Tirumala Tirupathi Devasthanams vs M/S Micro And Small Enterprises … on 28 March, 2025

0
6

Andhra Pradesh High Court – Amravati

Tirumala Tirupathi Devasthanams vs M/S Micro And Small Enterprises … on 28 March, 2025

                                        1


             *HIGH COURT OF ANDHRA PRADESH :: AMARAVATI

                      +WRIT PETITION No.28931 of 2023



Between:



#Tirumala Tirupathi Devasthanams                                ...PETITIONER

                                      AND

$M/s Micro And Small Enterprises Facilitation Council        ...RESPONDENT(S)
and Others



JUDGMENT PRONOUNCED ON 28.03.2025



               THE HON'BLE DR.JUSTICE K. MANMADHA RAO



   1. Whether Reporters of Local newspapers
      may be allowed to see the Judgments?
                                                                    -   Yes -


   2. Whether the copies of judgment may be marked to Law
      Reporters/Journals
                                                                    -   Yes -

   3. Whether Their Ladyship/Lordship wish to see the fair
      copy of the Judgment?
                                                                    -   Yes -



                                       ___________________________________

                                               DR.JUSTICE K. MANMADHA RAO
                                             2


               * THE HON'BLE DR.JUSTICE K. MANMADHA RAO

                         +WRIT PETITION No.28931 of 2023

% 28.03.2025



# Between:



#Tirumala Tirupathi Devasthanams                                        ...PETITIONER

                                           AND

$M/s Micro And Small Enterprises Facilitation Council            ...RESPONDENT(S)
and Others



! Counsel for the Petitioner :    Sri V. Venugopal rAo

                                  Ms. V. Dyumani



! Counsel for Respondents:        Sri G. Pedababu
                                  Sri P. Venkata Subbaiah



<Gist :

>Head Note:

? Cases referred:   1.      MANU/AP/1256/2022:AIR 2022 AP 150

                    2.     2021 SCC OnLine SC 439

                    3.     (2023) 6 SCC 401

                    4      (2009) 1 SCC 267

                    5      (2005) 8 SCC 618

                    6      (2020) 15 SCC 706

                    7      (2022) SCC 75

                    8      (2023) 6 SCC 401

                    9.     CRP Nos.112 of 2022 & batch dated 2.2.2022
                                                          3

 APHC010558812023
                           IN THE HIGH COURT OF ANDHRA PRADESH
                                         AT AMARAVATI                                                      [3310]
                                  (Special Original Jurisdiction)

                  FRIDAY ,THE TWENTY EIGHTH DAY OF MARCH
                       TWO THOUSAND AND TWENTY FIVE

                                                  PRESENT

              THE HONOURABLE DR JUSTICE K MANMADHA RAO

                                WRIT PETITION NO: 28931/2023

Between:

Tirumala Tirupathi Devasthanams                                                               ...PETITIONER

                                                      AND

M/s Micro And Small Enterprises Facilitation Council and ...RESPONDENT(S)
Others

Counsel for the Petitioner:

   1. V.DYUMANI (SC for TTD)

Counsel for the Respondent(S):

   1. G RAMA CHANDER RAO

   2. VENKATA SUBBAIAH POGULA

The Court made the following:

ORDER:

This writ petition is filed under Article 226 of the Constitution of India for

the following relief:

“…..to issue a writ order or direction particularly in the nature of a Writ of Prohibition restraining
the 1st Respondent in continuing the proceedings in Reference No 21C/IFC/2022/1669 Application No
UDYAMAP100007461/S/00002 and to declare the proceeding in the Reference No 21C/IFC/2022/1669
Application No IJDYAMAP10 0007461/S/00002 as without jurisdiction and beyond the jurisdiction and
scope of the 1st Respondent under the Micro Small and Medium Enterprises Act 2006 and consequently
direct the 1st Respondent to forthwith drop all further proceedings pursuant to Reference No 2
IC/IFC/2022/1669 Application No UDYAMAP100007461/S/00002 and pass……”

4

2. Brief facts of the case are that the 1st Respondent issued an

“Intimation” dated 25-05-2021 to the petitioner demanding payment of an

amount of Rs. 58,50,23,610/-. Challenging the said Intimation, the petitioner

filed W.P.No.18584 of 2021 before this Court and this Court permitted the

petitioner to treat the said intimation as a show cause notice and submit its

objections. But subsequent to filing of the said writ petition, the claim of the

respondents No.2 and 3 was settled and the same was brought to the notice

of the 1st respondent vide Memo dated 30.08.2022. As the claims between

the petitioner and the respondents No.2 and 3 were settled, the petitioner

asked the 1st respondent to drop all further proceedings before it. However, to

the shock and surprise of the petitioner, the 3 rd respondent filed reply Memo

dated 21.11.2022 stating that the no-due certificate ‘was forced out of’ it for

the purpose of paying bills, which is illegal and unlawful. It is stated that the

1st respondent should have dropped all further proceedings before it in the

light of the Memo filed by the petitioner and the communication addressed to it

by respondent No. 2 and 3. Instead, the respondents No.2 and 3 are trying to

make the 1st respondent adjudicate on the application that was withdrawn by

them. The 1st respondent is entertaining such requests and forcing the

petitioner to participate in the proceedings before it. The conduct of the

respondents in this regard is illegal and arbitrary. It is stated that

Respondents 2 and 3 initiated Arbitration proceedings against the Petitioner.

The Sole Arbitrator appointed by Respondents 2 and 3 was proceeding at

lightning speed and was about to grant the entire claim and that the Petitioner
5

timely took steps against the said proceedings as the Arbitrator had no

jurisdiction under the said Construction Agreement. The construction

Agreement provided for Arbitration for disputes below Rs.50,000/-. The

Agreement also specifically provides that all claims above Rs.50,000/- have to

be adjudicated by a competent Civil Court by way of a Civil Suit. Considering

the same, this Hon’ble Court in CMA 220 of 2021, filed by the Petitioner,

granted stay of all further proceedings before the said Arbitrator. The said

CMA is still pending before this Hon’ble Court. The Respondents 2 and 3, later

withdrew their claim before the said Arbitrator after their dues were settled in

October/November 2021. It is stated that in addition to all the amounts

received from the petitioner, the respondents No.2 and 3 have initiated the

complaint before the 1st respondent seeking a sum of Rs.55,30,81,823/- plus

interest to the tune of Rs.35,05,84,167/- (Total : Rs.90,36,65,990/-), which is

illegal and arbitrary. Hence, the present writ petition.

3. This Court vide order dated 04.11.2023, while issuing Notice before

admission, has granted direction as under:

“……..Since the jurisdiction of the respondent No.1 is raised in this writ
petition, the matter is Admitted and stay of all further proceedings before the
respondent No.1 is granted, pending further orders.”

4. The counter affidavit has been filed by the respondents No.2 and 3.

While denying the allegations made in the petition, inter alia, contended that,

these respondents have lodged two complaints online, UDAYAM-AP-10-

0007461.5/00001, on 25-05-2021 for a principal amount of Rs.73,61,14,782/-
6

and UDAYAM-AP-10-0007461.S/00002 for another principal amount of

Rs.58,50,23,610/- on 25-05-2021. The Petitioner filed a writ petition

challenging only UDAYAM-AP-10-0007461.S/00002 through WP No. 18584 of

2021, and the Hon’ble Court has permitted to treat the same as show cause

notice and submit its objections. Subsequently, the 2nd Respondent has

withdrawn the said UDAYAM-AP-10-0007461.S/00002, and as such, the

same has become infructuous. It is stated that the 2nd Respondent has raised

his claims in addition to the 44th & Final Bill, for Rs. 7,64,15,841 on 05-11-

2020, out of which Rs.2,64,15,841/-was paid on 05-12-2020 and 07-12-2020.

The Writ petition’s outstanding amount of Rs. 5,00,00,000/- was due. Before

the 44th & Final Bill was paid, the 2nd respondent was appointed M.

Jaganmohan Rao and that the said M. Jaganmohan Rao unilaterally

appointed himself as arbitrator and issued notices to the Writ Petitioner and

this Respondent. Upon receipt of the notices, Writ Petitioner stopped

payment of the admitted amount under the 44th and Final Bill, due to which,

the 2nd Respondent was in severe financial distress.

It is stated that the Indian Bank, Seethammadhara Branch, on

22.04.2021 issued notices for regularization of Open Cash Credit (OCC) limit

and on 12.05.2021, the bank issued a notice asking the 2 nd respondent to pay

a minimum of Rs. 10.00 crores, failing which the same will be flagged as NPA

on 31-05-2021 and SARFAESI proceedings will be started on 01-06-2021. As

this Respondent was reeling under severe financial distress, it approached the

Writ petitioner for payment of the outstanding admitted 44th & Final Bill, and
7

on 21-09-2021, the Writ Petitioner agreed (a) to release the balance payment

of Rs. 5,00,00,000/- passed under 44th & Final Bill; (b) to release service tax

component @4.944% for the work done in the GST regime i.e., from

01.07.2017; (c) It was decided to Release labour cess recovered in the final

bill as per agreement conditions. Despite agreeing to release the payments

without doing so on 11-10-2021, Executive Engineer-III, requested these

respondents to withdraw all the cases filed against the TTD, withdraw the

appointment of the sole arbitrator and submit a receipt for full and final

settlement of all claims against the TTD relating to the subject work so as to

release the balance payment.

It is further stated in the counter affidavit that on 30.10.2021, 44 th bill

has been released. However, other payments were not released, so on

01.11.2021, then this respondent again addressed a letter to the Executive

Officer, TTD, for the release of service Tax reimbursement, the release of

2.5% retention money, reimbursement of labour cess payment, release of

original bank guarantees, issuance of experience certificate and withdrawl of

all civil and criminal cases filed by TTD against M/s M.Nagireddy & Company

and this respondent as agreed in the meeting held on 21.09.2021. It is further

stated that as the sole arbitrator has unilaterally appointed himself, even prior

to the meeting, these respondents, have decided to withdraw the same and

accordingly in CMA 220 of 2021, these respondents have submitted the same

to the Hon’ble Division bench. The complaint before the lokayuktha was in
8

relation to the non-release of the 44th and Final Bill. As it was agreed to pay

the said amount, it was withdrawn.

It is mainly stated in the counter that the 2nd respondent is a registered

small entity under the MSMED Act, 2006 so the 2nd respondent is entitled to

file their claims before the 1st Respondent. As held by this Hon’ble Court in

Dalapathi Constructions vs. The State of Andhra Pradesh and Ors. 1 ,

wherein, it was held that there is nothing in the MSME Act which provides that

the registration for a particular activity will render an enterprise liable not to be

regarded as a micro, small or medium enterprise for any other activity. Once

registered, the status of the enterprise is that of a registered enterprise under

the MSME Act, and all the provisions of the MSME Act have to apply with full

force. Further as held by the Hon’ble Supreme Court M/s. Silpi Industries vs

Kerala State Road Transport Corporation 2 and Gujarat State Civil

Supplies Corporation Ltd., vs. Mahakali Foods (P) Ltd.,3 , on the issue of

jurisdiction of the council, it was held that :

“52.1. Chapter V of the MSMED Act, 2006, would override the

provisions of the Arbitration Act, 1996. 52.2. No party to a dispute with regard

to any amount due under Section 17 of the MSMED Act, 2006 would be

precluded from making a reference to the Micro and Small Enterprises

Facilitation Council, though an independent arbitration agreement exists

between the parties.”

1

MANU/AP/1256/2022: AIR 2022 AP 150
2
2021 SCC OnLine SC 439
3
(2023) 6 SCC 401
9

So, the 1st Respondent is entitled to be approached by the 3rd

Respondent for adjudication of claims, including a determination as to whether

full satisfaction was given under duress or not. Therefore, prayed to dismiss

the present writ petition as devoid of merits.

5. Heard Sri V. Venugopal Rao, learned Senior counsel representing

Ms. V.Dyumani, learned counsel appearing for the petitioner and Sri G.

Pedababu, learned counsel representing Sri P. Venakata Subbaiah, learned

counsel appearing for the respondents.

6. On hearing, learned Senior Counsel while reiterating the contents

made in the petition, submits that, the Respondents 2 and 3 have initiated

Arbitration proceedings against the Petitioner and that the Sole Arbitrator

appointed by Respondents 2 and 3 was proceeding at lightning speed and

was about to grant the entire claim. He submits that the Petitioner timely took

steps against the said proceedings as the Arbitrator had no jurisdiction under

the said Construction Agreement. The construction Agreement provided for

Arbitration for disputes below Rs.50,000/-, and that the Agreement also

specifically provides that all claims above Rs.50,000/- have to be adjudicated

by a competent Civil Court by way of a Civil Suit. Considering the same, this

Hon’ble Court in CMA 220 of 2021, filed by the Petitioner, granted stay of all

further proceedings before the said Arbitrator and the said CMA is still pending

consideration before this Hon’ble Court. He further submits that the

Respondents 2 and 3, later withdrew their claim before the said Arbitrator after

their dues were settled in October/November 2021. He further submits that
10

the respondents No.2 and 3 have initiated a complaint against the Petitioner

before the Lokayukta. Later, once the claim was settled as aforesaid and after

the amount was paid, the Respondents 2 and 3 withdrew the complaint before

the Lokayukta as well. He further submits that the Micro, Small and Medium

Enterprises Development Act, 2006 was enacted by the Union Government

for facilitating promotion, development and enhancing competitiveness of

Micro, Small and Medium Enterprises and for matters connected there with or

incidental thereto and the said Act is applicable to Micro, Small and Medium

Enterprises which are defined in the said Act in Clauses (e), (g) and (h) of

Sec.2 of the Act. He further submits that among other requirements, a Micro

Enterprise is defined as an Enterprise where investment in Plant and

Machinery does not exceed Rs.25 lakhs. A Small Enterprise is defined as an

Enterprise where the Plant and Machinery is more than Rs.25 lakhs, but does

not exceed Rs.5 crores. Similarly a Medium Enterprise is defined as an

Enterprise where the investment in Plant and Machinery is more than Rs.5

crores, but does not exceed Rs.10 crores.

7. Learned Senior counsel further submits that the Act applies to

“Buyer” and “Supplier” within the meaning of those expressions in Clauses (d)

and (n) of Sec.2 of the Act. The “Buyer” is whoever buys any goods or

receives any services from a “Supplier” for consideration. Similarly, “Supplier”

means a Micro or Small Enterprise which has filed Memorandum under Sec.

8(1) of the Act. A plain perusal of the above statutory scheme would make it

amply clear that the said Act has no application to the petitioner or to
11

respondents No.2 and 3. He further submits that the claim of the respondent

is way beyond the monetary limits imposed under the statute. At any rate, the

petitioner is not a buyer and the respondents No.2 and 3 are not suppliers

within the meaning of those expressions under the Act. He further submits

that the 1st respondent has no authority to entertain the claim per se. At any

rate, the conduct of the 1st respondent in continuing the proceedings despite

the representations given by the petitioner and the respondents No.2 and 3

withdrawing the said proceedings, is illegal and arbitrary. Therefore learned

counsel requests this court to pass appropriate orders.

8. Per contra, learned counsel appearing for the respondents also while

reiterating the contents made in the counter affidavit, argued that, on

30.10.2021 the 44th Bill has been released. However, other payments were

not released. So, on 01.11.2021 the petitioner addressed a letter to the

Executive Officer, TTD, for the release of service tax reimbursement, the

release of 2.5% retention money, reimbursement of labour cess payment,

release of original bank guarantees, issuance of experience certificate and

withdrawal of all civil and criminal cases filed by TTD against M/s M.

Nagireddy & Company and the petitioner as agreed in the meeting held on

21.09.2021. Reminder letters through email were issued on 17-11-2021 and

18-11-2021 and that on 18-11-2021, the Superintending Engineer-III, through

Roc.No.TTD.56021(31)/24/2019-SE III SEC-TTD, issued an urgent note to

Executive Engineer-III for (1) releasing the Service Tax amounts; (2) Withdraw

all the Civil & Criminal Cases by T.T.D. against the contractor; and (3) Any
12

other relevant pending payments. He further submits that in January 2022,

2.5% retention money was released, but to date, service tax reimbursement

and reimbursement of labour cess payments have not been paid despite

agreeing in the meeting on 21-09-2021. Learned Senior Counsel mainly

contended that under Section 18 (3) of the MSMED Act, 2006, after the failure

of the conciliation under Section 18 (2), the 1st Respondent will either act as

an arbitrator or refer the dispute to an institution or centre providing alternate

dispute resolution services for such arbitration and the provisions of Arbitration

and Conciliation Act, 1996 will apply. So, the arbitrator will be competent to

decide whether a full and final settlement letter was issued under duress or

not.

9. Learned Senior counsel further submits that , as the sole arbitrator

has unilaterally appointed himself, even prior to the meeting, the respondents

have decided to withdraw the same in CMA No.220 of 2021 and accordingly,

they have submitted the same before a Division Bench of this Court. Furterh,

the complaint before the lokayukta was in relation to the non-releas of the 44th

and Final Bill as it was agreed to pay the said amount, it was withdrawn. He

further submits that as the respondents are a registered small entity under the

MSMED Act 2006, so they are entitled to file their claims before the 1 st

respondent.

10. To support his contentions, learned counsel for the respondents

has relied upon a catena of decisions of Hon’ble Supreme Court (1) In a case
13

of National Insurance Co. Ltd v. Boghara Polyfab (P) Ltd.,4, wherein the

Apex Court held that :

Some illustrations (not exhaustive) as to when claims are arbitrable and when they are not, when
discharge of contract by accord and satisfaction are disputed, to round up the discussion on this subject
:

(i) A claim is referred to a conciliation or a pre-litigation Lok Adalat. The parties negotiate and arrive at a
settlement. The terms of settlement are drawn up and signed by both the parties and attested by the
Conciliator or the members of the Lok Adalat. After settlement by way of accord and satisfaction, there
can be no reference to arbitration.

(ii) A claimant makes several claims. The admitted or undisputed claims are paid. Thereafter
negotiations are held for settlement of the disputed claims resulting in an agreement in writing settling all
the pending claims and disputes. On such settlement, the amount agreed is paid and the contractor also
issues a discharge voucher/no claim certificate/full and final receipt. After the contract is discharged
by such accord and satisfaction, neither the contract nor any dispute survives for consideration. There
cannot be any reference of any dispute to arbitration thereafter.

(iii) A contractor executes the work and claims payment of say Rupees Ten Lakhs as due in terms of the
contract. The employer admits the claim only for Rupees six lakhs and informs the contractor either in
writing or orally that unless the contractor gives a discharge voucher in the prescribed format
acknowledging receipt of Rupees Six Lakhs in full and final satisfaction of the contract, payment of the
admitted amount will not be released. The contractor who is hard pressed for funds and keen to get the
admitted amount released, signs on the dotted line either in a printed form or otherwise, stating that the
amount is received in full and final settlement. In such a case, the discharge is under economic duress
on account of coercion employed by the employer. Obviously, the discharge voucher cannot be
considered to be voluntary or as having resulted in discharge of the contract by accord and satisfaction.

It will not be a bar to arbitration.

(2) SBP & Co. versus Patel Engineering Ltd. And another 5 ;
(3) Deep Industries Limited versus Oil and Natural Gas
Corporation Limited
and another6;

(4) Bhaven Construction through authorized signatory
Premjibhai K.Shah versus Executive Engineer, Sardar Sarovar Narmada
Nigam Limited and another7
(5) Gujarat State Civil Supplies Corporation Limited versus
Mahakali Foods Private Limited (Unit
2) and another8 , wherein it was held
that :

The upshot of the above is that:

(i) Chapter-V of the MSMED Act, 2006 would override the provisions of the Arbitration Act, 1996.

(ii) No party to a dispute with regard to any amount due under Section 17 of the MSMED Act, 2006
would be precluded from making a reference to the Micro and Small Enterprises Facilitation Council,
though an independent arbitration agreement exists between the parties.(iii) The Facilitation Council,

4
(2009) 1 Supreme Court Cases 267
5
(2005) 8 Supreme Court Cases 618
6
(2020) 15 Supreme Court Cases 706
7
(2022) 1 Supreme Court Cases 75
8
(2023) 6 Supreme Court Cases 401
14

which had initiated the Conciliation proceedings under Section 18(2) of the MSMED Act, 2006 would be
entitled to act as an arbitrator despite the bar contained in Section 80 of the Arbitration Act.

(iv) The proceedings before the Facilitation Council/institute/centre acting as an arbitrator/arbitration
tribunal under Section 18(3) of MSMED Act, 2006 would be governed by the Arbitration Act, 1996.

11. Learned counsel for the respondents while relying upon the above

decisions of Hon’ble Supreme Court, submits that, the 1st respondent is

entitled to be approached by the 3rd respondent for adjudication of claims,

including a determination as to whether full satisfaction was given under

duress or not. Therefore, in view of the above facts and circumstances,

learned counsel for the respondents prayed to dismiss the writ petition and

vacate the interim order granted by this Court on 4.11.2023 as well.

12. Perused the material on record.

13. It is the contention of the petitioner’s counsel that the respondents

No.2 and 3 have initiated a complaint against the petitioner before the 1st

respondent seeking for a sum of Rs.55,30,81,823/- plus interest to the tune of

Rs.35,05,84,167/- (total Rs.90,36,65,690/-), which is illegal and arbitrary.

Further it is also contended that as per Articles of Agreement (22.1 and 22.2)

settlement of disputes; settlement of claims and jurisdiction, stated as follows:

22.1 If any dispute of difference of any kind whatsoever arises between the department and
the Contractor in connection with, or arising out of the Contract, whether during the progress of the
works or after their completion and whether before or after the termination, abandonment or breach of
the Contract, it shall in the first place, be referred to and settled by the Engineer-in-charge who shall,
within a period of thirty days after being requested by the Contractor to do so. give written notice of his
decision to the Contractor. Upon receipt of the written notice of the decision of the Engineer-in-Charge
the Contractor shall promptly proceed without delay to comply with such notice of decision.

22.2 If the Engineer-in-Charge fails to give notice of his decision in writing within a period of
thirty days after being requested or if the Contractor is dissatisfied with the notice of the decision of the
Engineer-in-Charge, the Contractor may within thirty days after receiving the notice of decision appeal to
the Department who shall offer an opportunity to the contractor to be heard and to offer evidence in
support of his appeal, the Department shall give notice of his decision within a period of thirty days after
the Contractor has given the said evidence in support of his appeal, subject to arbitration, as hereinafter
provided. Such decision of the Department in respect of every matter so referred shall be final and
15

binding upon the Contractor and shall forthwith be given effect to by the Contractor, who shall proceed
with the execution of the works with all due diligence whether he requires arbitration as hereinafter
provided, or not. If the Department has given written notice of his decision to the Contractor and no claim
to arbitration, has been communicated to him by the Contractor within a period of thirty days from receipt
of such notice the said decision shall remain final and binding upon the Contractor. If the Department fail
to give notice of his decision, as aforesaid within a period of thirty days after being requested as
aforesaid, or if the Contractor be dissatisfied with any such decision, then and in any such case the
contractor within thirty days after the expiration of the first named period of thirty days as the case may
be, require that the matter or matters in dispute be referred to arbitration as detailed below:-

Settlement of Claims:

Settlement of claims for Rs.50,000/- and below by Arbitration.

All disputes or difference arising of or relating to the Contract shall be referred to the
adjudication as follows:

Claims up to a value of Rupees 10,000/-

Superintending Engineer, (or another circle in the same department).

Claims above Rs. 10,000/- and up to Rupees 50,000/-. Another Chief Engineer, [from the
Government Department of A.P.]

The arbitration shall be conducted in accordance with the provisions of Indian Arbitration an
Conciliation Act 1996 or any statutory modification thereof.

The arbitrator shall state his reasons in passing the award.

Claims above Rs. 50,000/-.

All claims of above Rs.50,000/- are to be settled by a Civil Court of competent jurisdiction by of
Civil suit and not by arbitration.

A reference for adjudication under this clauses shall be made by the contractor within six mo
from the date of intimating the contractor of the preparation of final bill or his having access payment
whichever is earlier.

22.3 JURISDICTION:

For the purpose of this agreement all the transactions shall be deemed to have taken place
within the state of ANDHRA PRADESH and the courts in ANDHRA PRADESH shall have jurisdiction
over the matters arising under or out of this agreement.

14. However, it is the contention of the respondents’ counsel that the

44th Bill has been released, however payments were not released so the

respondents have addressed a letter to the Executive Officer, tTD for the

release of Service Tax reimbursement, the release of 2.5% retention money

and that in January 2022, 2.5% retention money was released. Further,

service tax reimbursement and reimbursement of labour cess payments have

not been paid despite agreeing in the meeting on 21.09.2021. it is also
16

contended that the proceedings before the Facilitation Council/Institute/

Centre acting as an arbitrator/Arbitral Tribunal under Section 18(3) of the

MSMED Act 2006 would be governed by the Arbitration Act 1996 and that the

Facilitation Council/Institute/Centre acting as an Arbitral Tribunal by virtue of

Section 18(3) of the MSMED Act 2006 would be competent to rule on its own

jurisdiction as also the other issues in view of Section 16 of the Arbitration Act

1996.

15. As seen from the Minutes of the Meeting on “Construction of Multi

Storey Complex (Sri Padmavathi Nilayam) at Tiruchanoor” with regard to

releasing of payments to the contractor, held on 21.09.2021 by the Executive

Officer, TTD, Tirupati, wherein it was observed that:

“2) Releasing of the Service Tax component @ 4.944% for the work done in
the GST regime, i.e., from1.07.2017: Service Tax component @ 4.944% deducted,
while arriving the rates for the items for the work done in GST regime, the CE is
requested to examine the same in consultation with Finance Department.

(Action: FA&CAO & CE).

3) Release of labour cess recovered in the final bill: It is decided to release the
labour cess recovered in the final bill, as per the agreement conditions.

(Action: CE)

16. A learned Division Bench of this Court in “Bhajrang Cranes v.

Shiram Transport Finance Company Ltd.9,”wherein it was held as follows:

“46. The object of minimizing judicial intervention while the matter is in the process of being
arbitrated upon, will certainly be defeated if the High Court could be approached under Article
227
or under Article 226 of the Constitution against every order made by the arbitral tribunal.
Therefore, it is necessary to indicate that once the arbitration has commenced in the arbitral
tribunal, parties have to wait until the award is pronounced unless, of course, a right of appeal
is available to them under Section 37 of the Act even at an earlier stage.

47. We, therefore, sum up our conclusions as follows:

9

C.R.P.Nos. 112 of 2022 and batch dated 02.02.2022
17

(i) xxx…………xxx……….xxx

(ii) xxx…………xxx……….xxx

(vi) Once the matter reaches the arbitral tribunal or the sole arbitrator, the High Court would
not interfere with orders passed by the arbitrator or the arbitral tribunal during the course of
the arbitration proceedings and the parties could approach the court only in terms of Section
37
of the Act or in terms of Section 34 of the Act.

(xii) xxx…………xxx……….xxx

11.Having regard to the above, it is clear that, the order passed by the Arbitral Tribunal during
Arbitration proceedings cannot be challenged either under Article 226 or 227 of the
Constitution of India, unless a remedy is provided, under Section 34 of the Act. The parties
have to wait till the award is passed and then challenge the same. However, the learned
Counsel for the petitioner would contend that, the Court has got the power to se-aside the
Order passed by the Arbitrator in exceptional cases, wherein one party is remediless under
the Statute or a clear bad faith is shown by one of the parties.”

……

13. From the observation made by the Hon’ble Apex Court and having regard to the facts in
issue, it is pellucidly clear that only after completion of arbitral proceedings and if the Tribunal
passes an Order against the petitioner, it can raise these grounds in the Appeal filed under
Section 34 of the Act. Tested on the above anvil, the argument of the Petitioner cannot be
accepted in the given set of circumstances. Having regard to the above, the Order under
challenge requires no interference and accordingly, the Civil Revision Petitions stands
disposed off giving liberty to the petitioner to raise these issues in the Appeal if filed under
Section 34 of the Act after completion of arbitral proceedings. No order as to costs”.

17. On a perusal of the above decisions of Hon’ble Supreme Court

and having regard to the facts in issue, it is pellucidly clear that only after

completion of arbitral proceedings and if the Tribunal passes an Order

against the petitioner, it can raise these grounds in the Appeal filed under

Section 34 of the Act. Therefore, whatever the contentions raised by the

petitioner cannot be accepted. Further the Council-1st respondent has no

power to review its own order that once conciliation is closed and posted

for arbitration under Section 18(3), that order to closure cannot be reviewed

as contended by the 2nd respondent and that the parties could approach

the court only in terms of Section 37 of the Act or in terms of Section 34 of
18

the Act. In the instant case, the matter has been referred to Arbitrator as

per Section 18(3) of the MSMED Act. Therefore, the petitioner has a

remedy under Section 34 of the Act to challenge the award by way of an

Appeal after completion of arbitral proceedings.

18. Hence, the proceedings under challenge in this writ petition

warrant no interference. Finding no merit in the instant petition and the

same is liable to be dismissed

19. Accordingly, the Writ Petition is dismissed. No costs.. As a

sequel, all the pending miscellaneous applications shall stand closed.

______________________________

DR. K. MANMADHA RAO, J.

Date :         28 -03-2025

Gvl
                       19


      HON'BLE DR. JUSTICE K. MANMADHA RAO




       WRIT PETITION No. 28931 of 2023




             Date :   28 .03.2025




Gvl
 



Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here