Meghalaya High Court
Union Of India vs M/S Varindera Constructions Ltd. on 18 August, 2025
Author: W. Diengdoh
Bench: W. Diengdoh
Serial No. 02 HIGH COURT OF MEGHALAYA Daily List AT SHILLONG Arb.A. No. 2 of 2025 with MC (Arb.A) No. 1 of 2025 Date of order: 18.08.2025 Union of India vs M/s Varindera Constructions Ltd. Coram: Hon'ble Mr. Justice I.P. Mukerji, Chief Justice Hon'ble Mr. Justice W. Diengdoh, Judge Appearance: For the Appellant : Ms G.C. Marboh, Adv. For the Respondent : Mr Philemon Nongbri, Adv.
Learned counsel for the respondent raises a point of
maintainability of this appeal. Since it is an appeal from an order in
exercise of jurisdiction of the learned Arbitrator under Section 17 of the
Arbitration and Conciliation Act, 1996, the appeal under Section 37(2)
lies before the court defined in Section 2(1)(e) of the said Act, it is
submitted.
At this stage, we do not admit the appeal.
On the prayer of learned counsel for the appellant that her Senior
would argue this matter, this appeal and the stay application are adjourned
till 22nd August, 2025.
(W. Diengdoh) (I.P. Mukerji) Judge Chief Justice Meghalaya 18.08.2025 "Sylvana PS"