% 28.02.2025
1. This Petition has been filed under Section 11(6) of the Arbitration and
Conciliation Act, 1996 seeking appointment of an Arbitrator in terms of the
Work Order dated 18.05.2017 awarded to the Petitioner by the Respondent
herien.
2. It is stated that under the said work order, the Petitioner herein was to
replace two 350TR centrifugal Central AC Plants with New 350 TR water
cooled screw type chiller AC plant at AAI operation offices New Delhi. It is
stated that the Petitioner successfully installed the systems. However,
disputes have arisen between the parties. It is stated that the Petitioner has
been repeatedly sending demand notices to the Respondent and the last such
demand notice was sent on 22.02.2024 raising a demand of Rs.45,98,514/-.
It is stated that since no reply has been received from the Respondent, the
Petitioner has approached this Court seeking appointment of an Arbitrator
This is a digitally signed order.