Vidya Projects Private Limited vs Essel Infraprojects Limited & Ors on 19 August, 2025

0
3


I.A. 8819/2025 (by D-4 under Order XXXVII Rule 3(5) of CPC)
By way of the instant application, Defendant No. 4 seeks
unconditional leave to defend the present suit.

2. The instant suit is under Order XXXVII of the Code of Civil
Procedure, 1908 (hereinafter referred to as’CPC‟) for recovery of Rs 4, 10,
00,000/-, along with past, pendente lite, and future interest.

Submissions advanced by the parties

3. Mr. Monish Panda, learned counsel for Defendant No.4, submitted
that the suit is misconceived and not maintainable. He further contends that

Signed By:AMIT KUMAR Signed

Signing Date:22.08.2025 By:PURUSHAINDRA
11:43:52 3 KUMAR KAURAV
the Plaintiff is not entitled to any summary judgment against Defendant
No.4.