11.2018 for sanction. After preparation of Civil Revision

application, the file along with draft was sent for vetting and

after completing the procedure, the file was sent to the

Secretary-cum-Legal Remembrance on 11.12.2018. The

Secretary-cum-Legal Remembrance sent the file to the learned

Advocate General for filing Civil Revision application against

the impugned Award. Thereafter, the present Revision

application has been filed on 06.02.2019. It is further submitted

that petitioners had no knowledge about the Award dated

04.11.2015 passed in Reference Case No. 61 of 2012 and there

is no deliberate or intentional laches on the part of the

petitioners. The delay has occurred on account of complying the
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
45/66

procedural formalities and prayed that it may be condoned for

the ends of justice.

53. Learned counsel for the opposite party appeared

suo moto and filed his rejoinder to the interlocutory application

and vehemently opposed the condonation of delay in filing the

instant Revision application. It is further contended that the

Bihar Public Works Contracts Disputes Arbitration Tribunal Act,

2008 was enacted with the object of expeditious redressal of the

dispute and as such, while considering the application for

condonation of delay, the object of the Act is of paramount

consideration. The remedy against the Award passed by the

Tribunal is provided under Section 13 of the Bihar Public Works

Contracts Disputes Arbitration Tribunal Act, 2008 whereby any

party aggrieved by the Award may file Revision application

within 3 months from the date of Award while the present

application has been filed after about 3 years of expiry of

limitation period of 90 days. It is further contended that

petitioners were party in Reference Case No. 61 of 2012

represented through the counsel and they filed their reply in the

said Reference Case. Moreover, the said impugned Award was

passed by the Arbitration Tribunal in presence of learned

counsels for the parties after notifying the case ‘For Orders’ and
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
46/66

in such view of the matter petitioners cannot take plea that they

had no knowledge about the passing of the Award. There is no

plausible explanation for delay in the instant application. The

said Award was passed after hearing the parties and it is not an

ex parte Award. It is pertinent to mention that the petitioners

have themselves stated that they had learnt about the Execution

case on 28.05.2018 itself therefore their statement that they

learnt about the Award on 14.09.2018 is patently false. It is

further contended that the deponent in order to get order of

condonation of delay in favour of petitioner, has made false

statement in limitation petition and as such the petitioners are

not entitled to equitable relief in the nature of condonation of

delay as it is well settled that if the party approaches the Court

with unclean hands, as in the present case, no equitable relief

can be granted to such unfair litigants. Petitioners have not

furnished sufficient cause of delay in filing of the present

Revision application except saying that delay has occurred due

to movement of file from one office to another. It is further

contended that the State and its officers cannot be treated

differently while considering the prayer of condonation of delay.

The petitioners have miserably failed to give any acceptable and

cogent reason which may be sufficient to condone the delay of
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
47/66

about 3 years.

54. In support of their cases, learned counsel for the

petitioners, in all cases, submitted his common submission

placing the relevant citations for consideration of condonation

of delay in filing the Revision applications.

55. Learned counsel for the petitioners relied upon the

decision reported in 2023 (10) SCC 531 (Sheo Raj Singh (d)

through Lrs. & Ors. Vs. Union of India and Anr) wherein the

Apex Court has held in para 35.2 “the expression “sufficient

cause” is elastic enough for courts to do substantial justice.

35.3. It is upon the courts to consider the sufficiency of cause

shown for the delay, and the length of delay is not always

decisive while exercising discretion in such matters if the delay

is properly explained. 35.4. It is further held that a distinction

should be drawn between inordinate unexplained delay and

explained delay, where in the present case, the first respondent

had sufficiently explained the delay on account of negligence on

part of the government functionaries and the government

counsel on record before the Reference Court. 41. An exercise of

jurisdiction does, at times, call for liberal and justice oriented

approach by the courts where certain leeway could be provided

to the State. The hidden forces that are at work in preventing an
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
48/66

appeal by the State being presented within the prescribed period

of limitation so as not to allow a higher court to pronounce

upon the legality and validity of an order on lower court and

thereby secure unholy gains, can hardly be ignored”.

56. Learned counsel for the petitioners submitted that

due to special circumstances which were beyond the control of

the State authorities some time was consumed in taking

procedural formalities. It was further urged that delay may be

condoned as the interest of State would be jeopardized and

whatever be the laches were, they were neither willful nor

deliberate. In this context, learned counsel for the petitioners has

drawn the attention of this Court to a decision of the Apex Court

reported in 2015 (3) SCC 569 (Executive Officer, Antiyur Town

Panchayat vs.. G. Arumugam (D) By Lrs., wherein, the Apex

Court condoned the delay of 1373 days in filing the appeal.

Learned counsel submitted that in the interest of justice and

keeping in view the larger interest, the court should take lenient

view and condone the delay howsoever, the huge may be the

delay. Learned counsel(s) further relied upon a decision in the

case of Maniben Devraj Shah vs. Municipal Corporation of

Brihan Mumbai reported in 2012 (5) SCC 157. In the aforesaid

decision, the Apex Court in paragraph 18 has relied upon a
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
49/66

decision of the Apex Court reported in (1998) 7 SCC 123 (N.

Balakrishnan v. M. Krishnamurthy) wherein, the Apex Court

has held that rules of limitation are not meant to destroy the

rights of parties. They are meant to see that parties do not resort

to dilatory tactics, but seek their remedy promptly. In paragraph

13 of the aforesaid judgment, the Apex Court has held that while

condoning the delay, the court should not forget the opposite

party altogether. It must be borne in mind that he is a loser and

he too would have incurred quite large litigation expenses. It

would be a salutary guideline that when courts condone the

delay due to laches on the part of the applicant, the court shall

compensate the opposite party for his loss.

57. Reliance has also been placed by learned counsel

for the petitioners on the judgment in the case of Lanka

Venkateswarlu (D) By Lrs vs State Of A.P. & Ors reported in

2011 (4) SCC 363 wherein the Apex Court has held that the

concepts such as “liberal approach”, “justice oriented approach”,

“substantial justice” can not be employed to jettison the

substantial law of limitation. Especially, in cases where the

Court concludes that there is no justification for the delay. On

the similar point, reliance has been placed also on the decision

in the case of State of Nagaland v. Lipok AO and Ors. reported
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
50/66

in (2005) 3 SCC 752.

58. Per contra, learned senior counsel appearing on

behalf of opposite party has vehemently opposed the application

for condonation of delay and replied the submission based on

citation. Learned senior counsel submitted that the petitioners

have relied upon State of Nagaland v. Lipok AO (supra). The

said judgment arises out of a criminal appeal. The State

preferred appeal against acquittal and application for grant of

leave was made in terms of Section 378 (3) of the Code of

Criminal Procedure, 1973 as there was delay in making the

application for grant of leave in terms of Section 378(3) of the

Cr.P.C., application for condoning the delay was filed. There

was delay of 57 days in preferring application for grant of leave

under Section 378(3) of the Cr.P.C. The High Court refused to

condone the delay of 57 days on the ground that it is a duty of

litigant to file appeal before expiry of limitation period. Merely

because the Additional Advocate General did not file an appeal

inspite of instructions issued to him that did not constitute

sufficient cause and further the fact that the records were

purportedly missing was not valid ground. Consequently, the

application for grant of leave was rejected by the High Court.

The Apex Court condoned the delay of 57 days in filing the
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
51/66

grant of leave and set aside High Court’s judgment. In the

present cases, in all the revision applications, almost same

grounds have been taken by the authorities concerned with

regard to movement of file for obtaining sanction and other

formalities.

59. Learned senior counsel further submitted that it is

apparent from the records that there was delay at every stage

and there is no explanation except mentioning the dates of

movement of files even according to the petitioners, they

received the impugned Awards on 25.05.2014 (in Civil Revision

No. 9 of 2017 which has been filed on 12.01.2017), Award dated

01.03.2016 was received on 17.03.2016 (in Civil Revision No.

203 of 2017 which has been filed on 11.10.2017), Award dated

25.10.2016 was received on 01.12.2016 (in Civil Revision No.

208 of 2017 which has been filed on 17.10.2017), Award dated

17.08.2016 was received on 07.09.2016 sent by the Secretary of

the Arbitration Tribunal (in Civil Revision No. 258 of 2017

which has been filed on 20.12.2017), Award dated 21.08.2014

which was informed to the petitioners by opposite parties

through his representation dated 08.09.2014 ((in Civil Revision

No. 225 of 2017 which has been filed on 09.11.2017), for Award

dated 30.11.2016, requisition for certified copy of Award was
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
52/66

filed on 08.03.2017 and on the same day, the said certified copy

of Award was ready for delivery (in Civil Revision No. 5 of

2018) which has been filed on 09.01.2018, Award dated

31.08.2016 was received on 29.09.2016 by the petitioners (in

Civil Revision Application No. 194 of 2018) which has been

filed on 20.12.2018, Award dated 22.11.2016 was received on

06.12.2016 by the petitioners (in Civil Revision No. 9 of 2019

which has been filed on 15.01.2019), Award dated 20.01.2015

was received on 21.03.2015 (in Civil Revision No. 20 of 2019)

which has been filed on 06.02.2019 after prescribed period of

limitation and the impugned Award was passed in presence of

the petitioners’ counsel (in Civil Revision No. 21 of 2019 which

has been filed on 06.02.2019 after about 3 years of expiry of

limitation period of 90 days).

60. Reliance has been placed in the case of

Postmaster General and Others Vs. Living Media India Ltd.

And Another reported in (2012) 3 SCC 563. The Hon’ble Apex

Court in order to emphasize that the State and its officers cannot

be treated differently while considering the prayer for

condonation of delay has held in the aforesaid judgment as

follows:-

“27. It is not in dispute that the person(s)
concerned were well aware or conversant
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
53/66

with the issues involved including the
prescribed period of limitation for taking up
the matter by way of filing a special leave
petition in this Court. They cannot claim that
they have a separate period of limitation
when the Department was possessed with
competent persons familiar with court
proceedings. In the absence of plausible and
acceptable explanation, we are posing a
question why the delay is to be condoned
mechanically merely because the
Government or a wing of the Government is
a party before us.

28. Though we are conscious of the fact that
in a matter of condonation of delay when
there was no gross negligence or deliberate
inaction or lack of bona fides, a liberal
concession has to be adopted to advance
substantial justice, we are of the view that in
the facts and circumstances, the Department
cannot take advantage of various earlier
decisions. The claim on account of
impersonal machinery and inherited
bureaucratic methodology of making several
notes cannot be accepted in view of the
modern technologies being used and
available. The law of limitation undoubtedly
binds everybody, including the Government.

29. In our view, it is the right time to inform
all the government bodies, their agencies
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
54/66

and instrumentalities that unless they have
reasonable and acceptable explanation for
the delay and there was bona fide effort,
there is no need to accept the usual
explanation that the file was kept pending
for several months/years due to considerable
degree of procedural red tape in the process.
The government departments are under a
special obligation to ensure that they
perform their duties with diligence and
commitment. Condonation of delay is an
exception and should not be used as an
anticipated benefit for the government
departments. The law shelters everyone
under the same light and should not be
swirled for the benefit of a few.

30. Considering the fact that there was no
proper explanation offered by the
Department for the delay except mentioning
of various dates, according to us, the
Department has miserably failed to give any
acceptable and cogent reasons sufficient to
condone such a huge delay. Accordingly, the
appeals are liable to be dismissed on the
ground of delay.”

61. Learned senior counsel replied upon the decision

relied by the petitioners in the case of Maniben Devraj Shah

(Supra) and has placed paragraph nos. 18 & 19 of the said
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
55/66

judgment. Learned senior counsel also placed paragraph 28 &

29. The Apex Court has held that the learned single judge of the

High Court altogether ignored the gaping holes in the story

concocted by the Corporation about misplacement of the papers

and total absence of any explanation as to why nobody even

bothered to file applications for issue of certified copies of the

judgment for more than 7 years. It has been further held that the

reason assigned by the learned single judge be treated as poor

apology for exercise of discretion by the Court under Section 5

of the Limitation Act and dismissed the appeal filed by the

respondent against the judgment of the trial court.

62. Further, reliance has also been placed on the

judgment passed in the case of State of Bihar and Others Vs.

Santosh Kumar in Civil Revision No. 109 of 2018, whereby

this Court after considering the judgment of Apex Court as well

as this Court dismissed the application holding that the

petitioners have miserably failed to give any acceptable and

cogent reason which may be sufficient to condone the delay of 1

year 3 months 20 days in filling the instant revision application.

Further reliance has been placed in the case of State of Bihar &

Others Vs. M/s Trimurti Construction passed by this Court in

Civil Revision No. 48 of 2015 on 23.09.2015. This Court has
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
56/66

held that the petitioner had failed to furnish acceptable and

cogent explanation for delay of 9 months 26 days in filing the

revision application. Accordingly, the said revision application

was dismissed on the point of delay of 9 months 26 days

without any cogent explanation.

63. Shorn of unnecessary details, it may be stated that

the instant applications have been filed on behalf of the

petitioners against the impugned Award and in each of the

aforesaid Civil Revision applications, prayer has been made to

condone the delay of 2 years 6 months 16 days in Civil Revision

No. 09 of 2017, 1 year 3 months 22 days in Civil Revision

No.203 of 2017, 8 months 22 days in Civil Revision No. 208 of

2017, 1 year 1 month 3 days in Civil Revision No. 258 of 2017,

2 years 11 months 18 days in Civil Revision No. 225 of 2017,

10 months 9 days in Civil Revision No. 5 of 2018, 2 years 21

days in Civil Revision No. 194 of 2018, 1 year 10 months 24

days in Civil Revision No. 9 of 2019, 3 years 9 months 16 days

in Civil Revision No. 20 of 2019 and 3 years 2 days in Civil

Revision No. 21 of 2019. The Award dated 06.05.2014 passed in

Reference Case No. 85 of 2010 (Civil Revision No. 9 of 2017),

Award dated 01.03.2016 passed in Reference Case No. 115 of

2012 (Civil Revision No. 203 of 2017), Award dated 25.10.2016
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
57/66

passed in Reference Case No. 152 of 2014 ( Civil Revision No.

208 of 2017), Award dated 17.08.2016 passed in Reference Case

No. 59 of 2015 ( Civil Revision No. 258 of 2017), Award dated

21.08.2014 passed in Reference Case No. 38 of 2013 (Civil

Revision No. 225 of 2017), Award dated 30.11.2016 passed in

Reference Case No. 106 of 2012 ( Civil Revision No.05 of

2018), Award dated 31.08.2016 passed in Reference Case No.

134 of 2013 ( Civil Revision No. 194 of 2018), Award dated

22.11.2016 passed in Reference Case No. 110 of 2011 (Civil

Revision No. 9 of 2019), Award dated 20.01.2015 passed in

Reference Case No. 102 of 2011 (Civil Revision No. 20 of

2019) and Award dated 04.11.2015 passed in Reference Case

No. 61 of 2012 (Civil Revision No. 21 of 2019) have been

challenged separately in the aforesaid revision applications filed

under Section 13 of the Bihar Public Works Contracts Disputes

Arbitration Tribunal Act, 2008 which provides for revision

application to be filed within three months from the date on

which the Award is made. The limitation for filing of the

Revision Applications expired on 06.08.2014, 20.06.2016,

25.01.2017, 21.11.2014, 17.11.2016, 28.02.2017, 30.11.2016,

22.02.2017, 20.04.2015 & 04.02.2016 respectively.

64. The details of the each case has been mentioned in
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
58/66

the following table.

SI No. of Date of Date of Date of Award Date of Date of Delay
No Civil Award knowled requisiti ready supplied filing in
. Revisio ge/ on for for Civil filing
n commun C.C. of delivery Revisio Civil
ication Award n Revisi
of on
Award

1. 9/2017 06.05. 25.05. —– —- —- 12.01. 2 years
2014 2014 2017 5months
6 days

2. 203/201 01.03. 17.03. 02.08. 02.08. 08.08. 11.10. 1 year
7
2016 2016 2017 2017 2017 2017 3months
22
days

3. 208/2017
25.10. 01.12. 16.10. 16.10. 16.10. 17.10. 8
2016 2016 2017 2017 2017 2017 months 22
days

4. 258/2017
17.08. 07.09. 06.12. 06.12. 07.12. 20.12. 1 year
2016 2016 2016 2016 2016 2017 1month
3 days

5. 225/2017
21.08. 08.09. 10.07. 12.07. 13.07. 09.11. 2 years
2014 2014 2017 2017 2017 2017 11 months
18
days

6. 5/2018 30.11. 19.12. 08.03. 08.03. 10.03. 09.01. 10
2016 2016 2017 2017 2017 2018 months 9 days

7. 194/2018
31.08. 29.09. 18.12. 18.12. 18.12. 20.12. 2 years
2016 2016 2018 2018 2018 2018 21 days

8. 9/2019 22.11. 06.12. 04.01. 04.01. 04.01. 15.01. 1 year
2016 2016 2019 2019 2019 2019 10 months
24
days

9. 20/2019 20.01. 21.03. 09.10. 09.10. 09.10. 06.02. 3 years
2015 2015 2017 2017 2017 2019 9months
16
days

10. 21/2019 04.11. 28.05. 14.09. 14.09. 14.09. 06.02. 3 years
2015 2018 2018 2018 2018 2019 2 days
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
59/66

65. In all cases, the requisitions for certified copy of

Awards have been filed by the petitioners after long delay of the

prescribed period for filing the revision applications. It is

apparent from the limitation petitions filed in the aforesaid

revision applications that there was delay at every stage and

there is no plausible explanation except mentioning the dates of

movement of files. The matter has been dealt with by the

Hon’ble Apex Court in detail in the case of Government of

Maharashtra (Water Resources Department) represented by

Executive Engineer Vs. Borse Brothers Engineer and

Contractors Pvt. Ltd. reported in (2021) 6 SCC 460. The

Hon’ble Supreme Court has held that the object of speedy

disposal sought to be achieved both under the Arbitration Act

and the Commercial Courts Act, that is, the speedy resolution of

disputes, the expression “sufficient cause” is not elastic enough

to cover long delays beyond the period provided by the appeal

provision itself. Besides, the expression “sufficient cause” is not

itself a loose panacea for the ill of pressing negligent and stale

claims. The Apex Court has relied upon the decision in the case

of Basawaraj Vs. LAO reported in (2013) 14 SCC 81. The

expression “sufficient cause” should be given a liberal

interpretation to ensure that substantial justice is done, but only
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
60/66

so long as negligence, inaction or lack of bona fides cannot be

imputed to the party concerned, whether or not “sufficient

cause” has been furnished, can be decided on the facts of a

particular case and no straitjacket formula is possible.

66. The Hon’ble Apex Court further quoted policy of

Limitation Acts and unlimited limitation would lead to a sense

of insecurity and uncertainty, and therefore, limitation prevents

disturbances or deprivation of what any have acquired in equity

and justice by long enjoyment or what may have been lost by a

party’s own inaction, negligence or laches. It has been further

held in the case of P. Ramachandra Rao Vs. State of Karnatka

reported in (2002) 4 SCC 578, by the Hon’ble Apex Court held

that judicially engrafting principles of limitation amounts to

legislating and would fly in the face of law laid down by the

Constitution Bench in Abdul Rehman Antulay Vs. R.S. Nayak

reported in (1992) 1 SCC 225. It has been further quoted that

law on the issue can be summarized to the effect that where a

case has been presented in the court beyond limitation, the

applicant has to explain the court as to what was the “sufficient

cause” which means an adequate and enough reason which

prevented him to approach the Court within limitation. In case a

party is found to be negligent or for want of bona fide on his
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
61/66

part in the facts and circumstances of the case, or found to have

not acted diligently or remained inactive, there cannot be

justified grounds to condone the delay. No court could be

justified in condoning such an inordinate delay by imposing any

condition whatsoever. The Hon’ble Apex Court in number of

cases particularly in the Postmaster General (Supra) in

paragraph no. 27, 28 & 29 has observed that merely because the

Government is involved, a different yardstick for condonation of

delay cannot be laid down.

67. The decision in the Postmaster General (supra)

has been followed in the following subsequent judgment of the

Hon’ble Apex Court.

(i) The State of Rajasthan Vs. Bal Kishan

Mathur reported in (2014) 1 SCC 592 -at paras 8-8.2.

(ii) The State of U.P. Thr. Exe. Engineer & Anr.

Vs. Amar Nath Yadav reported in (2014) 2 SCC 422 –

paras 2-3.

(iii) The State of M.P. & Ors. Vs. Bherulal

reported in (2020) 10 SCC 654 – at paras 3-4.

68. In a recent decision, the Hon’ble Supreme Court

has laid down principles in the case of Pathapati Subba Reddy

(died) by Lrs. And Ors. Vs. The Special Duty Collector (LA) in
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
62/66

Special Leave Petition (Civil) No. 31248 of 2018 decided on

08.04.2024 reported in 2024 SCC OnLine SC 513 and has held

that while condoning the delay or refusing to condone the delay,

the principles laid down in the said judgment has to be

considered and discussed in Paragraph no. 26 of the judgment as

under:-

“26. On a harmonious consideration of the provisions

of law, as aforesaid, and the law laid down by this Court, it is

evident that:

(i) Law of limitation is based upon public policy
that there should be an end to litigation by
forfeiting the right to remedy rather than the right
itself;

(ii) A right or the remedy that has not been
exercised or availed of for a long time must come
to an end or cease to exist after a fixed period of
time;

(iii) The provisions of the Limitation Act have to be
construed differently, such as Section 3 has to be
construed in a strict sense whereas Section 5 has to
be construed liberally;

(iv) In order to advance substantial justice, though
liberal approach, justice-oriented approach or
cause of substantial justice may be kept in mind but
the same cannot be used to defeat the substantial
law of limitation contained in Section 3 of the
Limitation Act;

Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
63/66

(v) Courts are empowered to exercise discretion to
condone the delay if sufficient cause had been
explained, but that exercise of power is
discretionary in nature and may not be exercised
even if sufficient cause is established for various
factors such as, where there is inordinate delay,
negligence and want of due diligence;

(vi) Merely some persons obtained relief in similar
matter, it does not mean that others are also
entitled to the same benefit if the court is not
satisfied with the cause shown for the delay in
filing the appeal;

(vii) Merits of the case are not required to be
considered in condoning the delay; and

(viii) Delay condonation application has to be
decided on the parameters laid down for
condoning the delay and condoning the delay for
the reason that the conditions have been imposed,
tantamounts to disregarding the statutory
provision.

69. Having considered the judgment of the Hon’ble

Apex Court and materials on records, it is apparent that there is

no sufficient explanation except mentioning the movement of

files from one stage to another and a lame excuse. In limitation

petitions filed in Civil Revision Nos. 194 of 2018 & 9 of 2019.

Same grounds have been taken for explaining the delay in filing

the aforesaid two civil revision applications in which the
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
64/66

deponents stated that files were sent to the office of learned

Advocate General on 16.12.2016 and 28.03.2017 respectively.

The said files were kept in the bunch of regular cases by mistake

of Advocate’s Clerk of the concerned panel lawyers due to

which the said civil revision applications could not be filed in

time. The said revision applications were filed on 20.12.2018

and 15.01.2019. It is pertinent to mention that the said files were

located on 05.10.2018 and 28.09.2018 respectively while both

the revision applications were filed after 2 months 14 days and 3

months 16 days respectively. In another revision application i.e.

Civil Revision No. 20 of 2019, the plea has been taken that the

petitioners were not dealing with the matter in Reference Case.

The said work was being carried out by Road Construction

Department, NH Division, Aurangabad, and on 22.09.2015, the

work was handed over to NH Division, Gulzarbagh. This plea is

apparently false and misleading. It is apparent from the Award

dated 20.01.2015 passed by the Arbitration Tribunal in

Reference Case No. 102 of 2011 that the petitioners were one of

the opposite parties of the Award under challenge. Moreover, the

petitioners also filed rejoinder to the claim of the opposite party

in the said Reference case. The said petitioners have not come

with clean hand.

Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
65/66

70. In other cases, the petitioners had knowledge

about the cases through communication made by the Secretary

of the Arbitration Tribunal, who sent the copy of Award about

one month of passing of the aforesaid Awards. In all Awards, the

learned Arbitration Tribunal has passed the order in presence of

the petitioners. No ex parte order or Award was passed. In such

view of the matter, it is apparent that there was lack of bona fide

effort. The petitioners filed the revision applications after

inordinate delay i.e., much after the prescribed time and there

was complete lack of due diligence by the petitioners in taking

steps for filing the aforesaid revision applications.

71. Having considered the judgments of the Apex

Court as well as the principles laid down by the Hon’ble

Supreme Court and materials on record of the case, it is

apparent that there was delay at every stage and there is no

explanation except mentioning the dates of movement of files.

Even according to the petitioners, due information and copy of

the Award was sent by the Arbitration Tribunal within

prescribed period. Further, all the petitioners were represented

through their learned counsels before the Tribunal and the

Awards of the said cases were passed in presence of the

counsels of the petitioners. The petitioners have miserably failed
Patna High Court C.R. No.9 of 2017(32) dt.01-05-2025
66/66

to give any acceptable and cogent reason to condone such a

huge delay of 2 years 5 months 8 days, 1 year 3 months 22 days,

8 months 22 days, 1 year 1 month 3 days, 2 years 11 months 18

days, 10 months 9 days, 2 years 21 days, 1 year 10 months 24

days, 3 years 9 months 16 days & 3 years 2 days respectively.

72. Accordingly, the limitation petitions bearing I.A.

Nos. 161 of 2017 in C.R. No. 9 of 2017, 7500 of 2017 in C.R.

No. 203 of 2017, 7717 of 2017 in C.R. No. 208 of 2017, 9374 of

2017 in C.R. No. 258 of 2017 , 8105 of 2017 in C.R. No. 225 of

2017, 201 of 2018 in C.R. No. 05 of 2018 , 9684 of 2018 in

C.R. No. 194 of 2018, 1 of 2019 in C.R. No. 09 of 2019, 1 of

2019 in C.R. No. 20 of 2019 & 1 of 2020 in C.R. No. 21 of

2019 are dismissed having no merit in it.

73. Consequently, upon the dismissal of limitation

petitions, Civil Revision Nos. 09 of 2017, 203 of 2017, 208 of

2017, 258 of 2017, 225 of 2017, 05 of 2018, 194 of 2018, 9 of

2019, 20 of 2019 & 21 of 2019 are dismissed.

(Khatim Reza, J)

Sankalp/
Premchand-

U



Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here