The State Of West Bengal vs Sraddhananda Basu on 8 May, 2025

0
39

Calcutta High Court (Appellete Side)

The State Of West Bengal vs Sraddhananda Basu on 8 May, 2025

Author: Sabyasachi Bhattacharyya

Bench: Sabyasachi Bhattacharyya

                            In the High Court at Calcutta
                             Civil Appellate Jurisdiction
                                    Appellate Side


The Hon'ble Justice Sabyasachi Bhattacharyya
              And
The Hon'ble Justice Uday Kumar


                               F.A.T. No.516 of 2019
                                          +
                                   CAN 4 of 2023
                              The State of West Bengal
                                         Vs.
                                Sraddhananda Basu

                                        With

                            F.A.T. No.3 of 2019
                                      +
                               CAN 2 of 2022
                            Sraddhananda Basu
                                     Vs.
                     Land Acquisition Collector, Hooghly


For the appellant in
FAT No.516 of 2019
and
for the opposite party in
FAT No.3 of 2019                   :   Mr. Soumitra Bandyopadhyay, Sr. Govt. Adv.
                                       Mr. Aniruddha Sen

For the respondent in

FAT No.516 of 2019

and
For the appellant in
FAT No.3 of 2019 : Mr. Saptangsu Basu, Sr. Adv.,
Mr. Ayan Banerjee,
Ms. Debjani Sengupta,
Ms. Poulami Ghosh

Heard on : 24.04.2025 and 01.05.2025.

Hearing concluded on               :   01.05.2025

Judgment on                        :   08.05.2025
                                       2

Sabyasachi Bhattacharyya, J.:-


1. The present appeals have been filed respectively by the State, through

the Land Acquisition Collector, Hooghly, and by the referral claimant.

In the appeals, the judgment and decree passed by the learned

Additional District Judge, First Court at Hooghly Sadar, District –

Hooghly, in a reference under Section 18 of the Land Acquisition Act,

1894 (hereinafter referred to as “the 1894 Act”) has been challenged by

both sides.

2. Bereft of unnecessary details, a land at Mouza Bhadrakali at Uttarpara

was acquired by the State for the public purpose of rehabilitation of

squatters-refugees of the Bhadrakali Women‟s Home. A Notification was

issued under Section 4 of the 1894 Act, and a hearing was given under

Section 5(A) of the said Act by the District Collector. At that stage, in

connection with a writ petition, a learned Single Judge of this Court

was pleased to direct fresh hearing under Section 5(A) and annulled all

steps taken from the initial hearing under the said provision till

subsequent steps.

3. In the meantime, the Right to Fair Compensation and Transparency in

Land Acquisition, Rehabilitation and Resettlement Act, (for short, “the

2013 Act”) came into force with effect from April 1, 2024. Accordingly,

the calculation of compensation for the acquisition was required to be

done under Section 26 of the 2013 Act. Accordingly the matter was

taken up for hearing and an award was passed, in respect of which a

reference was initiated on the application of the claimant under Section

18 of the 1894 Act. By the order of another learned Single Judge of this
3

Court, since Rules had not yet been framed under the 2013 Act by the

State, it was directed that the reference would continue under Section

18 of the 1894 Act.

4. Thus, although the reference continued under the 1894 Act, the

calculation of compensation was supposedly made under the 2013 Act.

Subsequently, by the impugned judgment and decree dated September

20, 2018, the reference case was disposed of, being aggrieved by which

both sides have preferred their respective appeals.

5. Learned Senior Counsel appearing for the State argues that the

impugned judgment and decree were passed on the basis of five Sale

Deeds produced by the claimant. However, out of the said Deeds, at

least two were post-notification. It is relevant to mention here that the

date of notification under Section 4 of the 1894 Act, as published in the

Extraordinary Gazette, was September 20, 2011. Both parties agree

that for the purpose of calculation of compensation, the said date

would be the relevant date.

6. Learned senior counsel for the State next argues that whereas the

acquired lands were of „Bastu’ nature, those were without any

structures, whereas the lands covered by the said Sale Deeds produced

by the claimant all contains structures. As such, the said Deeds could

not be a reasonable basis for the assessment of compensation.

However, the learned Referral Court relied on the said documents to

come to its findings.

7. Thirdly, it is argued that the plots covered by the Sale Deeds are far

away from the suit plot and adjacent to a 25-ft wide road and, as such,
4

could not be a reasonable basis for valuation. On the other hand, sale

data was produced by the State in respect of the self-same cluster of

lands as acquired, which should have formed the basis of the

assessment of compensation.

8. It is next contended by the State that the Referral Court relied on one of

the Deeds produced by the claimant which contained an absurdly high

market value as opposed to the other Deeds. It is argued that the well-

settled proposition of law is that if there is a marked difference between

the sale price/market value shown in one of the Deeds and that shown

in the others, the different deed should be discarded for the purpose of

assessing compensation.

9. Learned senior counsel appearing for the State relies on the application

for production of documents filed under Order XLI Rule 27 of the Code

of Civil Procedure by the State seeking to produce e-assessment slips of

March 26, 2012 which, according to him, reflected the correct market

price of adjacent plots in respect of Sale Deeds executed during the

relevant period. It is submitted that those ought to have been taken

into consideration for assessing the correct market value of the

properties in question.

10. It is argued that the learned Referral Judge erred in law in overlooking

the sale data provided by the State and placing reliance solely on the

deeds produced by the claimant.

11. Learned senior counsel appearing for the claimant contends that the

impugned judgment and decree are perverse inasmuch as the learned

Referral Judge arrived at a finding that the average value of the Sale
5

Deeds was Rs.4,50,000/-, thereby going by the initial statement made

in the pleadings of the claimant. However, even if an average value of

the Sale Deeds are taken, the same comes to around Rs.5,49,694/-.

12. Learned senior counsel argues that the settled legal proposition is that,

out of various exemplars, the highest is to be taken while calculating

compensation. The highest market value reflected in the Deeds

produced by the claimant was found in Deed No.07282 dated

September 29, 2011, which is to the tune of Rs.6,36,666/-. In support

of the proposition that the comparable deed showing highest valuation

should be taken for calculating compensation, the claimant relies on

the following Judgments:

(i) Sri Ram M. Vijayalakshmamma Rao Bahadur Ranee of Vuyyur v.

Collector of Madras, reported at (1969) 1 MLJ (SC) 45;

(ii) Meherawal Khewaji Trust (Registered), Faridkot and Others v.

State of Punjab and Others, reported at (2012) 5 SCC 432;

(iii) Himmat Singh and Others v. State of M.P. and Another, reported

at (2013) 16 SCC 392;

(iv) Anjani Molu Dessai v. State of Goa and Another, reported at

(2010) 13 SCC 710.

13. Learned senior counsel appearing for the claimant submits that the

Supreme Court has repeatedly held that the Court has to assess just

and fair compensation in respect of land acquisition irrespective of the

amount actually claimed by the claimant. In support of such

proposition, learned senior counsel cites Ashok Kumar and Others v.

State of Haryana, reported at (2016) 4 SCC 544 and Bhimasha v.
6

Speical Land Acquisition Officer and Another, reported at (2008) 10 SCC

797.

14. It is further argued by the claimant that Section 26(1)(a) of the 2013 Act

provides the market value for the registration of sale deeds or

agreements to sell in the area where the land is situated to be one of

the tests for determining the market value of the land. Although in

Clause (b) of sub-section (1) of Section 26 average sale price has been

mentioned, the said sub-section clearly specifies that whichever is the

higher of the criteria laid down therein is to be followed. Going by the

same, it is the market value (the higher value), and not the average sale

price, which ought to have been looked into.

15. The sale data provided by the State in the Referral Court, it is

contended, did not reflect the market value but the set-forth value for

the sales and, as such, could not have been looked into for the purpose

of assessment of compensation.

16. Learned senior counsel contends that in Section 2(13) of the West

Bengal Panchayat Act, 1973 „Mouza” has been defined as the smallest

unit of area of land. Since the Sale Deeds produced by the claimant

were all pertaining to the Bhadrakali Mouza, which is the same Mouza

where the acquired lands are situated, the said deeds provided an

accurate measure of the compensation, as the market value as

determined by the Registration Office were mentioned in each of the

Deeds.

17. Learned senior counsel appearing for the claimant further argues that

the interest has been calculated on the market value till the date when
7

the award was actually passed, that is, July 30, 2015. However, in the

reply to a query made by the claimant under the Right to Information

Act, the Special Land Acquisition Officer, Hooghly enclosed a Memo

which reveals that the Governor was pleased to approve the award in

connection with the said acquisition on February 23, 2016. The said

document is sought to be brought on record by way of additional

evidence in the claimant‟s application under Order XLI Rule 27 of the

Code. Thus, according to the claimant, the interest on the market

value as per Section 64 of the 2013 Act should have been calculated till

February 23, 2016.

18. Learned senior counsel further argues that the Referral Court ought to

have granted additional compensation in terms of the Section 72 and

interest in terms of Section 80 of the 2013 Act as well.

19. Lastly, it is argued that the State did not file any written objection to

the referral application under Section 18 of the 1894 Act. As such, no

evidence adduced by the State can be looked into at all. In support of

the proposition that evidence cannot be looked into without pleadings,

learned senior counsel cites Ratanlal Alias Babulal Chunilal Samsuka v.

Sundarabai Govardhandas Samsuka (Dead) Through Legal

Representatives and Others, reported at (2018) 11 SCC 119 and

Bachhaj Nahar v. Nilima Mandal and Another, reported at (2008) 17 SCC

491.

20. Upon considering the arguments of parties, certain broad issues are

found to be germane in adjudicating the matter, which are as follows:
8

    (i)     Basis of valuation;

    (ii)    Whether compensation should have been granted till the date

            of the Governor's approval of the award;

(iii) Whether the claimant is entitled to get interest on excess

compensation in terms of Section 72 of the 2013 Act;

(iv) Whether the claimant is entitled to interest under Section 80

of the 2013 Act.

(i) Basis of valuation

21. Section 24(1)(a) of the 2013 Act provides that notwithstanding anything

contained in the said Act, in case of land acquisition proceedings

initiated under the 1894 Act where no award under Section 11 of the

1894 Act has been made, all provisions of the 2013 Act relating to the

determination of compensation shall apply.

22. It is an admitted position that in the present case, only a notification

was issued under Section 4 of the 1894 Act and no award under

Section 11 was passed, since the introduction of the 2013 Act

intervened, and the compensation was awarded on the basis of the

parameters laid down in the 2013 Act. Thus, the premise of calculation

has to be in respect of the 2013 Act in terms of Section 24(1)(a) of the

said Act, more so since on the date of the award, the 1894 Act stood

repealed under Section 114(1) of the 2013 Act.

23. The mode of determination of market value of land by Collector has

been provided in Section 26 of the 2013 Act. As per sub-section (1) of
9

Section 26, three objective criteria have been laid down in assessing

and determining the market value of land.

24. The first, contained in Clause (a), is the market value, if any, specified

in the Indian Stamp Act, 1899 for the registration of sale deeds or

agreements to sell, as the case may be, in the area where the land is

situated.

25. The second yardstick is the average sale price for similar type of land

situated in the nearest village or nearest vicinity area, as per Clause (b).

26. Clause (c) provides as a third yardstick the consented amount of

compensation as agreed upon under Section 2(2) in case of acquisition

of lands for private companies or for public-private partnership

projects.

27. Clause (c) does not apply in the present case at all and the conflict

sought to be raised is between Clauses (a) and (b). Whereas the State

seeks to rely on the average sale price as provided for in Clause (b), the

claimant argues that the market value under Clause (a) is applicable.

28. A perusal of Section 26(1) clearly shows that the above three criteria

have been disjuncted by the conjunction “or” and, in no uncertain

terms, sub-section (1) provides that out of the three criteria, whichever

is higher is to be adopted.

29. We find from the sale deeds and other documents produced in

connection with the matter that the market value is admittedly higher

than the sale prices as reflected in the deeds of nearby lands. Thus, it

is the market value which is to be considered in terms of Section 26(1)

for the purpose of assessment of compensation.

10

30. The State admits that the sale data produced in the court below was

not restricted to sale deeds but also contained gift deeds and other

nature of documents. Thus, the said documents could not have been a

reasonable yardstick for calculation of compensation. The e-assessment

slips sought to be produced before this Court were obtained in March,

2012, that is after the date of the notification. We cannot also overlook

the fact that the State did not file any written objection/statement in

the court below and hence, is precluded from producing evidence in the

absence of any pleadings to support the same. The ratio laid down in

Ratanlal Alias Babulal Chunilal Samsuka (supra) and Bachhaj Nahar

(supra) is germane in such context.

31. It is found from the impugned judgment that although initially the sale

deeds produced by the claimant were not exhibited, the Referral Court

observed that since the certified copies of such deeds were not objected

to by the State, those be exhibited and marked as Exhibits. Thus, the

technical objection taken to the marking of the said sale deeds as

exhibits on such count must give way to substantive justice,

particularly keeping in view the nature of the adjudication. Unlike an

ordinary civil suit, where it is for the respective parties to prove their

respective cases, in a compensation matter, it is for the Referral Court

to assess, on the basis of available documents, fair compensation.

32. Going by such yardstick, the market value as mentioned in the sale

deeds produced by the claimant could be validly looked into by the

Referral Court.

11

33. However, the State has raised a valid objection as to two out of the said

deeds pertaining to a period after the notification and, as such, we keep

those deeds beyond our consideration. Going by the three remaining

pre-notification sale deeds of the contemporaneous period, we find that

the highest market value among the same is Rs.6,02,500/- per Cottah,

as enumerated in Deed No.05821. It has been consistently held by the

Supreme Court and different High Courts that while calculating

compensation in respect of land acquisition, the comparable deed

showing highest valuation should be taken into consideration. The

said proposition is reflected in the judgments of Sri Ram M.

Vijayalakshmamma Rao Bahadur Ranee of Vuyyur (supra), Meherawal

Khewaji Trust (Registered), Faridkot (supra), Himmat Singh and Others

(supra) as well as Anjani Molu Dessai (supra) cited by the claimant. It is

a well-settled position of law that the highest exemplar is to be taken as

the basis for calculation of compensation.

34. The only other question left to be decided is whether the market value

shown in the highest exemplar in the present case is absurdly

disproportionate with that as indicated in the other deeds.

35. On a perusal of the three pre-notification deeds produced by the

claimant in the court below, we find that the respective market values

mentioned therein are Rs.5,03,472/- per cottah in Deed No.01192,

Rs.6,02,500/- per cottah in Deed No.05821 and Rs.5,28,333/- per

cottah in Deed No.01294. All the said deeds were registered prior to

executed prior to the notification dated September 20, 2011.
12

36. Since the other two deeds produced by the claimant were registered on

September 23 and September 30, 2011, those are kept outside the zone

of consideration.

37. Going by the above, the highest exemplar stipulated the market value

per cottah at Rs.6,02,500/-, which is not absurdly higher than the

market value reflected in the other two pre-notification deeds. Thus,

we cannot find substance in the contention of the State that the highest

exemplar carried an absurdly high figure.

38. Both the State and the Referral Court proceeded on the wrong premise

of taking the average of sale deeds, since Clause (b) of Section 26(1)

does not come into play at all. The Referral Court acted in a perverse

manner in making an arithmetically wrong calculation of the average of

the sale deeds as well. More importantly, it restricted the calculation of

compensation to the market value mentioned in the pleadings of the

claimant without considering the deeds, which goes against the grain of

the settled law in that regard. As mentioned earlier, in cases of

compensation, the Referral Court is not limited to the pleadings but

has, for itself, to assess compensation independently on the basis of

Section 26 of the 2013 Act.

39. The next sub-question which falls for consideration under the broad

issue of the basis of valuation is whether Deed No.05821 can be taken

into consideration, since the subject-land had a structure standing on

it, whereas the acquired properties had none.

40. Exploring the arguments of the parties on the said issue, we find that

the State, in Page 3 of its written notes of arguments filed before this
13

Court, has taken a stand that the lands covered by the three pre-

notification deeds had structures of 100 Sq. Ft. R.T. Sheds. Even as

per the State, the value of the R.T. Sheds should be deducted from the

valuation of the land. The State has contended that after such

deduction, in respect of the first two deeds, the actual value comes to

Rs.1,48,706/- per cottah. The said two deeds, even as per the State,

contain the respective values of Rs.1,76,944/- and Rs.1,98,662/- per

cottah.

41. For arriving at the actual value of the said two deeds as per the State‟s

version, that is, Rs.1,48,706/-, the valuation of the R.T. Sheds were

deducted. Thus, the valuation attributed to the R.T. Sheds in respect

of the two properties by the State can be arrived at if we deduct the

alleged actual value from the value shown in the deeds. Upon such

simple arithmetical calculation, we find that in respect of the two plots,

the structures have been evaluated by the State respectively at

Rs.49,956/- and Rs.28,238/-.

42. The claimant seeks to produce before this Court, by way of additional

evidence, documents which pertain to answers to his RTI queries, as

per which the valuation of the structures come approximately to

Rs.45,000/-. Even if we take the highest value of the structure out of

the three valuations, two given by the State and one by the claimant,

the highest value of the structure comes to Rs.49,956/-, which is the

version of the State itself.

43. Hence, even as per the logic of the State, the valuation of the land

covered by the highest exemplar can be arrived at by deducting the
14

value of the structure (as furnished by the State itself) from the market

value shown in the highest exemplar, that is, Rs.6,02,500/-. Thus, the

actual market value of the land, upon deduction of the value of the

structure standing thereon, would be Rs. (6,02,5000 – 49,956) =

5,52,544/- per cottah.

44. Thus, as we accept the highest value of the structure as per the State‟s

submission, the Order XLI Rule 27 application of neither of the parties

is required to be entertained. The documents sought to be produced by

the State as additional evidence, in any event, would be evidence

beyond its pleadings, since no written statement/objection was filed by

the State in the reference. Even otherwise, no satisfactory explanation

as to why such documents could not be produced in the Referral Court

by exercise of due diligence has been furnished.

45. In view of the above discussions, we come to the conclusion that the

compensation for the land should be in terms of the market value of the

highest exemplar, minus the value of the structure standing thereon,

which comes to Rs.5,52,544/-.

46. Two other factors are so to be taken note of. First, the sale deeds,

including the highest exemplar produced by the claimant, pertain to

the Bhadrakali Mouza (that is, the same Mouza where the acquired

lands are situated) and, as per the definition given in Section 2(13) of

the West Bengal Panchayat Act, 1973, a “Mouza” is the smallest unit of

land. Hence, the land covered by the said sale deed comes within the

purview of Section 26(1)(a) of the 2013 which contemplates, as a
15

parameter of assessment of compensation, the market value for the

registration of sale deeds in the area where the land is situated.

(ii) Whether compensation should have been granted till the date

of the Governor’s approval of the award

47. To ascertain the validity of the claimant‟s argument that it is not the

date of the actual award but that when the Governor gave approval to

the award which is to be considered to be the relevant dats up to which

compensation should be granted, we are to compare certain provisions

of the 1894 and 2013 Acts respectively. In this context, it is important

to keep in mind that in terms of Section 114, read with Section 24(1)(a)

of the 2013 Act, since no award was made under Section 11 of the

1894 Act but the acquisition proceeding was initiated under Section 4

of the 1894 Act, the provisions of the 2013 Act relating to the

determination of compensation shall apply in its entirety, despite the

basis for calculation of compensation being the market value as on the

date of the notification dated November 20, 2011 issued under Section

4 of the 1894 Act.

48. Section 12 of the 1894 Act provides that the award of the Collector

shall be final and binding when it is filed in the Collector‟s Office. The

corresponding provision in the 2013 Act is Section 37, which are rather

similar to Section 12 of the 1894 Act.

49. However, these provisions are respectively circumscribed by Section 11

of the 1894 Act and Section 23 of the 2013 Act, which roughly

correspond with each other. A marked difference, however, between the
16

two can be found in the context of the present arguments of the

claimant. Whereas the first proviso to Section 11(1) of 1894 Act

stipulates that no award shall be made by the Collector under the said

sub-section without the previous approval of the appropriate Government

or of such other Officer as the appropriate Government may authorize

in this behalf, there is no similar corresponding provision in Section 23

of the 2013 Act.

50. The latter Section stipulates that the Collector shall proceed to enquire

into the objections and shall make an award under his hand, without

any further requirement of approval by the Government (as expressed

through the Governor).

51. Hence, whereas the mandate of the 1894 Act is that, for an award to be

made, the same is to be approved first by the appropriate Government

(which will is generally expressed through the Governor in such cases),

there is complete absence of such restriction in the 2013 Act as per

which the award becomes final on the date of its passing.

52. Reverting back to Section 24(1)(a) of the 2013 Act, which is applicable

in the instant case, all provisions of the 2013 Act relating to the

determination of compensation shall apply. Thus, although the reference

was construed to be under Section 18 of the 1894 Act by an order of

this Court, since no Rules under the 2013 Act had yet been framed at

that stage, the assessment of compensation was to be in terms of the

2013 Act as per Section 24 (1) (a) of the 2013 Act; as such, all

provisions of the 2013 Act relating to the determination of
17

compensation, including Section 23, read with Section 37, of the said

Act are applicable in the instant case.

53. Thus, it is abundantly clear that whereas the 1894 Act imposes a fetter

in the shape of prior approval by the Government for an award to be

made, the unbridled provisions of the 2013 Act, which is applicable to

the present case, do away with such restriction for an award to be

passed.

54. Hence, the argument of the claimant to the effect that the

compensation should have been granted till the date of the Governor‟s

assent cannot be accepted, as no such assent was required in the first

place for making the present award of compensation, which was passed

in terms of the 2013 Act.

55. Thus, we decide this issue in the negative and come to the conclusion

that the date up to which compensation is to be awarded is the actual

date of passing of the award that is July 30, 2015.

(iii) Whether the claimant is entitled to get interest on excess

compensation in terms of Section 72 of the 2013 Act

56. Section 72 provides that if the sum, which in the opinion of the Referral

Authority the Collector ought to have awarded, is in excess of the sum

which the Collector awards, the said award of the Referral Authority

may direct that the Collector shall pay interest on the excess amount at

the rate of 9% per annum from the date on which he took possession of

the land to the date of payment of such excess to the Authority.

57. The proviso to Section 72 of the 2013 Act stipulates that where such

excess or any part thereof is paid to the Authority after the date or
18

expiry of a period of one year from the date of possession, interest at

the rate of 15% per annum is payable from the date of expiry of the said

period of one year on the amount of such excess or part thereof which

has not been paid to the Authority before the date of such expiry.

58. It is relevant to note that both the 1894 Act and the 2013 Act

contemplate possession to be taken after notice. As such, there is no

material difference between the two Acts regarding applicability of the

principle underlying Section 72 of the 2013 Act insofar as the relevant

date being the date of possession. Although the expression “may” has

been used in Section 72, we do not find any conceivable reason as to

why the claimant in the present case should be deprived of such

interest, upon ascertainment of the date on which possession was

taken from the claimant. The date of possession has not been

mentioned clearly in the award. Thus, it is for the Referral Court to

ascertain such date from the evidence and materials available on record

and to grant such interest as mentioned in Section 72 to the claimant.

59. Thus, this issue is decided in principle in the positive, in favour of the

claimant.

(iv) Whether the claimant is entitled to interest under Section 80

of the 2013 Act.

60. By the same logic as above, concerning the grant of interest under

Section 72, the Collector as well as the Referral Court was duty-bound

to direct payment of interest on the compensation at the rate of 9% per

annum from the time of taking possession until it has been paid or

deposited, in the event such compensation was not paid or deposited
19

on or before taking possession of the land. The proviso to Section 80

stipulates that if such compensation or any part thereof is not paid or

deposited within a period of one year from the date on which

possession was taken, interest at the rate of 15% per annum shall be

payable from the date of expiry of the said period of one year on the

amount of compensation or part thereof which has not been paid or

deposited before the date of such expiry. These mandates are statutory

and no pleading claiming such interest is required to be made by the

claimant, either for payment of interest on the excess or the principal

compensation. As a necessary corollary of grant of compensation, the

referral Court ought to have looked into the said issues and granted

such interest, if payable to the claimant. Hence, the entitlement of the

claimant to get the interest stipulated in Section 80 of the 2013 Act is

in principle decided in the positive, in favour of the claimant.

61. We find from the above discussions that the learned Referral Court did

not advert to the above questions at all or applied erroneous legal

principles and followed invalid legal yardsticks in coming to its

conclusions while passing the impugned award.

62. Accordingly, F.A.T. No.516 of 2019 and F.A.T. No.3 of 2019 are allowed

in part, thereby setting aside the judgment and impugned decree dated

September 20, 2018 passed by the learned Additional District Judge,

First Court at Hooghly Sadar, District – Hooghly in Land Acquisition

Miscellaneous Case No.7 of 2016 and remanding the matter to the

Referral Court for adjudication on the points given hereinbelow:
20

(i) The compensation of the acquired land of the claimant is fixed

at Rs.5,52,544/- per cottah;

(ii) The solatium of one hundred per cent of the compensation

amount, as stipulated in Section 30 of the 2013 Act, shall be

calculated by the Referral Court on the basis of the above

compensation and awarded to the claimant;

(iii) The Referral Court shall also award interest at the rate of 12%

per annum on the market value as mentioned above in terms of

sub-section (3) of Section 30 of the 2013 Act.

(iv) The Referral Court shall grant an opportunity to both sides to

adduce evidence, if they so choose, on the limited question of

the date of possession and as to whether the parameters of

Section 72 and Section 80 of the 2013 Act are satisfied in the

present case. In the event the parties or either of them choose

not to adduce evidence or the evidence is not satisfactory, it will

be open to the Referral Court to look into the relevant materials

and/or call for the necessary records from the appropriate

authorities for ascertaining the relevant factual parameters and,

upon such exercise, if it is found that the claimant is otherwise

entitled to the interest contemplated in Section 72 and/or

Section 80 of the 2013 Act, the referral court shall award such

interest(s) to the claimant in terms of the said Sections.

63. For the above considerations, the appropriate multiplier in terms of

sub-section (2) of Section 26 shall be applied by the Referral Court.
21

64. It is expected that the court of the learned Additional District Judge

(Referral Court under Section 18 of the 1894 Act) shall complete the

above exercise as expeditiously as the business of the said court

permits and pass a fresh award upon the above considerations,

preferably within eight (08) months from the date of communication of

this judgment and order to the said court.

65. The interim applications, bearing CAN 4 of 2023 in connection with

F.A.T. No.516 of 2019 and CAN 2 of 2022 in connection with F.A.T.

No.3 of 2019, are also disposed of in the light of the above observations.

66. There will be no order as to costs.

67. Urgent certified copies of this order, if applied for, be supplied to the

parties upon compliance of all necessary formalities.

(Sabyasachi Bhattacharyya, J.)

I agree.

(Uday Kumar, J.)

Later

After the above judgment is delivered, it is submitted by learned

counsel for the claimant that the decretal amount was deposited with

the learned Registrar General, out of which an amount of Rs.

30,00,000/- has been withdrawn by the claimant. Counsel prays for

permission to the claimant to withdraw the balance amount since the

compensation and interest payable to the claimant now, if calculated
22

at the rate as we have directed in our judgment, would come to a

higher amount than the decretal amount in any event.

We find substance in such argument.

Hence, the balance of the decretal amount deposited with the

learned Registrar General by the State, along with interest, shall be

disbursed in favour of the claimant, as and when so approached by

the claimant, by the learned Registrar General of this Court after

deduction of statutory charges.

The entire amount so withdrawn by the claimant shall be

adjusted with the amount to be awarded by the Referral Court after

remand.

(Uday Kumar, J.) (Sabyasachi Bhattacharyya, J.)

[ad_1]

Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here